Instructions to Bidders.pdf

PDF 193 KB Posted

Attached to
Demolition Buildings Foundations and Utilities Bundle Phase 2-Site Improvements
Solicitation number
PE-76110-NONST-2025-000000095
Issued by
Fulton County, Georgia

About this file

The Instructions to Bidders document is issued by Sovereign Cooper, Inc. for the Atlanta Independent School System, detailing a demolition and site improvement project located at 1701/1707 Metropolitan Parkway in Atlanta, Georgia. The project, Phase 2 of a demolition and utilities bundle, aims to redevelop an area where buildings have been removed and convert it into an extension of an existing school bus parking depot. Bids are to be submitted electronically by Friday, July 25, until 3:00 PM, with all questions required to be submitted by July 10, 2025. The project includes seven bid packages covering various scopes of work such as grading, utilities, asphalt paving, landscaping, fencing, pavement markings, concrete, and site electrical.

Bid documents, including plans, a sample subcontract, bid package, scope of work, and any addendum, are available through a provided Dropbox link. Interested bidders are instructed to reply to bids@sovereigncooper.com to confirm their desire to bid and specify their intended scope package. The architect for the project is SSOE, Inc., located in Alpharetta, Georgia, and the construction will be managed by Sovereign Cooper, Inc. from Cumming, Georgia. The bid documents provide detailed information for potential contractors to prepare and submit their proposals for this school district infrastructure improvement project.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INSTRUCTIONS TO BIDDERS

Demolition Buildings Foundations and Utilities Bundle Phase 2 – Site Improvements

Project Name & Location: Demolition Foundation and Utilities Bundle – Metropolitan Parkway Phase 2

1701/1707 Metropolitan

Parkway, Atlanta, GA

30135

Construction Manager: Sovereign Cooper, Inc.

304 Tribble Gap Rd.

Cumming, GA 30040

Owner: Atlanta Independent School

System 1631 LaFrance

Street NE, Atlanta, GA

30307

Architect: SSOE, Inc.

100 Peachtree Street, NW

Suite 2500

Alpharetta, GA 30303

Bid Time & Date: Bids are to be submitted electronically @ bids@sovereigncooper.com Friday July 25, UNTIL 3:00 PM.

Questions: All questions must be sent to bids@sovereigncooper.com. Any Questions must be submitted by July 10, 2025.

DESCRIPTION OF PROJECT:

Phase 2 -redevelop the area in the location where buildings have been removed and convert into an extension of adjacent school bus parking depot (at 1701/1707 Metropolitan Parkway) mailto:bids@sovereigncooper.com mailto:bids@sovereigncooper.com

Bid Documents

▪ Plans

▪ Sample Subcontract

▪ Bid package & scope of work

▪ All addendum & clarifications issued prior to bid opening

BID PACKAGES

The following Bid Packages are available for bidding:

Package # Work Description

02-03 Grading & Utilities

02-04 Asphalt Paving

02-05 Landscape

02-06 Fence

02-07 Pavement Markings

03-01 Concrete

26-01 Site Electrical

Bid Documents can be found at the link below.

Link:

https://www.dropbox.com/scl/fo/4nbhofad0xa62w4dvy0b4/AONWRPSAazPJ_pZZ0RfoaT0?rlkey=reeh3qi1cie73yd39rxz37 8jq&st=2q9ut1ms&dl=0

PLEASE REPLY BACK TO bids@sovereigncooper.com. AND CONFIRM YOUR DESIRE TO BID ON THIS PROJECT AND

FOR THE SCOPE PACKAGE FOR YOUR SPECIFIC SCOPE OF WORK

Bids and Questions regarding this project should be sent via e-mail to bids@sovereignccooper.com.

https://www.dropbox.com/scl/fo/4nbhofad0xa62w4dvy0b4/AONWRPSAazPJ_pZZ0RfoaT0?rlkey=reeh3qi1cie73yd39rxz378jq&st=2q9ut1ms&dl=0 https://www.dropbox.com/scl/fo/4nbhofad0xa62w4dvy0b4/AONWRPSAazPJ_pZZ0RfoaT0?rlkey=reeh3qi1cie73yd39rxz378jq&st=2q9ut1ms&dl=0 mailto:bids@sovereigncooper.com.

mailto:bids@sovereignccooper.com

File details come from the government source that posted it. Updated .