This is a Notice to Bidders and Specifications document issued by the Illinois Department of Transportation (IDOT) for Contract No. 78520, a highway construction project in Jefferson County. The project involves 4.4 miles of milling, resurfacing, crown and superelevation corrections, safety shoulders, earthwork, and drainage improvements on IL Route 37 (FAS 2826) from south of Structure Number 041-0032 over Casey Fork to Campground Road north of Bonnie. The work includes HMA milling of 2 inches and resurfacing with variable depth HMA binder course, HMA leveling binder of 1 inch, and HMA surface course of 1 inch; addition of 8-foot wide HMA safety shoulders with foreslope correction and rumble strips; and guardrail updates as needed. Three structures are included: Structure Number 041-0035 will be replaced, Structure Number 041-0105 will receive waterproofing treatment and a 1-inch HMA surface course overlay, and Structure Number 041-0097 will be gapped. Electronic bids must be submitted to the iCX system (Integrated Contractors Exchange) no later than 12:00 p.m. on July 31, 2026, at which time bids will be publicly opened from the iCX SecureVault.

The contract will be awarded to the lowest responsive and responsible bidder in accordance with the terms and conditions established by IDOT. The project is funded with federal-aid funds (HSIP-STP-8GMK(127)) and subject to applicable federal and state law requirements, including prevailing wage, EEO, and DBE participation provisions. The contract documents include the Notice to Bidders, invitation for bids, proposal forms, Standard Specifications for Road and Bridge Construction, Supplemental Specifications, Recurring Special Provisions, and project-specific Special Provisions. Bidders must verify the locations of underground utilities and coordinate with multiple utility companies operating in the project area, including Windstream, Rend Lake Conservancy District, AT&T, Ameren, and local municipal utilities. Traffic control requirements mandate that the highway remain open to at least one lane at all times and two lanes to the greatest extent possible, with specific provisions for changeable message signs, temporary rumble strips, drop-off protections, and nighttime work zone lighting.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting July 31, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 78520 JEFFERSON County Section (41-8,1,2)RS-5;1B-1 Route FAS 2826 Project HSIP-STP-8GMK(127) District 9 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

July 31, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 78520 JEFFERSON County Section (41-8,1,2)RS-5;1B-1 Project HSIP-STP-8GMK(127) Route FAS 2826 District 9 Construction Funds

4.4 miles of milling, resurfacing, crown and superelevation corrections, safety shoulders, earthwork and drainage improvements on IL 37 from south of SN 041-0032, carrying IL 37 over the Casey Fork, to Campground Road north of Bonnie.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

FAS Route 2826 (IL 37)

Section (41-8,1,2) RS-5; 1B-1

Jefferson County

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

Section (41-8,1,2) RS-5; 1B-1

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 X Polymer Concrete 16 Reserved 17 Bicycle Racks 18 X Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 X Concrete Mix Design – Department Provided 32 X Station Numbers in Pavements or Overlays

Section (41-8,1,2) RS-5; 1B-1 i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

UTILITIES

TRAFFIC CONTROL PLAN

NOTIFICATION PRIOR TO STARTING WORK

CHANGEABLE MESSAGE SIGNS

DROP-OFF NEAR THE EDGE OF TRAVELED WAY

COOPERATION BETWEEN CONTRACTORS

MOWING

AVAILABILITY OF ELECTRONIC FILES

BORROW EXCAVATION

HMA SURFACE REMOVAL, 2 ¼”

AGGREGATE FOR TEMPORARY ACCESS

PERMANENT SURVEY MARKERS

OVERNIGHT CULVERT REMOVAL AND REPLACEMENT

ASSEMBLE AND MATCH MARK PRECAST CONCRETE BOX CULVERT

ROCK FILL – FOUNDATION

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

SILICONE BRIDGE JOINT SEALER

TRAFFIC SIGNAL BATTERY BACKUP SYSTEM

APPROACH SLAB REPAIR

REFLECTIVE CRACK CONTROL TREATMENT

DETOUR SIGNING

HOT-MIX ASPHALT SURFACE REMOVAL

BRIDGE DECK THIN POLYMER OVERLAY

BAR SPLICERS, HEADED REINFORCEMENT

BITUMINOUS MATERIALS COST ADJUSTMENTS (BDE)

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

COMPENSABLE DELAY COSTS (BDE)

DECK SLAB REPAIR

DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)

EROSION CONTROL BLANKET (BDE)

