Information to Bidders Rocky Gap SP Pit Toilet Install BPM053960.pdf

PDF 480 KB Posted

Attached to
DNR Rocky Gap State Park TON Pit Toilet Installation
Solicitation number
BPM053960
Issued by
Allegany County, Ellicott City CDP, Maryland

About this file

Summary of Information to Bidders: Rocky Gap State Park Pit Toilet Installation

This document is an Information to Bidders notice from the Maryland Department of Natural Resources for a construction project involving the installation of a vault toilet facility at Rocky Gap State Park in Flintstone, Allegany County, Maryland. The project requires the contractor to provide all labor, equipment, materials, supplies, and insurance necessary to build, deliver, and install the toilet facility adjacent to the Touch of Nature Parking Lot at 12500 Pleasant Valley Road. A pre-bid conference is scheduled for Monday, November 17, 2025, at 10:00 AM at the project site. Bids must be submitted electronically through eMaryland Marketplace Advantage (eMMA) by Friday, November 28, 2025, at 5:00 PM. The project is classified as Class A (estimated cost up to $100,000), and work must be completed within 365 calendar days from the contract start date. All required forms and documentation must be submitted with the bid, including a Bid/Proposal Affidavit, Bidder/Offeror Information Sheet, Conflict of Interest Affidavit, Payment of Employee Health Care Expenses Certification, List of All Subcontractors, and Contract Affidavit.

This solicitation is designated for Small Business Reserve participation. The MBE (Minority Business Enterprise) subcontracting participation goal is 0%, as is the VSBE (Veteran-Owned Small Business Enterprise) goal. Award will be made to the lowest responsive and responsible bidder. Contractors will be subject to a one percent (1%) electronic transaction fee on payments from the State, which must be remitted within forty-five days of payment. If work is not completed within the specified 365-calendar-day period, liquidated damages of $350 per calendar day will apply. Bid prices are irrevocable for 120 calendar days following bid opening. Prevailing wage rates do not apply as this project is estimated under $250,000. Builder's Risk Insurance is not required for this project. The deadline for submitting written questions is November 20, 2025, at 5:00 PM. Upon notification of Intent to Award, the selected bidder must provide a Certificate of Insurance, current W-9, and Contract Affidavit within ten days.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Information to Bidders E&C Project # P-059-211-010/BPM#053960

This procurement is designated for Small Business Reserve.

NOTICE TO BIDDERS

Solicitation Fact Sheet

- PLEASE READ THOROUGHLY -

BIDS FOR THIS SOLICITATION ARE BEING ACCEPTED SOLELY ONLINE

THROUGH

https://emma.maryland.gov

Solicitation # BPM053960 DNR Project # P-059-211-010 DNR Project Title DNR Rocky Gap State Park TON Pit Toilet Installation

Project Location:

Rocky Gap State Park (12500 Pleasant Valley Road Flintstone, MD 21530 (Allegany County) (Adjacent to the Touch of Nature Parking Lot)

Procurement Officer: Shakira Johnson Procurement Email: shakira.johnson@maryland.gov Project Manager: Derek McFarland

For the purpose of this solicitation, the Department of General Services (DGS) Instructions to Bidders for Construction Projects (July 2022), and the DGS General Conditions for Construction Contracts (July 2022) have been supplemented as follows:

1. BID DUE DATE: Friday, November 28, 2025 @ 5:00 PM

2. PRE-BID CONFERENCE is scheduled for: Monday, November 17, 2025 @ 10:00

AM

LOCATION: Rocky Gap State Park (Adjacent to the Touch of Nature Parking Lot)

12500 Pleasant Valley Road Flintstone, MD 21530

3. Carefully review the Department of General Services (DGS) Instructions to Bidders for

Construction Projects (July 2022); which are attached to this solicitation; and the DGS General Conditions for Construction Contracts (July 2022).

