This is a Notice to Bidders and Special Provisions document issued by the Illinois Department of Transportation for Contract No. 78B35, a bridge overlay and repair project on Interstate 64 in White County, Illinois. The project involves bridge deck overlay and repairs to structures SN 097-0038 and SN 097-0039 spanning the Little Wabash River, approximately 5.9 miles west of the intersection of I-64 and IL 1. Work includes various bridge repairs, installation and removal of temporary crossovers for staged construction, milling and resurfacing, guardrail installation, temporary drainage items, new approach slabs, pavement connectors, and permanent seeding of disturbed areas. The project limits extend approximately 1,700 feet west and east of the bridge structures. Electronic bids must be submitted to the iCX (Integrated Contractors Exchange) system prior to 12:00 p.m. on November 6, 2026, at which time bids will be publicly opened. The contract will be awarded to the lowest responsive and responsible bidder. The Department reserves the right to reject any or all proposals and to determine responsibility at the time of award.
The contract is funded with Federal-aid Highway Program funds (NHPP-Y5YY(594)) and is classified as a construction contract requiring various federal and state certifications from bidders. Bidders must comply with prevailing wage requirements, Equal Employment Opportunity provisions, Disadvantaged Business Enterprise (DBE) participation requirements, and other federal-aid contract conditions. The project requires notification to the Engineer at least 14 days in advance of starting work, with an additional 7 days of notice required (21 days total) due to width, height, or closure restrictions. Two changeable message signs must be placed and operational for a minimum of 14 calendar days prior to lane or roadway closures. The project must maintain at least one lane of traffic in each direction at all times, with two lanes maintained to the greatest extent possible. Contractors must coordinate with adjacent projects under Contracts 78057 and 78C15 and provide five working days' advance notice of any work affecting those contracts.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Letting November 6, 2026
Notice to Bidders, Specifications and Proposal
Contract No. 78B35 WHITE County Section D9 BRIDGE OVERLAY 2026-2 Route FAI 64 Project NHPP-Y5YY(594) District 9 Construction Funds
Prepared by F
Checked by
(Printed by authority of the State of Illinois)
NOTICE TO BIDDERS
1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.
November 6, 2026 at which time the bids will be publicly opened from the iCX SecureVault.
2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the
Invitation for Bids as:
Contract No. 78B35 WHITE County Section D9 BRIDGE OVERLAY 2026-2 Project NHPP-Y5YY(594) Route FAI 64 District 9 Construction Funds
Bridge deck overlay and repairs to SN 097-0038 and 097-0039 on I-64 over the Little Wabash River, 4.8 miles west of IL 1.
3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.
(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.
4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.
By Order of the Illinois Department of Transportation
Gia Biagi, Secretary
FAI ROUTE 64 (I-64)
PROJECT NHPP-Y5YY(594)
SECTION D9 BRIDGE OVERLAY 2026-2
WHITE COUNTY
CONTRACT NO. 78B35
INDEX
FOR
SUPPLEMENTAL SPECIFICATIONS
AND RECURRING SPECIAL PROVISIONS
Adopted January 1, 2026
This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.
ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)
SUPPLEMENTAL SPECIFICATIONS
Std. Spec. Sec. Page No.
109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires
1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment
SECTION D9 BRIDGE OVERLAY 2026-2
RECURRING SPECIAL PROVISIONS
The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:
CHECK SHEET # PAGE NO.
1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)
3 X EEO
4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes
10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 X Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays
SECTION D9 BRIDGE OVERLAY 2026-2
i
TABLE OF CONTENTS
LOCATION OF PROJECT
DESCRIPTION OF PROJECT
UTILITIES
NOTIFICATION PRIOR TO STARTING WORK
AVAILABILITY OF ELECTRONIC FILES
TRAFFIC CONTROL PLAN
CHANGEABLE MESSAGE SIGNS
COOPERATION BETWEEN CONTRACTORS
TEMPORARY END SECTION
PIPE UNDERDRAINS 4” (SPECIAL)
REMOVE CONCRETE HEADWALLS FOR PIPE DRAINS
REMOVE AND REINSTALL CONCRETE HEADWALLS FOR PIPE DRAIN
INLETS, TYPE A, TYPE 8 GRATE, TEMPORARY
TEMPORARY DRAINAGE CONNECTION
TEMPORARY MANHOLE
TRAFFIC CONTROL AND PROTECTION, (SPECIAL)
RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REMOVAL
RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REPLACEMENT
TEMPORARY PAVEMENT
APPROACH SLAB REMOVAL
STRUCTURAL STEEL REPAIR
DRAINAGE SCUPPERS, DS-11
ACCESS DOOR
CLEANING AND PAINTING CONTACT SURFACE AREAS OF EXISTING STEEL STRUCTURES
DIAMOND GRINDING AND SURFACE TESTING BRIDGE SECTIONS
BRIDGE DECK CONSTRUCTION
BRIDGE DECK GROOVING (LONGITUDINAL)
HOT DIP GALVANIZING FOR STRUCTURAL STEEL
PREFORMED PAVEMENT JOINT SEAL
BRIDGE DECK CONCRETE OVERLAYS
CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)
COMPENSABLE DELAY COSTS (BDE)
DECK SLAB REPAIR
DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)
