About this file

These are industry day presentation slides for a Design-Bid-Build construction project to build an Area Maintenance Support Activity (AMSA) and Vehicle Maintenance Shop (VMS) at Joint Base Elmendorf-Richardson, Alaska. The project involves constructing approximately 13,000 gross square feet of one-story facility containing vehicle maintenance work bays, tool and parts storage, office space, classroom/break area, communications and electrical repair shop, fluid storage and distribution areas, building support functions, detached SATS canopy, covered wash rack, bi-level loading ramp, water treatment facility, and fire pump and tank. The U.S. Army Corps of Engineers Louisville District is conducting the procurement under solicitation number W912QR27RA007, with a full and open (unrestricted) acquisition available to contractors registered in NAICS code 236220 (Commercial and Institutional Building Construction).

The government plans to evaluate proposals on a single-phase best value trade-off basis using three rated technical factors in order of importance: past performance evaluation, management plan, and small business participation plan, which are collectively weighted approximately equal to price. All offerors—both large and small businesses—must submit a small business participation plan; only large businesses must submit a subcontracting plan. Proposals must be submitted through the PIEE Solicitation Module by January 2027, with source selection scheduled for February 2027 and contract award targeted for March 2027. There is no Project Labor Agreement (PLA) requirement for this project. Requests for Information are submitted through ProjNet.org. The solicitation documents, technical data package, and amendments will be available on SAM.gov. Offerors must register in SAM.gov as an Interested Vendor and obtain user credentials for the PIEE system prior to proposal submission. Site visits are optional, and RFIs and responses will be publicly available through ProjNet.

View the file

Other files

File Type Posted
Industry Day Attendees_Online.pdf PDF
Industry Day Attendees_In Person.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDUSTRY DAY FORUM

area maintenance support activity (AMSA) Joint Base Elmendorf-Richardson, alaska Presenters:

Jason L. Cain – Project Manager Chris Brackett – Contracting Officer John White – Project Engineer Crystal Harbin- Deputy for Small Business

Date | Time: 26 October 2026 1000 Alaska Time

Location: Lee Reserve Center

45580 Otter Lake Road
JBER, AK 99505

”The views, opinions and findings contained in this report are those of the author(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

Safety First

Please ensure that you have signed in Company Name, POC Name, Email, Phone Are you interested in being the Prime or Subcontractor

No recording

This briefing and the attendee roster will be posted to SAM

Please be advised that none of the information discussed today is contractually-binding

ADMINISTRATIVE ANNOUNCEMENTS

USACE Procurement Process Overview

Small Business Participation and Subcontracting Requirements

Army Reserve Overview

JBER AMSA Project Overview

Other Project Opportunities

Q&A Session

AGENDA

PROCUREMENT PROCESS OVERVIEW

Chris Brackett

CONTRACTING OFFICER

USACE-LOUIVILLE DISTRICT

System for Award Management (SAM) at www.SAM.gov

Solicitation Number W912QR27RA007 (NOTE THIS CHANGE) Solicitations for USACE-Louisville begin with W912QR Search using Keyword Search Feature (Select “Any Words” or “All Words”): JBER

View Interested Vendors List and register as an Interested Vendor.

Register to receive notifications and updates / amendments.

RFP Technical Information (i.e., Plans and Specs) will be available for download from www.SAM.gov

HOW TO OBTAIN THE SOLICITATION

Pre-Solicitation Notice

– Minimum 15 days prior to Solicitation

Advertisement

– Minimum requirement of 30 days to prepare proposals – Likely 45-day advertisement due to holiday season

Amendments issued to the RFP will also be posted on www.SAM.gov and the PIEE Solicitation Module at https://piee.eb.mil/sol/xhtml/unauth/index.xhtml

OBTAINING THE ISSUE DOCUMENTS

Requirements to download Technical Data Package:

Need to be registered in System for Award Management (SAM) database. You must sign up and sign-in to your account to use many features of SAM.gov (saving searches, viewing solicitations, etc.)