4. The PROJECT CLASSIFICATION for this solicitation is “A” (up to $100,000).

5. PLANS AND SPECIFICATIONS:

ALL BIDDERS are directed to obtain the Project Manual directly from eMaryland Marketplace Advantage (eMMA). Please go to the “Attachments” section of the solicitation to view, print, and/or download the plans, specifications, any/all addenda, and all other related documentation.

https://emma.maryland.gov/ https://dgs.maryland.gov/Documents/ofp/GeneralConditionsforConstruction2022.pdf https://dgs.maryland.gov/Documents/ofp/GeneralConditionsforConstruction2022.pdf https://dgs.maryland.gov/Documents/ofp/GeneralConditionsforConstruction2022.pdf https://dgs.maryland.gov/Documents/ofp/GeneralConditionsforConstruction2022.pdf

ATTACHMENTS

NOTE: For this solicitation, the following forms MUST be completed and submitted with the bid. ALL forms required to be submitted with the bid must be attached to the eMMA solicitation response form as one attachment. Faxed copies or emails will not be accepted.

• Attachment A - Bid/Proposal Affidavit – submit in accordance with Item 2.B(6) in the Instructions to Bidders for Construction Projects.

• Attachment C - Bid Bond (if bid is over $100,000) – submit in accordance Item 5 in the Instructions to Bidders for Construction Projects.

• Attachment F – Bidder/Offeror Information Sheet

• Attachment I – Conflict of Interest Affidavit and Disclosure

• Attachment O - Payment of Employee Health Care Expenses Certification – submit in accordance with State Finance & Procurement Article Title 17, Subtitle 8

• Attachment P – List of All Subcontractors - Prime Contractor List of ALL

Subcontractors Anticipated/Used During Contract.

• Attachment U - Contract Affidavit.

6. MINORITY BUSINESS ENTERPRISE:

The MBE subcontracting participation goal for this solicitation is: 0%

The MBE participation shall be a percentage of the TOTAL CONTRACT VALUE.

If the bidder fails to accurately complete and submit MBE Attachment D-1A with the bid, the procurement officer shall deem the bid non-responsive and reject the bid.

Please refer to the MDOT MBE Directory at https://marylandmdbe.mdbecert.com/ to determine if a firm is certified with the appropriate North American Industry Classification System (“NAICS”) Code and the product/services description. Only those specific products and/or services for which a firm is certified in the MDOT Directory can be used for purposes of achieving the MBE participation goals.

If, for any reason, the apparent successful bidder is unable to achieve the contract goal for each certified MBE classification specified as having a subcontract goal or the overall MBE contract goal, the bidder will be contacted to document its waiver request as stated in the Minority Business Enterprise Utilization Procedures – February 5, 2021.

Please review all MBE information carefully. Refer to the Minority Business Enterprise Attachment D – February 5, 2021 for further information.

7. VETERAN OWNED SMALL BUSINESS ENTERPRISE:

Confirmation of VSBE Program Certification – eMMA is the exclusive platform to use when verifying that a veteran vendor is certified in the state’s VSBE Program. The “VSBE Certification #” field must be populated and the “VSBE Expiration Date” must https://marylandmdbe.mdbecert.com/ be valid.

The VSBE subcontracting participation goal for this Solicitation is: 0% The VSBE participation shall be a percentage of the TOTAL CONTRACT VALUE.

Please review all VSBE information carefully. Refer to “Attachment E – Veteran-owned Small Business Enterprise” for further information.

8. ELECTRONIC TRANSACTION FEE:

A. For projects with Project Classifications valued at $5,000,000.00 and below, a Contractor shall pay an electronic transaction fee to the State equal to one percent (1%) of the amount paid to the Contractor by the State for accepted work. The electronic transaction fee shall not be charged directly to the customer, e.g., as a separate line item, fee or surcharge, but shall be included in the price listed in the Contractor’s Project Quotation.

B. Within forty-five (45) days of receiving payment from the State for accepted work, the Contractor shall submit the electronic transaction fee to the Office of State Procurement: Fiscal Services Division, 301 W. Preston Street, Room 1309 Baltimore, MD, 21201.