SECTION D9 BRIDGE OVERLAY 2026-2
ii
ENGINEER’S FIELD OFFICE (BDE)
EROSION CONTROL BLANKET (BDE)
FUEL COST ADJUSTMENT (BDE)
GUARDRAIL (BDE)
HOT-MIX ASPHALT (BDE)
PAVEMENT MARKING (BDE)
PERFORMANCE GRADED ASPHALT BINDER (BDE)
PREFORMED PLASTIC PAVEMENT MARKING (BDE)
REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)
SEEDING (BDE)
SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)
SIGN PANELS AND APPURTENANCES (BDE)
SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)
SPEED DISPLAY TRAILER (BDE)
STEEL COST ADJUSTMENT (BDE)
STRUCTURAL REPAIR OF CONCRETE (BDE)
SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)
SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)
SUBMISSION OF BIDDERS LIST INFORMATION (BDE)
SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)
SURVEYING SERVICES (BDE)
TEMPORARY CONCRETE BARRIER (BDE)
VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)
WEEKLY DBE TRUCKING REPORTS (BDE)
WORK ZONE TRAFFIC CONTROL DEVICES (BDE)
WORK ZONE WIDTH RESTRICTION (BDE)
WORKING DAYS (BDE)
SECTION D9 BRIDGE OVERLAY 2026-2
STATE OF ILLINOIS
SPECIAL PROVISIONS
The following Special Provisions supplement the “Standard Specifications for Road and Bridge Construction,” adopted January 1, 2022, the latest edition of the “Manual on Uniform Traffic Control Devices for Streets and Highways”, and the “Manual of Test Procedures for Materials” in effect on the date of invitation for bids, and the “Supplemental Specifications and Recurring Special Provisions” indicated on the Check Sheet included herein, which apply to and govern the construction of FAI Route 64 (I-64), Project NHPP-Y5YY(594), Section D9 Bridge Overlay 2026- 2, White County, Contract No. 78B35, and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.
FAI Route 64 (I-64)
Project NHPP-Y5YY(594) Section D9 Bridge Overlay 2026-2
White County Contract No. 78B35
LOCATION OF PROJECT
This project is located on I-64, approximately 5.9 miles west of the intersection of I-64 and IL 1 in White County. The structure currently carries I-64 over the Little Wabash River. The project limits are approximately 1,700 feet west and 1,700 feet east of SN 097-0038/0039.
DESCRIPTION OF PROJECT
This project consists of various bridge repairs on SN 097-0038 and SN 097-0039, along with the installation and removal of temporary crossovers for staged construction. It also includes milling and resurfacing, guardrail, temporary drainage items, and new approach slabs and pavement connectors. Disturbed areas will be stabilized with permanent seeding.
SECTION D9 BRIDGE OVERLAY 2026-2
UTILITIES
Effective 1984 Revised 4/8/20
There are no known utility conflicts within the project limits. However, the following utility companies have facilities within the project limits:
Status of JULIE Member Utilities 78B35 I-64 Bridge Repairs, White County
Name and Address of Utility
Type
Location
Estimated Adjustment
Status CountryMark 6701 Lower Harmony Rd Mt. Vernon, IN 47620 ATTN: Jamie Marques Tel: (812) 833-2598 Cell: (812) 270-2107 Email: Jamie.Marques@CountryMark.com
GAS
PIPELINE
THROUGHOUT NONE
ANTICIPATED
Grayville, City of 119 S. Middle Street Grayville, IL 62844 ATTN: Scott Irvine Tel: (618) 375-3671 Cell: (618) 384-7958 Email: sirvine2016@gmail.com
WATER THROUGHOUT NONE
ANTICIPATED
Additional utility information may be obtained by calling the "Joint Utility Location Information for Excavators" phone number, 800-892-0123. This project is located in White County.
NOTIFICATION PRIOR TO STARTING WORK
Effective 12/05 Revised 2/10/17
Revise the first sentence of Article 107.09 Public Convenience and Safety to the following “The Contractor shall notify the Engineer at least 14 days in advance of starting any construction work.
For projects involving width or height restrictions or complete closures of the roadway or ramp, an additional seven days of notice (21 days total) will be required.”
This additional notification is required, so the public can be notified of the pending construction.
SECTION D9 BRIDGE OVERLAY 2026-2
AVAILABILITY OF ELECTRONIC FILES
Effective 10/16 Revised 12/11/19
Electronic files of this project will be made available to the Contractor after contract award.
Contractor shall coordinate obtaining electronic files through the Engineer. If there is a conflict between the electronic files and the printed contract plans and documents, the printed contract plans and documents shall take precedence over the electronic files. The Contractor shall accept all risk associated with using the electronic files and shall hold the Department harmless for any errors or omissions in the electronic files and the data contained therein. Errors or delays resulting from the use of the electronic files by the Contractor shall not result in an extension of time for any interim or final completion date or shall not be considered cause for additional compensation.
The Contractor shall not use, share, or distribute these electronic files except for the purpose of constructing this contract. Any claims by third parties due to use or errors shall be the sole responsibility of the Contractor. The Contractor shall include this disclaimer with the transfer of these electronic files to any other parties and shall include appropriate language binding them to similar responsibilities.