Requirements to Submit Proposals:

You must register your business entity (you as an individual or your organization) to be able to propose on contracts or apply for federal assistance (grants, loans, etc.) from the Federal Government.

All proposals will be submitted through the PIEE Solicitation Module on time. Therefore, offerors must register in advance for a user ID and Password to access this system.

OBTAINING THE ISSUE DOCUMENTS

This project will be Design-Bid-Build (D-B-B) Request for Proposals (RFP)

The solicitation is a Full and Open (Unrestricted) procurement.

Project award will be made via a Single-Phase “Best Value Trade-off” basis as described in the Evaluation Criteria.

Proposals must be submitted on time.

The Louisville District is located within the Eastern time zone.

The Source Selection Evaluation Board (SSEB) will evaluate offerors’ proposals based on specific factors which are defined in the RFP Package.

THE PROCUREMENT PROCESS

This project will be a Single-Phase Design-Bid-Build Unrestricted procurement.

Source Selection Evaluation Criteria for the “Best Value Trade-Off” consists of the following elements:

1) Volume I – Factor I: Past Performance Evaluation

Relevancy - Recent projects, similar in size, scope, magnitude of effort & complexities; experience in successfully delivering the project(s) on time and within budget Quality of performance on submitted projects Other sources of relevant past performance information (i.e., CPARS, FAPIIS, eSRS)

Volume I – Factor II: Management Plan (i.e., Project Delivery Team/Staff, Resources, Collaboration, Communications Process, Quality Control, Plan to Mitigate Cost Growth and Schedule Creep, etc. . . . .)

PROPOSAL REQUIREMENTS

Section 00 22 12 will contain the proposal submission requirements and evaluation criteria. Follow the format described in Section 00 22 12 to keep the proposal in order, success is in the details. Please pay close attention to the requirements of the RFP.

For the Past Performance Factor, we will evaluate both the relevancy of experience and performance quality of prior experience. We will, at a minimum, review CPARS information available but reserve the right to check any and all sources of past performance information. This review will result in an overall assessment of confidence in performance.

For the Technical Evaluation Factors (Management Plan and Commissioning Plan), consider providing specifically tailored approaches for the solicited project. Don’t just tell us how you generally execute construction projects; tell us how you plan to execute this specific project and mitigate project specific risks (schedule, environmental, labor, etc.).

Source Selection Evaluation Criteria for a “Best Value Trade-Off” consists of the following elements:

Volume I – Factor III: Small Business Participation Plan (All - Large & Small Business Offerors)

Volume II – Pro Forma & Price Information Tab A: Standard Form 1442 & Price Tab B: Joint Venture Agreements (if applicable) Tab C: Evidence of Ability to Obtain Bonding & Proof of Financial Ability Tab D: Pre-Award Information (i.e., Reps & Certs, offeror information, etc.)

Tab E: Subcontracting Plan (Large Business Offerors only)

PROPOSAL REQUIREMENTS (CONT)

As a reminder, the Small Business Participation Plan is a rated evaluation factor and applies to all businesses, both large and small, and is based on total contract value. Only large businesses are required to submit a Subcontracting Plan.

Technical Factors listed in relative order of importance:

Volume I – Factor I: Past Performance1st
Volume I – Factor II: Management Plan2nd
Volume I – Factor III: Small Business Participation Plan3rd

All Technical Evaluation Factors, other than Price, when combined are considered approximately equal to Price.

Submit your best proposal the 1st time. If we receive an initial proposal that is awardable, discussions may not be opened.

PROPOSAL REQUIREMENTS

The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary.

No mandatory requirement for the use of Project Labor Agreement (PLA) for this project.

Louisville District performed market research regarding the use of PLAs IAW RFO 22.502-2(d).

Based on Industry feedback, an Exception from the Use of a PLA was pursued and approved by Head of Contracting Activity (HCA) in USACE.