C. Failure to remit transaction fees in a timely manner or remittance of fees inconsistent with the Contract’s requirements may result in the State exercising all recourse available under the contract including, but not limited to, a third-party analysis of all Contract activity, deeming the Contractor in default of the Contract, and Contract termination.

D. Prior to the award of a PO Agreement, the Contractor will be asked to confirm in writing that the price included in its Project Quotation includes the one percent (1%) electronic transaction fee.

9. COMPLETION TIME AND LIQUIDATED DAMAGES:

The work shall be completed within 365 calendar days from the start date of the contract. If the work is not completed within the time period specified, the contractor will be liable for liquidated damages of $350 per calendar day as specified in the “DGS General Conditions for Construction Projects (July 2022).”

10. INSURANCE REQUIREMENTS

The base bid shall include without limitation, labor, materials, bailing, shoring, removal, overhead, profit, insurance (including builder’s risk insurance, if applicable) etc.

Builder's Risk Insurance is NOT required for this project.

NOTE: Refer to the General Conditions for Construction Projects, 10.01: Insurance Requirements.

11. TIME FOR BID ACCEPTANCE:

Bid prices are irrevocable for a period of one hundred twenty (120) calendar days following bid opening. After opening bids, the Procurement Officer may request bidders to extend the time during which the State may accept their bids, provided that, with regard to bids, no other change is permitted.

12. BID SUBMISSION:

A. Bid response packages submitted in response to this solicitation must be uploaded via eMMA (https://emma.maryland.gov).

B. Prices shall be submitted via eMMA for all digital line items, referencing the Bid Response Package and Project Manual. Duplicate bid submissions will not be accepted.

C. Failure to complete all blanks in the Bid Response Package and associated attachments;

as well as, all digital line items on eMMA may result in the rejection of the contractor’s bid.

13. QUESTIONS DEADLINE:

The deadline for questions has been established as November 20, 2025 @ 5:00 p.m., to ensure that there is enough time to allow for the A/E to provide responses and possible Addendum issuance if necessary.

All questions must be submitted, in writing, to the Procurement Officer by email at shakira.johnson@maryland.gov.

14. AWARD AND EXECUTION OF THE CONTRACT:

A. The basis of the award will be to the lowest responsive and responsible bidder submitting the lowest Total Bid amount including any unit prices and alternates identified. All Unit Prices listed will be evaluated and awarded.

B. If notified by the Procurement Officer of “Intent to Award”, the following must be provided to the Department of Natural Resources via email.

a. Certificate of Insurance

b. Current W-9

c. Contract Affidavit (unless submitted with bid response)

Failure to submit these documents within 10 days of the notification of “Intent to Award” may result in the rejection of the bid.

https://emma.maryland.gov/

C. Upon review and approval of the Department and/or the Board of Public Works an executed contract will be mailed to the Contractor. The Contract issued as a result of the Bid Solicitation and any subsequent amendments, modifications or options issued relevant to the Bid Solicitation or Contract, shall comply with all of the terms, conditions and specifications issued with the Bid Solicitation and are incorporated in and made part of the Contract.

15. PAYMENT OF EMPLOYEE HEALTH CARE EXPENSES CERTIFICATION

Payment of Employee Health Care Expenses Certification, Under State Finance & Procurement Article Title 17, Subtitle 8, Form MUST be submitted with the bid. Failure to submit the form will deem the bidder as non-responsible and the bid will be rejected under

COMAR 21.06.01.01.

16. PREVAILING WAGE RATES

Prevailing wage rates apply to all contracts in the amount of $250,000.00 or more. Wage rates applicable to projects of $250,000.00 or more are attached to the specifications.

17. DETAILED SPECIFICATIONS

See the published Project Manual dated 11/04/2025.

State of Maryland · Department of Natural Resources

Instructions to Bidders for Construction Projects

July 1, 2022 Page 1

The Department of General Services Instructions to Bidders for Construction Projects, dated July 1, 2022; are hereinto adopted by the Maryland Department of Natural Resources.

