Construction of Roundabout at the Intersection of IL 162
Solicitation number
97877
Issued by
Madison County, Illinois

About this file

This is a Notice to Bidders and Special Provisions document issued by the Illinois Department of Transportation (IDOT) for the construction of a roundabout at the intersection of Illinois Route 162 and Old Troy Road in Madison County, Troy, Illinois. The project (Contract No. 97877, Section 17-00034-00-PV) involves comprehensive site improvements including traffic control and protection with full closure of IL 162 and Old Troy Road, construction layout, clearing and grubbing with tree protection, excavation and embankment work using onsite material, storm sewer and inlet installation with pipes up to 30 inches in diameter, erosion controls, lighting foundations and conduit, utility relocation accommodation, aggregate base installation, hot-mix asphalt stabilized subbase, concrete curb and gutter, jointed and stamped colored concrete pavement, raised reflective pavement markers, and pavement markings. Electronic bids must be submitted to the iCX system prior to 12:00 p.m. on November 6, 2026. The project allows a 60-consecutive-calendar-day full closure of IL 162 between May 25, 2027 (or the last day of Maryville Christian School attendance) and August 1, 2027, with an additional 40 working days permitted after the specified completion date to finalize all project work. The contract will be awarded to the lowest responsive and responsible bidder.

The contract includes liquidated damages of $6,750.00 per calendar day for failure to meet the completion date. Funding is derived from Federal-aid construction funds and District 8 Construction Funds. The project involves significant utility coordination, including existing and proposed ATT copper and fiber optic lines, Ameren natural gas distribution lines and high-pressure gas mains, Southwestern Electric Cooperative overhead and buried electric lines, Illinois American Water and City of Troy potable water mains, and agricultural tile drains. The document specifies numerous special provisions addressing specific work requirements including storm water pollution prevention plan (SWPPP) compliance under NPDES permit ILR10, removal and disposal of regulated substances at multiple PESA sites with documented contamination, pavement specifications and testing requirements, traffic control protocols, and quality assurance/quality management standards. A disadvantaged business enterprise (DBE) participation provision is indicated as revised effective July 2, 2026.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting November 6, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 97877 MADISON County Section 17-00034-00-PV (Troy) Route FAP 586A (Il 162) Project AT03-347 () District 8 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

November 6, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 97877 MADISON County Section 17-00034-00-PV (Troy) Project AT03-347 () Route FAP 586A (Il 162) District 8 Construction Funds

Construction of roundabout at the intersection of IL 162 and Troy Rd. in the city of Troy. Work includes PCC pavement, storm sewer, curb & gutter, roadway lighting and pavement markings.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

CONTRACT 97877

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)

3 EEO

4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS

Table of Contents

CHECK SHEET # PAGE NO.

LRS 1 Reserved LRS 2 Furnished Excavation LRS 3 Work Zone Traffic Control Surveillance LRS 4 Flaggers in Work Zones LRS 5 Contract Claims LRS 6 Bidding Requirements and Conditions for Contract Proposals LRS 7 Bidding Requirements and Conditions for Material Proposals LRS 8 Reserved LRS 9 Bituminous Surface Treatments LRS 10 Reserved LRS 11 Employment Practices LRS 12 Wages of Employees on Public Works LRS 13 Selection of Labor LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS 15 Partial Payments LRS 16 Protests on Local Lettings LRS 17 Substance Abuse Prevention Program LRS 18 Multigrade Cold Mix Asphalt LRS 19 Reflective Crack Control Treatment