Project Labor Agreement (PLA) – N/A

Requests for Information (RFI) Instructions for submitting a Request for Information (RFI) will be included in the Solicitation.

RFIs for these projects will be received and answered through the ProjNet system: www.ProjNet.org

Any RFIs submitted/emailed directly to the Project Team will NOT receive a response, and offerors will be directed to the ProjNet system.

A ProjNet Bidder’s Key included in the solicitation’s Project Instructions section of the RFP, which is used to post your RFIs/questions.

RFIs and their responses will be available for public review through ProjNet.

Information for an Optional Site Visit will be provided.

We will utilize the Electronic Receipt of Proposal process – Instructions will be in Section 00 21 00 of the solicitation package

Proposals are uploaded to and submitted through PIEE Solicitation Module Recommend performing a test run well in advance

Don’t wait until the last minute to upload your proposal. Late is Late! No exceptions!

PROPOSAL SUBMISSION

As mentioned earlier, all proposals will be submitted through the PIEE Solicitation Module on time. Therefore, offerors must register in advance for a user ID and Password to access this system.

****Note: Attachments will not be available in PIEE, and will be downloadable from SAM. The Solicitation and Amendments take time to fully process from PIEE to SAM. If you see the solicitation or amendment without attachments in SAM, please continue to check periodically as they will be available by the close of business (COB).

Crystal Harbin Regional Small Business Director Great Lakes and Ohio River Division

SBO-LRL@usace.army.mil

Small Business Participation Plan and Subcontracting Plan The Small Business Participation Plan is a rated evaluation factor in all unrestricted procurements Both large and small business offerors must submit a participation plan

The participation plan is based on total contract value

Large Business offerors must submit a Small Business Subcontracting Plan Mandated by FAR 19.109

This is not a rated element as a part of the Source Selection process; however, the offeror shall submit an acceptable plan prior to award

The subcontracting plan is based on total subcontracted dollars Every option must be broken out separately.

Failure to comply in good faith is in material breach of the contract

Attend Industry Days, Pre-Proposal Conferences, and Site Visits Obtain copies of attendee listings for subcontracting opportunities Register as an interested Vendor on SAM

Attend Workshops, Conferences, Trade Fairs Annual Louisville District Open House will be held 03 February 2027

Review Forecast, https://www.lrd.usace.army.mil/Business-With-Us/ Obtain Information

Contracting opportunities are posted in the System for Award Management (SAM) website at www.sam.gov. Use “W912QR” to search for Louisville District projects.

Actively Respond to Sources Sought Notices (Market Surveys) posted to SAM Actively respond to PLA Surveys posted to SAM

Actively Respond to Competitive Requirements posted to SAM

To view Louisville District prime contract holders, please visit https://www.lrd.usace.army.mil/Business-With-Us/ Additional Opportunities

US Army Reserve OVERVIEW

Jason L. Cain Program Manager U.S. Army Corps of Engineers Louisville District

Army reserve program

JBER, AK

Area Maintenance Support Activity PROJECT

CHRIS DRUMMOND

Design Team Lead Michael Baker International

JOHN WHITE

Project Engineer US Army Corps of Engineers Louisville District

JASON L. CAIN

Project Manager US Army Corps of Engineers

Project site overview

Architectural site plan

VMS | AMSA Work bays 10-ton bridge crane w/ 20’ hook height Eye wash stations Equipment Alcoves Safety Aisle Roof Access Ships Ladder Drinking fountains

Workforce Facilities Admin offices and open office work areas Classroom / break room Tools and Parts Storage Library Latrines and locker rooms POV parking lot

Operational Support Wash rack with concrete apron Tracked vehicle parking area Heated Organizational Storage Building

Safety and Environmental Hazmat, controlled waste & battery storage Fluid distribution system Oil / water separator Fire protection

