HMA Roadway Reconstruction of Ghent Rd. from Main St. to Christina Ct.
Solicitation number
97866
Issued by
Moultrie County, Illinois

About this file

Summary of ildot 97866-069.pdf

This is a project specification document for the Illinois Department of Transportation (IDOT) related to the HMA Roadway Reconstruction of Ghent Road in Columbia, Illinois. The project encompasses roadway reconstruction work along Ghent Road from Main Street to Christina Court, spanning 1,300 feet (0.246 miles). The scope of work includes PCC base course widening, HMA milling and resurfacing, full depth HMA pavement, storm sewer installation, combination concrete curb and gutter construction, ADA-compliant curb ramps, driveway pavement, and other incidental work necessary to complete the project as detailed in the engineering plans. The document provides technical specifications and requirements that contractors must follow to execute the project in accordance with IDOT standards and the City of Columbia's requirements.

The specification document establishes material standards, construction methodologies, quality assurance requirements, and workmanship standards for all components of the roadway reconstruction project. It includes detailed requirements for asphalt, concrete, drainage, and site work to ensure compliance with applicable codes and standards. The document serves as the technical basis for bid preparation and contract administration, outlining the specifications that successful bidders must meet during project execution.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting July 31, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 97866 MONROE County Section 21-00053-01-PV (Columbia) Route FAU 9310 (Ghent Road) Project J2AU-378 () District 8 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

July 31, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 97866 MONROE County Section 21-00053-01-PV (Columbia) Project J2AU-378 () Route FAU 9310 (Ghent Road) District 8 Construction Funds

HMA roadway reconstruction of Ghent Rd. from Main St. to Christina Ct. in the city of Columbia.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

CONTRACT 97866

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)

3 EEO

4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS

Table of Contents

CHECK SHEET # PAGE NO.

LRS 1 Reserved LRS 2 Furnished Excavation LRS 3 Work Zone Traffic Control Surveillance LRS 4 Flaggers in Work Zones LRS 5 Contract Claims LRS 6 Bidding Requirements and Conditions for Contract Proposals LRS 7 Bidding Requirements and Conditions for Material Proposals LRS 8 Reserved LRS 9 Bituminous Surface Treatments LRS 10 Reserved LRS 11 Employment Practices LRS 12 Wages of Employees on Public Works LRS 13 Selection of Labor LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS 15 Partial Payments LRS 16 Protests on Local Lettings LRS 17 Substance Abuse Prevention Program LRS 18 Multigrade Cold Mix Asphalt LRS 19 Reflective Crack Control Treatment

Project No. J2AU(378) Section 21-00053-01-PV

Monroe County Ghent Road Improvements – Phase II

SPECIAL PROVISIONS

GHENT ROAD IMPROVEMENTS – PHASE II

COLUMBIA, ILLINOIS

INDEX TO SPECIAL PROVISIONS

PAGE

DESCRIPTION OF WORK

LOCATION OF WORK

NOTIFICATION REQUIREMENTS

SAFETY AND PROTECTION ..................................................................................1-2

STATUS OF UTILITIES TO BE ADJUSTED

KEEPING THE STREETS OPEN TO TRAFFIC .......................................................3-4

SAWCUTS…….…………………………………………………………………………..4

SEEDING…………………………………………………………………………………..4

PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT………………………4-5

PORTLAND CEMENT CONCRETE SIDEWALK………………………………………5

RECTANGULAR RAPID FLASHING BEACONS (COMPLETE)……………………..5-6

LOCATING UNDERGROUND UTILITIES………………………………………………6-7

HOT-MIX ASPHALT SURFACE REMOVAL (VARIABLE DEPTH)…………………..7-8

TRENCH DRAIN ……………………………………………………………………………8

INLETS, SPECIAL …………………………………………………………………………..8

TRAFFIC CONTROL AND PROTECTION, (SPECIAL)………………………………….8-9

STORM SEWERS, WATER MAIN QUALITY PIPE……………………………………..9-11

Monroe County

CONSTRUCTION LAYOUT……………………………………………………………...12-13

COMPLETION DATE PLUS WORKING DAYS ………………………………………..13

CONSTRUCTION COORDINATION……………………………………………………..13

LR 107-4 INSURANCE

LR 1030-2 LOCAL QUALITY ASSURANCE/ QUALITY MANAGEMENT QC/QA..15-16

SUBMITTAL OF EE/LABOR DOCUMENTATION…………………………………….17-18

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING ...................19-20

BDE SPECIAL PROVISIONS

The following special provisions indicated by an “X” are applicable to this contract. An * indicates a new or revised special provision for the letting.

