ildot 76M45-112.pdf
PDF 6 MB Posted
- Attached to
- Resurfacing and Bridge Repairs on I-255
- Solicitation number
- 76M45
- Issued by
- St. Clair County, Illinois
About this file
Summary
This is a Notice to Bidders and Specifications document from the Illinois Department of Transportation (IDOT) for Contract No. 76M45, a resurfacing and bridge repairs project on Interstate 255 (I-255) in St. Clair County. The project is located from 0.5 miles south of Illinois Route 3 at Dupo to 0.2 miles north of Illinois Route 157, including the southbound Illinois Route 3 to northbound I-255 ramp, the southbound I-255 ramp from Illinois Route 157 to northbound I-255 ramp, and six additional structure numbers (SNs 082-0217, 0218, 0219, 0220, 0221, 0222). Electronic bids must be submitted to the iCX-Integrated Contractors Exchange system by 12:00 p.m. on November 6, 2026, at which time bids will be publicly opened. The project work includes pavement resurfacing, concrete repairs, bridge repairs, guardrail installation and removal, temporary traffic control devices, drainage improvements, and associated site work. The contract award will be made to the lowest responsive and responsible bidder, with the Illinois Department of Transportation reserving the right to reject any or all proposals and re-advertise the project.
The project is funded through National Highway Performance Program-Emergency Relief Mitigation (NHPP-EREM) District 8 Construction Funds. This is a federal-aid construction contract subject to compliance with state and federal requirements, including prevailing wage provisions, equal employment opportunity (EEO) obligations, and Disadvantaged Business Enterprise (DBE) participation. Contractors must submit certified payroll records (Form SBE 48), Statements of Compliance (Form SBE 348), and Monthly Labor Summary Reports according to specified timelines. A Project Labor Agreement is required, and contractors must provide an Engineer's Field Office, Type A (Special) equipped with specific furniture, technology infrastructure with minimum internet speeds of 5 Mbps download and 2 Mbps upload, telecommunications systems including six telephone lines, and multifunction printer capabilities. The contract includes various bid-dependent special provisions, traffic control costs, and liquidated damages provisions. Notification of I-255 closure must be provided 21 working days in advance to multiple emergency response agencies and IDOT's Traffic Management Center.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Letting November 6, 2026
Notice to Bidders, Specifications and Proposal
Contract No. 76M45 ST CLAIR County Section 82-(6,7)RS-2 Route FAI 255 Project NHPP-EREM(944) District 8 Construction Funds
Prepared by F
Checked by
(Printed by authority of the State of Illinois)
NOTICE TO BIDDERS
1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.
November 6, 2026 at which time the bids will be publicly opened from the iCX SecureVault.
2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the
Invitation for Bids as:
Contract No. 76M45 ST CLAIR County Section 82-(6,7)RS-2 Project NHPP-EREM(944) Route FAI 255 District 8 Construction Funds
Resurfacing and bridge repairs on I-255 from 0.5 miles south of IL 3 at Dupo to 0.2 miles north of IL 157; Southbound IL 3 to Northbound I-255 ramp; Southbound I-255 ramp, IL 157 to Northbound I-255 ramp and SN 082-0217, 0218, 0219, 0220, 0221, 0222.
3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.
(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.
4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.
By Order of the Illinois Department of Transportation
Gia Biagi, Secretary
FAI ROUTE 255 (I-255)
PROJECT NHPP-EREM(944)
SECTION 82-(6,7)RS-2
ST. CLAIR COUNTY
CONTRACT NO. 76M45
INDEX
FOR
SUPPLEMENTAL SPECIFICATIONS
AND RECURRING SPECIAL PROVISIONS
Adopted January 1, 2026
This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.
ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)
SUPPLEMENTAL SPECIFICATIONS
Std. Spec. Sec. Page No.
109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires
1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment
SECTION 82-(6,7)RS-2
RECURRING SPECIAL PROVISIONS
The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:
CHECK SHEET # PAGE NO.