TRAFFIC CONTROL PLAN
Effective 1985 Revised 4/17/23
During the entire construction period, the road shall be kept open to traffic as follows:
(a) I-64 shall be kept open to at least one lane of traffic in each direction at all times and to two lanes of traffic to the greatest extent possible.
CHANGEABLE MESSAGE SIGNS
Revised 4/15/20
This work consists of furnishing, placing, and maintaining changeable message sign(s) according to Section 701 and the following:
A total of two changeable message signs shall be required in this contract. All signs must be in place and operational for a minimum of 14 calendar days prior to lane or roadway closures. Each sign shall state the day work will begin and delays are possible. The exact message will be approved by the Engineer. The Contractor may be required to relocate each sign multiple times during the contract at his or her expense. The exact location of the placement of these signs shall be determined in the field by the Engineer.
The furnishing, placing, and maintaining of portable changeable message sign(s) will be paid for per CALENDAR DAY as CHANGEABLE MESSAGE SIGN.
SECTION D9 BRIDGE OVERLAY 2026-2
COOPERATION BETWEEN CONTRACTORS
Revised 2/10/17
The Contractor is to be aware that traffic control limits of this contract may overlap those of another project(s) that may be under construction along I-64 concurrently with this work. The Contractor shall coordinate his/her work with the other contractors to minimize any possible conflicts. The Contractor shall also notify the Engineer five working days in advance of any work that may affect other adjacent contracts.
• Adjacent Project, Contract No. 78057: Replacement of SN 097-0003(04)- Carrying I-64 over the Wabash River
• Adjacent Project, Contract No. 78C15: Painting SN 097-0045 carrying TR-214 over I-64 and SN 097-0050 carrying TR-394 over I-64
TEMPORARY END SECTION
This work shall consist of constructing, maintaining, and removing end sections for the temporary pipes to be installed at the crossover locations. This work shall be in accordance with section 542 of the Standard Specifications.
This work will be paid for per EACH as TEMPORARY END SECTION.
PIPE UNDERDRAINS 4” (SPECIAL)
Description. This work shall consist of installing the necessary pipe underdrain outlets as shown in the plans and in accordance with the applicable portions of Sections 601 and 602 of the Standard Specifications. Pipe underdrains shall be type 2, 4” in size. This work shall be according to Section 601 of the Standard Specifications and Standard 601001. Except, the perforated pipe shall be encased in fabric in accordance with Article 1080.01.
This work will be temporary and shall include its removal at the appropriate stage.
Method of Measurement. This work will be measured for payment in feet in place.
Basis of Payment. This work will be paid for at the contract unit price per FOOT for PIPE UNDERDRAINS 4” (SPECIAL), which shall include all labor, equipment, and materials required to complete the work as herein specified.
SECTION D9 BRIDGE OVERLAY 2026-2
REMOVE CONCRETE HEADWALLS FOR PIPE DRAINS
Description. This work shall consist of the complete removal and disposal of concrete headwalls for pipe drains at the locations shown in the plans.
Method of Measurement. This work will be measured for payment for each headwall removed.
Basis of Payment. This work will be paid for at the contract unit price per EACH for REMOVE
CONCRETE HEADWALLS FOR PIPE DRAINS.
REMOVE AND REINSTALL CONCRETE HEADWALLS FOR PIPE DRAIN
Description. This work shall consist of the complete removal and reinstallation of existing precast concrete headwalls for pipe underdrain outlet pipes as shown in the plans or as directed by the Engineer.
Method of Measurement. This work will be measured for payment in units of each at the location shown on the plans regardless of size, type, or material. The excavation of earth necessary to perform the removal of end treatments and all backfill required to fill depressions will not be measured for payment but shall be included in the cost of the concrete headwall removal.
Basis of Payment. This work will be paid for the contract unit price per EACH for REMOVE AND
REINSTALL CONCRETE HEADWALLS FOR PIPE DRAINS.
INLETS, TYPE A, TYPE 8 GRATE, TEMPORARY
This work shall consist of constructing, maintaining, and removing inlets and associated frames, grates, and lids of the size and type specified for the temporary pipes to be installed at the crossover locations. This work shall be in accordance with Section 602, 604, and 605 of the Standard Specifications.
The temporary inlet at station 5504+00, 18’ RT shall be an inlet, type A with a type 8 grate.
The temporary inlet at station 5504+00, 18’ LT shall be an inlet, type A with a type 8 grate.
The temporary inlet at station 5528+00, 19’ RT shall be an inlet, type A with a Type 8 grate.
The temporary inlet at station 5528+00, 19’ LT shall be an inlet, type A with a Type 8 grate.
Basis of Payment. The work will be paid for per EACH as INLETS, TYPE A, TYPE 8 GRATE, TEMPORARY.
SECTION D9 BRIDGE OVERLAY 2026-2
TEMPORARY DRAINAGE CONNECTION
Description. This work shall consist of connecting existing pipe underdrains to proposed pipe underdrains, as well as connecting proposed pipe underdrains to the proposed temporary pipe culverts, 24”. All temporary drainage connections are meant to maintain existing drainage system functionality as shown in the plans and in accordance with Section 542, 550, and 601 of the Standard Specifications.