File Name Pg. Special Provision Title Effective Revised 80099 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 _ 80274 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 Automated Flagger Assistance Device Jan. 1, 2008 April 1, 2023 80173 21 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017 80426 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 April 1, 2026 80475 Bridge Deck Concrete Overlays Jan. 1, 2026 80241 Bridge Demolition Debris July 1, 2009

5053I Building Removal Sept. 1, 1990 Aug. 1, 2022 5026I Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022

80460 23 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 40 Compensable Delay Costs June 2, 2017 April 1, 2019 80198 Completion Date (via calendar days) April 1, 2008 80199 Completion Date (via calendar days) Plus Working Days April 1, 2008 80461 Concrete Barrier Jan. 1, 2025 80453 Concrete Sealer Nov. 1, 2023 80261 44 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 Deck Slab Repair Jan. 1, 2026

* 80029 46 Disadvantaged Business Enterprise Participation Sept. 1, 2000 July 2, 2026 80467 Erosion Control Blanket Aug. 1, 2025 80229 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 Guardrail Nov. 1, 2025 80472 High Friction Surface Treatment Nov. 1, 2025 80456 50 Hot-Mix Asphalt Jan. 1, 2024 April 1, 2026 80446 Hot-Mix Asphalt – Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024 80483 Inlet Filters April 1, 2026

* 80477 Longitudinal Tining Jan. 1, 2026 July 1, 2026 80450 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 54 Pavement Marking April 1, 2025 Nov. 1, 2025 80468 55 Pavement Patching Aug. 1, 2025 80441 56 Performance Graded Asphalt Binder Jan 1, 2023 April 1, 2026 80459 Preformed Plastic Pavement Marking June 2, 2024 3426I Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 Raised Reflective Pavement Markers Nov. 1, 2025 80455 62 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2026 80474 Residential Driveway Temporary Signal Nov. 1, 2025

* 80445 64 Seeding Nov. 1, 2022 July 1, 2026 80457 70 Short Term and Temporary Pavement Markings April 1, 2024 April 2, 2024 80462 74 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 Sinusoidal Rumble Strips Jan. 1, 2026 80469 Slope Wall Aug. 1, 2025 80448 76 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 Structural Repair of Concrete Jan. 1, 2026 80397 78 Subcontractor and DBE Payment Reporting April 2, 2018 80391 79 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019 80463 80 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025

File Name Pg. Special Provision Title Effective Revised 80482 81 Submission of Payroll Records – Federal Aid Contract April 1, 2026 80437 Submission of Payroll Records – State Contract April 1, 2021 April 1, 2026 80435 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 83 Surveying Services April 1, 2025 80481 Temporary Concrete Barrier Jan. 1, 2026 80466 Temporary Rumble Strips April 1, 2025

* 80484 Tolerance in Thickness for Continuously Reinforced PCC Pavement July 1, 2026 80470 Traffic Signal Backplate Aug. 1, 2025 20338 84 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022 80439 87 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2022 80458 Waterproofing Membrane System Aug. 1, 2024 80302 88 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 Wood Sign Support Nov. 1, 2023 80427 89 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026

* 80485 92 Work Zone Width Restriction July 1, 2026 80071 Working Days Jan. 1, 2002

Monroe County Ghent Road Improvements – Phase II

SPECIAL PROVISIONS

Ghent Road Improvements – Phase II Columbia, ILLINOIS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction", adopted January 1, 2022 by the Department of Transportation, of the State of Illinois, and the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways" and the “Manual of Test Procedures of Materials” in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of the Ghent Road Improvements – Phase II, Section 21-00053-01-PV, in Columbia, Monroe County, Illinois, and in case of conflict with any part, or parts, of said specifications, the said Special Provisions shall take precedence and shall govern.

DESCRIPTION OF WORK: This project consists of PCC base course widening, HMA milling and resurfacing, full depth HMA pavement, storm sewer, combination concrete curb and gutter, ADA compliant curb ramps, driveway pavement and other incidental work required to complete the plans as proposed in the City of Columbia, Illinois.

LOCATION OF WORK: The work shall start at the intersection of Main Street and Ghent Road and end at the intersection of Christina Court and Ghent Road. The project length is 1,300 feet (0.246 miles).

NOTIFICATION REQUIREMENTS: The Contractor shall be responsible for notifying residents and businesses about driveway closures. All residents and businesses affected by the driveway closures shall be notified 48 hours in advance of such operation. The Contractor shall leave written notification in an obvious place at all affected residences or businesses.

This work will not be paid for separately but shall be considered as included in the cost of TRAFFIC CONTROL AND PROTECTION (SPECIAL) and no additional compensation will be allowed.

SAFETY AND PROTECTION: In addition to the requirements of the Standard Specifications for Road and Bridge Construction articles 107.09 and 107.28, the following shall apply. In case of conflict therein, the more stringent requirement shall apply.

The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. The Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to:

• All employees on the Work and other persons and organizations who may

Monroe County be affected thereby;

• All the Work and materials and equipment to be incorporated therein, whether in storage on or off the site; and

• Other property at the site adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities and underground facilities not designated for removal, relocation or replacement in the course of construction.