1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)
3 X EEO
4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes
10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 X Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 X Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 X Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 X Station Numbers in Pavements or Overlays
SECTION 82-(6,7)RS-2
i
TABLE OF CONTENTS
LOCATION OF PROJECT
DESCRIPTION OF PROJECT
SUBMITTAL OF EEO/LABOR DOCUMENTATION
SEEDING, CLASS 2
CLASS A PATCHES (SPECIAL)
PARTIAL DEPTH HOT-MIX ASPHALT PATCHING
HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH
INSTALLATION OF TEMPORARY CONCRETE BARRIERS AND/OR TEMPORARY BRIDGE RAIL
CONCRETE BARRIER
CONCRETE BARRIER BASE (SPECIAL)
PORTLAND CEMENT CONCRETE SURFACE REMOVAL (VARIABLE DEPTH)
PORTLAND CEMENT CONCRETE SURFACE REMOVAL 1"
REMOVE EXISTING RIPRAP
PORTLAND CEMENT CONCRETE SHOULDERS 12” (SPECIAL)
PIPE DRAIN REMOVAL
REMOVE CONCRETE HEADWALLS FOR PIPE DRAINS
REMOVE EXISTING UNDERDRAINS
REMOVE EXISTING FLARED END SECTION
FRAMES AND GRATES TO BE ADJUSTED
ENGINEER’S FIELD OFFICE, TYPE A (SPECIAL)
PIPE DRAIN CONNECTIONS
CONCRETE BARRIER REMOVAL (SPECIAL)
LONGITUDINAL PARTIAL DEPTH REMOVAL 1 ½” AND PATCHING
JOINT OR CRACK FILLING
GUARDRAIL REMOVAL
CLEARING AND GRUBBING
DRILL WEEP HOLE
METAL SCREEN
REPLACE SPLICE FLANGE BOLTS
BOLT REPLACEMENT
DISCONNECT SIGN LIGHTING AND REMOVE WIRING TO NEAREST SPLICE
TRAFFIC CONTROL PLAN
TRAFFIC CONTROL AND PROTECTION, (SPECIAL)
OFF-PEAK INTERSTATE SINGLE LANE CLOSURES
DETOUR SIGNING
SECTION 82-(6,7)RS-2
ii
PREFORMED PLASTIC PAVEMENT MARKING
MILE POST MARKER ASSEMBLY (SPECIAL)
LIGHT POLE FOUNDATION, INTEGRAL WITH BARRIER WALL
TRANSFER SERVICE SIGN
CLEANING BRIDGE SEATS
SLOPE WALL REPAIR
STONE DUMPED RIPRAP, CLASS A4 (SPECIAL)
TEMPORARY SHORING AND CRIBBING
GUTTERS TO BE CLEANED
SURFACE FILLER (SPECIAL)
PROTECTIVE COAT (SPECIAL)
APPROACH SLAB REPAIR
CONCRETE BARRIER, SINGLE FACE, 44 INCH HEIGHT
COMPLETION DATE PLUS WORKING DAYS
LIQUIDATED DAMAGES
WORK DURING PEAK HOURS
START OF WORK NOTIFICATION
JACK AND REMOVE EXISTING BEARINGS
CLEANING AND PAINTING CONTACT SURFACE AREAS OF EXISTING STEEL STRUCTURES
CLEANING AND PAINTING EXISTING STEEL STRUCTURES
CONTAINMENT AND DISPOSAL OF LEAD PAINT CLEANING RESIDUES
DIAMOND GRINDING AND SURFACE TESTING BRIDGE SECTIONS
BRIDGE DECK GROOVING (LONGITUDINAL)
HOT DIP GALVANIZING FOR STRUCTURAL STEEL
BITUMINOUS MATERIALS COST ADJUSTMENTS (BDE)
BRIDGE DECK CONCRETE OVERLAYS
CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)
COMPENSABLE DELAY COSTS (BDE)
CONCRETE BARRIER (BDE)
CONCRETE SEALER (BDE)
CONSTRUCTION AIR QUALITY – DIESEL RETROFIT (BDE)
DECK SLAB REPAIR
DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)
ENGINEER’S FIELD OFFICE (BDE)
EROSION CONTROL BLANKET (BDE)
FUEL COST ADJUSTMENT (BDE)
GUARDRAIL (BDE)
SECTION 82-(6,7)RS-2
iii
HOT-MIX ASPHALT (BDE)
HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)
PAVEMENT MARKING (BDE)
PAVEMENT PATCHING (BDE)
PERFORMANCE GRADED ASPHALT BINDER (BDE)
PREFORMED PLASTIC PAVEMENT MARKING (BDE)
RAILROAD PROTECTIVE LIABILITY INSURANCE (BDE)
THE MAINTENANCE OF CONSENT LETTER TO UNION PACIFIC RAILROAD PROPERTY / RAILROAD
FLAGGERS
RAISED REFLECTIVE PAVEMENT MARKERS (BDE)
REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)
SEEDING (BDE)
SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)
SIGN PANELS AND APPURTENANCES (BDE)
SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)
SPEED DISPLAY TRAILER (BDE)
STEEL COST ADJUSTMENT (BDE)
STRUCTURAL REPAIR OF CONCRETE (BDE)
SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)
SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)
SUBMISSION OF BIDDERS LIST INFORMATION (BDE)
SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)
SURFACE TESTING OF PAVEMENTS – IRI (BDE)
SURVEYING SERVICES (BDE)
TEMPORARY CONCRETE BARRIER (BDE)
TRAINING SPECIAL PROVISIONS (BDE)
IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION
VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)
WEEKLY DBE TRUCKING REPORTS (BDE)
WOOD SIGN SUPPORT (BDE)
WORK ZONE TRAFFIC CONTROL DEVICES (BDE)
WORK ZONE WIDTH RESTRICTION (BDE)
PROJECT LABOR AGREEMENT
STORM WATER POLLUTION PREVENTION PLAN
SECTION 82-(6,7)RS-2
STATE OF ILLINOIS
SPECIAL PROVISIONS
The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1, 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of FAI Route 255 (I-255), Project NHPP-EREM(944), Section 82-(6,7)RS-2, St. Clair County, Contract No. 76M45, and in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.
FAI Route 255 (I-255) Project NHPP-EREM(944)
Section 82-(6,7)RS-2 St. Clair County
Contract No. 76M45
LOCATION OF PROJECT
This project is located on I-255 from 0.5 miles south of IL 3 at Dupo to 0.2 miles north of IL 157;
SB IL 3 to NB I-255 ramp; SB I-255 ramp, IL 157 to NB I-255 ramp and SNs 082-0217, 0218, 0219, 0220, 0221, and 0222.
DESCRIPTION OF PROJECT
This project consists of resurfacing and bridge repairs.
SUBMITTAL OF EEO/LABOR DOCUMENTATION
Effective: April 2016
This work shall be done in accordance with Check Sheets No. 1, 3, and 5 of the IDOT Supplemental Specifications and Recurring Special Provisions and the Weekly DBE Trucking Reports (BDE) special provision, except as here-in modified.
