INDUSTRY DAY: SURVIVABLE AIRBORNE OPERATIONS CENTER (SAOC), Offutt AFB, NE (SAOC) CONSTRUCTION
Solicitation number
Not on record
Issued by

About this file

This document is an industry day presentation for the Survivable Airborne Operations Center (SAOC) Beddown at Offutt Air Force Base, Nebraska, conducted by USACE Omaha District. The presentation outlines a military construction program to support the replacement of the aging E-4B Nightwatch aircraft with the newer E-4C SAOC platform, with Sierra Nevada Corporation awarded a $13.08 billion contract in April 2024. The Air Force approved Offutt AFB as the preferred beddown location on May 6, 2024, pending NEPA completion estimated for September 2026.

The SAOC beddown project comprises five major facilities under a Design-Bid-Build acquisition model: (1) a 2-Bay Maintenance Hangar with Ramps and Taxiway (280,000 SF facility plus 56 acres of paving, $500M+ magnitude, target FY28 award, 42-month duration) with an Ignitable Liquid Drainage Floor Assembly and 254-foot clear span doors; (2) a 1-Bay Fuel Cell Hangar (129,000 SF, $250M-$500M, target FY30 award, 36 months); (3) Operations and Training Facility (133,000 SF, $250M-$500M, target FY28 award, 36 months); (4) Fire Station (15,000 SF, $25M-$100M, target FY29 award, 36 months); and (5) Supply Storage Facility (160,000 SF, $100M-$250M, target FY29 award, 30 months). The acquisition is structured as an unrestricted, firm fixed-price contract using a best-value trade-off bifurcated selection process. NAICS code 236220 applies with a $45 million small business size standard. Key considerations include Project Labor Agreement requirements (pending market research outcomes and litigation resolution), CMMC Level I self-assessment requirements, bonding, and site environmental remediation including PFAS and lead contamination. Ramps and Taxiway utilizes government design while the 2-Bay Hangar uses non-government architect-engineer design. Design contracts are being executed through USACE MATOCs with the 35% Relative-to-Award hangar design posted for award in December 2025 (target award May 2026). Questions may be submitted via ProjNet through Jessica Jackson (jessica.r.jackson@usace.army.mil) or Margarette Wolfe (margarette.e.wolfe@usace.army.mil).

View the file

Other files

File Type Posted
Industry Day In-Person Sign In Sheets_.pdf PDF
SAOC Industry Day Attendence List.pdf PDF
Industry Day Project Info Read Ahead.pptx PPTX presentation

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SURVIVABLE AIRBORNE

OPERATIONS CENTER

(SAOC) BEDDOWN AT

OFFUTT AFB, NE

USACE Omaha District

Graphic images used throughout prepared by USACE, USAF, Burns & McDonnell, Sierra Nevada Corp.

• Existing E-4B Nightwatch entered service 1974. Requires replacement

• April 2024: Sierra Nevada Corp. awarded $13.08B contract to replace E-4B with E-4C

SAOC

• Currently acquiring and outfitting new airframes in Dayton, OH

• AF approved Offutt AFB, NE as preferred location on 06 May 2024, pending NEPA

• Led by Air Force Global Strike Command (AFGSC, Barksdale)

• Environmental Assessment – Ongoing

• Estimated completion – Sept 2026

SAOC BACKGROUND, BASING, AND BEDDOWN

Aircraft

Specifications E-4B

(Boeing 747-200) E-4C

(Boeing 747-8i)

Length 231’ 10” 250’ 2”

Wingspan 195’ 8” 224’ 7”

Height 63’ 5” 63’ 6”

Quantity 4 6 to 8

• US Army Corps of Engineers (USACE)

• Design, procurement, and field level construction agent for the beddown

• Air Force Civil Engineer Center (AFCEC)

• Official point of contact and authority for the Air

Force for the bed down of facilities

• Air Force liaison to USACE

• Air Force Global Strike Command (AFGSC)

• Primary user command.

• AF Installation & Mission Support Center Detachment 10 (AFIMSC Det-10)

• Represents AFGSC and provides program policy, guidance, and goals

• AF Life Cycle Management Center (AFLCMC)

• SAOC Program Office

• OAFB SAOC Program Integration Office (OAFB

SAOC PIO)

• Responsible for integration/coordination of SAOC requirements into existing conditions and mission set at OAFB, NE

• Responsible for coordination of all end-user requirements into beddown impacted facilities

• 55 Civil Engineer Squadron, Offutt AFB

• Accepting authority for real property

• Responsible for ensuring facilities meet base requirements

GOVERNMENT STAKEHOLDERS

PROGRAM OVERVIEW

2-Bay Maintenance Hangar with Ramps and Taxiway

- FY28

- CWE: $500M+

1-Bay Fuel Cell Hangar

- FY30 (est.)