Security ATFP and Physical Security compliant Intrusion Detection System

Facility Requirements Mechanical, Electrical, Telecom Rooms

PROJECT KEY FEATURES

RENDERING

Floor plan

Project Schedule (Subject to Change)
Industry Day Forum26 OCT 2026
DBB Solicitation Posted to SAMDEC 2026
Proposals DueJAN 2027
Source Selection BoardFEB 2027
DBB Construction Contract AwardMAR 2027
Admin NTPMAR 2027
Construction NTPAPR 2027

PROJECT SCHEDULE

Other PROJECT OPPORTUNITIES

Jason L. Cain Program Manager U.S. Army Corps of Engineers

Project: Equipment Concentration Site [Warehouse + AMSA + MEP lot] Location: Ft Carson, CO Acquisition: OTA - Construction Management At Risk

Construct an Equipment Concentration Site (ECS) on Fort Carson, CO. Primary facilities include an Area Maintenance Support Activity (AMSA) shop and General Purpose (GP) Warehouse. Facilities will be designed in accordance with the Army Reserve Design Guide. Supporting facilities include land clearing, general site improvements, organizational parking, non-organizational parking, concrete parking, concrete aprons, vehicle wash rack/platform, bi-level equipment loading ramp, fencing, walks, signage, curbs and gutters, storm drainage, SATS Trailer canopy, information systems, and utility connections. Supporting Facilities costs are higher than average due to special building foundations, extensive pavements, improved surfaces, site clearing, and excavation costs associated with developing the 48-acre parcel of land. Sustainability/Energy and cybersecurity measures are included.

Aerial View of the Project Site

Site Layout

General purpose warehouse + Area Maintenance support activity floor plan

Renderings

Project: New Training Barracks Location: Ft Hunter-Liggett, CA Acquisition: OTA – Progressive Design Build

The primary scope of work delivers four (4) CTE Barracks and one (1) IPIMT Barracks to restore modern housing capabilities to the installation. The four (4) CTE Barracks will each span approximately 46,000 square feet, utilizing open-bay configurations equipped with integrated officer sleeping rooms, team rooms, laundry facilities, restrooms, showers, storage, and janitorial closets.

Complementing these collective spaces, the single 45,000-square-foot IPIMT Barracks will provide individual sleeping quarters with private bathrooms, study/day rooms, laundry rooms, storage, and janitorial closets.

Also, part of this project is to completely demolish and dispose of the five existing legacy multi-story barracks that have exceeded their useful life. This comprehensive replacement directly resolves critical facility deficits, bringing Fort Hunter Liggett's training housing into full alignment with modern operational requirements.

Ft Hunter-Liggett – New Training Barracks Location of new CT Barracks

COA –

Demo four CT Barracks. All barracks are three-story with load bearing masonry construction.

Construct four 3-story CT Barracks (300 beds each).

BuildingBeds CurrentNew Bedspaces after Construction
205360300
207360300
208360300
230360300
Total14401400

Existing four CT Barracks to be demolished

Ft Hunter-Liggett – New Training Barracks Location of new IPIMT Barracks

COA –

Demo existing 156 IPIMT Barracks.

Construct new 156 two or three story IPIMT Barracks.

BuildingBeds CurrentNew Bedspaces after Construction
229156156

Existing IPIMT Barracks to be demolished

QUESTIONS | DISCUSSIONS

Directions to SITE VISIT

FROM LEE RESERVE CENTER

Take a left out of the parking lot onto Otter Lake Dr

Slight right onto D Street followed by an immediate right into the Navy Reserve Center Parking lot

Meet at the southwest corner of the existing USAR AMSA facility image3.png image4.png image7.png image8.png oleObject1.bin image9.emf image10.png image11.png image12.png image13.png image14.png image15.png image16.png image17.png image18.png image19.png image20.png image21.jpeg image22.jpeg image23.jpeg image24.png image25.png image26.png image27.jpeg image1.png image2.png image5.png image6.png

File details come from the government source that posted it. Updated .