Direct connections will be allowed to or from existing pipes that will be removed in a subsequent construction stage. Backfill of excavation is included in the cost of this item. Backfill material shall be in accordance with Section 208 or as approved by the Engineer.
Basis of Payment. This work will be paid for at the contract unit price per EACH for TEMPORARY
DRAINAGE CONNECTION.
TEMPORARY MANHOLE
Description. This work shall consist of furnishing, installing, maintaining, and removing manholes and associated frames, grates, and lids of the size and type specified at the locations shown in the plans for the purpose of providing positive pavement drainage during construction. This work shall be performed in accordance with Section 602, 604, and 605 of the Standard Specifications.
Basis of Payment. This work will be paid for at the contract unit price per EACH for TEMPORARY
MANHOLE.
TRAFFIC CONTROL AND PROTECTION, (SPECIAL)
This work includes furnishing, installing, maintaining, and removing all traffic control devices;
removing conflicting pavement markings including any conflicting markings outside the project limits; and providing all paint required for traffic control and protection as shown on Standards 701101, 701106, 701400, 701401, 701406, 701416, 701422, 701423, 701426, 701428, and 701901, as shown in the plans in accordance with the Traffic Control Plan, in accordance with Section 701 of the Standard Specifications, as directed by the Engineer, and as specified herein.
This work includes an estimated 53,000 feet of temporary pavement marking for all stages combined that will also include pavement marking removal. As directed by the Engineer, any subsequent temporary pavement markings required to be placed between stages or at the end of a construction season shall not be measured for payment but shall be included in the cost of Traffic Control and Protection, (Special).
Prior to beginning work on the project, the Contractor shall furnish and install type III barricades and advance warning signs as shown on the plans and as detailed in the applicable highway
SECTION D9 BRIDGE OVERLAY 2026-2
standards. Barricade placement and sign spacing may be adjusted by the Engineer to suit field conditions.
Throughout the construction period, all material piles, equipment, open excavations, or other obstructions or hazards to motorists or pedestrians shall be enclosed by fences or protected by barricades and proper lighting.
Traffic control and protection required for the successful completion of this project will be paid for at the contract unit price per LUMP SUM for TRAFFIC CONTROL AND PROTECTION, (SPECIAL), which shall include all work as specified herein and all other provisions required by law for the protection and safety of property and individuals in a construction zone.
RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REMOVAL
Description. This work shall be completed in accordance with Section 783 of the Standard Specifications. This work shall consist of removing the reflector unit from existing raised reflector pavement markers that will remain in place at the end of construction activities. Existing reflectors that conflict with revised traffic patterns shall be removed immediately to facilitate a change in lane assignment. If darkness or inclement weather prohibits the removal operations, such operations shall be resumed the next morning when weather permits.
The base casting shall remain in place in areas where no pavement rehabilitation is required, therefore only the reflector shall be removed. Debris from the removal operations shall be removed from the pavement prior to opening the roadway to traffic.
Basis of Payment. This work will be measured for payment at the contract unit price per EACH for RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REMOVAL. Payment shall be full compensation for materials, labor, and equipment required to complete this work.
RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REPLACEMENT
Description. This work shall be completed in accordance with Section 781 of the Standard Specifications. This work shall consist of the reinstallation of reflectors into the raised pavement marker castings upon completion of staging in which the markers were in conflict with temporary lane usage.
Basis of Payment. This work will be paid for at the contract unit price per EACH for RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REPLACEMENT. Payment shall be full compensation for materials, labor, and equipment required to complete this work.
SECTION D9 BRIDGE OVERLAY 2026-2
TEMPORARY PAVEMENT
This work shall consist of installing pavement at the proposed crossover locations. The Contractor shall construct 12¼” full depth HMA pavement or 10” jointed PCC pavement as temporary pavement.
HMA work shall be done according to Section 407 of the Standard Specifications.
The temporary pavement will be measured in place, and the quantity computed in square yards. The width of measurement shall be the width of the top surface as shown on the plans. Bituminous materials (tack coat and prime coat) will not be paid for separately but will be considered included in the cost of temporary pavement.
The work will be paid for at the contract unit price per SQUARE YARD for TEMPORARY
PAVEMENT.
APPROACH SLAB REMOVAL
Description. This work shall consist of the complete removal and disposal of the existing concrete approach slabs including bituminous overlays, reinforcing bars, and sleeper slabs in accordance with the applicable portions of Sections 440 and 501 of the Standard Specifications or as directed by the Engineer. The bituminous overlays are approximately a total thickness of 1.75 inches.
This work shall also include the removal and disposal of existing timber piles, pile caps, and other related appurtenances to at least 1 foot below the proposed elevation of subgrade, bottom of approach slab, or ground surface within the area of construction and within the limits of right of way when encountered. This work shall also include the removal and disposal of any mud jack cylinders encountered within the existing approach slabs.
The Contractor shall remove the existing approach slabs in a manner so as not to damage the adjacent structures that are to remain.
Method of Measurement. This work will be measured for payment in place, and the area will be computed in square yards.
Saw cuts will not be measured for payment and shall be included in the cost of approach slab removal.