Troy-Maryville, Illinois IL 162 & Old Troy Road RAB, 2025

Section 17-00034-00-PV

Contract 97877

Table of Contents to Special Provisions

LOCATION OF PROJECT 1

DESCRIPTION OF PROJECT 1

STATUS OF UTILITIES 2-3

AVAILABILITY OF ELECTRONIC FILES 4

ROUNDABOUT CLOSURE 4

COMPLETION DATE PLUS WORKING DAYS 4

CONSTRUCTION LAYOUT 5

SEQUENCE OF OPERATIONS 5

TRAFFIC CONTROL AND PROTECTION PLAN 5-6

TRAFFIC CONTROL AND PROTECTION, SPECIAL 6

REMOVE EXISTING SIGN COMPLETE 6

REMOVE AND RELOCATE EXISTING SIGN PANEL 6-7

CLEARING AND GRUBBING 7

STORM SEWER REMOVAL 7

REMOVE EXISTING FLARED END SECTION 7

REMOVAL AND DISPOSAL OF UNSUITABLE MATERIAL 7-8

UNLOCATED SUMP LINES AND DOWNSPOUTS 8

SELECT GRANULAR BACKFILL, SPECIAL 8-9

PROPOSED STORM SEWER CONNECTION TO EXISTING STORM SEWER 9

TOPSOIL EXCAVATION AND PLACEMENT 9-10

EARTH EXCAVATION 10-11

FURNISHED EXCAVATION 11-12

AGGREGATE SUBGRADE IMPROVEMENT 12

SUBBASE GRANULAR MATERIAL 12

AGGREGATE FOR TEMPORARY ACCESS 12

STABILIZED SUBBASE – HOT-MIX ASPHALT, 4” 12-13

COMBINATION CONCRETE CURB AND GUTTER, TYPE B (MODIFIED) 13

DETECTABLE WARNINGS 13

PAINT CURB 13-14

PORTLAND CEMENT CONCRETE PAVEMENT 9” (JOINTED) 14-15

STAMPED PORTLAND CEMENT CONCRETE PAVEMENT 9” (JOINTED) 15-16

STAMPED PORTLAND CEMENT CONCRETE MEDIAN SURFACE 6 INCH 16

LANDSCAPING GRAVEL 16-17

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES 17-18

NON-SPECIAL WASTE DISPOSAL INTERPRETATION 19

PORTLAND CEMENT CONCRETE SHOULDERS 19

GULBOX JUNCTION, COMPOSITE CONCRETE 19

ELECTRIC CABLE IN CONDUIT, 600V (XLP-TYPE USE) 20

JUNCTION BOX (SPECIAL) 20-21

STORM WATER POLLUTION PREVENTION PLAN (SWPPP) 22-32

SPECIAL PROVISION FOR INSURANCE (LR107-4) 33

SUBMITTAL OF EEO/LABOR DOCUMENTATION 34-35

LOCAL QUALITY ASSURANCE/QUALITY MANAGEMENT QC/QA (LR 1030-2) ----------- 36-37

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING ---------------------------- 38-39

BDE SPECIAL PROVISIONS

The following special provisions indicated by an “X” are applicable to this contract. An * indicates a new or revised special provision for the letting.

File Name Pg. Special Provision Title Effective Revised 80099 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 _ 80274 40 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 Automated Flagger Assistance Device Jan. 1, 2008 April 1, 2023 80173 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017 80426 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 April 1, 2026 80475 Bridge Deck Concrete Overlays Jan. 1, 2026 80241 Bridge Demolition Debris July 1, 2009

5053I Building Removal Sept. 1, 1990 Aug. 1, 2022 5026I Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022

80460 43 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 60 Compensable Delay Costs June 2, 2017 April 1, 2019 80198 Completion Date (via calendar days) April 1, 2008 80199 Completion Date (via calendar days) Plus Working Days April 1, 2008 80461 Concrete Barrier Jan. 1, 2025 80453 Concrete Sealer Nov. 1, 2023 80261 64 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 Deck Slab Repair Jan. 1, 2026

* 80029 66 Disadvantaged Business Enterprise Participation Sept. 1, 2000 July 2, 2026

* 80486 Engineer’s Field Office Nov. 1, 2026 80467 Erosion Control Blanket Aug. 1, 2025 80229 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 Guardrail Nov. 1, 2025 80472 High Friction Surface Treatment Nov. 1, 2025 80456 70 Hot-Mix Asphalt Jan. 1, 2024 April 1, 2026 80446 Hot-Mix Asphalt – Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024 80483 Inlet Filters April 1, 2026 80477 Longitudinal Tining Jan. 1, 2026 July 1, 2026 80450 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 74 Pavement Marking April 1, 2025 Nov. 1, 2025 80468 Pavement Patching Aug. 1, 2025 80441 75 Performance Graded Asphalt Binder Jan 1, 2023 April 1, 2026 80459 Preformed Plastic Pavement Marking June 2, 2024 3426I Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 81 Raised Reflective Pavement Markers Nov. 1, 2025 80455 82 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2026 80474 Residential Driveway Temporary Signal Nov. 1, 2025 80445 84 Seeding Nov. 1, 2022 July 1, 2026

* 80457 Short Term and Temporary Pavement Markings April 1, 2024 Nov. 1, 2026 80462 90 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 Sinusoidal Rumble Strips Jan. 1, 2026 80469 Slope Wall Aug. 1, 2025 80448 92 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 94 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 Structural Repair of Concrete Jan. 1, 2026 80397 96 Subcontractor and DBE Payment Reporting April 2, 2018 80391 97 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019

File Name Pg. Special Provision Title Effective Revised 80463 98 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025 80482 99 Submission of Payroll Records – Federal Aid Contract April 1, 2026 80437 Submission of Payroll Records – State Contract April 1, 2021 April 1, 2026 80435 101 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 107 Surveying Services April 1, 2025 80481 Temporary Concrete Barrier Jan. 1, 2026 80466 Temporary Rumble Strips April 1, 2025 80484 Tolerance in Thickness for Continuously Reinforced PCC Pavement July 1, 2026 80470 Traffic Signal Backplate Aug. 1, 2025 20338 108 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022

* 80439 111 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2026 80458 Waterproofing Membrane System Aug. 1, 2024 80302 112 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 Wood Sign Support Nov. 1, 2023 80427 113 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026 80485 116 Work Zone Width Restriction July 1, 2026 80071 Working Days Jan. 1, 2002

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1, 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of FAP Route 586 (Illinois Route 162), and FAU Route 8898 (Old Troy Road), Project AT03(347), Section 17-00034-00-PV, Madison County, and in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.