The Contractor shall comply with all applicable Laws and Regulation of any public body having jurisdiction for the safety of persons and property or to protect them from damage, injury or loss; and shall erect and maintain all necessary safeguards for such safety and protection. The Contractor shall notify owners of adjacent property and of underground facilities and utility owners when prosecution of the work may affect them and shall cooperate with them in the protection, removal, relocation and replacement of their property. All damage, injury or loss to any property caused, directly or indirectly, in whole or in part, by the Contractor, any subcontractor, supplier or any other person or organization directly or indirectly employed by any of them to perform or furnish any of the work or anyone for whose acts either of them may be liable, shall be remedied by the Contractor (except damage or loss attributable to the fault of drawings or specifications or to the acts or omissions of the Engineer, City or anyone employed therein or anyone for whose acts either of them may be liable, and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of The Contractor). The Contractor's duties and responsibilities for the safety and protection of the work shall continue until such time as all the Work is completed and the Engineer has issued a notice to the Contractor that the work is acceptable (accept as otherwise expressly provided in connection with Substantial Completion).

The Contractor shall designate a responsible representative at the site whose duty shall be the prevention of accidents. This person shall be the Contractor's superintendent, unless otherwise designated in writing by the Contractor to the City.

In emergencies affecting the safety or protection of persons or the work or property at the site or adjacent thereto, the Contractor, without special instructions or authorization from the City, is obligated to act to prevent threatened damage, injury or loss. The Contractor shall give the City prompt, written notice if the Contractor believes that any significant changes in the work or variations from the contract documents have been caused thereby.

If the City determines that a change in the contract documents is required because of the action taken in response to an emergency, a work directive change or change order will be issued to document the consequences of the changes or variations.

No separate payment will be made for safety and protection. Work, materials, and labor for this work shall be considered included in the cost of the contract.

Monroe County

STATUS OF UTILITIES TO BE ADJUSTED

Estimated Date

Name and Address of Utility Type Location Relocation Completed Harrisonville Telephone Telephone TBD TBD Attn: Thomas Schrieber 618-939-9256

Ameren Illinois (South) Gas STA. 16+00 TBD Attn: Nathan Hill TO STA. 19+00 618-301-5327

Ameren Illinois (South) Electric N/A N/A Attn: Nathan Hill 618-301-5327

City of Columbia Water/Sewer Water Service During Attn: Chris Smith Construction 208 S Rapp Ave

Charter Communications Communications TBD TBD Attn: Chris Shelton 618-386-1649

Everstream Communications Communications TBD TBD

The above represents the best information of the City and is only included for the convenience of the bidder. The applicable provision of Articles 102 and 105.07 of the Standard Specifications for Road and Bridge Construction and the special provision for “Cooperation with Utilities” shall apply.

If any utility adjustment or removal has not been completed when required by the Contractor’s operations, the Contractor should notify the Engineer in writing. Requests for an extension of time will be considered to the extent the Contractor’s operations were affected.

KEEPING THE STREETS OPEN TO TRAFFIC: The Contractor for this improvement is advised that they will be required to conduct and coordinate the construction activities required for this improvement in such a manner to cause the least interference to the motoring public, pedestrian traffic, operating businesses, and to general public access and usage of the areas under construction. Access to private and public properties, including buildings, will be maintained at all times during construction in a manner meeting the approval of the Engineer and as provided for on the plans. The construction zone shall remain accessible to emergency vehicles, local traffic and private properties at all times.

Advance warning signs shall be installed on approach of all streets within the limits of this

Monroe County project. These signs shall be installed prior to performing work on this project and shall remain in place for the duration of this contract unless otherwise directed by the Engineer.

The cost for the advance warning signs will not be paid for separately but considered included in the TRAFFIC CONTROL AND PROTECTION, (SPECIAL) pay item.

The Contractor shall take into account the requirements for maintaining traffic as herein specified in submitting the contract unit prices for the various items of work, as no additional compensation will be allowed for any cost or delays that result from compliance with this provision.

SAWCUTS: This work shall consist of saw cutting existing concrete and asphalt pavement, concrete curb and gutter, driveway pavement and sidewalk as shown on the Plans and as directed by the Engineer.

All saw cuts shall be full depth sawing of the existing thickness to be removed, unless otherwise directed by the Engineer. Care shall be taken to prevent spalling damage to the pavement, curb or sidewalk that is to remain in place and if any damage occurs the contractor shall replace items to remain in place with no additional compensation.

This work will not be paid for separately but shall be considered included in the contract unit price for the items to be removed.

SEEDING: This work shall consist of preparing the seed bed, and furnishing, transporting and placing the seed required to restore all disturbed earth surfaces according to Sections 250 and 251 of the “Standard Specifications for Road and Bridge Construction”.

Prior to seeding, the top 6” of fill shall be free from ALL rocks, roots and other foreign debris. The site shall be inspected by the Engineer prior to seeding to verify that the backfill is in compliance with the above.