Basis of Payment. This work will be paid for at the contract unit price per SQUARE YARD for APPROACH SLAB REMOVAL, which shall include all labor and equipment necessary to remove and dispose of the entire approach slab pavement and it’s appurtenances.
SECTION D9 BRIDGE OVERLAY 2026-2
STRUCTURAL STEEL REPAIR
Description. This work shall consist of furnishing all labor, equipment, and materials necessary to furnish and install steel repair plates and members according to Section 505 and removal and disposal of structural steel members as necessary according to Section 501 of the Standard Specifications, as indicated on the plans, and in this special provision.
Existing members noted in the plans to have structural steel repair, that are also noted to be straightened, shall be straightened prior to the connection of any new steel repair plates or members. If beam straightening is required, it shall not be included in this item and shall be paid for separately.
Where required to align with existing holes, field drilling of holes in new members shall be accomplished using existing holes as a template unless field measurements are used to verify the plan dimensions. Burning of holes will not be permitted. All field drilling and grinding necessary to furnish and install the new steel plates and members shall be included in this item.
The removal and disposal of any existing members, bolts, or rivets necessary for the installation of the new members as shown in the plans shall be included in this item. Burning existing rivets will only be allowed near steel surfaces which are to be removed and discarded. Burning existing rivets will not be allowed for members to remain in place or members that are to be removed and reinstalled. When burning rivets is not allowed, the head of the rivet shall be sheared off, and the shank driven or drilled out. Extreme care shall be taken while removing the rivets so to not damage the existing structural steel which is to remain. All damage to existing members which are to remain shall be repaired or the member replaced to the satisfaction of the Engineer. Repair or replacement of damaged members shall be at the Contractor’s expense.
Method of Measurement. The structural steel will be measured in pounds using the approved shipping weight or by measuring on approved platform scales.
Basis of Payment. This work will be paid for at the contract unit price per POUND for
STRUCTURAL STEEL REPAIR.
DRAINAGE SCUPPERS, DS-11
Description. This work shall consist of furnishing and installing drainage scuppers, and all appurtenances, as shown on the structure plans.
Method of Measurement. This work will be measured for payment in place as each per scupper.
Basis of Payment. This work will be paid for at the contract unit price per EACH for DRAINAGE SCUPPERS, DS-11, which shall include installation and all materials. No additional compensation will be allowed.
SECTION D9 BRIDGE OVERLAY 2026-2
ACCESS DOOR
Description. This work shall consist of furnishing all labor, material, and equipment required for the installation of access doors and frames in the curtain wall of the existing vaulted abutments and in the face of piers as detailed on the plans.
Materials. Materials shall be according to the following.
Item ............................................................................................................ Article/Section (a) Structural Steel ......................................................................................................1006.04(b) Stainless Steel Hardware.......................................................................................1006.31(c) Expansion Bolts .....................................................................................................1006.09(d) Metal Hardware Cast into Concrete ......................................................................1006.13(e) Aluminum Alloy ................................................................................. ASTM B308 6061-T6(f) Nonshrink Grout..........................................................................................................1024.02
Equipment. It will be the Contractor’s responsibility to determine and utilize the method and equipment which best suits the operation to install the door. This equipment shall be available to the inspector until final acceptance of the work.
General. The steel door frames in the abutment curtain walls shall be cast into the concrete walls per applicable provisions of Section 503 of the Standard Specifications and the details provided in the plans.
Anchors shall be installed through pre-drilled holes in the pier door frames. Installation shall be in accordance with Article 509.06 of the Standard Specifications.
The Contractor shall be responsible for ensuring the door frames in the pier walls fit the openings cut in those walls for the doors. All accumulated foreign material shall be removed from the door opening and immediate surroundings. Any space between the steel frame and the concrete opening shall be filled with steel shims and non-shrink grout. This work shall be included in the cost of the access door.
Method of Measurement. This work will be measured per each at the locations specified.
Basis of Payment. This work will be paid for at the contract unit price per EACH for ACCESS DOOR at the locations specified.
SECTION D9 BRIDGE OVERLAY 2026-2
CLEANING AND PAINTING CONTACT SURFACE AREAS OF EXISTING STEEL
STRUCTURES
Effective: June 30, 2003 Revised: October 23, 2020
Description. This work shall consist of the surface preparation and painting of existing steel structures in areas that will be in contact with new steel.
The existing steel at primary connections (faying surfaces) shall be prepared and primed as specified herein prior to connecting new structural steel to the existing structure.
The existing steel at secondary connections shall be prepared, and if bare metal is exposed, primed as specified herein prior to connecting new structural steel to the existing structure.
General. The existing coatings shall be assumed to contain lead and may also contain other toxic metals. Any plans that may be furnished for the work, and any dimensions or other information given regarding a structure, are only for the purpose of assisting bidders in determining the type and location of steel to be cleaned and painted. It is the responsibility of the Contractor to verify this information and the accuracy of the information provided shall in no way affect the price bid for structural steel.
Materials. The Bureau of Materials and Physical Research has established a list of all products that have met preliminary requirements. Each batch of material must be tested and approved before use.