FAU Route 586 (Illinois Route 162) Project AT03(347)

Section 17-00034-00-PV Madison County

Contract No. 97877

LOCATION OF PROJECT

This project is located along Illinois Route 162 at its intersection with Old Troy Road. Just to the east of said intersection, the Madison County Transit (MCT) Goshen Trail, a walking and bicycling trail, goes over Illinois Route 162 via a small pedestrian bridge. The project begins at the east entrance to the First Baptist Church of Maryville, along IL 162, extends under the trail bridge, to a point at Kennedy Drive. The project extends northward from Il 162, to the southmost entrance of the MCT Goshen Trail parking area along Old Troy Road.

DESCRIPTION OF PROJECT

The project consists of: traffic control and protection for a full closure of IL 162 and a portion of

Old Troy Road, with detours; construction layout; some brush removal and protection of small trees; excavation and embankment work with onsite material; removal and disposal of non-special waste earth; the employ of testing of excavation work throughout the project, furnished excavation to be hauled and placed at the site; storm sewer and inlet trenching, with pipes up to 30” in diameter; erosion controls for a project SWPPP; lighting foundations and conduit; accommodation of any remaining utility relocation work; aggregate bases; hot-mix asphalt stabilized subbase under PCC pavement; combination concrete curb and gutter and medians; jointed plain concrete pavement; stamped colored pavement and medians; raised reflective markers; and pavement marking on HMA and PCC.

STATUS OF UTILITIES:

Utility Type Location Status /Adjustments

ATT Copper & FO N & S of IL 162

Plans show both old lines and PROPOSED lines, the latter based on plans provided by ATT. Some lines have been installed but no as builts incorporated into Contract Plans.

ATT’s consultant (Farnsworth) developed plans using Contract Plans, and some lines installed (approximated in Contract Plans.)

i3 FO Proposed N of IL

I3 sent PROPOSED plans 1-2026 to which Engineer sent a modification. Plans depict PROPOSED, but not yet installed, work.

Ameren Natural gas distribution lines and services.

South of IL 162. NW of existing intersections.

Ameren has stated that these will be moved into easement beyond ROW. Schedule for this unknown.

Ameren High pressure gas main.

Northwest of the proposed roundabout circulatory.

Const. limits close to high pressure main, but no conflicts. Main to remain in place.

Southwestern Electric Cooperative

Overhead electric

(OHE).

Across North leg, along west side of MCT trail, and North of IL 162, east of MCT trail.

OHE lines east of the MCT bridge to remain.

OHE lines west/parallel to MCT trail to remain. OHE lines across the exiting intersections to be relocated. Schedule for this unknown.

Southwestern Electric Cooperative

Buried electric.

Northwest of the existing intersections and proposed roundabout circulatory.

SWECoop has indicated, 1-2025, these would be relocated.

Illinois American Water (ILAMW)

Buried potable water main.

A large 16” main is located northwest of the existing intersections and proposed work.

Utility company has not responded. It is anticipated that only loss of cover over pipes will occur in spot locations and that no relocations are required.

City of Troy Buried potable water mains.

10” south of IL 162.

A PVC 16” crosses IL 162 at the MCT/private drive and then turns east along the north side of IL 162.

Mains have been potholed at key points and these are not anticipated to be in conflict with grading.

Agency or Utility

Type Location Status / Adjustments

Sedlacek farms, Ruth (Sedlacek) Morris - trustee

Buried agricultural tile.

Northwest of the existing intersections and proposed circulatory of the roundabout, west of Old Troy Road at approximately Station 651+26, Left.

3-25-25 per discussions with John Sedlacek, the operator that farms the ground, a field tile discharges at the Station noted. No relocation is required, however, the drain tile may require cutting and removal back to a point in the back slope of the proposed ditchwork.

First Baptist Church of Maryville.

Buried agricultural tile.

South of IL 162 near the existing downstream end of the culvert under IL 162 near Station 547+60, Right.

3-25-25 per discussions with John Sedlacek, an agricultural field tile may drain to the Station noted from the south soccer fields owned by the Baptist Church. No relocation is required, however, the drain tile may require cutting and removal back to a point in the back slope of the proposed ditchwork.

Illinois Department of Transportation

Existing culverts Under IL 162 and Old Troy Road.

Plans detail removal of all crossroad culverts, except the exiting 3’ x 3’ box culvert east of the MCT bridge.

The box culvert is to remain in place and functional.

The above represents the best information of the Department and is only included for the convenience of the Bidder. The underground utilities shown on the Plans and described herein are depicted from available information and do not necessarily reflect the actual existence, non-existence, size, type, number, or location of these or other utilities. The Contractor shall be responsible for verifying the actual location of all underground utilities, shown or not shown, and shall locate the utilities in the field prior to any improvements. As noted herein, some utilities shown in Plans are proposed alignments and have not yet been installed.

The applicable provisions of Sections 105 and 107 of the Standard Specifications for Road and Bridge Construction shall apply and these sections shall be modified herein.

Article 107.30: The Engineer shall not be the party responsible for requesting horizontal and vertical locations of utilities as this shall be the responsibility of the Contractor.

Article 107.40 (a) (1) (c) pertaining to tolerances shall be eliminated. This is due to the inaccuracies of locating as performed by utility companies and/or their sub-contracted located service, and recent repeal of the referenced sections of Code.

Article 107.40 (a) (2) and Article 105.07 shall be reconciled by elimination of 107.40 (a) (2). Due to the project timelines utilities may not have their facilities fully relocated at beginning of Contract construction. Article 105.07 shall extend to the situations where utilities planned to be relocated, but not relocated at the start of construction, may be relocated during construction.