FUEL COST ADJUSTMENT (BDE)

GUARDRAIL (BDE)

Section (41-8,1,2) RS-5; 1B-1 ii

HOT-MIX ASPHALT (BDE)

HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)

LONGITUDINAL TINING (BDE)

PAVEMENT MARKING (BDE)

PAVEMENT PATCHING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

RAILROAD PROTECTIVE LIABILITY INSURANCE (BDE)

RAISED REFLECTIVE PAVEMENT MARKERS (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SEEDING (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SINUSOIDAL RUMBLE STRIPS (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

STEEL COST ADJUSTMENT (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURFACE TESTING OF PAVEMENTS – IRI (BDE)

SURVEYING SERVICES (BDE)

TEMPORARY CONCRETE BARRIER (BDE)

TEMPORARY RUMBLE STRIPS (BDE)

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

WATERPROOFING MEMBRANE SYSTEM (BDE)

WEEKLY DBE TRUCKING REPORTS (BDE)

WOOD SIGN SUPPORT (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

WORK ZONE WIDTH RESTRICTION (BDE)

WORKING DAYS (BDE)

PROJECT LABOR AGREEMENT

STORM WATER POLLUTION PREVENTION PLAN

Section (41-8,1,2) RS-5; 1B-1

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1, 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of FAS Route 2826 (IL 37), Project HSIP-STP-8GMK(127), Section (41-8,1,2) RS-5;

1B-1, Jefferson County, Contract No. 78520, and in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.

Section (41-8,1,2) RS-5; 1B-1

LOCATION OF PROJECT

This project is located along IL 37 in Jefferson County, just north of Bonnie. The project starts just south of SN 041-0032, over the Casey Fork, and continues south to Campground Road just north of Bonnie. The length of the project is 4.40 miles.

DESCRIPTION OF PROJECT

The proposed improvement will include safety shoulders with rumble strips, crown and superelevation correction, earthwork, and drainage improvements. The project will include HMA milling of 2” and resurfacing with variable depth HMA binder course, HMA leveling binder 1 ½” and HMA surface course 1 ½”. HMA safety shoulders, 8’ wide, will be added with foreslope correction. Guardrail within the project will be updated as needed. There are three structures within the project limits. SN 041-0035 will be replaced, SN 041-0105 will receive waterproofing treatment and overlay of 1 ½” HMA surface course. Structure Number 041-0097 will be gapped.

Section (41-8,1,2) RS-5; 1B-1

UTILITIES

Effective 1984 Revised 2/15/23

Add the following after the first paragraph of Article 105.07:

Underground utilities have been plotted from available surveys and records, and, therefore, their locations must be considered approximate only. There also may be utilities for which the locations are unknown. Verification of locations of underground utilities, shown or not shown, will be the responsibility of the Contractor. The following utility companies have facilities within the project limits which may require adjustment:

Status of JULIE Member Utilities

78520 IL 37 West Campground Road to Bunny Farm Road in Jefferson County

Name and Address of Utility

Type

Location

Estimated Adjustment

Status Windstream KDL 148 Co Hwy 25 Shumway, IL 62461 ATTN: Eric Porter Cell: (217) 343-0864 Email: Eric.Porter@windstream.com

FIBER OPTIC PARALLEL

THROUGHOUT

BEFORE OR

DURING

CONSTRUCTION

Rend Lake Conservancy District P.O. Box 907 Benton, IL 62812 ATTN: Sean Pickford Tel: (618) 439-4321 Email: spickford@rendlake.org

WATER PARALLEL

THROUGHOUT

NONE

ANTICIPATED

Mt. Vernon, City of P.O. Box 1708 Mt. Vernon, IL 62864 ATTN: Brad Ruble Tel: (618) 242-6853 Email: Brad.Ruble@mtvernon.com

WATER NORTH END OF

PROJECT

NONE

ANTICIPATED

AT&T Distribution & Engineering 800 Broadway Cape Girardeau, MO 63701 ATTN: Dean Litzenburg Tel: (618) 624-4004 Email: dl6686@att.com

TELEPHONE PARALLEL

THROUGHOUT

BEFORE OR

DURING

CONSTRUCTION

1800 West Main Street Marion, IL 62959 ATTN: Eric Turner Tel: (618) 751-1283 Email: eturner@ameren.com

ELECTRIC/GAS PARALLEL

THROUGHOUT

BEFORE OR

DURING

CONSTRUCTION

Section (41-8,1,2) RS-5; 1B-1

Tri County Electric Co-Op.