PAYROLL AND STATEMENT OF COMPLIANCE:
Certified payroll (FORM SBE 48 OR AN APPROVED FACSIMILE) and the Statement of Compliance (FORM SBE 348) shall be submitted by two methods:
SECTION 82-(6,7)RS-2
1. By Mail (United States Postal Service): The ORIGINAL of the certified payroll and the Statement of Compliance for the Prime Contractor and each Subcontractor shall be submitted by mail to the Regional Engineer for District 8.
2. Electronically: Scan both the ORIGINAL of the certified payroll and the Statement of
Compliance to the same PDF file, and email to the District at the email address designated by the District EEO Officer.
SBE 48 and SBE 348 forms shall be submitted weekly and will be considered late if received after midnight seven business days after the payroll ending date.
WEEKLY DBE TRUCKING REPORT:
The Weekly DBE Trucking Report (FORM SBE 723) shall be submitted electronically.
Scan the form to a PDF file, and email to the District at the email address designated by the District EEO Officer.
SBE 723 forms shall be submitted weekly and will be considered late if received after midnight ten business days following the reporting period.
MONTHLY LABOR SUMMARY & MONTHLY CONTRACT ACTIVITY REPORTS:
The Monthly Labor Summary Report (MLSR) shall be submitted by one of two methods:
1. For contractors having IDOT contracts valued in the aggregate at $250,000 or less, the report may be typed or clearly handwritten using Form D8 PI0148. Submit the ORIGINAL report by mail to the Regional Engineer for District Eight. Contractors also have the option of using the method #2 outlined below.
2. For contractors having IDOT contracts valued in the aggregate at more than
$250,000, the report must be submitted in a specific “Fixed Length Comma Delimited ASCII Text File Format”. This file shall be submitted by e-mail using specific file formatting criteria provided by the District EEO Officer. Contractors must submit a sample text file to District 8 for review at least 14 days prior to the start of construction.
The Monthly Contract Activity Report (MCAR) may be typed or clearly handwritten using Form D8 PI0149.
The MLSR and the MCAR shall be submitted concurrently. If the method of transmittal is method #1 above, then both the MLSR and the MCAR shall be mailed together in the same envelope. If the method of transmittal is method #2 above, then the MCAR shall be scanned to a .pdf file and attached to the email containing the MLSR .txt file.
The MLSR and MCAR must be submitted for each consecutive month for the duration of the project and will be considered late if received after midnight ten calendar days following the reporting period.
REQUEST FOR APPROVAL OF SUBCONTRACTOR:
SECTION 82-(6,7)RS-2
The ORIGINAL and one copy of the Request for Approval of Subcontractor (FORM BC 260A) shall be submitted to the District at the IDOT Preconstruction Conference.
SUBSTANCE ABUSE PREVENTION PROGRAM CERTIFICATION:
The ORIGINAL and one copy of the Substance Abuse Prevention Program Certification (FORM BC 261) shall be submitted to the District at the IDOT Preconstruction Conference.
The Contractor is required to follow submittal procedures as provided by the EEO Officer at the preconstruction conference and to follow all revisions to those procedures as issued thereafter.
If a report is rejected, it is the Contractor’s responsibility to make required adjustments and/or corrections and resubmit the report. Reports not submitted and accepted within the established timeframes will be considered late.
Disclosure of this information is necessary to accomplish the statutory purpose as outlined under 23CFR part 230 and 41CFR part 60.4 and the Illinois Human Rights Act. Disclosure of this information is REQUIRED. Failure to comply with this special provision may result in the withholding of payments to the Contractor and/or cancellation, termination, or suspension of the contract in whole or part.
This special provision must be included in each subcontract agreement.
ALL HARD COPY FORMS TO BE SUBMITTED TO:
Region 5 Engineer Illinois Department of Transportation
ATTN: EEO/LABOR OFFICE
1102 Eastport Plaza Drive Collinsville, IL 62234-6198
Compliance with this special provision shall be included in the cost of the contract, and no additional compensation will be allowed for any costs incurred.
SEEDING, CLASS 2
In addition to the requirements of Section 250 when class 2 seeding is done between March 1st and June 1st, the seed mixture shall also include 48 pounds per acre of Spring Oats. When class 2 seeding is done between August 1st and November 15th, the seed mixture shall also include 56 pounds per acre of Balboa Farm Rye or 60 pounds per acre of Winter Wheat.
SECTION 82-(6,7)RS-2
CLASS A PATCHES (SPECIAL)
Effective: February 8, 2021
Description. This work shall consist of the removal of the existing pavement, the necessary excavation, and the replacement with the class and type of patch specified at designated locations. This work shall be according to Section 442 of the Standard Specifications for class A.
Materials. Materials shall be according to Article 442.02 of the Standard Specifications.
CONSTRUCTION REQUIREMENTS
Pavement Removal. Pavement removal shall be according to Article 442.05 of the Standard Specifications and as modified herein.
Revise Article 442.05(a) to read:
(a) Class A Patches. Two transverse full depth saw cuts shall be made perpendicular to the centerline at each end of the patch. Except, the saw cuts may be skewed slightly if necessary to maintain a minimum distance of 18 inches from the end of the patch to the nearest transverse crack in the pavement to remain in place. When approved by the Engineer, this minimum distance may be reduced to 6 inches in areas of close crack spacing where the pavement otherwise appears to be sound. The longitudinal edges of the patch shall be formed by full-depth saw cuts. Saw cut extensions into pavement which is to remain in place will not be permitted. All saw cuts shall be made with an approved concrete saw. After the transverse saw cuts have been made, intermediate cuts as shown on plan details may be made to make pressure relief cuts or to reduce the pavement length to a size that accommodates removal and hauling operations. The saw cutting operations shall be controlled to limit subbase penetration to a maximum of 1/2 inch.