The paint materials shall meet the requirements of the following articles of the Standard Specification:
Item Article
a) Organic Zinc Rich Primer 1008.05
b) Aluminum Epoxy Mastic 1008.03
Submittals:
a) Manufacturer's application instructions and product data sheets. Copies of the paint manufacturer's application instructions and product data sheets shall be furnished to the Engineer at the field site before steel cleaning begins.
b) Waste Management Plan. The Waste Management Plan shall address all aspects of waste handling, storage, testing, hauling and disposal. Include the names, addresses, and a contact person for the proposed licensed waste haulers and disposal facilities. Submit the name and qualifications of the laboratory proposed for Toxicity Characteristic Leaching Procedure (TCLP) analysis.
c) Quality Control (QC) Program. The QC Program shall identify the following; the instrumentation that will be used, a schedule of required measurements and observations, procedures for correcting unacceptable work, and procedures for improving surface preparation and painting quality as a result of quality control findings.
SECTION D9 BRIDGE OVERLAY 2026-2
Construction Requirements. The Contractor shall perform first line, in process QC inspections.
The Contractor shall implement the submitted and accepted QC Program to ensure that the work accomplished complies with these specifications. The designated Quality Control inspector shall be onsite full time during any operations that affect the quality of the coating system (e.g., surface preparation, coating mixing and application, and evaluations between coats and upon completion of the work). The Contractor shall provide artificial lighting in areas where natural light is inadequate, as determined by the Engineer, to allow proper cleaning, inspection, and painting.
Illumination for inspection shall be at least 30 foot-candles (325 LUX). Illumination for cleaning and priming, including the working platforms, access, and entryways shall be at least 20 foot-candles (215 LUX).
The Contractor shall be responsible for any damage caused to persons, vehicles, or property, except as indemnified by the Response Action Contractor Indemnification Act. Whenever the intended purposes of the protective devices are not being accomplished, as determined by the Engineer, work shall be immediately suspended until corrections are made. Painted surfaces damaged by any Contractor's operation shall be removed and repainted, as directed by the Engineer, at the Contractor's expense.
Weather Conditions. Surfaces to be primed after cleaning shall remain free of moisture and other contaminants. The Contractor shall control his/her operations to ensure that dust, dirt, or moisture does not come in contact with surfaces cleaned prior to painting. Surfaces painted shall be protected until the coating is sufficiently cured to protect itself from damage.
Restrictions on ambient conditions shall be as per the coating manufacturer’s written specifications.
Surface Preparation: Prior to making connections or painting, all loose abrasives, paint, and residue shall be contained, collected, removed from the surface area and properly disposed of as specified later in this specification.
Soluble Salt Remediation. The Contractor shall implement surface preparation procedures and processes that will remove chloride from the surfaces to levels below 7 micrograms per square centimeter. Surfaces that may be contaminated with chloride include, but are not limited to, expansion joints and all areas that are subject to roadway splash or runoff such as fascia beams and stringers. Surfaces shall be tested for chlorides at a frequency of five tests per bearing line, with tests performed on both the beams and diaphragms/cross-frames at expansion joints.
Methods of chloride removal may include, but are not limited to, hand washing, steam cleaning, or pressure washing with or without the addition of a chemical soluble salt remover as approved by the coating manufacturer and scrubbing before or after initial paint removal. The Contractor may also elect to clean the steel and allow it to rust overnight followed by recleaning, or by utilizing blends of fine and coarse abrasives during blast cleaning, wet abrasive/water jetting methods of preparation, or combinations of the above. If steam or water cleaning methods of chloride removal are utilized over surfaces where the coating has been completely removed, and the water does not contact any lead containing coatings, the water does not have to be collected. The Contractor shall provide the proposed procedures for chloride remediation in the Surface Preparation/Painting Plan.
Upon completion of the chloride remediation steps, the Contractor shall use cell methods of field chloride extraction and test procedures (e.g., silver dichromate) accepted by the Engineer, to test
SECTION D9 BRIDGE OVERLAY 2026-2
representative surfaces that were previously rusted (e.g., pitted steel) for the presence of remaining chlorides. Remaining chloride levels shall be no greater than 7µg/sq cm as read directly from the surface without any multiplier applied to the results. The testing must be performed, and the results must be acceptable, prior to painting each day.
A minimum of 5 tests per 1000 sq. ft. (93 sq m) or fraction thereof completed in a given day, shall be conducted at project start up. If results greater than 7 µg/sq cm are detected, the surfaces shall be recleaned and retested at the same frequency. If acceptable results are achieved on three consecutive days in which testing is conducted, the test frequency may be reduced to 1 test per 1000 sq. ft. (93 sq. m) prepared each day provided the chloride remediation process remains unchanged. If unacceptable results are encountered, or the methods of chloride remediation are changed, the Contractor shall resume testing at a frequency of 5 tests per 1000 sq. ft. (93 sq. m).
Following successful chloride testing the chloride test areas shall be cleaned as specified below.
Painted surfaces of new steel damaged by abrasive blasting or by the Contractor's operations shall be repainted, as directed by the Engineer, at the Contractor's expense.
a) Primary Connections. Primary connections shall be defined as faying (contact) surfaces of high-strength bolted connections specifically noted in plans.