All areas disturbed due to construction shall be seeded, fertilized and mulched. All mulch shall be applied using Method 2 and securely stabilized. The Contractor shall guarantee a minimum of 90 percent uniform growth over the entire seeded area(s). Area sustaining less than 90 percent uniform growth shall be interseeded or reseeded, as determined by the Engineer, at no additional cost.

This work will be measured and paid for according to Section 250 of the Standard Specifications for SEEDING, of type specified.

PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT: This work shall be in accordance with Section 423 of the Standard Specifications, the plans, and as modified by this Special Provision. Fill may be required to bring the driveway to the proper elevation.

When the Engineer determines that acceptable earth embankment is not available or acceptable compactive efforts cannot be made, due to restrictive space, to earthen subgrade the fill shall be CA-6 aggregate and shall be compacted to the satisfaction of the Engineer.

Monroe County

In the event that there are any uncontrolled cracks occurring in the driveway pavement while construction operations are on-going, the Contractor shall remove and replace the portion of the driveway pavement to the nearest sawed joint either side of the crack for uncontrolled transverse cracks at no additional cost to the Contract.

All labor, equipment, and materials required to complete this work including the saw cuts and any necessary CA-6 aggregate shall be included in the cost of PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT, of thickness specified.

This work shall be measured and paid for according to Section 423 of the Standard Specifications for PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT, of thickness specified.

PORTLAND CEMENT CONCRETE SIDEWALK: This work shall be in accordance with Section 424 of the Standard Specifications, the plans, and as modified by this Special Provision. Fill may be required to bring sidewalk to the proper elevation. When the Engineer determines that acceptable earth embankment is not available or acceptable compactive efforts cannot be made, due to restrictive space, to earthen subgrade the fill shall be CA-6 aggregate and shall be compacted to the satisfaction of the Engineer.

In the event that there are any uncontrolled cracks occurring in the sidewalk while construction operations are on-going, the Contractor shall remove and replace the full width of the sidewalk to the nearest troweled joints either side of the crack for uncontrolled transverse cracks at no additional cost to the Contract.

All labor, equipment, and materials required to complete this work including the saw cuts and any necessary CA-6 aggregate shall be included in the cost for PORTLAND CEMENT CONCRETE SIDEWALK, of thickness specified.

This work shall be measured and paid for according to Section 424 of the Standard Specifications for PORTLAND CEMENT CONCRETE SIDEWALK, of thickness specified.

RECTANGULAR RAPID FLASHING BEACONS (COMPLETE): This work shall consist of furnishing and installing a solar powered rectangular rapid flash beacon sign assembly at the locations shown on the plans according to the construction details on the plans.

The solar powered rectangular rapid flash beacon sign assembly shown on the plans shall be included in the cost of the entire assembly. The following shall apply:

Sign Panel: A 30” x 30” W11-2 and a 24” x 12” W16-7P shall be mounted on both sides of the pole, and a 9” x 12” R10-25 shall be mounted above the ADA push button. All signs shall conform to the MUTCD’s current edition.

Reflective Sheeting: Shall conform to Section 1091 of the “Standard Specifications for Road and Bridge Construction”.

Monroe County

Solar System: 20W with a 12v, up to 44Ah battery. NEMA 3R rated aluminum housing.

Light Emitting Source: Flashing beacon, LED array viewable from all directions, SAE J595 certified. Flash frequency must be MUTCD compliant.

Pole: 4.5” diameter aluminum conforming to section 1077.01 of the “Standard Specifications for Road and Bridge Construction”, the applicable Highway Standards, and the construction details on the plans.

Concrete Foundation: Shall conform to section 1077.01 of the “Standard Specifications for Road and Bridge Construction” and the construction details on the plans.

Activation: ADA Pedestrian pushbutton detector.

Wireless Communication: 900 feet range, 900 MHz frequency

Mounting Hardware: Stainless steel hardware.

Warranty: 3 year (min.) on entire assembly.

The assembly shall be integrated into the wiring system for the push button post and programmed to activate for 60 seconds after the button is pushed. The assembly shall be synchronized with the assembly on the opposite side of the street (wireless communication) and activate at the push of either button.

The Contractor shall supply manufacture specification’s to the Engineer prior to bidding.

This work will be paid for at the contract unit price per each for RECTANGULAR RAPID

FLASHING BEACON ASSEMBLY (COMPLETE).

LOCATING UNDERGROUND UTILITIES: This work shall consist of the Contractor providing potholes to determine the exact location of all underground utilities (electric, water, gas, sewer, etc.) which are in possible conflict with construction operations. This work shall only be done as directed by the Engineer by written authorization, when the location of the utility cannot be readily identified horizontally and vertically by the utility owner and there is proposed structures, pipes, culverts, road excavation in close proximity to underground utility in question.

Prior to the beginning of any work which may impact nearby underground utilities, the Contractor shall provide 12” diameter potholes through nondestructive or minimally intrusive excavation methods. The method of potholing may be by machine or hand. All equipment and tools shall be approved by the Engineer. After the Contractor exposes the subsurface utilities the utility type, size, condition, and material shall be obtained by the Contractor, as well as the horizontal coordinates and vertical elevations.