P.O. Box 369 Mt. Vernon, IL. 62864 ATTN: Danny Hopfinger Tel: (618) 244-5151 Email: dhopfinger@tricountycoop.com

ELECTRIC NORTH END OF

PROJECT

NONE

ANTICIPATED

Bonnie, Village of P.O. Box 117 Bonnie, Illinois 62816 ATTN: James (Bud) Parkhill Tel: (618) 242-5646 Email: villageofbonnie@mvn.net

WATER/SEWER SOUTH END OF

PROJECT

BEFORE OR

DURING

CONSTRUCTION

Metro Communications P.O. Box 808 Harrisburg, IL 62946 ATTN: Mylon Rice Tel: (618) 918-1539 Email: Mylon.Rice@Metrocomm.com

FIBER OPTIC PARALLEL

THROUGHOUT

BEFORE OR

CONSTRUCTION

Belle Rive, Village of P.O. Box 147 Belle Rive, IL 62810 ATTN: Chris Richardson Tel: (618) 316-2437 Email: brive1@hamiltoncom.net

WATER NORTH END OF

PROJECT

BEFORE OR

CONSTRUCTION

Additional utility information may be obtained by calling the "Joint Utility Location Information for Excavators" phone number, 800-892-0123. This project is located in the Dodds and Spring Garden Townships.

TRAFFIC CONTROL PLAN

Effective 1985 Revised 4/17/23

During the entire construction period, the road shall be kept open to traffic as follows:

(a) The highway shall be kept open to at least one lane of traffic at all times and to two lanes of traffic to the greatest extent possible, except for as stated within these special provisions.

(b) Access to all public roads and private entrances shall be maintained during all stages of the work.

(c) The road shall be kept open on the detour road during construction of the proposed structure, grade change, or relocation.

(d) The road shall be kept open over one lane of the existing or new bridge during construction of the opposite lane of the structure.

Prior to allowing traffic on any portion of the roadway that has been cold milled, the Contractor shall have erected "Rough Grooved Surface" and "Uneven Pavement" signs that conform to the details shown in the plans. A minimum of one sign at each end of the improvement will be required. The Contractor shall maintain the "Rough Grooved Surface" signs until the cold milled

Section (41-8,1,2) RS-5; 1B-1 surface is covered with binder. The Contractor shall maintain the "Uneven Pavement" signs until the resurfacing operations are completed. The cost of furnishing, erecting, maintaining, and removing the required signs shall be included in the cost of the contract.

The temporary rumble strips shown on the Traffic Control Detail in the plans will be required on this project.

At all locations where the Contractor's equipment is required to cross the traffic lanes, traffic control and protection in accordance with Standard 701306 shall be used. The "One Lane Road Ahead" signs indicated on this standard shall be replaced with "Road Machinery Ahead" signs [W21-3(0)-48]. The cost of furnishing, erecting, maintaining, and removing the required signs shall be included in the cost of the contract.

NOTIFICATION PRIOR TO STARTING WORK

Effective 12/05 Revised 2/10/17

Revise the first sentence of Article 107.09 Public Convenience and Safety to the following: “The Contractor shall notify the Engineer at least 14 days in advance of starting any construction work.

For projects involving width or height restrictions or complete closures of the roadway or ramp, an additional seven days of notice (21 days total) will be required.”

This additional notification is required, so the public can be notified of the pending construction.

CHANGEABLE MESSAGE SIGNS

Revised 4/15/20

This work consists of furnishing, placing, and maintaining changeable message sign(s) according to Section 701 and the following:

A total of five changeable message signs shall be required in this contract. All signs must be in place and operational for a minimum of 14 calendar days prior to lane or roadway closures. Each sign shall state the day work will begin and delays are possible. The exact message will be approved by the Engineer. The Contractor may be required to relocate each sign multiple times during the contract at his or her expense. The exact location of the placement of these signs shall be determined in the field by the Engineer.

This work will be paid for per CALENDAR DAY for CHANGEABLE MESSAGE SIGN.