The shoulder between the full-depth saw cut and the pavement edge shall be removed using a hand held hammer and hand tools prior to pavement removal. If available, the Contractor may use an approved wheel saw to make the shoulder cut and removal.
When the patch is adjacent to a PCC shoulder, a saw cut shall be made at the shoulder-pavement joint sufficiently deep to sever the tie bars. A second full-depth saw cut shall be made in the pavement a minimum of 4 inches from the edge of the shoulder. The pavement between the full-depth saw cut and the shoulder edge shall be removed using a hand held hammer and hand tools prior to the removal of the remaining pavement.
The pavement between the saw cuts shall be removed by lifting. Sufficient care shall be taken to minimize subbase disturbance and prevent spalling of the pavement that is to remain in place. Any subbase or stabilized subbase material disturbed during pavement removal operations or determined unsuitable by the Engineer shall be removed and replaced with patch material.
If the Engineer determines that the concrete has deteriorated to the extent that it is not practical to lift, the pavement may be broken into small pieces and removed. The breaking
SECTION 82-(6,7)RS-2
equipment shall not transfer impact energy more than 3,000 foot-pound per blow to the pavement surface.
Should the Contractor’s operation cause a spall having a width or depth greater than 1 inch in the pavement to remain in place or cause excessive shattering or underbreaking of the existing slab to remain in place, a new saw cut shall be made extending the patch to remove the spall or underbreaking. After pavement removal, the pavement structure will be inspected by the Engineer to determine if it is sufficiently sound. If determined unsound, the Contractor shall extend the patch as directed by the Engineer.
Revise Article 442.06(a) to read:
(a) Reinforcement, Dowel Bars, and Joints. Reinforcement, dowel bars, and joints shall be according to the following.
• Class A Patching. The reinforcement shall be constructed according to Articles
508.03 through 508.09.
Patch reinforcement (longitudinal) shall be tied to No. 6 epoxy coated tie bars, 32 inch long drilled and grouted into existing pavement at 12 inch centers.
Patches more than 20 feet in length shall be tied to the adjacent pavement, PCC shoulders, and curb and gutter with No. 6 transverse epoxy coated tie bars, 24 inches long, embedded 8 inches at 36-inch centers according to Article 420.05(b).
The Contractor shall tie the steel together using at least two secure ties for each lap splice according to Article 508.08(a)(1).
Reinforcement steel shall be placed and supported on chairs according to Article 508.06, and the placement tolerance for individual reinforcement bars shall be +/- 1 inch horizontally and vertically.
Revise the first paragraph of Article 442.06(d) to read:
(d) Concrete Placement. The patch material shall match the elevation of the existing concrete pavement or HMA surface. Concrete shall be placed according to Article 420.07 of the Standard Specifications, except that a mechanical spreader will not be required.
Placement shall be governed by the limitations set forth in Article 1020.14.
Method of Measurement. This work will be measured according to Article 442.10 and as modified herein.
Revise the table and the third paragraph of the article to read:
% change of thickness % change of quantity 0 to less than 15 0 15 to less than 20 10 20 to less than 30 15 30 to less than 50 20
SECTION 82-(6,7)RS-2
If the thickness of the existing pavement varies by 50% or more from that shown on the plans, the character of the work will be considered significantly changed, and an adjustment to the contract will be made according to Article 104.02.
Basis of payment. This work will be measured according to Article 442.11 and as modified herein.
Revise second paragraph to read:
Where the Department requires a specific class of patch used, this work will be paid for at the contract unit price per SQUARE YARD for CLASS A PATCHES (SPECIAL), of the type and thickness specified. When a patch is adjacent to a wide flange beam terminal joint, this work will be paid for at the contract unit price per SQUARE YARD for PAVEMENT PATCHING
(SPECIAL).
PARTIAL DEPTH HOT-MIX ASPHALT PATCHING
Effective: April 1, 2014 Revised: April 13, 2020
Description. This work shall consist of partial depth removal of the existing PCC or HMA pavement and replacement with HMA.
The partial depth removal on a lane width or less shall be classified by type/size as follows.
Type I Less than 8 sq yd (9 sq m) Type II 8 sq yd (9 sq m) or more, but less than 50 sq yd (42 sq m) Type III 50 sq yd (42 sq m) or more, but less than 100 sq yd (84 sq m) Type IV 100 sq yd (84 sq m) or more
Materials. Materials shall be according to the following Articles/Sections of the Standard Specifications.
Item Article/Section
(a) Bituminous Material for Prime Coat ........................................................................ 406.02
(b) Hot-Mix Asphalt (Note 1)
Note1. If the patch is going to be resurfaced, the HMA for partial depth patches shall be a surface mixture of the same type as the proposed resurfacing or as approved by the Engineer. If the patch is not going to be resurfaced, the mix shall be as shown on the plans.
Equipment. Equipment shall be according to the following Articles/Sections of the Standard Specifications.
Item Article/Section
(a) Self-Propelled Milling Machine .............................................................................. 1101.16
(b) Concrete Saw ....................................................................................................... 442.03(f)
(c) Wheel Saw .......................................................................................................... 442.03(g)
(d) Rollers ..................................................................................................................... 442.03
SECTION 82-(6,7)RS-2
(e) Mechanical Sweeper ............................................................................................. 1101.03
(f) Air Equipment (Note 1)
Note 1. The air equipment shall be capable of supplying compressed air at a minimum pressure of 100 psi and shall have sufficient flow rate to remove all disturbed pavement debris. The equipment shall also be according to ASTM D 4285.
Construction Requirements
The minimum patch dimension shall be 24 x 24 in.