July 1, 2022 Page 2

1. NOTICE TO BIDDERS:

A. GENERAL:

As provided in this document, references to “Bidder” shall be deemed to include “Offeror”, and references to “bid” shall be deemed to include “Proposal”, where appropriate. Provisions of State statutes and regulations are incorporated into the contract pursuant to COMAR

(Code of Maryland Regulations) 21.03.01.05B.

B. PROJECT CLASSIFICATION:

The Department will estimate the cost of the contract and classify it as falling within one of the following cost groups:

Estimate Class

Up to $100,000 A

$100,000 to $500,000 B

$500,000 to $1,000,000 C

$1,000,000 to $2,500,000 D

$2,500,000 to $5,000,000 E

$5,000,000 to $10,000,000 F

$10,000,000 to $15,000,000 G

Over $15,000,000 H

2. CONSTRUCTION BID REQUIREMENTS:

A. The Construction Bid Form / Price Proposal Form is that form which is part of the contract documents and which sets forth the cost of the work, unit prices (if any), and alternates (if any).

B. All bidders must comply with the following requirements:

(1) Submit a price for each line item on the bid form. Failure to submit a price for each line item will result the bid being found non-responsive. Bidders shall not provide any comments on the bid form. If comments are provided, the bid may be found non-responsive.

(2) Submit a bid bond in accordance with the requirements in Section 5, below.

(3) Complete and submit all required attachments.

(4) Submit the necessary Minority Business Enterprise (MBE) documents in accordance with the requirements in Section 4, below.

(5) Carefully review the entire solicitation and applicable instructions.

(6) Bidders must read and truthfully execute a Bid/Proposal Affidavit and must submit it with the bid. The Contract Affidavit must be executed and submitted prior to the final award of the contract.

C. Bids for construction projects being conducted by the Department are accepted solely online thru eMaryland Marketplace

Advantage (“eMMA”) unless the contract/documents specifically direct otherwise.

D. Any contractor calling itself a “joint venture” shall be, as between the contractor and the State, an ordinary partnership, whose partners are liable to the State as provided in Corporations and Associations Article, Title 9A, Subtitle 3 of the Annotated Code of

Maryland.

E. A bidder or contractor which is a partnership or joint venture must furnish the Department with a copy of the partnership or joint venture agreement prior to award.

July 1, 2022 Page 3

3. COMPONENTS OF THE BID:

A. Words not defined in these Instructions to Bidders but defined in the General Conditions shall have the meanings stated in the

General Conditions as revised July 1, 2022.

B. Definitions:

(1) “Total Bid”: The Total Bid will include: (a) the Base Bid; (b) extended Unit Price calculations, (c) Allowances, and (d)

Alternates (Add or Deduct). Alternates will be selected to be added (or deducted) in accordance with Section 17.E of these

Instructions to Bidders.

(2) “Base Bid”: The Base Bid is the price submitted on the Bid Form and will include the total cost to complete all of the work specified in the contract documents, not referenced as Alternate work or as a Unit Price, which shall include without limitation, labor, materials, bailing, shoring, removal, overhead, profit, insurance, etc.

(3) “Unit Price”: A Unit Price is the cost per unit of measure specified for materials and labor. An extended Unit Price is the

Unit Price multiplied by an estimated quantity specified in the contract documents. This cost, or extended Unit Price, shall be included in the Total Bid amount. Actual usage of Unit Price items will be verified by the Owner or Owner's representative. Adjustment to the contract sum based on actual verified usage will be made by Change Order.

Should the contractor be required to perform Unit Price work in excess of the estimated quantity specified, an equitable adjustment shall be made to the contract price, subject to Sections 3.06 and 3.07 of the General Conditions. Similarly, should the contractor perform Unit Price work less than that estimated, an equitable adjustment shall be made to the contract price, subject to Sections 3.06 and 3.07 of the General Conditions.