AVAILABILITY OF ELECTRONIC FILES

Electronic files of this project will be made available to the Contractor after Contract award. The electronic files provided shall be determined pertinent for the project solely by the Engineer and additional information beyond that provided will not be required to be provided. The Contractor shall coordinate obtaining electronic files through the project resident Engineer. If there is a conflict between the electronic files and the printed contract plans and documents, the printed contract plans and documents shall take precedence over the electronic files. The Engineer will not be responsible for adjusting electronic information for different software platforms being used by the Contractor. The Contractor shall accept all risk associated with using the electronic files and shall hold the Department harmless for any errors or omissions in the electronic files and the data contained therein. Errors or delays resulting from the use of the electronic files by the Contractor shall not result in an extension of time for any interim or final completion date or shall not be considered cause for additional compensation. The Contractor shall not use, share, or distribute these electronic files except for the purpose of constructing the Contract work. Any claims by third parties due to use or errors shall be the sole responsibility of the Contractor. The Contractor shall include this disclaimer with the transfer of these electronic files to any other parties and shall include appropriate language binding them to similar responsibilities.

ROUNDABOUT CLOSURE

The Contractor will be allowed to close IL 162 and Old Troy Road for 60 consecutive calendar days between May 25, 2027, or the last day of required attendance at Maryville Christian School, and August 1, 2027.

No overnight lane closures along IL 162 will be allowed outside of this full closure.

This full closure shall be in accordance with the Maintenance of Traffic as shown in the plans and any associated labor or equipment are included in the cost of TRAFFIC CONTROL AND

PROTECTION, SPECIAL.

COMPLETION DATE PLUS WORKING DAYS

The Contractor shall complete PCC pavements, curbs, shoulders, and truck aprons, to allow two-way traffic on IL 162, on or before the completion date of this Contract which will be based upon a 60 consecutive calendar day full closure of IL 162 between the dates of May 25th, 2027, or the last day of required attendance at Maryville Christian School, and August 1, 2027. After completion date, an additional 40 working days will be allowed to complete the project. The completion date will be determined by adding the specified number of calendar days to the date the Contractor begins the full closure of IL 162.

Failure to Complete the Work on Time: Should the Contractor fail to complete the work on or before the specified completion date or within such extended time allowed by the Department, the Contractor shall be liable to the Department in the amount of $6,750.00, not as a penalty, but as liquidated and ascertained damages for each calendar day beyond the date of completion or extended time as may be allowed. Such damages may be deducted by the Department from any monies due the Contractor.

CONSTRUCTION LAYOUT

This work shall be in accordance with the Local Roads Checksheet #9 Special Provision for Construction Layout Stakes and as modified by this Special Provision. “Responsibility of the Department” Items (e) and (f) will not be undertaken. Note that existing right-of-way may only be staked in key locations by the Department/Engineer. “Responsibility of the Contractor” Items (b) and (c) will not be required.

This work will be paid for at the Contract unit price per LUMP SUM for CONSTRUCTION

LAYOUT.

SEQUENCE OF OPERATIONS

The Contractor operations shall be in accordance with the maintenance of traffic depicted in the Contract: Plans, applicable Highway Standards, the Standard Specifications, and Special Provisions. The Contractor may upgrade the maintenance of traffic depicted in the Contract Plans or offer rearrangements, upon agreement by the Engineer, prior to undertaking work, at no additional cost to the Contract.

The Contractor may opt to undertake some storm sewer and grading work without closure of the highway and road to conserve working days. All streets and entrances shall remain open to at least one (1) lane of traffic in both directions of travel at all times that the full closure is not in effect. The Contract has not made allowances for partial road closures for storm sewer installation across existing streets via Highway Standards or other pay items such as sheet piling. No additional compensation for utilization of different highway standards, such as those utilizing flaggers, for partial road closures, sheet piling, steel plates, and other required installations to effect crossroad trenching shall be made with this Contract.

TRAFFIC CONTROL AND PROTECTION PLAN

Traffic control shall be in accordance with the applicable sections of the IDOT Standard Specifications for Road and Bridge Construction, the guidelines contained in the National Manual on Uniform Traffic Control Devices for Streets and Highways, the Supplemental Specification, these Special Provisions, and any special detail or highway standards contained herein and in the plans.

At the preconstruction meeting, the Contractor shall furnish the name of individuals in his direct employ who are responsible for the actual installation and maintenance of the controls for the project, with or without utilization of sub-Contractors.

The Contractor shall furnish, erect, maintain, and remove all warning signs, flags, barricades, and lights according to Article 107.14 and Section 701 of the Standard Specifications, the latest edition of the Manual of Uniform Traffic Control Devices for Construction and Maintenance Operations (MUTCD), this Special Provision, and/or as directed by the Engineer. This work shall also include required traffic control for pedestrians. Note that the number of, and type of, barricades and drums shown on the stage construction plan sheets do not represent the full number required and the Contractor shall be responsible for providing the necessary number required. This extends to UNEVEN LANE signs that may be required during paving operations.