Partial Depth Removal. Partial depth removal of the pavement shall be accomplished by using a milling machine and/or the wheel saw. The patch area shall be cleaned by air equipment or mechanical sweeper, and all disturbed pavement debris and any loose or unsound concrete shall be removed. Materials resulting from the removal shall be disposed of according to Article 202.03 of the Standard Specifications.
Exposed reinforcement shall be removed back to the point where the steel is in contact with sound concrete. Where high steel is encountered, the depth of the patch may be reduced as directed by the Engineer.
Replacement with HMA. When the Engineer determines the exposed pavement will be suitable for a partial depth patch, a bituminous prime coat shall be applied according to Article 406.05(b) of the Standard Specifications. The prepared patch shall be filled using an HMA Surface Course IL 9.5 Mixture “D” N90. The HMA shall be compacted to the satisfaction of the Engineer.
Patch Maintenance. Patches opened to traffic which are high or become rough by rutting, shoving, or heaving shall be corrected by trimming off high areas and/or filling depressions. Filled areas shall be rolled again.
Areas Unsuitable for a Partial Depth Patch. When the Engineer determines the exposed pavement will not be suitable for a partial depth patch or removal is one half or more of the pavement thickness, the remaining portion of the pavement shall be removed, and a full depth patch shall be constructed according to Section 442 of the Standard Specifications for the class of full depth patches included in the contract. The exposed area may be filled with HMA, and the full depth patch constructed at a later date. HMA shall be placed as specified for the partial depth repair.
Method of Measurement. Partial depth removal of the pavement will be measured in place, and the area computed in square yards.
HMA for partial depth patching of the pavement and for the backfilling of partial depth removal when it is determined the area is not suitable for a partial depth patch will be measured in tons according to Article 406.13 of the Standard Specifications.
Basis of Payment. Partial depth removal of the pavement will be paid for at the contract unit price per SQUARE YARD for PARTIAL DEPTH REMOVAL, of the type and thickness specified.
HMA for partial depth patching and for backfilling areas unsuitable for a partial depth patch will be paid for at the contract unit price per TON for PARTIAL DEPTH PATCHING.
SECTION 82-(6,7)RS-2
When the Engineer determines to convert any partial depth patch to a full depth patch after the partial depth removal of the pavement has begun, the partial depth removal will still be paid for as Partial Depth Removal. The remaining removal for the full depth patch will be considered as included in the appropriate full depth patching pay item.
HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH
Description. This work shall consist of removing the HMA surface from the existing pavement along portions of I-255 as shown in the plans, in accordance with the applicable portions of Section 440 of the Standard Specifications, and as directed by the Engineer.
The intent of the HMA surface removal, variable depth is to provide variable milling depth transitions between existing or proposed changes in resurfacing thickness. The depths for removal shown in the plans are based on previous resurfacing plans within these removal areas.
No additional compensation will be made for deviations in actual thickness.
Method of Measurement. This work will be measured in place in square yards.
Basis of Payment. This work will be paid for at the contract unit price per SQUARE YARD for
HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH.
INSTALLATION OF TEMPORARY CONCRETE BARRIERS AND/OR TEMPORARY BRIDGE
RAIL
Effective: May 18, 1993 Revised: November 1, 2006
The following procedure and traffic control shall be used for the placement, relocation, and removal of temporary concrete barrier and/or temporary bridge rail on this project:
Placement of Temporary Concrete Barrier and/or Temporary Bridge Rail:
1. Erect Standard 701321 as shown on the plans for stage 1 construction except for the temporary concrete barrier and/or temporary bridge rail.
2. Place the temporary traffic signals in the red flash mode.
3. Close the stage 1 construction lane to traffic, and route two-way traffic over the stage 1 traffic lane. One flagman will be required at each end of the lane closure at all times to direct traffic.
4. Erect the temporary concrete barrier and/or temporary bridge rail in the stage 1 location beginning at the approach end of the lane closure and proceeding to the departure end.
Relocation of Temporary Concrete Barrier and/or Temporary Bridge Rail:
1. When stage 1 construction is complete, relocate temporary concrete barrier tapers parallel to the roadway centerline beginning at the departure end and proceeding to the approach
SECTION 82-(6,7)RS-2
end. Place cones at 25 ft centers to establish temporary tapers to close the stage 2 construction lane to traffic and route traffic over the stage 2 traffic lane.
2. Place the temporary concrete barrier and/or temporary bridge rail in the stage 2 location starting with the approach end and proceed to the departure end.
3. This procedure shall be followed for any adjustment of temporary concrete barrier and/or bridge rail during any stage.
Removal of the Temporary Concrete Barrier and/or Temporary Bridge Rail:
1. When stage 2 construction is completed, remove the temporary concrete barrier and/or temporary bridge rail beginning at the departure end of the lane closure and proceeding to the approach end. Place cones at 25 ft centers to delineate the closed lane until all the temporary concrete barrier and/or bridge rail is removed.
2. Remove Standard 701321, and route two-way traffic over the structure.
Additional Requirements During Placement, Relocation, and Removal of Temporary Concrete Barrier and/or Temporary Bridge Rail:
1. One lane of traffic shall be maintained at all times.
2. Workers and equipment will not be permitted to encroach on the lane open to traffic.
3. Any length of temporary concrete barrier and/or temporary bridge rail not completed in a one-day time period shall be protected by barricades with steady-burning lights at 25 ft centers until the barrier work is complete. A temporary attenuator shall be placed on the end of any length of temporary concrete barrier and/or temporary bridge rail not completed.
4. Traffic control devices, as specified on the plans for Standard 701321, shall be placed on all temporary concrete barrier and/or temporary bridge rail in use overnight.