In determining the amount of any such adjustment to the contract price, the amount of the increase to the contract price will be calculated using the Unit Price bid by the contractor, or a reasonable price, whichever is less. The amount of any credit due the State will be calculated using the Unit Price bid by the contractor or a reasonable price, whichever is greater.

A Unit Price bid shall be the sum total price per unit for such items to include without limitation all work, labor, materials, bailing, shoring, removal, overhead, profit, insurance, etc.

(4) “Allowance”: An Allowance is a specified dollar amount to be included in the Base Bid. Allowances are established in lieu of specific requirements and defer selection of materials and equipment to a later date when additional design and/or specifications can be developed. Further information regarding Allowances is in Section 9.01 of the General Conditions.

(5) “Alternate”: An Alternate(s) is for a specific scope of work or material. Alternates may Add or Deduct. The bid price for the Alternate shall represent only the amount bid for the work associated with the Alternate and shall be the sum total price to include without limitation all work, labor, materials, bailing, shoring, removal, overhead, profit, insurance, etc. Any Completion Schedule accepted by the Department shall include all Alternate work awarded. The process for selection and award of Alternates is explained in Section 17.E of these Instructions to Bidders.

C. MINORITY BUSINESS ENTERPRISE REQUIREMENTS:

The following forms must be received by the Department with the bid:

MBE Attachment D-1A – Certified MBE Utilization and Fair Solicitation

Affidavit & Participation Schedule

Failure of the bidder to submit these properly completed forms shall result in the bid being rejected as non-responsive.

5. BID BONDS (For bids over $100,000):

A. When the sum of the total bid amount plus all add alternates, but excluding all deduct alternates, is in excess of $100,000, a bidder must furnish, prior to the bid due date, a bid bond in an amount not less than five percent (5%) of the total bid amount plus all add alternates, but excluding all deduct alternates.

B. DNR’ preferred form of bid bond is part of the contract documents. Bid bonds must provide for minimum liability of the principal and surety in the amount provided in COMAR 21.06.07.09 D (2). Bonds shall be issued by a surety licensed by the Maryland

Insurance Administration or by a surety that transacts business through an insurance agency licensed by the Maryland Insurance

Administration. The contractor may not split its bid bond among multiple sureties or bonds.

July 1, 2022 Page 4

C. Forms of bid security other than bonds are not permitted.

D. Bid bonds will not be returned to unsuccessful bidders.

E. Bidder may submit paper or electronic bid bonds in accordance with applicable provisions of this solicitation, COMAR 21.06.07, and other applicable provisions of the law.

F. BID BONDS:

(1) If a bidder is required to submit a bid bond, it must be submitted in accordance with this section. Bid bonds are also subject to Section 13-226 of the State Finance and Procurement Article of the Annotated Code of Maryland; COMAR

21.06.07; applicable provisions of Title 21 of the Commercial Law Article of the Annotated Code of Maryland; and other applicable laws.

(2) A copy of the bid bond must be uploaded to eMMA and submitted with the bid response.

(3) The bid bond must be accompanied by a properly executed power of attorney. The scanned copy of the bond and power of attorney attached to the bid and any electronic or printed copies of them shall be enforceable and admissible in evidence in all proceedings to the same extent as the original bond and power of attorney.

(4) Once a bid is submitted in eMMA with a bid bond attached to it, the bid bond shall be binding and enforceable against the principal and the surety until the contract award has been completed. Bid bonds may not be revoked, rescinded, or withdrawn by the bidder or the surety after bids are opened. Bidders and their sureties will have no liability on bid bonds after the contract is awarded, executed by the State, and sent to the successful bidder.

(5) The bid bond attached to the bid must reflect on its face that it has been executed on behalf of the principal and the surety with valid, authenticated, signatures. The power of attorney attached to the bid bond must reflect on its face that it has been executed on behalf of the surety by the requisite officer(s) and upon proper authorization. Powers of attorney must be submitted with a bid bond in PDF format. Authorization by the surety in a power of attorney of the use of facsimile seals or signatures shall constitute authorization by the surety of the attachment of the power of attorney to a bid bond by electronic means, including in PDF or other format.