Section (41-8,1,2) RS-5; 1B-1

DROP-OFF NEAR THE EDGE OF TRAVELED WAY

Revised 2/27/17

In order to be in compliance with Safety Engineering Policy Memorandum 4-15 (Drop Off Policy) the Contractor will utilize Traffic Control and Protection Standard 701326 and night time work zone lighting at any time a greater than 12” drop-off is located within 8 ft. of the edge of the nearest open traffic lane. Additionally, to reduce the time traffic is exposed to a drop-off, nighttime work will be allowed. Night time traffic control shall conform to the requirements for the standard in use and all applicable portions of Article 702.

For drop offs >1.5” but <12” there shall be no long duration stationary operation allowed (14 days or more) located within 8 ft. of the edge of the nearest open traffic lane.

The Contractor will be assessed a traffic control deficiency deduction per Article 105.03(b) for each day a drop off greater than 1.5” exists for more than 14 days within 8 ft. of the edge of the nearest open traffic lane.

COOPERATION BETWEEN CONTRACTORS

Revised 2/10/17

The Contractor is to be aware that traffic control limits of this contract may overlap those of another project(s) that may be under construction along IL 37 concurrently with this work. The Contractor shall coordinate his/her work with the other contractors to minimize any possible conflicts. The Contractor shall also notify the Engineer five working days in advance of any work that may affect other adjacent contracts.

Adjacent Project, Contract No. 78B49 reconstructing IL 37 under between the I-64 interchange ramps: Jefferson County, reconstruct Lang Road railroad crossing, and pave between IL 37 and the railroad crossing.

MOWING

Effective 12/11/01 Revised 7/17/17

This work shall consist of mowing the roadway foreslopes to the ditchline or for a width of 15’ from both edges of pavement or paved shoulder, whichever is less. At intersecting roadways, the mowing shall extend to the proposed right of way for a distance of 300’ on either side of the intersection. The height of the mowing shall not be more that 6’’. Equipment used shall be capable of completely severing all growth at the cutting height and distributing it evenly over the mowed area. The Contractor will not be required to mow continuously wet ditches and drainage ways, slopes greater than 1:2.5 (V:H), or areas which may be designated by the Engineer as not mowable. Mowing shall be done within the project limits during the construction of the project as directed by the Engineer and prior to the final inspection of the project. Any subsequent mowing required to disperse mowed material shall be considered as included in the cost of the mowing. Debris encountered during mowing, which interferes with the mowing operation or is visible from the roadway shall be removed and disposed of according to Article 201.01(a) and 201.10(a).

Section (41-8,1,2) RS-5; 1B-1

Method of Measurement: Mowing will be measured for payment in units of 100’ in horizontal distances along the roadway centerline. For purposes of measurement, the quantity of units to be paid for each individual mowing is defined as the net length of the project as shown on the cover sheet of the construction plans divided by 100’ which includes the left and right sides of the roadway. No allowances will be made for variations in width of mowing.

Basis of Payment: This work will be paid for at the contract unit price per UNIT for MOWING.

AVAILABILITY OF ELECTRONIC FILES

Effective 10/16 Revised 12/11/19

Electronic files of this project will be made available to the Contractor after contract award.

Contractor shall coordinate obtaining electronic files through the Engineer. If there is a conflict between the electronic files and the printed contract plans and documents, the printed contract plans and documents shall take precedence over the electronic files. The Contractor shall accept all risk associated with using the electronic files and shall hold the Department harmless for any errors or omissions in the electronic files and the data contained therein. Errors or delays resulting from the use of the electronic files by the Contractor shall not result in an extension of time for any interim or final completion date or shall not be considered cause for additional compensation.

The Contractor shall not use, share, or distribute these electronic files except for the purpose of constructing this contract. Any claims by third parties due to use or errors shall be the sole responsibility of the Contractor. The Contractor shall include this disclaimer with the transfer of these electronic files to any other parties and shall include appropriate language binding them to similar responsibilities.

BORROW EXCAVATION

Revised 08/02/21

In addition to the requirements of Article 107.22 and Section 204, the Contractor shall submit to the Department a request for approval of the material in a proposed borrow pit. The submittal shall contain an 8 1/2" x 11" topographic map or sketch containing the dimensions of the area proposed and the locations of pertinent landmarks, the name(s) of the property owner, and the proposed depth of cut. Copies of this map may also be used for subsequent submittal required for the archeological survey of the borrow pit.

The Contractor shall provide access for truck mounted drilling equipment, if required, to and from and in all areas where he/she requests material investigations.

