About this file

This document is an Infection Prevention & Control Class V Precautions specification for installing VAV Boxes in the Surgery area at Overton Brooks VA Medical Center, dated January 6, 2025. The document provides detailed requirements for maintaining strict infection control during construction, including establishing NFPA 241-compliant barriers, creating an anteroom, maintaining negative air pressure, managing construction waste, and implementing worker protection protocols such as mandatory coveralls, shoe covers, and HEPA filtration.

The related federal contract opportunity (Solicitation Number: 36C25625R0064) is for Project 667-25-185, involving VAV Box installation in the Surgery Storage area, issued by the Department of Veterans Affairs Veterans Health Administration. The solicitation closes on 4/29/2025 at 2:00 pm, with specific technical requirements outlined in the attached infection control precautions document that contractors must strictly follow during the installation process. The comprehensive precautions aim to minimize infection risks during construction activities in a medical facility environment.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Project 667-25-185 CON Install VAV Boxes Surgery Storage, newest first.
File Type Posted
VAV Project_Updated Drawings 4.7.25.pdf PDF
36C25625R0064 0001.pdf PDF
Project No. 667-25-185 Site Visit Sign In 4.7.25.pdf PDF
Install VAV Boxes Surgery Storage ICRA.pdf PDF
P07 WD LA20250031 Mod 0 dtd 1.3.2025.txt TXT text file
36C25625R0064 EXHIBIT C.docx DOCX document
36C25625R0064 EXHIBIT E.docx DOCX document
SURGERY VAV - 2 - DRAWINGS.pdf PDF
36C25625R0064 EXHIBIT D.docx DOCX document
P09 Surgery VAV - 1 - SOW.doc DOC document
667-25-185 Combined Specs.pdf PDF
36C25625R0064 EXHIBIT A.docx DOCX document
36C25625R0064 EXHIBIT B.docx DOCX document
36C25625R0064 EXHIBIT F.docx DOCX document
36C25625R0064 SOL.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VA Medical Center Infection Prevention & Control Class V Precautions Minimum Infection Control Precautions Required for

Project: VAV Boxes – Surgery Date: January 6, 2025

CLASS V PRECAUTIONS
Before and During Work
Upon Completion

1. Construct NFPA 241 compliant barriers extending to the ceiling or if ceiling tile is removed, to the deck above.

2. Perform plastic/hard barrier construction with minimal dust release. Affix plastic barriers without gaps to the floor, walls, & ceiling using tape that will not leave a residue.

3. Seal all penetrations in barriers, including floors and ceiling, using approved materials (i.e., UL schedule firestop).

4. Construct an anteroom adjacent to the work area entrance that is large enough for equipment staging, cart cleaning, and workers.

5. Remove/isolate return air diffusers.

6. Remove/isolate supply air diffusers to prevent positive pressure of the space.

7. Maintain negative pressure and airflow for the area:

A. Airflow from entry → anteroom → construction area.

B. HEPA filter outdoor exhaust UNLESS the exhaust is >25 feet from entrances, air intakes, or open windows then HEPA filtration of exhaust is not required.

C. HEPA filter indoor exhaust AND prior to start of work, conduct particulate measurement to verify > 99.97% efficiency and confirm no change of airflow/pressure relationships in adjacent areas.

D. DO NOT exhaust into shared or recirculating HVAC systems, or other systems (e.g., bathroom exhaust).

E. Install device (e.g., magnehelic, manometer, or digital monitoring) outside the work site to continually monitor negative pressure. DO NOT use “ball in the wall” or similar apparatus.

8. Construction Waste:

A. Contain all trash and debris in the work area.

B. Transport container should be nonporous/smooth, cleanable and have a hard lid.

C. Containers must be damp-wiped clean and free of visible dust/debris before leaving the work area.

D. Use the designated route to the outside waste area.

9. Install a sticky (dust collection) mat at the entrance of the work area. Change mat routinely and when visibly soiled.

10. Worker activities and clothing:

A. Coveralls are REQUIRED while in the work area and removed before exiting the anteroom to the outside.

B. Clothing must be clean and visibly dust free before leaving the work area. HEPA vacuuming or use of cover suites is acceptable.

C. Shoe covers are required when entering the work area, changed prior to exiting the anteroom into the non-work area, and change damaged shoe covers immediately.

11. Consider collection of particulate data during work to monitor and ensure that contaminates do not enter the occupied spaces. Routine collection of particulate samples may be used to verify HEPA filtration efficiencies.

1. Construction areas must be inspected by an infection preventionist or designee and engineering representative for discontinuation or downgrading of ICRA precautions.

2. Work Area Cleaning:

A. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.

B. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.

3. Removal of Critical Barriers:

A. All (plastic or hard) barrier removal activities below must be completed in a manner that prevents dust release.

1) Remove screws & painter tape. Use hand-held HEPA vacuum if there is dust.

2) No drywall cutting during removal process.

3) Clean all stud tracks with HEPA vacuum before removing outer hard barrier.

4) Erect a plastic barrier if dust could be generated.

4. Negative Air Requirements:

A. The use of negative air must be designed to remove contaminates from the work area.

B. Negative air devices must always remain operational and in place for a period after completion of dust creating activities to remove contaminants from the work area and before removal of critical barriers.

5. HVAC systems:

A. Upon removal of critical barriers, remove isolation of HVAC system in areas where work is being performed.

B. Verify that HVAC systems are clean and operational.

C. Verify the HVAC systems meets original airflow and air exchange design specifications.

image1.emf