(6) Nothing in these provisions changes requirements of the law concerning the responsiveness of bids. Bids accompanied by materially defective bid bonds or powers of attorney will be rejected as non-responsive.

6. PAYMENT TO CONTRACTORS:

Payments to the Contractor pursuant to this Contract shall be made no later than 30 days after the State’s receipt of a proper invoice from the

Contractor. Charges for late payment of invoices, other than as prescribed by Title 15, Subtitle 1, of the State Finance and

Procurement Article, Annotated Code of Maryland, or by the Public Service Commission of Maryland with respect to regulated public utilities, as applicable, are prohibited.

7. PAYMENT TO CONTRACTORS BY ELECTRONIC FUND TRANSFER (EFT) FOR AWARDS OVER $200,000:

EFT applies to contracts over $200,000 for which payments are made through the State Comptroller. For awards over $200,000, EFT will be used by the State to pay the contractor unless the State Comptroller’s Office grants Contractor an exemption. By submitting a response to this solicitation, the Bidder agrees to accept payments by EFT unless the State Comptroller’s Office grants an exemption. After award of a contract, the selected bidder shall register with the Comptroller of Maryland using the forms required by the Comptroller. For further information go to:

https://www.marylandtaxes.gov/divisions/gad/eft-program.php

Note: Any request for exemption must be submitted to the State Comptroller’s Office for approval at the address specified on the COT/GAD X-

10 form.

https://www.marylandtaxes.gov/divisions/gad/eft-program.php

July 1, 2022 Page 5

8. SITE INVESTIGATION:

See Section 3.02 of the General Conditions.

9. BID OPENING:

A. Bids will be opened electronically in eMMA as soon as practicable after the deadline for receipt of bids in the solicitation.

B. Competitive Sealed Bids not conducted electronically will be opened in public at the time and place stated in the solicitation.

C. This subsection C applies only when a solicitation permits the submission of bids or any necessary bid documents by means other than electronic submission on eMMA. From time to time, unforeseen circumstances may cause the State Office Building (301 W.

Preston Street, Baltimore MD) to be closed to the public. If in the event of such closure, if the State Office Building is not open to the public at least one (1) full hour immediately preceding the deadline established in the contract documents for receipt of bids or offers, the deadline for the receipt of bids or offers will be extended automatically, without further action or notice by the

Procurement Officer being necessary, to the next regularly scheduled business day at the same time and location.

D. Any bid received after the due date and time set in the solicitation is late and cannot be considered.

10. DOCUMENT SUBMISSION REQUIREMENTS AFTER THE BID OPENING:

A. Upon notification by the Procurement Officer that the bidder is the apparent low bidder, that bidder shall fully complete and return to the Procurement Officer the Contractor Questionnaire and any other requested documentation. Failure to complete and return the required documents may result in a determination that the bidder is not responsible and bid rejection.

B. If the State of Maryland or other regulatory body requires a license or certificate to perform the services required, a copy of the license or certificate shall be submitted to the Procurement Officer.

11. TIME FOR BID ACCEPTANCE:

Unless otherwise provided in the solicitation, bid prices are irrevocable for a period of one hundred twenty (120) days following bid opening.

After opening bids, the Procurement Officer may request bidders to extend the time during which the State may accept their bids, provided that, with regard to bids, no other change is permitted.

12. ALL NON-RESIDENT BIDDERS

As set forth in §14-401 of the State Finance and Procurement Article of the Annotated Code of Maryland, a non-resident bidder submitting a bid shall attach to its bid a copy of the current statute, resolution, policy, procedure, or executive order of the resident State of the non-resident bidder that pertains to that state’s treatment of non-resident bidders.