The cost of complying with this procedure shall be considered included in the cost of Temporary Concrete Barrier, Relocating Temporary Concrete Barrier, and/or Temporary Bridge Rail outlined in the plans.
CONCRETE BARRIER
Description. This work consists of the installation of the concrete barrier along applicable sections of the mainline after the removal of the existing concrete median barrier. The barrier shall be constructed in accordance with Section 637 except as modified herein.
At locations where the median fill between barriers is to remain, the Contractor shall remove the existing material as necessary to construct the proposed concrete barrier and barrier base. The fill material shall be replaced in kind and as approved by the Engineer following construction of the concrete barriers and barrier base.
Method of Measurement. Add the following:
“Removal and replacement of the material between the concrete barriers and barrier bases will not be measured for payment separately but considered included in the cost of these proposed pay items.”
SECTION 82-(6,7)RS-2
CONCRETE BARRIER BASE (SPECIAL)
Description. This work consists of installing the concrete barrier base along applicable sections of the mainline after removal of the existing concrete median barrier. The barrier base width shall be as shown in the typical sections from face of the removed single face barrier to the opposing face of the other single face barrier. This work shall be as directed by the Engineer and in accordance with the applicable portions of Section 440 of the Standard Specifications.
Basis of Payment. This work will be paid for at the contract unit price per FOOT for CONCRETE
BARRIER BASE (SPECIAL).
PORTLAND CEMENT CONCRETE SURFACE REMOVAL (VARIABLE DEPTH)
This work shall be in accordance with applicable portions of Section 440 of the Standard Specifications, the plans, and as herein specified.
The equipment shall be capable of milling the existing PCC pavement to a nominal depth of 1”.
At pavement transitions, the depth of milling shall be adjusted to provide the transition as shown on the plans. The Engineer shall be notified immediately of any reinforcing that is exposed during the milling operations so adjustments may be made.
All labor and materials required to complete this work including, but not limited to, the milling of the existing pavement shall be included for payment under this item.
This work will be paid for at the contract unit price per SQUARE YARD for PORTLAND CEMENT
CONCRETE SURFACE REMOVAL (VARIABLE DEPTH).
PORTLAND CEMENT CONCRETE SURFACE REMOVAL 1"
Description. This item consists of the removal of PCC pavement surface as described on the plans or as directed by the Engineer. The work shall be performed in accordance with the plans and Section 440 of the Standard Specifications.
Method of Measurement. This work shall be measured in square yards of removed surface.
Basis of Payment. This work shall be paid for at the contract unit price per SQUARE YARD for PORTLAND CEMENT CONCRETE SURFACE REMOVAL 1”, which price shall include the labor, equipment, and materials necessary to perform the work.
SECTION 82-(6,7)RS-2
REMOVE EXISTING RIPRAP
Description. This work shall consist of removing existing stone riprap and broken concrete that has been placed behind the existing guardrail to stop erosion. The depth is not uniform and can vary from 6 inches to 2 feet in depth. The existing riprap shall be removed in a manner that does not create further erosion problems.
Method of Measurement. This work will be measured in place in square yards.
REMOVE EXISTING RIPRAP.
PORTLAND CEMENT CONCRETE SHOULDERS 12” (SPECIAL)
Description. This work consists of replacing shoulders around concrete median barrier inlets as shown on the plans, as directed by the Engineer, and in accordance with the applicable portions of Section 483 of the Standard Specifications.
The removal of the shoulder and frame and grate adjustment shall be paid for separately. The use of the metal comb finish shall not be required.
PORTLAND CEMENT CONCRETE SHOULDERS 12” (SPECIAL).
PIPE DRAIN REMOVAL
Description. This work consists of removing existing pipe drains at locations shown on the plans, as directed by the Engineer, and in accordance with the applicable portions of Section 501 of the Standard Specifications. The pipe drains to be removed under this item generally conform to Highway Standard Drawings for Shoulder Pavement or special details for Bridge Approach Shoulder Pavement and Drain.
When a portion of the existing pipe drain shall be removed as part of removing inlets, the remaining portion of the pipe drain will not be abandoned but incorporated in final drainage systems as shown on the plans. When the existing pipe drain shall be removed completely from the existing shoulder inlet to the end of the pipe drain, the existing thrust blocks and metal end sections shall also be removed.
Basis of Payment. This work will be paid for at the contract unit price per FOOT for PIPE DRAIN
REMOVAL.
SECTION 82-(6,7)RS-2
REMOVE CONCRETE HEADWALLS FOR PIPE DRAINS
This work shall consist of the removal of existing precast concrete headwalls for pipe underdrain outlet pipes as shown in the plans.
Existing concrete headwalls shall be removed completely at the locations shown.
This work will be measured for payment in units of each at the location shown on the plans regardless of size, type, or material. Excavation of earth necessary to perform the removal of end treatments and topsoil required to fill depressions will not be measured for payment but shall be included in the cost of the concrete headwall removal.
This work will be paid for at the contract unit price per EACH for REMOVE CONCRETE
HEADWALLS FOR PIPE DRAINS.
REMOVE EXISTING UNDERDRAINS
Description. This work shall consist of removing the existing pipe underdrain outlet pipes at the locations shown in the plans. The removal limits can be from the existing underdrain to the existing precast headwalls or from the edge of the HMA shoulder to the existing precast headwalls.
Method of Measurement. This work will be measured for payment in place in feet.
Basis of Payment. This work will be paid for at the contract unit price per FOOT for REMOVE
EXISTING UNDERDRAINS.