The surfaces of existing steel in all areas that will be in direct contact with new steel shall be prepared according to SSPC-SP15, Commercial Grade Power Tool Cleaning using vacuum-shrouded power tools equipped with HEPA filtration. The surface preparation shall remove all rust, mill scale, and existing paint from the contact surface. At the Contractors option, vacuum blast cleaning according to SSPC-SP6, Commercial Blast Cleaning may be substituted for SSPC-SP15 at no additional cost to the Department. The surface profile for primary connection surfaces shall be 1.5 to 3.5 mils (38 to 90 microns).
b) Secondary Connections. Secondary connections shall be defined as all surface areas of existing members that will be in contact with new steel except as previously defined as primary connections.
These surfaces of existing steel in all areas that will be in direct contact with new steel shall be prepared according to SSPC-SP3, Power Tool Cleaning using vacuum-shrouded power tools equipped with HEPA filtration. The surface preparation shall remove all loose rust, loose mill scale, and loose, checked, alligatored and peeling paint from the contact surface. At the Contractors option, vacuum blast cleaning according to SSPC-SP6, Commercial Blast Cleaning or SSPC-SP15, Commercial Grade Power Tool Cleaning may be substituted for SSPC-SP3 at no additional cost to the Department. The surface profile for abrasive blast cleaning and Commercial Grade Power Tool Cleaning shall be 1.5 to 3.5 mils (38 to 90 microns).
Painting. The manufacturer’s written instructions shall be followed for paint storage, mixing, thinning, application, ambient conditions, and drying times between coats. The surface shall be free of dirt, dust, and debris prior to the application of any coat. The coatings shall be applied as a continuous film of uniform thickness free of defects including, but not limited to, runs, sags, overspray, dryspray, pinholes, voids, skips, misses, and shadow-through. Defects such as runs and sags shall be brushed out immediately during application.
SECTION D9 BRIDGE OVERLAY 2026-2
The Engineer will approve surface preparation prior to priming.
a) For Primary connections the surface of the prepared steel cleaned to bare metal shall be primed with an organic zinc rich primer between 3.5 and 5.0 mils (90 and 125 microns) dry film thickness.
b) For Secondary Connections the surface of the prepared steel cleaned to bare metal shall be painted with either one coat of epoxy mastic between 5 and 7 mils (125 microns to 180 microns) in thickness or one coat of an organic zinc rich primer between 3.5 and 5.0 mils (90 and 125 microns) in thickness. Areas not cleaned to bare metal need not be painted.
For primary connections, the primer on the surface of the prepared steel shall cure according to the manufacturers instructions prior to connecting new structural steel to the existing structure.
For secondary connections, the primer on the surface of the prepared steel need only be dry to touch prior to connecting new steel to the existing structure.
The surrounding coating at each prepared location shall be feathered for a minimum distance of 1 1/2 in. (40 mm) to achieve a smooth transition between the prepared areas and the existing coating.
Collection, Temporary Storage, Transportation and Disposal of Waste. The Contractor and the Department are considered to be co-generators of the waste.
The Contractor is responsible for all aspects of waste collection, testing and identification, handling, storage, transportation, and disposal according to these specifications and all applicable Federal, State, and Local regulations. The Contractor shall provide for Engineer review and acceptance a Waste Management Plan that addresses all aspects of waste handling, storage, and testing, and provides the names, addresses, and a contact person for the proposed licensed waste haulers and disposal facilities. The Department will not perform any functions relating to the waste other than provide EPA identification numbers, provide the Contractor with the emergency response information, the emergency response telephone number required to be provided on the manifest, and to sign the waste manifest. The Engineer will obtain the identification numbers from the state and federal environmental protection agencies for the bridge(s) to be painted and furnish those to the Contractor.
All surface preparation/paint residues shall be collected daily and deposited in all-weather containers supplied by the Contractor as temporary storage. The storage area shall be secure to prevent unauthorized entry or tampering with the containers. Acceptable measures include storage within a fully enclosed (e.g., fenced in) and locked area, within a temporary building, or implementing other reasonable means to reduce the possibility of vandalism or exposure of the waste to the public or the environment (e.g., securing the lids or covers of waste containers and roll-off boxes). Waste shall not be stored outside of the containers. Waste shall be collected and transferred to bulk containers taking extra precautions as necessary to prevent the suspension of residues in air or contamination of surrounding surfaces. Precautions may include the transfer of the material within a tarpaulin enclosure. Transfer into roll-off boxes shall be planned to minimize the need for workers to enter the roll-off box.
No residues shall remain on uncontained surfaces overnight. Waste materials shall not be removed through floor drains or by throwing them over the side of the bridge. Flammable materials shall not be stored around or under any bridge structures.
SECTION D9 BRIDGE OVERLAY 2026-2
The all-weather containers shall meet the requirements for the transportation of hazardous materials and as approved by the Department. Acceptable containers include covered roll-off boxes and 55-gallon drums (17H). The Contractor shall insure that no breaks and no deterioration of these containers occurs and shall maintain a written log of weekly inspections of the condition of the containers. A copy of the log shall be furnished to the Engineer upon request. The containers shall be kept closed and sealed from moisture except during the addition of waste.