13. RIGHT TO REJECT BIDS AND WAIVE IRREGULARITIES/INFORMALITIES:

The State reserves the right to cancel a solicitation, to reject any and all bids, and to waive any minor irregularity in a bid in accordance with

COMAR 21.06.02.

14. DISCREPANCIES:

Should a bidder find discrepancies in the contract documents, or should they be in doubt as to the meaning or intent of any part thereof, they must, prior to the bid opening: (a) request and receive clarification from the Procurement Officer (who will issue a written addendum if necessary); or (b) file a protest. Failure of the bidder to request clarification will constitute a waiver of any claim by the bidder for expenses or costs of complying with the Procurement Officer’s interpretation of the contract documents after contract award. Only written addenda issued by the Procurement Officer are binding on the State. Oral or other written explanations from the State before bid opening will not be binding on the State.

15. MODIFICATIONS AND WITHDRAWAL OF BIDS:

A. Withdrawal or modification of bids will be allowed only as provided in COMAR 21.05.02.09 and .10.

July 1, 2022 Page 6

B. Mistakes in bids may be corrected only as provided in COMAR 21.05.02.12.

16. PUBLIC INFORMATION ACT:

Bidders must identify those portions of their bids which they deem to be confidential or proprietary information or trade secrets and must provide, upon demand by the Department, justification for why such materials should not be disclosed by the State upon request under the

Maryland Public Information Act, §§10-611, et seq., of the State Government Article of the Annotated Code of Maryland.

17. AWARD OF CONTRACT:

A. Unless otherwise stated in the contract documents, the basis of award will be to the responsible bidder submitting the lowest responsive Total Bid including any alternates awarded.

B. If notified by the Procurement Officer of the Department’s intent to award, the bidder shall submit the following to the Department as directed by the Procurement Officer:

(1) An executed contract (Blanket Purchase Order)

(2) Certificate of Insurance

(3) Contract Affidavit

(4) Performance and Payment Bonds, including Power of Attorney (if the total intended award value is in excess of $100,000)

Failure to submit these documents within 10 days of the notification of “Intent to Award” may result in the rejection of your bid and the Department will not be responsible for bonding costs incurred by the bidder.

C. The Department will not execute any contract unless, and until, all approvals required by law are obtained.

D. The State reserves the right to apply, before or after award of the contract, any reciprocal preference for Resident Bidders as set forth in §14-401 of the State Finance and Procurement Article of the Annotated Code of Maryland, at no additional cost to the State.

See also COMAR 21.05.01.04.

E. If alternates are solicited, one or more alternates may be awarded at the discretion of the Department in the order in which the alternates are listed in the Solicitation; provided that in the event the State lacks funds for award of the base bid and any succeeding alternate, the State in its discretion may forego the award of the alternate for which funds are not available but may award one or more succeeding alternates for which funds are available.

18. EXECUTION OF CONTRACT:

A. Upon the Department’s notification of Intent to Award following a bid, the Procurement Officer may issue a Blanket Purchase

Order ("BPO"), in a form to be determined by the Department. Both parties shall execute this document as the embodiment of the contract between the parties.

B. In the event of a conflict between provisions of the solicitation documents and the BPO, the controlling provisions shall be, in the following order: the solicitation documents; the BPO; the General Conditions; and then the bid.

C. As a prerequisite to execution of the contract, the bidder shall have furnished the following in the form and content required by the

General Conditions: (1) Performance and Payment Bonds (if required); (2) Certificates of Insurance; (3) Contract Affidavit; and (4) all other documents required by the contract documents to be furnished by the contractor as a condition of award. For minimum insurance requirements under this contract please see Section 10 of the General Conditions.

D. The Department will only execute the contract following and receipt of all approvals required by law. The Department will execute the contract within 90 days following the final approval required by law. After execution, the Department will forward the contractor a signed copy of the contract. In the event the Department fails to execute the contract within the 90-day period, the contractor will have, as its only remedy, the option: a) to declare the contract void without any liability or obligation by the State to the contractor, or b) to accept an extended period for execution by the State at no additional cost to the State.