Monroe County

All information obtained in conjunction with this work shall be provided to Engineer upon request. The Contractor shall notify the Engineer immediately, in writing, of any conflicts between the project work and any existing utility.

Upon field verification of the location of existing utilities, the Engineer may elect to delay, relocate and/or adjust the location of the proposed work or existing utility. No additional compensation will be allowed for any inconveniences or damages sustained by the Contractor due to any delay, relocation and/or adjustment of the proposed work or existing utility.

The Contractor shall take proper precautions to protect the existing underground utilities from damage or interruption during locating and construction operations. Any exposed utility shall be protected, shielded and supported per the appropriate utility company standards and as directed by the Engineer.

In the event that any utility is damaged, the Contractor shall be responsible for any damage resulting from neglect, misconduct, or omission in the Contractor’s manner or method of execution or non-execution of the work or caused by defective work or the use of unsatisfactory materials. Whenever any damage, destruction or interruption of a utility facility occurs as a result of the work performed by the Contractor, the Contractor shall immediately notify the utility owner. The utility company will make arrangements to restore such facilities to a condition equal to that existing before any such damage or destruction was done.

In the event that the repairs are not made by the Contractor, the Contractor shall reimburse the utility owner for such repairs within 60 days of receiving written notification of said damage. Otherwise, the cost of such repairs will be deducted from the monies due or which will become due the Contractor under the terms of the Contract.

Payment for exploratory potholes for utilities will be made at the contract unit price per FOOT for LOCATING UNDERGROUND UTILITIES as measured from the existing ground surface to the top of the exposed utility. This price shall include all necessary labor, supervision, tools, equipment, permits and incidental to excavate, identity and survey the utility.

HOT-MIX ASPHALT SURFACE REMOVAL (VARIABLE DEPTH): The work covered by this section consists of all labor, tools, equipment, and operations necessary to remove the existing hot-mix asphalt cold-patch overlay as shown on the plans and/or as directed by the Engineer.

HOT-MIX ASPHALT SURFACE REMOVAL (VARIABLE DEPTH) shall be done in accordance with Section 440 of the Standard Specifications, as shown on the plans and/or directed by the Engineer.

The purpose of the HOT-MIX ASPHALT SURFACE REMOVAL (VARIABLE DEPTH) is to remove the existing oil and chi and hot-mix asphalt surface to a depth, which would allow

Monroe County for a two (2) inch HMA surface course to be placed to bring the final pavement surface to the lines and grades as shown on the plans. HOT-MIX ASPHALT SURFACE REMOVAL (VARIABLE DEPTH) is estimated to require the removal of existing pavement from zero (0) to four (4) inches.

The cuttings from the HMA surface removal shall become the property of the contractor and their salvage removal shall be reflected in the contract unit price per square yard for HOT

MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH.

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH shall be paid for at the contract unit price per SQUARE YARD.

TRENCH DRAIN: This work shall consist of constructing cast in place concrete trench drain as shown on the plans, together with necessary cast iron frames according to section 602 and 604 of the Standard Specifications, the plans, as directed by the Engineer, and as herein described

The required cast-iron frame to be set into the cast in place concrete trench drain shall be a heavy-duty trench drain lid. The Contractor shall submit a shop drawing of the proposed trench drain lid to the Engineer for approval according to Article 505.03 of the Standard Specifications.

This work will be paid for at the contract unit price per each for TRENCH DRAIN.

INLETS, SPECIAL: This item of work shall consist of construction and/or reconstruction of inlets according to Section 602 of the Standard Specifications, the plans, as directed by the Engineer, and as herein described.

For INLETS SPECIAL, of number specified, the dimensions shown shall be the inside dimensions. The inlet lid used shall be according to the details as shown in the plans. The ring and cover shall be according to the details shown in the plans. All Inlets, Special, of number specified, shall have cast iron manhole steps in accordance with Standard 602701, Cast Iron Steps. The Contractor shall construct a concrete throat area in front of each inlet at locations according to the details shown on the plans. The cost of construction of the concrete throat area shall be considered included in the cost of constructing the inlet.

This work will be measured and paid for at the contract unit price per each for INLETS, SPECIAL of number specified and no additional compensation will be allowed.

TRAFFIC CONTROL AND PROTECTION, (SPECIAL): Traffic control shall be in accordance with the applicable sections of the “Standard Specifications for Road and Bridge Construction”, the applicable guidelines contained in the “National Manual on Uniform Traffic Control Devices for Streets and Highways”, Illinois Supplement to the National Manual of Uniform Traffic Control Devices, these Special Provisions, and the Traffic Control Plan details and Highway Standards contained herein and in the plans.