REMOVE EXISTING FLARED END SECTION
Description. This work shall consist of the removal and satisfactory disposal of existing flared end sections according to Section 551 of the Standard Specifications for Road and Bridge Construction. At locations where the end section to be removed is connected to storm sewer pipe to remain, the Contractor shall take care not to damage the storm sewer pipe. Any damage to elements to remain beyond the limits of removal shall be repaired at the Contractor’s expense.
Basis of Payment. This work will be paid for at the contract unit price per EACH for REMOVE EXISTING FLARED END SECTION of unspecified type and diameter, including backfill if required.
SECTION 82-(6,7)RS-2
FRAMES AND GRATES TO BE ADJUSTED
Description: This work consists of adjusting frames and grates at locations shown on the plans, as directed by the Engineer, and in accordance with Section 603 of the Standard Specifications.
Frames and grates to be adjusted under this item are due to HMA resurfacing of the various roadways within the project limits. The existing frames and grates generally conform to highway standards ranging from conventional manhole and inlet frame and grates to 3 foot square median inlets.
Method of Measurement. The method of adjustment shall meet the approval of the Engineer.
Basis of Payment: This work will be paid for at the contract unit price per EACH for FRAMES AND
GRATES TO BE ADJUSTED.
ENGINEER’S FIELD OFFICE, TYPE A (SPECIAL)
Description. This work shall consist of furnishing and maintaining in good condition for the exclusive use of the Engineer a weatherproof building hereinafter described at a location approved by the Engineer. This field office shall be independent of any building used by the Contractor, and all keys to the field office shall be turned over to the Engineer. The Engineer will designate the location for the building, and it shall remain on the jobsite until released by the Engineer.
The field office shall have a ceiling height of no less than 7 ft, and a floor space of no less than 1300 sq ft. The building shall be new.
The field office shall be equipped with two entrance doors located on the same side of the building.
Doors and windows shall be equipped with locks approved by the Engineer. The entrance doors for the building shall be keyed with ten keys provided to the Engineer. A landing of a minimum 5 x 5 ft dimension shall be provided at each entrance doorway with integral steps and railings. An awning shall be provided to protect each entry. A 100-watt light shall be attached to the exterior of the building at each doorway.
Windows shall be equipped with exterior screens to allow adequate ventilation. All windows shall be equipped with interior shades, curtains, or blinds.
Workspace in the building shall be divided into four separate office rooms and one large conference area. Each office room shall have an independently keyed locking door with three keys provided to the Engineer. The building shall be provided with sufficient heat, natural and artificial light, and air conditioning.
One suitable onsite sanitary facility meeting federal, state, and local health department requirements shall be provided in the building, maintained clean and in good working condition, and shall be stocked with lavatory and sanitary supplies at all times during the period of the
SECTION 82-(6,7)RS-2
contract. Sanitary facilities shall include hot and cold potable running water, lavatory, mirror, ventilation fan, and toilet as an integral part of each structure.
Solid waste disposal consisting of eight small (26 quart) waste baskets, two large (35 gallon) waste baskets, and an outside trash container of sufficient size to accommodate a weekly provided pick-up service shall be provided.
An electronic security system that will respond to any breach of exterior doors and windows with an on-site alarm will be provided.
With the approval of the Engineer, a mobile unit of approximately the same dimensions and having similar facilities may be substituted for the above-described building. The mobile unit must be tied down near the four corners at each end of the mobile unit. The tiedown equipment shall be of the type commonly sold by mobile home equipment suppliers to protect mobile homes in areas affected by hurricanes. The tie-down shall be made to the satisfaction of the Engineer.
The mobile unit shall be securely supported by adequate blocking. The blocking shall provide a foundation to prevent settlement. The mobile unit shall be equipped with two entrance doors located on the same side of the structure. A landing of a minimum 5 x 5 ft dimension shall be provided at each entrance doorway with integral steps and railings. An awning shall be provided to protect each entry. A 100-watt light shall be attached to the exterior of the unit at each doorway.
In addition, the following equipment and furniture meeting the approval of the Engineer shall be furnished new.
a) Twelve desks with minimum working surface of 42 x 30 in. each.
b) Twelve non-folding chairs with upholstered seats on caster bases. Chairs shall have adjustable height, arms, and backs.
c) Twelve under-chair floor mats.
d) One four-post drafting table with minimum top size of 37 x 48 in. The top shall be basswood or equivalent and capable of being tilted through an angle of 50°.
e) One adjustable height drafting stool with upholstered seats and backs.
f) Eight free standing four drawer legal size file cabinets with locks and an UL insulated file device 350° one hour rating.
g) Twenty folding chairs and three folding tables 8 feet long.
h) Two equipment cabinets with minimum inside dimension of 44 in. high x 24 in. wide x 30
in. deep with lock. The walls shall be steel with a 3/32 in. minimum thickness with concealed hinges and enclosed lock constructed in such a manner as to prevent entry by force. The cabinet assemblies shall be permanently attached to a structural element of the office in a manner to prevent theft of the entire cabinet.
i) Six dry erase boards, 4 x 6 ft, with markers and erasers.
j) Two first aid cabinets fully equipped and meeting OSHA requirements.
k) Six fire extinguishers having a minimum UL rating of 4A60BC.
l) One refrigerator with a minimum size of 18.0 cubic feet with a freezer unit and ice maker.
m) One electric water cooler dispenser, in addition to water service connection.
n) One 2.0 cubic feet microwave ovens 1000 watt minimum.
o) Four electric desk-type tape printing calculators.
p) One large electric paper shredder.
q) One post mounted rain gauge, viewable from 20’ away.
r) A minimum of two communication paths. The configuration shall include:
SECTION 82-(6,7)RS-2
(1) Internet Connection. An internet connection using telephone DSL, cable broadband, or LTE, 4G or newer, wireless technology. The ISC shall have a minimum 5 mbps download speed and 2mbps upload speed. Additionally, wireless technology systems shall have a RSRP greater than or equal to -90 dBm, a RSRQ greater than or equal to -15 dB, SINR greater than or equal to 13 dB, and a RSSI greater than or equal to - 85 dBm. Signal boosters and external antenna may be incorporated to increase the signal strength at no additional cost.