Borrow excavation which is to be used in the roadway embankment without restrictions must have more than 35% of the total sample passing the No. 200 sieve. The soil must have a liquid limit value of 50.0 or less and a plasticity index value of 12.0 or more as defined by the AASHTO Classification System. These soils shall be capable of obtaining the required design embankment strengths. Soils proposed by the Contractor for furnished excavation or borrow which do not meet the aforementioned requirements will be assigned varying degrees of restrictions up to and

Section (41-8,1,2) RS-5; 1B-1 including complete rejection depending on the nature and engineering properties of the material.

These restrictions, if any, will be set forth in the proposed borrow material report.

It is anticipated that, depending upon the workload at the time, this field and laboratory investigation may take up to 15 days.

HMA SURFACE REMOVAL, 2 ¼”

The cost of HMA surface removal in areas of transition between 2 ¼” and 2” depth will be paid for as HMA Surface Removal, 2”.

AGGREGATE FOR TEMPORARY ACCESS

This work shall consist of placing aggregate at entrances to maintain access and at other locations as determined by the Engineer in accordance with Section 402. The aggregate shall be CA 6 or CA 10 and shall be placed and compacted to the satisfaction of the Engineer.

PERMANENT SURVEY MARKERS

A total of 12 type II permanent survey markers shall be set along IL 37. Final locations of the permanent survey markers will be determined by the Engineer in coordination with the District 9 Survey Unit. If a precast marker is used, it must be backfilled with quickcrete to be included in the cost of Permanent Survey Markers, Type II.

OVERNIGHT CULVERT REMOVAL AND REPLACEMENT

IL 37 shall be allowed to be closed to all traffic for the removal and replacement of existing culverts and backfilling the culverts.

STA 150+89

STA 162+98

STA 177+97

STA 189+63

STA 213+25

STA 230+56

STA 232+97

STA 245+73

STA 250+12

STA 254+79

STA 259+14

STA 275+64

STA 290+32

Section (41-8,1,2) RS-5; 1B-1

STA 297+16

STA 304+30

STA 321+77

STA 326+92

STA 329+97

STA 336+26

STA 356+15

There will be 20 closures permitted for the removal and replacement of culverts, from 6:00 pm to 6:00 am, with no closures occurring on Friday, Saturday, or Sunday nights. Outside of this period, IL 37 shall be open to at least one lane of traffic. This closure shall not be permitted during any holiday period as stated in Article 107.09. After the roadway is opened to traffic, items such as pavement patching and riprap may be installed along with any other applicable items using the appropriate traffic control standard. There will be no additional compensation for the 18 inches of granular embankment, to bring the roadway up to grade, if the pavement patch is built after opening the roadway to traffic. The pavement patch shall be installed within seven days of installation of the associated culvert.

Structures at STA 177+97, 189+63, and 213+25 may be completed on the same night closure.

Structures at STA 245+73, 250+12, 254+79, and 259+14 may be completed on the same night closure.

Detours will be established on IL 154 and I-64. Work shall be sequenced so that access from entrances to the local road network shall be provided at all times as approved by the Engineer.

Access to IL 37 for the entrances shall remain via the local road network. The Engineer will meet with local emergency services prior to any road closures.

The Contractor will be charged a monetary assessment of $1,000 each hour any road closure is taking place outside the allotted times from 6:00 p.m. to 6:00 a.m. All road closures will be accomplished using the appropriate traffic control standards.

ASSEMBLE AND MATCH MARK PRECAST CONCRETE BOX CULVERT

Precast concrete box culverts shall be constructed according to Section 540 of the Standard Specifications, except as modified by this special provision. This special provision applies to all proposed precast concrete box culverts.

It shall be the Contractor’s responsibility to ensure that the precast concrete box culvert sections are assembled and match marked prior to the sections arriving at the jobsite and prior to the road closure in order to secure a proper fit on each joint. Any sections that do not provide a proper fit shall be rejected by the Engineer and replaced by the Contractor with no additional compensation.

This work will not be paid for separately but shall be considered included in the unit price for Precast Concrete Box Culverts of the size specified.

Section (41-8,1,2) RS-5; 1B-1

ROCK FILL – FOUNDATION

Revised: November 24, 2025

This work consists of constructing a layer of rock fill below culverts or shallow foundations having unstable or unsuitable soil conditions. When shown on the plans, the rock fill limits and thickness shall be confirmed by the Engineer prior to excavating below the theoretical top of rock fill line.