Monroe County

Special attention is called to Articles 107.09 and 107.14 of the “Standard Specifications for Road and Bridge Construction and the following Highway Standards relating to traffic control:

701501 701801 701901

In addition, the following Special Provision(s) will also govern traffic control for this project:

VEHICLE AND EQUIPMENT WARNING LIGHTS

WORK ZONE TRAFFIC CONTROL DEVICES

The Contractor shall keep all roads within the project limits open to traffic at all times.

When it is necessary only one lane of traffic may be closed to through traffic. At such times when a lane is closed to thru traffic, the Contractor must provide flaggers and traffic control as depicted on the applicable Highway Standards until such time as the roadway can be reopened to traffic. Additionally, local access to individual properties as well as emergency vehicles shall be maintained at all times. It shall be the Contractor's responsibility to notify the applicable emergency services, postal services, bus services and local school districts of the potential for closures. Sideroad and entrance flaggers shall be required and shall be included in the cost of TRAFFIC CONTROL AND PROTECTION, (SPECIAL).

If at any time signs are in place but are not applicable, they shall be turned from the view of the motorist or covered as directed by the Engineer.

TRAFFIC CONTROL AND PROTECTION, (SPECIAL) will be measured as Lump Sum, which price shall include furnishing, installation, maintenance, relocation, and removal of all signs, cones, barricades, warning lights, flaggers, or any other traffic control device necessary to complete the work as shown in the plans.

This work will be paid for at the contract unit price per lump sum for TRAFFIC CONTROL

AND PROTECTION, (SPECIAL).

STORM SEWERS, WATER MAIN QUALITY PIPE: This work consists of constructing storm sewer to meet water main standards, as required by the IEPA or when otherwise specified. The work shall be performed in accordance with applicable parts of Section 550 of the Standard Specifications, applicable sections of the current edition of the IEPA Regulations (Title 35 of the Illinois Administrative Code, Subtitle F, Chapter II, Section 653.119), the applicable sections of the current edition of the “Standard Specifications for Water and Sewer Main Construction in Illinois”, and as herein specified.

This provision shall govern the installation of all storm sewers which do not meet IEPA criteria for separation distance between storm sewers and water mains. Separation criteria for storm sewers placed adjacent to water mains and water service lines are as follows:

(1) Water mains and water service lines shall be located at least 10 feet horizontally from any existing or proposed drain, storm sewer, sanitary sewer, or sewer service connections.

Monroe County

(2) Water mains and water service lines may be located closer than 10 feet to a sewer line when:

(a) Local conditions prevent a lateral separation of 10 feet; and

(b) The water main or water service invert is 18 inches above the crown of the sewer; and

(c) The water main or water service is either in a separate trench or in the same trench on an undisturbed earth shelf located to one side of the sewer.

(3) A water main or water service shall be separated from a sewer so that its invert is a minimum of 18 inches above the crown of the drain or sewer whenever water mains or services cross storm sewers, sanitary sewers or sewer service connections. The vertical separation shall be maintained for that portion of the water main or water services located within 10 feet horizontally of any sewer or drain crossed.

When it is impossible to meet (1), (2) or (3) above, the storm sewer shall be constructed of concrete pressure pipe, slip-on or mechanical joints ductile iron pipe, or PVC pipe equivalent to water main standards of construction. Construction shall extend on each side of the crossing until the perpendicular distance from the water main or water service to the sewer or drain line is at least 10 feet. Storm sewer meeting water main requirements shall be constructed of the following pipe materials:

Concrete Pressure Pipe Concrete pressure pipe shall conform to the latest ANSI/AWWA C300, C301, C302, or C303.

Joints shall conform to Article 41-2.07B of the “Standard Specifications for Water and Sewer Main Construction in Illinois.”

Ductile Iron Pipe Ductile Iron pipe shall conform to ANSI A 21.51 (AWWA C151), class or thickness designed per ANSI A 21,50 (AWWA C150), tar (seal) coated and/or cement lined per ANSI A 21.4 (AWWA C104), with a mechanical or rubber ring (slip seal or push on) joints.

Joints for ductile iron pipe shall be in accordance with the following applicable specifications.

1. Mechanical Joints - AWWA C111 and C600

2. Push-On Joints - AWWA C111 and C600

Plastic Pipe Plastic pipe shall be marked with the manufacturer’s name (or trademark); ASTM or AWWA specification; Schedule Number, Dimension Ratio (DR) Number or Standard Dimension Ratio (SDR) Number; and Cell Class. The pipe and fittings shall also meet NSF Standard 14 and bear the NSF seal of approval. Fittings shall be compatible with the type of pipe used. The plastic pipe options shall be in accordance with the following:

Monroe County

1. Polyvinyl Chloride (PVC) conforming to ASTM Standard D 1785. Schedule 80 is the minimum required for all pipe sizes, except when the pipe is to be threaded, and then it shall be Schedule 120. It shall be made from PVC compound meeting ASTM D 1784, Class 12454.