July 1, 2022 Page 7

19. CONTRACTOR’S FAILURE TO EXECUTE CONTRACT:

Failure of the contractor to execute the contract and submit all documents required within the time provided shall be just cause for the payment of the penal sum of the bid bond or other security to the Department. In the event that the damages sustained by the State exceed the amount of the bid security, the State reserves the right to proceed against the contractor for the balance of its damages, which shall include any and all costs of obtaining the work from another source, including additional administrative costs, architects’ fees, and other costs and expenses. In the alternative, if the contractor executes the contract but fails to furnish other required documents, the State may treat the contractor’s failure to furnish the required documents as a default of the contract and may terminate the contract for default under the General

Conditions and avail itself of any other remedy provided by the contract.

20. PERFORMANCE AND PAYMENT BONDS:

A. Performance and Payment Bonds are required when the amount of the contract, including the base bid and any alternates awarded, is in excess of $100,000. Performance and Payment Bonds shall each be in the full amount of the contract price.

Performance and Payment Bonds are subject to the applicable provisions of COMAR 21.06.07.

B. Performance and payment security shall be in the form of bonds only - no other form of security will be permitted.

C. The contractor may not split its performance or payment bonds among multiple sureties.

D. Prior to the award of the contract, the State will provide the contractor with copies of the required Performance and Payment Bond forms (see COMAR 21.07.02.10). Submission of other forms is not acceptable. The bonds must be executed and returned to the

Department. Premiums for the bonds shall be paid by the contractor.

E. The Department may reject a bid on the ground that the bidder is not responsible if the bidder fails to furnish Performance and

Payment Bonds from a surety which the Department determines has in the past responded diligently and in good faith to bond claims of the State or of subcontractors and suppliers.

F. At the direction of the Department, the contractor may be required to increase the amount of the penal sum of Performance or

Payment Bonds; for such increases, the contractor will be reimbursed by the State in the amount of the actual increased bond cost incurred by the contractor. Whenever the amount of the contractor’s bonds is increased at the State’s request, the State must receive proof of the increase in satisfactory form from the surety. The State will not be liable to the contractor for any increase in bonds not requested by the State.

G. Performance Bonds:

(1) The State may declare the contractor to be in default, so as to obligate the surety to perform as required by the

Performance Bond, with or without terminating the contract for default.

(2) If the State declares the contractor to be in default, the surety has no right to require the State to contract with a contractor of the surety’s choosing. The surety must either: (a) complete the project or cure the default; or (b) allow the State to complete the project or cure or remedy the default, with the surety to remain liable to the State for excess completion costs and other damages incurred.

(3) If the State terminates the contract for default, the State has the right to prohibit the surety from using the terminated contractor to complete the work or any part of it.

H. The contractor shall submit:

(1) Two original Performance Bonds

(2) Two original Payment Bonds

(3) If the business is registered in Maryland as Sole proprietorship, Partnership, or Limited Liability Company, four Powers of Attorney (one for each bond)

(4) If the business is registered as a corporation or Corporate Principal – eight Powers of Attorney (four for the surety and four for the corporate principal)

July 1, 2022 Page 8

21. ARREARAGES TO STATE:

By submitting a response to this solicitation, a bidder represents that it is not in arrears in the payment of any obligation due and owing the

State of Maryland, including the payment of taxes and employee benefits, and that it shall not become so in arrears during the term of the contract, if selected for award.

Information to Bidders Rocky Gap SP Pit Toilet Install BPM053960.pdf
A. Bid response packages submitted in response to this solicitation must be uploaded via
eMMA (https://emma.maryland.gov).
B. Prices shall be submitted via eMMA for all digital line items, referencing the Bid
Response Package and Project Manual. Duplicate bid submissions will not be accepted.
C. Failure to complete all blanks in the Bid Response Package and associated attachments; as well as, all digital line items on eMMA may result in the rejection of the contractor’s bid.

DGS Instructions to Bidders for Construction Projects (ver03.2025).pdf