Materials shall meet the requirements of the following Articles of the Standard Specifications:

CA-6 and CA-7 1004.04 Rock fill 1005.01

All rock fill shall be well graded. The gradation of rock fill shall be selected based on layer thickness as shown below:

Less than or equal to 1 ft ................... Stone Riprap RR 1 Greater than 1 ft ................... Stone Riprap RR 1 Greater than 3 ft ................... Primary Crusher Run or Shot Rock (18" max size)

The method of rock fill placement shall be approved by the Engineer. Rock fill shall be capped according to application as shown below:

Shallow Foundations 4 to 6 inches CA-6 Cast-In-Place Box Culverts 6 inches CA-6 Pre-Cast Box Culverts Porous Granular Bedding Material (Article 540.06) Pre-Cast Pipe Culverts 4 to 6 inches Fine Aggregate (Article 542.04(c))

In shallow foundation applications, the CA-6 cap shall be compacted to the satisfaction of the Engineer. No compaction of rock fill is required for culvert applications.

This work will be paid for at the contract unit price per TON for ROCK FILL – FOUNDATION. The contract price for rock fill – foundation shall include aggregate materials and aggregate material placement.

Excavation for the rock fill will be performed in accordance with Section 502 of the Standard Specifications and measured according to Article 502.12 (b). Unless otherwise specified in the plans, the excavation will be paid for at the contract unit price per CUBIC YARD for REMOVAL

AND DISPOSAL OF UNSUITABLE MATERIALS FOR STRUCTURES.

Section (41-8,1,2) RS-5; 1B-1

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

Description. This work shall consist of the removal and disposal of regulated substances according to Section 669 of the Standard Specifications as revised below.

Contract Specific Work Areas. For stationing, the lateral distance is measured from centerline, and the farthest distance is the offset distance or construction limit, whichever is less.

The following contract specific work areas shall be monitored by the environmental firm for soil contamination and workers protection.

ISGS PESA 3443V-2, Railroad, 100-600 and 5500-9600 blocks of IL 37, Bonnie, Jefferson County

• Station 129+50 to Station 142+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: pH, Benzo(a)pyrene, TCLP/SPLP Arsenic, TCLP/SPLP Beryllium, TCLP/SPLP Chromium, TCLP/SPLP Lead, TCLP/SPLP Nickel, TCLP/SPLP Thallium, TCLP/SPLP Vanadium, Iron, Manganese, and Thallium.

• Station 129+50 to Station 132+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(2). Contaminants of concern sampling parameters include: TCLP/SPLP Beryllium.

• Station 132+50 to Station 139+00, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: TCLP/SPLP Beryllium, TCLP/SPLP Chromium, TCLP/SPLP Lead, TCLP/SPLP Vanadium, and Iron.

• Station 139+00 to Station 142+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron, pH.

• Station 142+50 to Station 143+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: pH, Cobalt, Iron, Manganese, and Thallium.

• Station 143+50 to Station 144+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: pH, Cobalt, Iron, Manganese, and Thallium.

• Station 144+50 to Station 145+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: pH, Cobalt, Iron, Manganese, and Thallium.

• Station 142+50 to Station 145+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Dibenz(a,h)anthracene, TCLP/SPLP Arsenic, TCLP/SPLP

Section (41-8,1,2) RS-5; 1B-1

Beryllium, TCLP/SPLP Chromium, TCLP/SPLP Lead, TCLP/SPLP Nickel, TCLP/SPLP Thallium, TCLP/SPLP Vanadium, and Iron.

• Station 145+50 to Station 148+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: TCLP/SPLP Arsenic, TCLP/SPLP Chromium, TCLP/SPLP Lead, TCLP/SPLP Vanadium, and Iron.

• Station 148+50 to Station 149+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Benzo(a)pyrene and Lead.

• Station 149+50 to Station 150+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: Benzo(a)pyrene and Lead (total, TCLP, SPLP).

• Station 150+50 to Station 151+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Benzo(a)pyrene and Lead.

• Station 148+50 to Station 151+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: pH.

• Station 151+50 to Station 154+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 154+50 to Station 157+00, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: pH.

• Station 154+50 to Station 157+00, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: pH.

• Station 157+50 to Station 158+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Benzo(a)pyrene, Iron, Manganese, and Lead TCLP/SPLP.

• Station 158+50 to Station 159+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: Benzo(a)pyrene, Iron, Manganese, and Lead (total, TCLP, SPLP).

• Station 159+50 to Station 160+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of sampling parameters include: Benzo(a)pyrene, Iron, and Manganese.

Section (41-8,1,2) RS-5; 1B-1

• Station 163+50 to Station 165+00, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Manganese and Thallium.

• Station 165+00 to Station 166+00, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: Manganese, Thallium, and Mercury.

• Station 166+00 to Station 167+00, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Manganese and Thallium.

• Station 163+50 to Station 167+00, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron and pH.

• Station 175+50 to Station 178+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Manganese and Thallium.

• Station 181+ 50 to Station 184+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Manganese and pH.

• Station 190+50 to Station 196+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: pH.

• Station 202+50 to Station 205+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: Manganese.

• Station 205+50 to Station 208+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Manganese and pH.

• Station 214+50 to station 215+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Benzo(a)pyrene, Benzo(b)fluoranthene, Dibenz(a,h)anthracene, Chromium, Iron, Manganese.

• Station 215+50 to station 216+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: Benzo(a)pyrene, Benzo(b)fluoranthene, Dibenz(a,h)anthracene, Chromium, Iron, Manganese and Lead (total, TCLP, SPLP).

• Station 216+50 to station 217+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of

Section (41-8,1,2) RS-5; 1B-1 sampling parameters include: Benzo(a)pyrene, Benzo(b)fluoranthene, Dibenz(a,h)anthracene, Chromium, Iron, and Manganese.

• Station 217+50 to station 218+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Chromium, Iron, Manganese.

• Station 218+50 to station 219+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: Chromium, Iron, Manganese and Lead (total, TCLP, SPLP).

• Station 219+50 to station 220+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Chromium, Iron, and Manganese.

• Station 217+50 to Station 220+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Cobalt and Iron.

• Station 220+50 to Station 223+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 223+50 to Station 226+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 226+50 to Station 229+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron and pH.

• Station 226+50 to Station 229+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 229+50 to Station 232+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: pH, Benzo(a)pyrene and Iron.

• Station 229+50 to Station 232+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron and pH.

• Station 232+50 to Station 241+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron and pH.

• Station 241+50 to Station 244+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of

Section (41-8,1,2) RS-5; 1B-1 and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 244+50 to Station 247+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 247+50 to Station 250+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 247+50 to Station 250+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(2). Contaminants of concern sampling parameters include: TCLP/SPLP Lead.

• Station 250+50 to Station 253+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(3). Contaminants of concern sampling parameters include: Benzo(a)pyrene.

• Station 250+50 to Station 253+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron and pH.

• Station 256+50 to Station 259+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron and pH.

• Station 262+50 to Station 271+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron and pH.

• Station 265+50 to Station 268+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Cobalt, Iron, and Manganese.

• Station 268+50 to Station 271+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: pH.

• Station 271+00 to Station 274+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(2). Contaminants of concern sampling parameters include: TCLP/SPLP Lead.

• Station 271+00 to Station 274+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: pH.

• Station 274+50 to Station 277+50, 0 to 50 feet LT. The Engineer has determined this

Section (41-8,1,2) RS-5; 1B-1 and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron and pH.

• Station 274+50 to Station 277+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Iron and TCLP/SPLP Lead.

• Station 277+50 to Station 278+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Selenium.

• Station 278+50 to Station 279+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: Selenium and Manganese.

• Station 279+50 to Station 280+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Selenium and Manganese.

• Station 280+50 to Station 281+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Iron.

• Station 281+50 to Station 282+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters include: Lead and Iron.

• Station 282+50 to Station 283+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Lead and Iron.

• Station 277+50 to Station 280+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: pH.

• Station 283+50 to Station 286+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 283+50 to Station 286+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: pH.

• Station 286+50 to Station 292+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 5 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters include: Chromium and Iron.

• Station 286+50 to Station 289+50, 0 to 50 feet LT. The Engineer has determined this material from 5 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of

Section (41-8,1,2) RS-5; 1B-1 sampling parameters include: pH.

• Station 292+50 to Station 304+50, 0 to 50 feet LT. The Engineer has determined this material from 0 to 8 feet bgs in the vicinity of the station and off-set meets the criteria of and shall be managed in accordance with Article 669.05(b)(1). Contaminants of concern sampling parameters include: Iron, Manganese and pH.

• Station 304+50 to Station 307+50, 0 to 50 feet LT.

This is the start of the file's text. The full file is on GovTribe.