2. Polyvinyl Chloride (PVC) conforming to ASTM D 2241. A minimum wall thickness of SDR 26 is required for all pipe sizes. It shall be made from PVC compound meeting ASTM D 1784, Class 12454.

3. Chlorinated Polyvinyl Chloride (CPVC) conforming to ASTM f 441. A minimum of Schedule 80 is required for all pipe sizes. Threaded joints are not allowed. It shall be made from CPVC compound meeting ASTM D 1784, Class 23447.

4. Chlorinated Polyvinyl Chloride (CPVC) conforming to ASTM F 442. A minimum wall thickness of SDR 26 is required for all pipe sizes. It shall be made from CPVC compound meeting ASTM D 1784.

5. Polyvinyl Chloride (PVC) conforming to ANSI/AWWA C900. A minimum of wall thickness of DR 25 is required for all pipe sizes. It shall be made from PVC compound meeting ASTM D 1784, Class 12454.

6. Polyvinyl Chloride (PVC) conforming to ANSI/AWWA C905. A minimum of wall thickness of DR 26 is required for all pipe sizes. It shall be made from PVC compound meeting ASTM D 1784, Class 12454.

7. High Density Poly Ethelyn (HDPE) pressure-rate pipe conforming to ANSI/AWWA C906, ASTM F714, ASTM D3035, ASTM D3350 Cell Class 445574C/E, PPI (TR-4) PE 4710, ANSI/NSF 61/14. A minimum of wall thickness of DR 26 is required for all pipe sizes.

Joining of plastic pipe shall be by push-on joint, solvent welded joint, heat welded joint, flanged joint, or threaded joint, in accordance with the pipe manufacturer’s instructions and industry standards. Special precautions shall be taken to insure clean, dry contact surfaces when making solvent or heat welded joints. Adequate setting time shall be allowed for maximum strength.

Elastotmeric seals (gaskets) used for push-on joints shall comply with ASTM F477.

Solvent cement shall be specific for the plastic pipe material and shall comply with ASTM D 2564 (PVC) or ASTM F 493 (CPVC) and be approved by NSF.

For water-sewer line crossings only, storm sewer meeting water main requirements may also be constructed of reinforced concrete sewer pipe. The pipe shall conform to ASTM C 76 with a joint and rubber gasket meeting ASTM C 443. The joint shall meet the leakage performance test in ASTM C 443. The pipe manufacturer must demonstrate to the owner that the joints pass the leakage performance test prior to installation of the pipe. The pipe class shall meet the requirements of Section 550 of the Standard Specifications for Road and Bridge Construction.

This work will be measured and paid for at the contract unit price per foot for STORM SEWERS, of type specified, WATER MAIN QUALITY PIPE, of the diameter specified.

Monroe County

CONSTRUCTION LAYOUT: This work shall consist of construction staking according to Article 105.09 of the “Standard Specifications for Road and Bridge Construction”, except as modified herein.

The Local Agency will provide adequate reference points to the centerline of survey and benchmarks as shown on the plans and listed herein. All additional control points set by the Local Agency will be identified in the field to the Contractor and all field notes will be kept in the office of the Resident Engineer.

The Contractor shall provide labor, equipment and material to set all additional stakes for the project, which are needed to establish offset stakes, reference points, and all other horizontal or vertical controls, including supplementary benchmarks, necessary to secure a correct layout for the roadway portion of the work.

The Contractor shall be responsible for having the finished work conform to the lines, grades, elevations and dimensions called for on the plans. Inspection or checking of the Contractor’s layout by the Engineer and the acceptance of all or any part of it shall not relieve the Contractor of his/her responsibility to secure the proper dimensions, grades and elevations of the several parts of the work. The Contractor shall exercise care in the preservation of stakes and benchmarks and shall have them reset at his/her expense when any are disturbed.

Responsibility of the Local Agency

• Centerline will be marked with mag nails and painted on the existing pavement surface one time only.

• Control points referenced to the survey centerline will be provided at intervals not exceeding 1000 ft.

• Benchmarks will be established along the project outside of the construction limits lines not exceeding 1000 ft. intervals horizontally and 20 ft. vertically.

• Critical points for proposed curb ramps and corner radii will be staked to establish proper grades.

• Main line concrete curb and gutter will be staked at 50 ft. intervals, including high/low points and points of horizontal inflection for curvature.

• Proposed profile grade line will be established off the completed concrete curb and gutter and will be based on the proposed widths and slopes of the new pavement structure.

• Additional interior pavement stakes or curb and gutter stakes with intervals less than stated above will not be provided. If these locations are needed the contractor will be responsible for setting additional stakes by interpolating between the provided stakes.

• Proposed right-of-way and temporary construction easements limits will be staked at break points and on tangent at intervals not to exceed 100 ft.

• Drainage structures will be staked by the Local Agency to establish proposed horizontal and vertical locations for the drainage system.