- CWE: $250M - $500M

Operations Training Facility

- FY28

- CWE: $250M - $500M

Fire Station

- FY29 (est.)

- CWE: <$100M

Supply Storage Facility

- FY29 (est.)

- CWE: $100M - $250M

3 2

0. Planning Charrette Reports

• Contract complete

1. 2-Bay Maintenance Hangar

• PCR to 35% through USACE Unrestricted MATOC

– Contract awarded

• 35%-RTA Design to be separate, stand-alone contract.

– Posted: December 2025 » https://sam.gov/workspace/contract/opp/43b8752297604

16a90e45c92706466aa/view

– Target award: May 2026

Ramp and Taxiway

• 100% design through USACE in-house designers

2. 1-Bay Fuel Cell Hangar

• 100% design stand-alone contract or MATOC (FY27)*

3. Operations and Training Facility

• 100% design through USACE Unrestricted MATOC

4. Fire Station

• 100% design through USACE-Omaha MATOC (FY26)*

5. Supply Storage Facility

• 100% design through USACE-Omaha MATOC (FY26)*

SAOC BEDDOWN DESIGN

AE action complete AE action ongoing AE action not started

Sec 2814 - AUTHORITY FOR ADVANCE PROCUREMENT.—A Secretary of a military department may enter into one or more contracts for an advance procurement associated with a military construction project for which authorization to enter into a multiyear contract is provided under subsection (a)…

FY26 NDAA

Description of Project

• 2-bay hangar to fully enclose two 747-8i aircraft

• Contractor logistic support warehouse

• Secure spaces

• Site fill

• Aircraft parking apron for seven E-4Cs

• Airfield infrastructure

• Demolition of existing hangar

• Fuel system upgrades

• Unique phasing requirements

• May include O&M options for FF&E, A/V, ESS, etc.

Acquisition

• Incrementally funded

• Bifurcated Best Value Trade Off selection process

– Vol. I Technical Target Advertise: FY26Q4

– Vol. II Pricing Target Advertise: FY27Q2

SAOC 2-BAY MAINTENANCE HANGAR WITH RAMPS

AND TAXIWAY

Note: All project information is provided for information only, is considered approximate, and is subject to change without notice.

Size: +/- 280,000 SF (facility) +/- 56 acres (paving) Type: MILCON Contract Type: Design-Bid-Build Magnitude: $500M+ Target Award: FY28 Estimated Duration: 36 mo.

SAOC 1-BAY FUEL CELL HANGAR

Description of Project

• 1-bay fuel cell hangar to fully enclose 747-8i aircraft

• Limited corrosion control activities

• Support warehouse

• Airfield apron and infrastructure

• Admin and support spaces

• May include O&M options for FF&E, A/V, ESS, etc Acquisition

• Bifurcated Best Value Trade Off selection process

– Vol. I Technical Target Advertise: FY29 (est.)

– Vol. II Pricing Target Advertise: FY30 (est.)

Note: All project information is provided for information only, is considered approximate, and is subject to change without notice.

Size: +/- 129,000 SF Type: MILCON Contract Type: Design-Bid-Build Magnitude: $250M - $500M Target Award: FY30 (est.)

SAOC OPERATIONS AND TRAINING FACILITY

Description of Project

• Aircrew mission trainer

• Maintenance equipment trainers

• Full motion and static flight simulators

• Secure spaces

• Admin and support spaces

• Temporary utilities

• Site fill

• May include O&M options for FF&E, A/V, ESS, etc.

Acquisition

• Best Value Trade Off selection process

– Target Advertise: FY27Q4

– Target Award: FY28Q2

Note: All project information is provided for information only, is considered approximate, and is subject to change without notice.

Size: +/- 133,000 SF Type: MILCON Contract Type: Design-Bid-Build Magnitude: $250M - $500M Target Award: FY27Q4

SAOC FIRE STATION

Description of Project

• Standard small to medium size fire station

• Site fill

• May include O&M options for FF&E, A/V, ESS, etc.

Acquisition

• Best Value Trade Off selection process

– Target Advertise: FY28Q4

– Target Award: FY29

Note: All project information is provided for information only, is considered approximate, and is subject to change without notice.