Special attention is called to Articles 107.09 and 107.14 of the Standard Specifications for Road and Bridge Construction and the following traffic control related Highway Standards.

Traffic Control Highway Standards:

701001 701006 701011 701311 701901

There shall be advance signing prior to closures of lanes, according to applicable Highway Standards and as depicted on the Plans.

In addition, the following Special Provisions will also govern traffic control for the project:

ROUNDABOUT CLOSURE, COMPLETION DATE PLUS WORKING DAYS, SEQUENCE OF

OPERATIONS, and TRAFFIC CONTROL AND PROTECTION, SPECIAL.

TRAFFIC CONTROL AND PROTECTION, SPECIAL

This work shall be in accordance with Section 701 of the Standard Specifications and as modified by this Special Provision. This work shall consist of furnishing, installing, maintaining, relocating, and removing all traffic control devices used for the purposed of regulating, warning, or directing the traffic during the construction of this project, all construction related signs, and organizing labor required for this work including any flagging.

All traffic control devices, markings, layout, and labor shall conform to the Highway Standards, Standard Specifications, and this Special Provision.

This work shall include any traffic control, including flagger requirements, for intermittent lane closures for deliveries to and from the work zone, for any number of times the Contractor utilizes said controls, and overall controls depicted in the Plans, including any detours controls.

This work will be paid for at the Contract unit price per LUMP SUM for TRAFFIC CONTROL AND

PROTECTION, SPECIAL.

REMOVE EXISTING SIGN COMPLETE

This work shall be in accordance with Section 720 of the Standard Specifications and as modified by this Special Provision.

This work shall include removal of any posts, sign panels, attachment hardware, and buried foundations. This work shall not commence until traffic controls, per the maintenance of traffic in the Plans, has been initiated.

This work will be paid for at the Contract unit price per EACH for REMOVE EXISTING SIGN

COMPLETE.

REMOVE AND RELOCATE EXISTING SIGN PANEL

This work shall be in accordance with Section 720 of the Standard Specifications and as modified by this Special Provision.

This work shall include the removal, salvage, and storage of existing sign panels and hardware for reinstallation on new posts within the project limits.

This work will be paid for at the Contract unit price per EACH for REMOVE AND RELOCATE

EXISTING SIGN PANEL.

CLEARING AND GRUBBING

This work shall be in accordance with Section 201 of the Standard Specifications and as modified by this Special Provision.

This work is intended to improve sight lines along IL 162 east of the Madison County Transit pedestrian bridge, north and south of IL 162.

North of IL 162, the vegetation in these areas surrounding the trees in this area (five (5) with trunk diameters greater than six (6) inches) shall be cleared to the ground surface with skid steer mounted brush cutters, mowers, or other means that will not damage established trees. Grubs and roots with vegetation shall be pulled with loader buckets or ground with grinders. In early 2025, similar work was done for the adjoining overhead electric lines in the area. Material can be mulched and incorporated into the soil for subsequent Contract seeding.

South of IL 162, around the existing downstream opening of the 3’ x 3’ concrete box culvert under IL 162, east of the MCT trail parking lot entrance, vegetation and roots shall be similarly removed in order for excavation for riprap. In this area, the removed and dead vegetative material (mulch) shall be removed from the site and not placed beneath the proposed riprap placement.

This work will be paid for at the Contract unit price per LUMP SUM for CLEARING AND

GRUBBING.

STORM SEWER REMOVAL

This work shall be in accordance with Section 551 of the Standard Specifications and as modified by this Special Provision. This work entails excavation to expose and remove existing storm sewers for installation of new pipes and collars. Existing storm sewers to remain shall be undisturbed by excavation work and the Contractor shall employ sawing to relieve connections, as required by field conditions. Existing waste storm sewer pipes shall not be disposed of in trenches and excavations but offsite.

All labor, equipment, and material for this work will be paid for at the Contract unit price per FOOT for STORM SEWER REMOVAL.

REMOVE EXISTING FLARED END SECTION

This work shall be in accordance with Section 551 of the Standard Specifications and as modified by this Special Provision. This work entails excavation to expose and remove existing sections.

Existing storm sewers to remain shall be undisturbed by excavation work and the Contractor shall employ sawing to relieve connections, as required by field conditions. Existing waste storm sewer pipes shall not be disposed of in trenches and excavations but offsite.

All labor, equipment, and material for this work will be paid for at the Contract unit price per EACH for REMOVE EXISTING FLARED END SECTION.

REMOVAL AND DISPOSAL OF UNSUITABLE MATERIAL

This work shall be in accordance with Section 202 of the Standard Specifications and as modified by this Special Provision.

This Special Provision clarifies removal of known, existing aggregate material along shoulders and in certain pavements. This material cannot be utilized back in embankments, bases, and surface graded areas and shall be properly disposed of offsite.

All labor, equipment, and material for this work will be paid for at the Contract unit price per CUBIC YARD for REMOVAL AND DISPOSAL OF UNSUITABLE MATERIAL.

UNLOCATED SUMP LINES AND DOWNSPOUTS

This work shall be in accordance with Section 551 of the Standard Specifications and as modified by this Special Provision. This Special Provision is intended for information and not associated with a specific Pay Item.