• The Local Agency will accept responsibility for the accuracy of the initial control points and stakes as provided herein. The Contractor shall assume full

Monroe County responsibility for all dimensions and measurements taken or derived by the Contractor from control points or stakes set by the Local Agency. It is not the responsibility of the Local Agency, except as provided herein, to check the correctness of the Contractor’s stakes.

• The Local Agency will set all stakes that are the responsibility of the Local Agency one time only. If any additional staking or re-staking is required, the Contractor shall pay the Local Agency for all costs incurred at an hourly rate of $150. Payment for additional staking shall be made directly to the City.

Responsibility of the Contractor

• The Contractor shall provide written requests for all staking to be provided by the Local Agency. A minimum 48-hour advance notice will be required prior to the commencement of all requested staking activities.

• The Contractor shall establish from the given survey points and benchmarks, all additional control points necessary to construct the individual project elements. It is the Contractor’s responsibility to tie in centerline control points in order to preserve them during construction operations.

• The Contractor shall provide all additional staking required to assure completion of the work in substantial conformance with the plans.

• The Contractor shall be responsible for re-establishing all stakes removed or disturbed by construction operations.

• All work shall be according to normally accepted surveying practices. Field notes shall be kept in standard survey field notebooks and those books shall become the property of the Local Agency at the completion of the project. All notes shall be neat, orderly, and in accepted form.

This work will not be measured separately for payment. The cost incurred by the Contractor in complying with the requirement shall be considered as included in the contractor unit prices bid for the various items of work.

COMPLETION DATE PLUS WORKING DAYS: The Contractor shall complete substantial work by April 30, 2027. Substantial work shall consist of all items required to open the road to thru traffic. After the completion date, an additional 10 working days will be allowed to complete seeding, punch list, and final clean up.

CONSTRUCTION COORDINATION: The Contractor shall coordinate construction with the contractor constructing the proposed roundabout at the intersection of Ghent Road and Quarry Road. These project’s working days may overlap, and road closure of Ghent Road will not be allowed during construction of the roundabout project.

LR107-4

State of Illinois Department of Transportation

Bureau of Local Roads and Streets

SPECIAL PROVISION

FOR

INSURANCE

Effective: February 1, 2007 Revised: August 1, 2007

All references to Sections or Articles in this specification shall be construed to mean specific Section or Article of the Standard Specifications for Road and Bridge Construction, adopted by the Department of Transportation.

The Contractor shall name the following entities as additional insured under the Contractor’s general liability insurance policy in accordance with Article 107.27:

The entities listed above and their officers, employees, and agents shall be indemnified and held harmless in accordance with Article 107.26.

City of Columbia

208 S Rapp Street, Columbia IL, 62236

LR1030‐2

State of Illinois

DEPARTMENT OF TRANSPORTATION

Bureau of Local Roads & Streets

SPECIAL PROVISION

FOR

LOCAL QUALITY ASSURANCE/ QUALITY MANAGEMENT QC/QA

Effective: January 1, 2022

Replace the first five paragraphs of Article 1030.06 of the Standard Specifications with the following:

“ 1030.06 Quality Management Program. The Quality Management Program (QMP) will be Quality Control / Quality Assurance (QC/QA) according to the following.”

Delete Article 1030.06(d)(1) of the Standard Specifications.

Revise Article 1030.09(g)(3) of the Standard Specifications to read:

“ (3) If core testing is the density verification method, the Contractor shall provide personnel and equipment to collect density verification cores for the Engineer. Core locations will be determined by the Engineer following the document “Hot-Mix Asphalt QC/QA Procedure for Determining Random Density Locations” at density verification intervals defined in Article 1030.09(b). After the Engineer identifies a density verification location and prior to opening to traffic, the Contractor shall cut a 4 in. (100 mm) diameter core. With the approval of the Engineer, the cores may be cut at a later time.”

Revise Article 1030.09(h)(2) of the Standard Specifications to read:

“ (2) After final rolling and prior to paving subsequent lifts, the Engineer will identify the random density verification test locations. Cores or nuclear density gauge testing will be used for density verification. The method used for density verification will be as selected below.

Density Verification Method Cores

Nuclear Density Gauge (Correlated when paving ≥ 3,000 tons per mixture)

Density verification test locations will be determined according to the document “Hot- Mix Asphalt QC/QA Procedure for Determining Random Density Locations”. The density testing interval for paving wider than or equal to 3 ft (1 m) will be 0.5 miles (800

m) for lift thicknesses of 3 in. (75 mm) or less and 0.2 miles (320 m) for lift thicknesses greater than 3 in. (75 mm). The density testing interval for paving less than 3 ft (1 m) wide will be 1 mile (1,600 m). If a day’s paving will be less than the prescribed density testing interval, the length of the day’s paving will be the interval for that day. The density testing interval for mixtures used for patching will be 50 patches with a minimum of one test per mixture per project.

If core testing is the density verification method, the Engineer will witness the Contractor coring, and secure and take possession of all density samples at the x

LR1030‐2

density verification locations.