Additionally, an 802.11g/N wireless router shall be provided and shall be backwards compatible with 802.11b equipment for a data transfer rate of up to 11 Mbps. The router shall have a built-in four-port 10/100 Ethernet Switch, built-in NAT/SPI firewall, and security consisting of 64-bit WEP data encryption and WPA with TKIP & AES. ISC shall be hard wire connected using Cat 5e or better to the router and protected by a Tripp Lite Isobar 2 or equivalent. Router/ISC modem shall be centrally located in the common area of the field office. If this is not possible, a Cat 5e or better wire shall be installed from the router to all connected devices. The router’s wireless SSID access point shall be renamed and set to not broadcast the access point name.
(2) Six telephone lines. A phone line shall be dedicated to each individual office, one shall be dedicated to the conference area, and one shall service the remaining common area.
s) Eight touchtone phones, four with digital answering machines and speakerphone capability. The Contractor shall submit specifications for the telephone answering machine to the Engineer for review and approval prior the purchase of this item. The telephone answering machine shall meet the following additional minimum specifications:
(1) Time/Day Indication-A computerized voice records the date and time that each message is received.
(2) Beeperless Remote-Any remote touch-tone phone can be used to review all messages using an access code.
(3) Digital System-Pre-recorded and received messages are managed electronically through a voicemail system.
(4) Conversation Record-The operator can record any phone call.
(5) Remote Turn-On-Any remote touch-tone phone can be used to turn on the answering machine using an access code.
(6) Full Message-The Caller is advised if the memory is insufficient to record the call.
(7) Battery Back-Up-The settings and messages are protected from power failures.
(8) Two-Line Capacity-Projects that have a second phone line through the provision of a
670.05 Engineer’s Field Laboratory shall provide a single phone answering machine that services both lines.
t) A Multifunction Printer (MFP) shall be provided with the ability to copy/print/fax from and scan to networked devices. Color printing is not required. Laser is preferred over Inkjet.
MFP shall meet the following specifications:
(1) Centrally located in the field office and hardwire connected to the router using a Cat
5e or better wire and protected by a Tripp Lite Isobar 2 or equivalent. Compatible with Microsoft Windows 7 or newer operating system as well as Apple iOS (AirPrint).
SECTION 82-(6,7)RS-2
(2) Ability to print to the MFP device using direct IP printing using a universal print driver or model specific print driver that is downloadable and can be freely distributed.
(3) Main printer tray of letter size paper (8 ½” x 11”), secondary paper tray of tabloid size paper (11” x 17”), both holding at least ½ ream of paper (250 sheets). Manufacturer specifications of minimum monthly duty cycle of 40,000 pages, print minimum of 25 letter size pages per minute, and duplex printing ability.
(4) Scan in color up to tabloid size documents at a minimum of 300 dpi (dots per inch).
Paper feed capability of storing 30 sheets of paper and handle duplex printed documents. The option to save the scanned file in .pdf and/or.jpg format. Scanned file either saved to an internal hard drive that is accessible from any networked device or be able to scan directly to the Engineer’s computer and/or tablet (iPad).
(5) Contractor is responsible for all maintenance of the MFP and supply all printer ink/toner cartridges and paper for the duration of the field office.
The Engineer shall be informed of the date and estimated time the ISC, router, and MFP will be installed. The Engineer shall be given all administrator ID and passwords at the time of installation.
All ISC/router passwords will be managed by the Engineer.
Basis of Payment. The engineer’s field office, type A (special) shall be furnished complete and ready for acceptance by the Engineer within ten working days of the date delivered to the jobsite.
The building fully equipped as specified and accepted by the Engineer will be paid for on a monthly basis until released by the Engineer. The Contractor will be paid the contract bid price each month provided the building is maintained, equipped, and utilities furnished. Payment will not be made when the contract is suspended according to Article 108.07 for failure of the Contractor to comply with the provisions of the contract.
This work will be paid for at the contract unit price per CALENDAR MONTH or fraction thereof for ENGINEER’S FIELD OFFICE, TYPE A (SPECIAL). This price shall include all utility costs and shall reflect the salvage value of the buildings, equipment, and furniture which remain the property of the Contractor after release by the Engineer except that the Department will pay that portion of the monthly long distance and monthly local telephone bills that, when combined, exceed $150.
Any extraordinary damage attributed to State operations during the job will be repaired by the Contractor and may be paid for according to Article 109.04. No extra payment will be made for systems maintenance, repairs or replacement, or for damages incurred as a result of vandalism, theft, or other criminal activities.
SECTION 82-(6,7)RS-2
PIPE DRAIN CONNECTIONS
Connections of the new or existing pipe drains to new or existing drainage structures shall be made in a manner which results in a neat and watertight joint. When placed through the wall of a drainage structure, pipe drains shall be placed or cut flush with the face of the wall and dressed with mortar to provide a smooth, rounded, or beveled edge. This work will not be paid for separately but shall be included in the cost of the pipe drains, underdrains, and drainage structures involved.
CONCRETE BARRIER REMOVAL (SPECIAL)
Description. This work shall consist of the complete removal of all concrete barrier as shown in the plans or directed by the Engineer.