No existing field tiles, sump drains carrying seepage water from buildings, downspouts carrying surface runoff from direct rainfall, sump drains within downspout drains, and other below ground drainage features were located via field survey work for this project other than surficial features denoted. As noted in the Status of Utilities special provision, the general location of some agricultural field tile outlets are known. The Contractor shall exercise care in excavating around these known areas to protect their capacity to flow and in order to adequately cut and remove sections back to proposed ditch backslopes.

For this Contract, no additional compensation for monitoring these areas is provided. During construction, the Engineer and Contractor shall evaluate methods to facilitate continued discharges and how to remove and terminate these tiles.

SELECT GRANULAR BACKFILL, SPECIAL

This work shall be in accordance with Sections 208, 550.07, and Article 602.12 of the Standard Specifications and as modified by this Special Provision.

This work includes all backfilling for new and removed storm sewers, and drainage structures and other structures, of all sizes from the haunching of pipe to the surface of ground or pavement at the time of installation of storm sewers. All trenches within two (2) feet, horizontally, from edges of pavement, curb, and sidewalk, shall receive SELECT GRANULAR BACKFILL, SPECIAL.

This Special Provision also prescribes bedding of trenches, bedding in excavations to receive structures, and material from bedding to haunching: all shall be the same as for backfill from haunching to surface as described herein. Additionally, the Special Provision prescribes similar material be used for backfilling around all structures within limits noted herein.

References to “Fine Aggregate” in Section 208 and Article 1003.04 of the Standard Specifications shall be relaced with “Coarse Aggregate”. Section 1004 rather than 1003 shall be utilized. Coarse aggregate described in Article 1004.05 (a) shall be utilized. Article 1004.06 (b) requirements shall apply except that only CA6 gradation shall be utilized.

The second paragraph in Article 602.12 shall be revised such that no sand shall be used as backfill between the sides of excavation and outer surfaces of structures.

Frozen backfill shall not be placed in any excavation. All backfill material shall be compacted by Method 1 of Article 550.07 in lifts no greater than eight (8) inches by mechanical means – vibratory compactors – to a minimum of 95 percent standard lab densities. No ponding in the bottom of trenches shall be present.

All labor, equipment, and materials required for this work shall be paid for at the Contract unit price per CUBIC YARD for SELECT GRANULAR BACKFILL, SPECIAL. Bedding under pipes and structures, backfilling around structures, and other backfilling other than haunch to surface backfill shall be paid for separately and included in work associated with other Pay Items.

PROPOSED STORM SEWER CONNECTION TO EXISTING STORM SEWER

This work shall be in accordance with Section 550 of the Standard Specifications and as modified by this Special Provision.

This Pay Item involves work to cut into installed storm sewer for connecting smaller diameter storm sewers. These are storm sewers that have relatively low flows. Connections are prescribed in lieu of manholes due to the latter requiring too much expense, effort, or large for constraints of the connection. Storm sewers shall be cut with clean edges and abutting pipes shall be aligned with sufficiently large cut holes that will not impede flows. The width of gap between the abutting pipes shall be minimized. The Contractor shall form and pour Concrete Collars around these connections below, above, and around said connections.

All labor, equipment, and materials required for this work shall be paid for at the Contract unit price per EACH for PROPOSED STORM SEWER CONNECTION TO EXISTING STORM

SEWER.

TOPSOIL EXCVAVATION AND PLACEMENT

This work shall be in accordance with Section 211 of the Standard Specifications and as modified by this Special Provision.

This pay item work involves excavating material from the limits of the site, stockpiling said material, and placing said material as non-structural embankments. Non-structural embankments are those not under pavements. It is noted that this work is distinct and separate from TOPSOIL FURNISH AND PLACE. The TOPSOIL FURNISH AND PLACE material is needed because the topsoil excavation material onsite is not sufficient after use as non-structural embankments to cover the top surfaces, thus TOPSOIL FURNISH AND PLACE material shall be procured from off-site areas.

The geotechnical report recommends before embankments under pavement are constructed, the top surface of existing farm fields and other soils, twelve (12) inches thick, shall be removed.

These soils are herein referred to as TOPSOIL, though some of the described material may be a mixture of topsoil material and inorganics. These materials are not considered conducive for modification with lime, nor is lime desired at this site due to adjoining residential properties.

Essentially, this material will be re-used on upper surfaces of embankment.

The topsoil material excavated has a conservative shrinkage factor applied per the IDOT design manual recommendations – to insure sufficient material. The excavated topsoil material shall be stored on site or at a location the Contractor can utilize as a storage area. At the required time, once structural fills are in place, the Contractor shall haul said excavated topsoil material and deposit it to grades and slopes shown in the Plans and compact it to 95% standard laboratory density.

Due to the interdependencies of earthwork quantities calculations for this project as presented in the Plans, agreement to Plan quantity for all or any combination of the Pay Items TOPSOIL EXCAVATION AND PLACEMENT, EARTH EXCAVATION, and FURNISHED EXCAVATION is also interdependent. As an example, in the event the Contractor agrees to FURNISHED EXCAVATION Plan quantity, the Contractor shall agree to TOPSOIL EXCAVATION AND PLACEMENT, and EARTH EXCAVATION Plan quantities due to the interdependencies.