Size: +/- 15,000 SF Type: MILCON Contract Type: Design-Bid-Build Magnitude: $25M - $100M Target Award: FY29

SAOC SUPPLY STORAGE FACILITY

Description of Project

• Contractor logistic support warehouse

• Pre-Engineered Metal Building

• Entry control point

• Admin and support spaces

• May include O&M options for FF&E, A/V, etc.

Acquisition

• Best Value Trade Off selection process

– Target Advertise: FY28Q4

– Target Award: FY29

Note: All project information is provided for information only, is considered approximate, and is subject to change without notice.

Size: +/- 160,000 SF Type: MILCON Contract Type: Design-Bid-Build Magnitude: $100M - $250M Target Award: FY29 (est.)

Estimated Duration: 30 mo.

PHASING SEQUENCE

2-Bay Maintenance Hangar with Ramps

Operations & Training Facility

Beddown Project List

2-Bay Maintenance Hangar with Ramps

Operations & Training Facility

Beddown Project List

Fire Station4 Supply Storage Facility5

1-Bay Maintenance Hangar

Operations & Training Facility

Beddown Project List

Fire Station4 Supply Storage Facility5

2-Bay Maintenance Hangar with Ops AMU1

1-Bay Maintenance Hangar2

Beddown Project List

Fire Station4

2-Bay Maintenance Hangar with Ops AMU1

1-Bay Maintenance Hangar2 Beddown Project List4

• Features of work

• Site

• ~800,000 CY fill

• Demolition of existing hangar

• PFAS and lead contamination

• Site dewatering

• De-icing operations

• Common utilities

• Ramps and Taxiway

• +/- 56 acres of paving

• Extension/expansion of Type III Fueling System

• In-Pavement and/or microwave Intrusion Detection System

• Utiliduct servicing a/c parking positions

• Concrete batch plant (constrained site)

• Phasing constraints for tie-in to existing airfield

• 2-Bay Hangar

• Ignitable Liquid Drainage Floor Assembly (ILDFA)

• 254-foot clear span hangar doors

• Contractor Logistic Support (CLS) and Combined Tool Kit (CTK) warehouse space

• ~80,000 SF office space

• 4.5 acres of hangar floor (44.5 NCAA Basketball Courts)

SAOC 2-BAY MAINTENANCE HANGAR WITH RAMPS

AND TAXIWAY

HEAT MAP

ILDFA

•Hollow aluminum extruded floor with a perforated top surface, connected to a trench system to remove any spilled liquid to an acceptable location

•Designed to contain and remove ignitable liquid spills before they develop into a pool fire

SITE ENVIRO

SAOC TWO-BAY HANGAR

WITH RAMPS AND TAXIWAY

ACQUISITION

Jessica Jackson Contracting Officer Military Construction Branch (Contracting) USACE Omaha District

Graphic images used throughout prepared by USACE, USAF, Burns & McDonnell, Sierra Nevada Corp.

• PLEASE REGISTER! https://www.surveymonkey.com/r/R5B8MQX

• Objective of Today’s Event – Government’s Benefit

• Industry Day ProjNet Info:

Project ID: SAOC Project Name: SAOC Program Industry Day Bidder Inquiry Key: ARXZ4J-WMPBZV

Sensitive or Proprietary Questions may be emailed to Maggie Wolfe (margarette.e.wolfe@usace.army.mil) and Jessica Jackson (jessica.r.jackson@usace.army.mil)

• Interested Vendors Listing in SAM.gov

ACQUISITION PREFACE

https://www.surveymonkey.com/r/R5B8MQX mailto:margarette.e.wolfe@usace.army.mil mailto:jessica.r.jackson@usace.army.mil

• Firm Fixed Price Construction Design-Bid-Build (DBB) RFP

• Best Value Trade-off, Bi-furcated

• NAICS 236220, Commercial and Institutional Building Construction

• SB Size Standard - $45M

• Consolidated Effort

• Currently Ramps and Taxiway and the Two-Bay Hangar have separate DD1391s.

• Consolidation subject to approval

• Two-Bay Hangar is incrementally funded (FY28-FY30)

• Ramps and Taxiway is Government design

• Two-Bay Hangar is non-Government A-E design

• Magnitude of Construction for consolidated effort >$500M

• Unrestricted

• Subject to outcome of Market Research

– Bonding

– PLAs

– CMMC

– Sources Sought/PLA Survey ~Feb-Mar 2026 timeframe

ACQUISITION OVERVIEW

• BLUF: PLA will be included unless the results of Market Research indicate inclusion will limit competition. PLAs are not an evaluation factor but (if included) is a condition of award.

BACKGROUND: Beginning in 2009, PLAs were considered optional for construction projects over $25 million dollars in value under a prior Executive Order (EO) 13502.

• On February 4, 2022, President Biden signed EO 14063, entitled “Use of Project Labor Agreements for Federal Construction.” Under EO 14063, the President required PLAs for all construction projects over $35 million dollars in value, subject to exceptions and terms in EO 14063. EO 14063 also directed the FAR Council to promulgate FAR provisions codifying EO 14063 in the FAR, resulting in FAR Subpart 22.5. See FAR 22.501.

• Extensive litigation followed until the decision in MVL USA, Inc. v. United States, 174 Fed. Cl. 437, 463 (2025), which found that a PLA requirement may or may not be acceptable, depending on the circumstances in an individual solicitation.

• On February 7, 2025, the Undersecretary of Defense issued a memorandum that introduced a Class Deviation waiving the PLA requirement. That memorandum was successfully challenged and enjoined in the case of North America’s Building Trades Unions (NABTU) v. Department of Defense et al., No. 1:25-cv-01070 (DDC May 16, 2025).

• The Class Deviation was rescinded on June 2, 2025. Thereafter, DoD agencies were required to follow the FAR Subpart 22.5 requirements.

• December 18, 2025, the U.S. Court of Federal Claims ruled in Brasfield & Gorrie, LLC v. United States, COFC Case No. 25-1140, that a requirement to use a PLA on a large-scale federal construction project (contract value over $35 million) violates the Competition in Contracting Act (CICA). The court further issued a permanent injunction removing the PLA requirement from the challenged solicitation.

• USACE Districts are awaiting implementation guidance from DOJ and HQUSACE, in light of the Brasfield decision. It is possible that an appeal could be filed with the Court of Appeals for the Federal Circuit.

PLA

• Level I – Self-Assessment

• Effective 10 Nov 2025 CMMC is required for all non-COTS acquisitions >$10k

• DFARS Clause 252.204-7021 will apply

• Prior to award, the Contracting Officer must verify in SPRS the awardee holds a current CMMC that meets or exceeds the level required for the action.

• IAW DFARS 252.204-7021, the definition of current for a Level I Self-Assessment is, “not older than 1 year with no changes in compliance with the requirements at 32 CFR part 170 since the Conditional CMMC Status date and a corresponding affirmation of continuous compliance, not older than 1 year, by an affirming official

• Further, IAW DFARS 204.7501(b), Contracting officers shall not exercise an option period or extend the period of performance on a contract, task order, or delivery order, unless the contract has a current (i.e., not more than 3 years old) CMMC certificate at the level required by the contract, task order, or delivery order.

CMMC

QUESTIONS FOR INDUSTRY

General

• What risks do you see with the current approach?

• How do we make it easier/more appealing to the market?

• What are we not thinking about?

• PLA

• CMMC

• Bonding

• Addressing PFAS

• What is your estimated cost for the 2-Bay with Ramps? Magnitude of Construction is >$500M

Estimated construction durations too aggressive, or not aggressive enough?

• 2-Bay with Ramps and Taxiway – 42 months

• O&TF – 36 months

• Supply Storage – 24 months

• 1-Bay – 30 months

THAT’S ALL FOLKS

Questions/Comments:

PROJNET

Jessica.R.Jackson@usace.army.mil Margarette.E.Wolfe@usace.army.mil

Survivable airborne operations center (Saoc) beddown at Offutt afb, ne
Saoc background, basing, and beddown
Government stakeholders
Program overview
Saoc beddown Design
FY26 NDAA
SAOC 2-Bay Maintenance hangar with ramps and taxiway
SAOC 1-bay fuel cell hangar
SAOC operations and training facility
SAOC fire station
SAOC supply storage facility
Phasing sequence
Slide Number 14
Slide Number 15
Slide Number 16
Slide Number 17
Slide Number 18
Slide Number 19
Saoc 2-bay maintenance hangar with ramps and taxiway
Heat map
ildfa
Site enviro
SAOC Two-bay hangar with ramps and taxiway acquisition
ACQUISITION PREFACE
ACQUISITION OVERVIEW
PLA
CMMC
Questions for INDUSTRY
That’s all folks