Each container shall be permanently identified with the date that waste was placed into the container, contract number, hazardous waste name and ID number, and other information required by the IEPA.
The Contractor shall have each waste stream sampled for each project and tested by TCLP and according to EPA and disposal company requirements. The Engineer shall be notified in advance when the samples will be collected. The samples shall be collected and shipped for testing within the first week of the project, with the results due back to the Engineer within 10 days. The costs of testing shall be considered included in this work. Copies of the test results shall be provided to the Engineer prior to shipping the waste.
The existing paint removed, together with the surface preparation media (e.g. abrasive) shall be handled as a hazardous waste, regardless of the TCLP results. The waste shall be transported by a licensed hazardous waste transporter, treated by an IEPA permitted treatment facility to a non-hazardous special waste and disposed of at an IEPA permitted disposal facility in Illinois.
The treatment/disposal facilities shall be approved by the Engineer and shall hold an IEPA permit for waste disposal and waste stream authorization for this cleaning residue. The IEPA permit and waste stream authorization must be obtained prior to beginning cleaning, except that if necessary, limited paint removal will be permitted in order to obtain samples of the waste for the disposal facilities. The waste shall be shipped to the facility within 90 days of the first accumulation of the waste in the containers. When permitted by the Engineer, waste from multiple bridges in the same contract may be transported by the Contractor to a central waste storage location(s) approved by the Engineer in order to consolidate the material for pick up, and to minimize the storage of waste containers at multiple remote sites after demobilization. Arrangements for the final waste pickup shall be made with the waste hauler by the time blast cleaning operations are completed or as required to meet the 90-day limit stated above.
The Contractor shall submit a waste accumulation inventory table to the Engineer no later than the 5th day of the month. The table shall show the number and size of waste containers filled each day in the preceding month and the amount of waste shipped that month, including the dates of shipments.
The Contractor shall prepare a manifest supplied by the IEPA for off-site treatment and disposal before transporting the hazardous waste off-site. The Contractor shall prepare a land ban notification for the waste to be furnished to the disposal facility. The Contractor shall obtain the handwritten signature of the initial transporter and date of the acceptance of the manifest. The Contractor shall send one copy of the manifest to the IEPA within two working days of transporting the waste off-site. The Contractor shall furnish the generator copy of the manifest and a copy of the land ban notification to the Engineer. The Contractor shall give the transporter the remaining copies of the manifest.
SECTION D9 BRIDGE OVERLAY 2026-2
All other project waste shall be removed from the site according to Federal, State and Local regulations, with all waste removed from the site prior to final Contractor demobilization.
The Contractor shall make arrangements to have other hazardous waste, which he/she generates, such as used paint solvent, transported to the Contractor's facility at the end of each day that this waste is generated. These hazardous wastes shall be manifested using the Contractor's own generator number to a treatment or disposal facility from the Contractor's facility.
The Contractor shall not combine solvents or other wastes with cleaning residue wastes. All waste streams shall be stored in separate containers.
The Contractor is responsible for the payment of any fines and undertaking any clean up activities mandated by State or federal environmental agencies for improper waste handling, storage, transportation, or disposal.
Contractor personnel shall be trained in the proper handling of hazardous waste, and the necessary notification and clean up requirements in the event of a spill. The Contractor shall maintain a copy of the personnel training records at each bridge site.
It is understood and agreed that the cost of all work outlined above, unless otherwise specified, has been included in the bid, and no extra compensation will be allowed.
Basis of Payment: This work will be considered included in the cost of "Furnishing and Erecting Structural Steel”, "Erecting Structural Steel", or “Structural Steel Repair”, as applicable, according to the Standard Specifications, unless otherwise specified on the plans.
DIAMOND GRINDING AND SURFACE TESTING BRIDGE SECTIONS
Effective: December 6, 2004 Revised: April 15, 2022
Description. This work shall consist of diamond grinding and surface testing bridge sections.
The bridge section shall consist of the bridge deck plus the bridge approach slab and pavement connector, if present, at each end of the bridge.
Equipment. Equipment shall be according to the following.
(a) Diamond Grinder. The diamond grinder shall be a self-propelled planing machine specifically designed for diamond saw grinding. It shall be capable of accurately establishing the profile grade and controlling the grinding cross slope. It shall also have an effective means for removing excess material and slurry from the surface and for preventing dust from escaping into the air. The removal of slurry shall be continuous throughout the grinding operation. The slurry shall be disposed of according to Article 202.03.
The grinding head shall be a minimum of 4 ft. (1.2 m) wide and the diamond saw blades shall be gang mounted on the grinding head at a rate of 50 to 60 blades / ft. (164 to 197 blades/m).
SECTION D9 BRIDGE OVERLAY 2026-2
(b) Surface Testing Equipment. Required surface testing and analysis equipment and their jobsite transportation shall be provided by the Contractor. The Profile Testing Device shall be according to Illinois Test Procedure 701 except the trace analysis shall be based on traces from bridge sections.
CONSTRUCTION REQUIREMENTS
General. After all components have been properly cured, the bridge section shall be ground over its entire length and over a width that extends to within 2 ft. (600 mm) of the curbs or parapets.
Grinding shall be done separately before any saw cut grooving, and no concurrent combination of the two operations…