Agreement to Plan quantity does not negate the possibility of the need for additional or less quantity, but with this, only the changed amount will be measured with an associated agreement to Plan quantity.

Areas where additional material is removed due to soil testing for waste material, can only correspond to EARTH EXCAVATION, though it will be paid for as NON-SPECIAL WASTE DISPOSAL, due to the topsoil excavation areas covering all areas of the project.

Article 211.07, regarding measurements, shall be modified herein. Topsoil excavated shall be measured by utilizing the dimensions shown Plan sections, in combination with depth checks made in the field, at the stations depicted in the Plans, to establish average end areas type calculations. Digital terrain models will not be utilized for these measurements by the Engineer due to topsoil excavation essentially extending over the entire project limits. Spreadsheets can be utilized for presentation for this particular quantity.

All labor, equipment, and material for this work will be paid for at the Contract unit price per CUBIC YARD for TOPSOIL EXCAVATION AND PLACEMENT.

EARTH EXCAVATION

This work shall be in accordance with Sections 202 and 205 of the Standard Specifications and as modified by this Special Provision.

This pay item work involves excavating material below topsoil that can be used as structural fill under pavements. This material can be excavated, stockpiled and later hauled and compacted, or excavated, hauled, and compacted. Plan typicals show this material’s use under pavements.

This material once placed shall be compacted per Section 205 requirements, as embankment.

Due to the interdependencies of earthwork quantities calculations for this project as presented in the Plans, agreement to Plan quantity for all or any combination of the Pay Items TOPSOIL EXCAVATION AND PLACEMENT, EARTH EXCAVATION, and FURNISHED EXCAVATION is also interdependent. As an example, in the event the Contractor agrees to FURNISHED EXCAVATION Plan quantity, the Contractor shall agree to TOPSOIL EXCAVATION AND PLACEMENT, and EARTH EXCAVATION Plan quantities due to the interdependencies.

Agreement to Plan quantity does not negate the possibility of the need for additional or less quantity, but with this, only the changed amount will be measured with an associated agreement to Plan quantity.

Areas where additional material is removed due to soil testing for waste material, can only correspond to EARTH EXCAVATION, though it will be paid for as NON-SPECIAL WASTE DISPOSAL, due to the topsoil excavation areas covering all areas of the project.

Article 202.07 (b), regarding measurements, shall be modified herein. Measurements of EARTH EXCAVATION are complicated due to the topsoil excavation work, and that EARTH EXCAVATION does not extend across the entire area of the project. Earth excavation cuts shall be measured at the stations depicted in the Plans. Manual measurements of cut at said sections using hand levels can be made, or with total stations, and displayed on CADD sections for subsequent end area comparisons. Comparisons utilizing digital terrain models will not be made due to the differences in triangulation and outer boundaries.

All labor, equipment, and material for this work will be paid for at the Contract unit price per CUBIC YARD for EARTH EXCAVATION.

FURNISHED EXCAVATION

This work shall be in accordance with Section 204, Section 205, and Article 1009.04 of the Standard Specifications and as modified by this Special Provision.

This pay item work involves excavation of suitable earth material from offsite, hauling it to the site, placing it, and compacting it, to the grades and elevations shown in the Plans. This material shall have liquid limits less than 50, as per Article 1009.04, and be composed predominately of clay material free of organics. This material is comparable to the earth excavation material, referred to as structural fill beneath pavements.

Due to the interdependencies of earthwork quantities calculations for this project as presented in the Plans, agreement to Plan quantity for all or any combination of the Pay Items TOPSOIL EXCAVATION AND PLACEMENT, EARTH EXCAVATION, and FURNISHED EXCAVATION is also interdependent. As an example, in the event the Contractor agrees to FURNISHED EXCAVATION Plan quantity, the Contractor shall agree to TOPSOIL EXCAVATION AND PLACEMENT, and EARTH EXCAVATION Plan quantities due to the interdependencies.

Agreement to Plan quantity does not negate the possibility of the need for additional or less quantity, but with this, only the changed amount will be measured with an associated agreement to Plan quantity.

Areas where additional material is removed due to soil testing for waste material, can only correspond to EARTH EXCAVATION, though it will be paid for as NON-SPECIAL WASTE DISPOSAL, due to the topsoil excavation areas covering all areas of the project. FURNISHED EXCAVATION is tied to additional EARTH EXCAVATION and NON-SPECIAL WASTE DISPOSAL as the created voids require additional topsoil excavation material and likely additional FURNISHED EXCAVATION material.

Article 204.07 regarding measurements, shall be modified herein. The Engineer will not reestablish the existing ground line. Utilizing measurements for TOPSOIL EXCAVATION AND PLACEMENT, EARTH EXCAVATION and NON-SPECIAL WASTE DISPOSAL, at the stations depicted in the Plans and proposed roadway and embankment CAD linework, end area type calculations will be utilized to generate FURNISHED EXCAVATION quantities.

All labor, equipment, and material for this work will be paid for at the Contract unit price per CUBIC YARD for FURNISHED EXCAVATION.

AGGREGATE SUBGRADE IMPROVEMENT

This work shall be in accordance with Sections 311 and 1004 of the Standard Specifications and as modified by this Special Provision. This work and material is intended to be utilized where visible pumping and rutting occur in exposed subgrade following pavement removal or earth excavation work.

The EARTH EXCAVATION pay item shall be utilized for removal of existing material. The replacement material may be the same material use for Subbase Granular Material with said material compacted to 95% standard laboratory density, if achievable, as opposed “to the satisfaction of the Engineer”. Replacement material may also be a larger gradation, such as CA5.

All labor, equipment, and material for this work will be paid for at the Contract unit price per CUBIC YARD for AGGREGATE SUBGRADE IMPROVEMENT.

SUBBASE GRANULAR MATERIAL

This work shall be in accordance with Sections 311 and 1004 of the Standard Specifications and as modified by this Special Provision.

Reference in Article 311.05 (c) to “satisfaction of the Engineer” shall be replaced with “to 95% standard laboratory density”. Thickness checks shall be undertaken

All labor, equipment, and material for this work will be paid for at the Contract unit price per SQUARE YARD for SUBBASE GRANULAR MATERIAL of the type and thickness specified.

AGGREGATE FOR TEMPORARY ACCESS

This work shall be in accordance with Sections 401.10 of the Standard Specifications and as modified by this Special Provision.

References in Article 402.07, referenced by Article 402.10, to Article 1004.04, shall be modified such that the aggregate shall be the same type and gradation as SUBBASE GRANULAR MATERIAL called for in the Contract. The material shall be compacted by proof rolling with loaded trucks to the satisfaction of the Engineer. The Engineer and Contractor shall measure the volume of the placed material and apply Plan rates of application for aggregate to establish the tonnage used for each location.

The Contractor shall remove all material from the site after it is no longer required. This material shall not be used for other Pay Item work.

All labor, equipment, and material for this work will be paid for at the Contract unit price per TON for AGGREGATE FOR TEMPORARY ACCESS.

STABILIZED SUBBASE – HOT-MIX ASPHALT, 4”

This work shall be in accordance with Sections 312 of the Standard Specifications and as modified by this Special Provision.

Hot-mix asphalt mixture shall be IL-19.0 binder with 4% air voids and an N of 70 gyrations.

CAM shall not be utilized in lieu of hot-mix asphalt for any subbase on the project. CAM’s rigidity for planar, vertical, curling, and warping deflections of PCC slabs and the material’s susceptibility to uncontrolled cracking that will not match controlled, sawn joints of the PCC slabs, prevent its use.

Control of elevations of the stabilized subbase may be notably difficult in order to achieve required surface elevations and minimum thicknesses for the PCC pavement and curbs. Placing subbase granular material and stabilized bases at slightly lower elevations such that PCC pavement and curbs are poured slightly thicker than required, may be a means of avoiding milling or reconstructed stabilized base. Variation in PCC pavement should not be abrupt.

All labor, equipment, and material for this work will be paid for at the Contract unit price per SQUARE YARD for STABILIZED SUBBASE – HOT-MIX ASPHALT 4” of the type and thickness specified.

COMBINATION CONCRETE CURB AND GUTTER, TYPE B (MODIFIED)

This work shall be in accordance with Sections 606 of the Standard Specifications and as modified by this Special Provision.

This curb shall be constructed as shown in Plan details.

All labor, equipment, and material for this work will be paid for at the Contract unit price per FOOT for COMBINATION CONCRETE CURB AND GUTTER, TYPE B, of the type and size specified, (MODIFIED).

DETECTABLE WARNINGS

This work shall be in accordance with Section 424 of the Standard Specifications and as modified by this Special Provision.

Detectable warnings shall not be imprinted into the sidewalk. Fiberglass, plastic systems, and modular block systems that are positioned and sometimes secured with adhesive will not be allowed. Only systems utilizing cementitious panels secured with grout or placed in wet concrete or cast iron panels, approved by the City and IDOT, will be allowed.

All labor, equipment, and material required for this work shall be paid for at the Contract unit price per SQUARE FOOT for DETECTABLE WARNINGS.

PAINT CURB

This work shall be in accordance with Section 780 of the Standard Specifications and as modified by this Special Provision.

The top and face of curb shall be painted and both are included in the linear foot measurement for payment. The Contractor shall demonstrate their ability to paint curb without overspray onto adjoining surfaces. In the event that the Contractor’s method is not satisfactory to the Engineer, the Engineer may require the Contractor to manually paint the curb with brushes.

The Contractor shall remove any spilled paint and overspray on paved, aggregate, and earthen surfaces to the satisfaction of the Engineer by water blasting or other approved methods, at no additional cost to the Contract.

All labor, equipment, and material required for this work shall be paid for at the Contract unit price per FOOT for PAINT CURB.

PORTLAND CEMENT CONCRETE PAVEMENT 9” (JOINTED)

This work shall be in accordance with Section 420 of the Standard Specifications as modified by this Special Provision.

Sealing Requirements: All transverse and longitudinal pavement joints sawn shall be sealed, per Article 420.12. When concrete panels, panels being areas of concrete bounded by joints, defined in the Plans are poured monolithically through proposed joints, all proposed joints shall be sawn and sealed. Only when adjoining panels are poured separately shall joints not be sawn and sealed to avoid the risk of creating slivered sections of PCC pavement.

Equipment: It is…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .