ildot 72342.082.pdf

PDF 5 MB Posted

Attached to
Reconstruction of Sudduth Road Project
Solicitation number
72342
Issued by
St. Clair County, Illinois

About this file

This is a Notice to Bidders and Special Provisions document issued by the Illinois Department of Transportation (IDOT) for the reconstruction of Sudduth Road in Sangamon County, Contract No. 72342. The project involves the removal and reconstruction of structure SN 084-0100 carrying Sudduth Road over Interstate 55, located approximately 0.6 miles north of the I-55 Sherman interchange. Major work items include earth excavation, embankment, topsoil placement, bridge removal and construction, maintenance of traffic, pipe culverts, erosion control, hot-mix asphalt (HMA) base and surface courses, pavement markings, and seeding. The project extends 1,140 feet along Sudduth Road, beginning approximately 200 feet west of West Outer Road and extending east to approximately 500 feet past the I-55 structure. Electronic bids must be submitted to the iCX (Integrated Contractors Exchange) system prior to 12:00 p.m. on November 6, 2026. The contract will be awarded to the lowest responsive and responsible bidder. Completion is required by October 31, 2027, with an additional 10 working days permitted for remaining items while maintaining traffic. Construction shall be staged in three phases to minimize traffic disruption while maintaining access to adjacent properties.

Substantial traffic control requirements are mandated throughout the project, including temporary lane closures on I-55 restricted to 7:00 p.m. to 6:00 a.m. Sunday through Friday, with complete northbound I-55 closures limited to three separate work shifts for beam removal and replacement operations. The project is funded with Federal-aid highway construction funds under the NHPP-T4CS program. Multiple utility relocations are required prior to and during construction, involving Ameren Illinois (gas/electric), AT&T, Comcast, Frontier Communications, Level 3/Lumen, Menard Electric Cooperative, and the Village of Williamsville. The contractor must provide five portable changeable message signs and maintain coordination with the District 6 Bureau of Operations, Illinois State Police, Sangamon County Emergency Services, and other agencies. The document includes comprehensive supplemental specifications and recurring special provisions addressing concrete quality control, asphalt requirements, structural steel hot-dip galvanizing, preformed pavement joint seals, slipform parapet construction, and disadvantaged business enterprise (DBE) participation requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting November 6, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 72342 SANGAMON County Section (84-2HB-1)R,BR Route FAI 55 Project BR-NHPP-T4CS(819) District 6 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

November 6, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 72342 SANGAMON County Section (84-2HB-1)R,BR Project BR-NHPP-T4CS(819) Route FAI 55 District 6 Construction Funds

Reconstruction of Sudduth Road, 0.6 miles north of the I-55 Sherman interchange. Project includes the removal and reconstruction of SN 084-0100 carrying Sudduth Road over I-55.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

FAI ROUTE 55 (I-55)

PROJECT BR-NHPP-T4CS(819)

SECTION (84-2HB-1) R, BR

SANGAMON COUNTY

CONTRACT NO. 72342

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

SECTION (84-2HB-1) R, BR

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 X Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 X Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

SECTION (84-2HB-1) R, BR

i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF IMPROVEMENT

SUGGESTED CONSTRUCTION SEQUENCE AND SCHEDULE

TRAFFIC CONTROL PLAN

STATUS OF UTILITIES TO BE ADJUSTED

UNDERGROUND FACILITIES – DEPARTMENT OWNED

COMPLETION DATE PLUS WORKING DAYS

ROAD CLOSURE RESTRICTION

DETOUR SIGNING

CLEARING (SPECIAL)

BARRICADES, TYPE III

SAWING PAVEMENT (FULL DEPTH)

REMOVE EXISTING RIPRAP

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH

HMA ANTI-STRIP ADDITIVE REQUIREMENTS

HOT-MIX ASPHALT BASE COURSE, (VARIABLE DEPTH)

PIPE CULVERTS, CLASS A (JACKED)

PIPE UNDERDRAINS 4” (SPECIAL)

REMOVE AND REINSTALL IMPACT ATTENUATORS

REMOVE ATTENUATOR BASE

REMOVE AND REINSTALL HIGH TENSION CABLE MEDIAN BARRIER

REMOVAL OF EXISTING STRUCTURE (SPECIAL)

PAVEMENT STATIONING NUMBERS AND PLACEMENT

SLIPFORM PARAPET

BRIDGE DECK CONSTRUCTION

HOT DIP GALVANIZING FOR STRUCTURAL STEEL

PREFORMED PAVEMENT JOINT SEAL

BAR SPLICERS, HEADED REINFORCEMENT

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

COMPENSABLE DELAY COSTS (BDE)

CONCRETE SEALER (BDE)

DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)

ENGINEER’S FIELD OFFICE (BDE)

EROSION CONTROL BLANKET (BDE)

SECTION (84-2HB-1) R, BR

ii

FUEL COST ADJUSTMENT (BDE)

GUARDRAIL (BDE)

HOT-MIX ASPHALT (BDE)

HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)

PAVEMENT MARKING (BDE)

PAVEMENT PATCHING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SEEDING (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SLOPE WALL (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

SPEED DISPLAY TRAILER (BDE)

STEEL COST ADJUSTMENT (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURVEYING SERVICES (BDE)

TEMPORARY CONCRETE BARRIER (BDE)

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

WEEKLY DBE TRUCKING REPORTS (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

WORK ZONE WIDTH RESTRICTION (BDE)

STORM WATER POLLUTION PREVENTION PLAN

SECTION (84-2HB-1) R, BR

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," Adopted January 1, 2022, the latest edition of the "Illinois Manual on Uniform Traffic Control Devices for Streets and Highways" and the “Manual of Test Procedures for Materials” in effect on the date of invitation for bids; and the "Supplemental Specifications and Recurring Special Provisions," indicated on the Check Sheet, included herein, which apply to and govern the construction of FAI Route 55 (I-55), Project BR-NHPP-T4CS(819), Section (84-2HB-

1) R, BR, Sangamon County, Contract No. 72342, in case of conflict with any part or parts of said specifications, the said Special Provisions shall take precedence and shall govern.

FAI Route 55 (I-55) Project BR-NHPP-T4CS(819)

Section (84-2HB-1) R, BR Sangamon County Contract No. 72342

LOCATION OF PROJECT

This project is located along Sudduth Road in Sangamon County. It begins approximately 200 ft.

west of its intersection with West Outer Road (North I-55 Frontage Road) and extends east to approximately 500 ft. past the structure over I-55. The improvement is 1,140 ft. long.

DESCRIPTION OF IMPROVEMENT

This project includes the reconstruction of Sudduth Road including the removal and reconstruction of the structure over I-55 (proposed SN 084-0599). Major items of work include earth excavation, embankment, topsoil placement, construction layout, bridge removal and construction, maintenance of traffic, pipe culverts, erosion control, HMA base course, HMA and aggregate shoulders, HMA binder and surface course, HMA milling and resurfacing, bituminous tack coat, entrances, sign panels, seeding, and pavement markings.

SECTION (84-2HB-1) R, BR

SUGGESTED CONSTRUCTION SEQUENCE AND SCHEDULE

The Contractor shall prepare a progress schedule, which includes the work to be performed by utilities, and shall coordinate items of work to keep hazards and traffic inconvenience to a minimum. Sudduth Road will be closed to through traffic between West Outer Road and the private entrances east of the bridge. Contractor shall maintain access to adjacent property owners and accommodate access at all time. Construction shall be staged as shown on the plans and as listed below to meet the following requirements:

Stage 1. Close Sudduth Road from just east of West Outer Road to west of the private entrances on the east side of the bridge over I-55. Place maintenance of traffic items along I-55, remove the existing bridge, and complete the clearing around the bridge. Begin constructing the new bridge.

Construct earthwork, drainage items, HMA base course, HMA binder course, and shoulders for Sudduth Road.

Stage 2. Continue structure work. Mill the connections back down to existing ground at the west and east ends of the project. This work should be completed while keeping the intersection of Sudduth Road and West Outer Road and the church entrance open to vehicles turning west. The private entrances on the east end of the project shall remain open in the eastbound direction as well. Complete the HMA surface course along Sudduth Road and at the entrances. Complete the intersection work at West Outer Road.

Stage 3. Finalize the structure work. Remove traffic control items from I-55. Complete signing, pavement markings, and guardrail placement along Sudduth Road. Remove the barricades at the beginning and end of project, and open Sudduth Road to traffic.

TRAFFIC CONTROL PLAN

Effective: November 1, 1984 Revised: October 10, 2022

The following traffic control and protection will apply to this project:

Highway Standards:

701001 This standard will be used on 2 lane / 2 way traffic for all work activities greater than 15 ft. from the edge of pavement.

701006 This standard will be used on 2 lane / 2 way traffic for all work activities within 24 inches to 15 ft. from the edge of pavement.

701101 This standard will be used on multi-lane highways for all work activities within 24 inches and 15 ft. from the edge of pavement.

701106 This standard will be used on multi-lane highways for all work activities greater than 15 ft. from the edge of pavement.

SECTION (84-2HB-1) R, BR

701301 This standard will be used on 2 lane / 2 way traffic for construction activities such as stringline operations, work zone pavement marking removal, and cleaning debris on the pavement.

701311 This standard will be used on 2 lane / 2 way traffic for construction activities that require continuous moving operations such as installing pavement markings.

701400 This standard will be used any time a lane is closed on a freeway or expressway.

701401 (Special)

This standard will be used any time a night-time lane closure is required on a freeway or expressway due to work encroaching on a travel lane adjacent to the shoulder or on the shoulder within 24” of the edge of pavement. This standard is applicable for construction activities such as bridge removal and replacement at the location specified in the plans.

This standard will be used to close northbound I-55 for beam removal and replacement operations. See plans for additional details. This standard shall be used in conjunction with Standard 701400.

This work will be paid at the contract unit price per LUMP SUM for TRAFFIC

CONTROL AND PROTECTION, STANDARD 701401 (SPECIAL)

701402 (Special)

This standard will be used any time a lane closure is required on a freeway or expressway due to work encroaching on a travel lane adjacent to the shoulder or on the shoulder within 24” of the edge of pavement and where temporary concrete barrier wall is utilized. This standard is applicable for construction activities such as bridge removal and replacement at the locations specified in the plans and shall be used in conjunction with Standard 701400.

During times when I-55 additional lane closures are not allowed but temporary concrete barrier is present, the “Work Zone Speed Limit 55” and “Trailer Mounted Speed Display” signs and devices shall continue to be displayed as indicated in Standard 701400. The cost associated with keeping these traffic control devices in place will not be paid for separately but considered included in the cost of Traffic Control and Protection, Standard 701402 (Special).

This standard will be used for the long-term closure of the southbound I-55 passing lane for the duration of the work. This detail will also be used for nighttime lane closures for northbound I-55. Use of this detail for the long-term lane closure shall be considered as one application of the standard detail. Use of this detail for the northbound and southbound lane closures, regardless of the number of setups required for each direction, shall be considered as one application per direction.

This work will be paid at the contract unit price per EACH for TRAFFIC CONTROL

AND PROTECTION, STANDARD 701402 (SPECIAL)

701428 This standard will be used for setup and removal of lane closures on freeways and expressways having an ADT greater than 25,000.

SECTION (84-2HB-1) R, BR

701446 This standard will be used any time a two-lane lane closure is required on a freeway or expressway due to work encroaching on a travel lane adjacent to the shoulder or on the shoulder within 24” of the edge of pavement. This standard is applicable for construction activities requiring southbound I-55 to be reduced to one lane of traffic and shall be used in conjunction with Standard 701400.

701901 This standard describes all permissible traffic control devices that can be utilized with the listed traffic control standards.

BLR 21 This standard shall be used during construction activities which involve a temporary road closure of Sudduth Road. This work shall be done in accordance with Section 701 of the Standard Specifications, as per Highway Standard BLR 21 and the plan details. This work will be measured and paid for at the contract unit price per LUMP SUM for TRAFFIC CONTROL AND PROTECTION, STANDARD

BLR 21.

Limitations Of Construction: The Contractor shall coordinate the items of work to keep hazards and traffic inconveniences to a minimum, as specified below.

1. The Contractor shall contact the District 6 Bureau of Operations, (217) 785-0494, at least 72 hours in advance of beginning work and three weeks prior to implementing any traffic control.

2. The Contractor shall erect portable changeable message signs (PCMS) seven days in advance of implementing Standards 701400, 701401 (Special), 701402 (Special), and 701446 alerting the public of upcoming work. These are in addition to the five PCMS described later in this provision. The exact location of these changeable message signs will be confirmed by the Engineer and shall remain in place until the temporary concrete barrier wall on I-55 is removed.

3. All traffic control signs shall be new and meet current reflectivity standards. Remaining traffic control devices shall be new, or like new, equipped with new reflective sheeting at the time of use. The Engineer will be the sole judge of the condition of the devices.

4. In addition to the signs required by Standards 701400, 701401 (Special), 701402 (Special), and 701446, the Contractor shall erect two ROAD CONSTRUCTION AHEAD (W10-I103(O)-48) and two X MILES (W16-3A(O)48) signs 3 and 5 miles in advance of the work zone. The additional signs will not be paid for separately but considered included in the contract unit bid prices for the traffic control and protection pay items.

5. In advance of each lane closure, the Contractor shall provide four “BE PREPARED TO STOP” (W3-4(O)48 SIGNS. These signs shall be tripod mounted and placed on southbound and northbound I-55 to provide adequate warning in advance of traffic back-ups. The signs will not be paid for separately but considered included in the contract unit bid prices for the traffic control standard they are being used in conjunction with.

6. Any signs shown on the plans that are in addition to the signs required by traffic control standards shall be included in the cost of the traffic control standard that they are being used in conjunction with.

7. Temporary lane closures restricting I-55 to one lane in either direction shall only be allowed from 7:00 PM to 6:00 AM Sunday night through Friday morning, except as specified in Items 8 and 9. Lane closures will not be permitted between 6:00 AM Friday through 7:00 PM Sunday.

8. The complete closure of northbound I-55 for beam removal and replacement operations

SECTION (84-2HB-1) R, BR

will be limited to three separate work shifts from 7:00 PM to 6:00 AM Sunday night through Friday morning. Closures of northbound I-55 will not be permitted between 6:00 AM Friday through 8:00 PM Sunday.

9. The complete short-term closure of southbound I-55 for beam removal and replacement operations will be limited to three separate work shifts and shall occur between 10:00 PM to 6:00 AM Sunday night through Friday morning. Short-term closures of southbound I-55 will not be permitted between 6:00 AM Friday through 10:00 PM Sunday. Short-term closures of southbound I-55 shall be limited to15 minute intervals.

Keeping Roads Open to Traffic: During the construction of this section, a minimum of two lanes of I-55 in each direction shall remain open to traffic except as allowed below:

• Long-Term Southbound Passing Lane Closure: A long-term closure of the southbound passing lane on I-55 shall be implemented for removal of the existing bridge piers and construction of the new center pier. Temporary concrete barrier shall be installed along both sides of the roadway, positioned 2 feet from the edge of pavement.

• Nighttime Single-Lane Closures: Periodic nighttime single-lane closures for both northbound and southbound directions shall be permitted as needed. These closures will support the removal and replacement of shoulders and pavement adjacent to the outside piers during bridge demolition and reconstruction operations.

• Full-Stop Operations: Short-term full-stop operations for southbound I-55 shall be permitted for beam removal and replacement activities. Such closures shall be coordinated with law enforcement and staged in accordance with the plans and the provisions stated herein.

• Full Closure: Northbound I-55 closures shall be permitted for beam removal and replacement activities. Such closures shall be staged in accordance with the plans and the provisions stated herein.

The Contractor shall provide five PCMS units, in addition to the two advanced warning PCMS required elsewhere in this provision. PCMS (#1 & #4) are to be erected in advance of I-55 lane closures (long-term or overnight).

One PCMS (#1) will be provided on southbound I-55 in advance of the long-term closure of the passing lane and will display the message:

LT LANE

CLOSED

X MILES

An additional PCMS (#2) shall be provided to cover supplemental nighttime left or right lane closures for southbound I-55 and PCMS (#5) shall be provided to cover supplemental northbound lane closures. These will display the messages:

LT/RT LANE

AHEAD

MERGE

LT/RT

SECTION (84-2HB-1) R, BR

PCMS shall be placed at approximate locations as shown on the Detour Plan/PCMS Locations plan or at locations designated by the Engineer.

I-55 Closures (Northbound): The existing bridge beams over the northbound lanes shall be removed and new beams placed utilizing Standard 701401 (Special) to temporarily close northbound I-55 by reducing traffic down to a single lane and then directing traffic onto the northbound Sherman exit ramp. From there, northbound I-55 traffic will use a temporary detour to rejoin I-55 north of Sudduth Road via I-55 BUS. See Detour Plan sheets for additional information.

A PCMS (#5) will be provided south of the northbound I-55 exit ramp (Exit 105) to direct traffic onto the ramp. The sign shall display the following message:

I-55

TRAFFIC

MUST

EXIT

I-55 Short-Term Closures (Southbound): The existing bridge beams over the southbound lanes shall be removed and new beams placed by implementing Standard 701446 reducing traffic down to the driving lane for a maximum time of 15-minutes.

The Contractor shall provide a PCMS (#3) north of the work area at a location to be determined by the Engineer to facilitate the temporary (15-minute maximum) full stop nighttime closures of southbound I-55. The sign shall display the following message:

I-55

AHEAD

BE

PREPARED

TO STOP

EXPECT

DELAYS

Full stops shall only be permitted when all equipment, materials, and personnel are in position and beam removal or setting operations are ready to proceed immediately.

Temporary full stops will be permitted only for the duration necessary to safely perform beam removal and replacement operations but shall not exceed the allowable 15 minutes. If the operation cannot be completed within the allowable time, traffic shall be released and the operation rescheduled. The subsequent 15-minute full stop shall not be implemented until the full queue has dissipated from the previous stop.

SECTION (84-2HB-1) R, BR

The Contractor shall provide the following for temporary full stop operations.

• Flaggers and Law Enforcement. Southbound traffic shall be stopped by flaggers and/or law enforcement personnel at locations approved by the Engineer.

• Advance warning signing shall be provided in accordance with Section 701 and the plans.

• PCMS shall be used at the approximate locations specified in the plans. Actual locations to be determined by the Engineer.

• Truck mounted attenuators and additional queue protection devices shall be provided for each open lane at the back of traffic queues as directed by the Engineer.

• The Contractor shall provide and maintain continuous two-way communication between traffic control personnel and the work operation.

See the Maintenance of Traffic (MOT) plan sheets and this special provision for additional information.

The Contractor shall furnish, maintain, and operate a total of seven changeable message signs.

The signs shall be operational seven days prior to beginning construction on I-55 and shall be located as shown on the plans and as directed by the Engineer.

Sudduth Road: Sudduth Road shall be closed to traffic from east of the West Outer Road intersection to west of the private entrances located east of the I-55 overhead structure. The closure limits, barricades, and detour signage shall conform to BLR 21 and to all applicable details shown in the plans. The Contractor shall maintain the closure for the duration of work associated with the bridge removal and replacement.

Changeable message signs will be paid for at the contract unit price per CALENDAR DAY for CHANGEABLE MESSAGE SIGN. Any portion of one calendar day during which the sign is operated, as directed by the Engineer, shall be paid as one full calendar day. Any relocation of the signs, as directed by the Engineer, during construction will not be paid for separately but shall be included in the cost of the changeable message sign.

STATUS OF UTILITIES TO BE ADJUSTED

Reviewed: April 14, 2020

The following utilities are involved in this project. The utility companies have provided the estimated dates.

Name & Address of Utility Type Location Estimated Date of Relocation Completed

Ameren Illinois Mr. Nathan Hill-gas/electric 1915 Old Bus Line Road Hillsboro, IL 62049 Phone: (618) 301-5327

Gas/Electric Prior to and during construction

SECTION (84-2HB-1) R, BR

AT&T Transmission Ms. Vanessa Ross 555 E. Cook St.

Springfield, IL 62703 Phone: (217) 381-4824 Email: VF2021@ATT.com

Communication Prior to and during construction

Ameren Illinois Nolan Severson - gas 825 MacArthur Springfield, IL 62703 217-206-5461 nserverson@ameren.com

Gas Prior to and during Construction

Ameren Central IL Light Co.

Mr. Doug Palmer – electric 825 N. MacArthur Springfield, IL Dpalmer3@ameren.com Phone: (217) 714-7258

Electric Prior to and during Construction

CASSCOMM

Chris Parlier – tele/cable Chris.parlier@casscabletv.com Phone: (217) 452-3022

Fiber Optic Cable Prior to and during

Construction

Comcast Martha Gieras - fiber Martha_gieras@cable.comcast.com Phone: (224) 229-5862

Communications Prior to and during Construction

Frontier Communications of IL Mr. Kalin Hinshaw – cable/fiber 214 S. First Street Monmouth, IL 61462 Kalin.hinshaw@ftr.com Phone: (815) 895-1515

Communication Prior to and During Construction

Level 3/Lumen - fiber NationalRelo@centurylink.com Phone: (877) 366-8344 X2

Menard Electric Cooperative Brady Smith – Electric 14300 State Highway 97 P.O. Box 200 Petersburg, IL 62675 Phone: 217-632-7746 Email: Bsmith@menard.com

Village of Williamsville Kent Thompson – sewer/water 141 West Main St.

Williamsville, IL 62693 Phone: 217-566-3806 Email: wville@gcctv.com

Communication

Electric

Sewer/Water

The above represents the best information available and is included for the convenience of the bidder. The applicable provisions of Articles 105.07, 107.20, 107.37, 107.38, 107.39, SECTION (84-2HB-1) R, BR

107.40, and 108.02 of the Standard Specifications shall apply.

Estimated utility relocation dates should be part of the progress schedule submitted by the Contractor. If any utility adjustments or relocations have not been completed by the above dates specified and when required by the Contractor’s operations after these dates, the Contractor should notify the Engineer in writing. A request for an extension of time will be considered to the extent the Contractor’s critical path schedule is affected.

UNDERGROUND FACILITIES – DEPARTMENT OWNED

Effective: February 1, 1996 Reviewed: September 20, 2024

The Contractor’s attention is directed to the presence of state-owned underground utilities within the limits of the proposed improvement. The Contractor shall notify the Illinois Department of Transportation, Bureau of Traffic Operations, a minimum of 72 hours in advance of work being done in the area at (217) 622-0608 to locate department owned underground facilities. The Illinois Department of Transportation IS NOT a member of the Joint Utility Locating Information for Excavators (JULIE) system.

Any damage to the underground facilities, caused by the Contractor resulting from his failure to contact the Illinois Department of Transportation as specified above or from negligent operation, shall be repaired to the satisfaction of the Department at the Contractor’s expense, including temporary repairs which may be required to keep the facility operational while material is being obtained to make permanent repairs. Splicing of electric and fiber optic cables will not be allowed.

Electric cables shall be replaced from pole to pole or controller.

COMPLETION DATE PLUS WORKING DAYS

The Contractor shall complete all contract items by October 31, 2027, except as provided below.

An additional 10 working days will be allowed after October 31, 2027, to complete the remaining work items while maintaining traffic utilizing applicable traffic control standards. Anticipated remaining work items include:

• Seeding and nutrients

• Mulch

• Miscellaneous items as determined by the Engineer

If the Contractor fails to complete the required work and open the road on or before the completion date stated herein, they shall be liable to the Department for liquidated damages in accordance with Article 108.09 of the Standard Specifications. In addition, failure to open the road on or before the completion date will be considered a traffic control deficiency and will result in a deduction in accordance with Article 105.03(b) of the Standard Specifications.

SECTION (84-2HB-1) R, BR

ROAD CLOSURE RESTRICTION

Reviewed: April 14, 2020

The removal of SN 084-0100 shall be performed under road closure, which shall not be implemented until work in that area is ready to commence.

Prior to the closing I-55 or Sudduth Road, the Contractor shall notify the Engineer and the other agencies listed below at least 21 days in advance of the closure. The notification must also list the projected start and end date of road closure.

Traffic Operations Engineer (District 6) (217) 785-5306 Traffic Control Technician (District 6) (217) 785-0494 Illinois State Police (Troop 6) (217) 786-6677 Sangamon County Central Dispatch System (217) 753-6666 Emergency Services (911) (217) 753-6839 Sangamon County Sheriff’s Department (217) 753-6855 Sangamon County Engineer (217) 535-3070 Village of Sherman (217) 496-2621 Williams Township Highway Commissioner (217) 725-5842 United States Postal Service (217) 546-0463

Up to three complete closures of northbound I-55 will be allowed. Closures shall be limited to the hours of 7:00 pm and 6:00 am Sunday night through Friday morning.

DETOUR SIGNING

Reviewed: April 14, 2020

Description. This work shall consist of furnishing, erecting, maintaining, covering, uncovering, and removing the detour signage as shown in the plans for the temporary closure of I-55 and for the closure of Sudduth Road.

Materials. The materials used shall be in accordance with Section/Article 1090, 1091, 1006.29, and 1007.05 of the Standard Specifications.

Construction Requirements. The Contractor shall furnish and erect new detour signs at locations indicated in the plans. The signs shall be post mounted. Where it is possible, signs may be attached to existing posts or poles. The Contractor can contact District 6 Operations (Traffic) at

(217) 785-5306 for assistance in detour signage locations. The signs are to be in place and uncovered prior to any road closure. When a detour is not in use, the detour signing shall be completely covered. The signs and posts shall be removed when detours are no longer required.

The Contractor shall return the area around the signs to its previous condition, at no additional cost to the Department. This may include seeding.

Basis of Payment. This work will be paid for at the contract unit price per LUMP SUM for DETOUR

SIGNING.

SECTION (84-2HB-1) R, BR

CLEARING (SPECIAL)

Description. This work shall consist of the removal and disposal of all obstructions such as accumulations of rubbish, logs, shrubs, bushes, saplings, weeds, other vegetation, stumps, and trees along the four corners of the structure and behind the existing guardrail along mainline I-55 within existing right of way. All trees, to be removed, including those greater than 6 inches in diameter, shall be included in this work.

Basis of Payment. This work will be paid for at the contract unit price per LUMP SUM for

CLEARING (SPECIAL).

BARRICADES, TYPE III

Description. This work shall consist of furnishing, installing, maintaining, relocating, and removing type III barricades as detailed in the plans. All barricade locations, quantities, and supplemental signage shown in the plans shall be followed unless otherwise directed by the Engineer.

Type III barricades shall be installed to maintain the closure of Sudduth Road between the West Outer Road intersection and the private entrances on the east side of the bridge over I-55.

Additional type III barricades shall be installed on northbound I-55 as shown in the plans for intermittent closures required for beam removal and beam installation.

Basis of Payment. This work will not be paid for separately but shall be included in the cost for Traffic Control and Protection, Standard BLR 21 for Sudduth Road and for Traffic Control and Protection, Standard 701401 (SPECIAL) for I-55.

SAWING PAVEMENT (FULL DEPTH)

Description. This work shall consist of making a full depth saw cut for the removal of driveway pavement and pavement in areas where new work will adjoin the existing. The saw cut shall be made straight with no spalling.

Basis of Payment. This work will not be paid for separately but shall be included in the contract unit price for the item to be removed.

REMOVE EXISTING RIPRAP

Description. This work shall consist of the removal and proper disposal of existing stone riprap and any associated bedding material or filter fabric in accordance with the plans and this special provision.

Basis of Payment. This work will be paid for at the contract unit price per SQUARE YARD for

REMOVE EXISTING RIPRAP.

SECTION (84-2HB-1) R, BR

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH

Revised: March 7, 2025

Description. This work shall consist of the removal of HMA surfaces in preparation for subsequent resurfacing at locations shown in the plans and as directed by the Engineer. This work shall be performed in accordance with applicable portions of Section 440 of the Standard Specifications and the following additional requirements.

Construction Requirements. The typical cross sections and existing HMA surface information plan sheets show expected milling depths and cross slopes to achieve this result. The Engineer will monitor the milling and adjust the milling scheme as necessary to provide the closest possible match to the intended results.

Method of Measurement. This work will be measured for payment according to applicable portions of Article 440.07 of the Standard Specifications. No deduction shall be made for areas traversed by the milling machine where the teeth do not touch the pavement surface provided the work is performed to meet the intent of this special provision and as directed by the Engineer.

Basis of Payment. This work will be paid for at the contract unit price per SQUARE YARD for

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH.

HMA ANTI-STRIP ADDITIVE REQUIREMENTS

HMA mixtures utilizing crushed gravel or sandstone coarse aggregate shall incorporate an anti-strip additive according to Article 1030.05(c). The additive shall be sufficient to achieve a TSR equal to 0.90 or greater for 6-inch specimens. If a liquid additive is used, the additive quantity shall be between 0.25% and 1.0% of the total weight of liquid asphalt. The mixture shall meet the minimum conditioned tensile strength requirements described in Article 1030.05(c).

The anti-strip additive product utilized for mix design verification shall be used for mixture production. A change in anti-strip additive product requires a reverification of the TSR and minimum conditioned tensile strength requirements prior to mixture production.

HMA mixtures having an ABR greater than 20% incorporating RAP/FRAP materials consisting of crushed gravel or sandstone coarse aggregate shall include an anti-strip additive. Where the RAP/FRAP materials requiring anti-strip were not included in the initial mix design verification, a new mix design is not required. However, a reverification of the TSR and minimum conditioned tensile strength requirements is required prior to mixture production.

This work will not be measured for payment. The cost of furnishing and introducing anti-stripping additives in the HMA shall be in included in the contract unit price of the HMA item involved.

SECTION (84-2HB-1) R, BR

HOT-MIX ASPHALT BASE COURSE, (VARIABLE DEPTH)

Description. This work shall consist of placing HMA base course at the locations and depths shown on the plans. Maximum lift requirements shall be in accordance with Section 407.06 of the Standard Specifications.

Materials. The mixture requirements shall be in accordance with the Mixture Requirements table included in the plans for base course, variable depth.

Basis of Payment. This work will be paid for at the contract unit price per TON for HOT-MIX

ASPHALT BASE COURSE, (VARIABLE DEPTH).

PIPE CULVERTS, CLASS A (JACKED)

Description. This work shall consist of furnishing and installing culverts by jacking, capping the ends of the jacked culverts, and restoring areas disturbed by culvert installation.

Construction. The existing culverts adjacent to this work are to remain in service. Damage to existing culverts shall be repaired as directed by the Engineer at no additional cost to the Department.

Furnishing and installing culverts by jacking shall be according to Articles 552.02 through 552.06.

The Contractor may shorten or eliminate the length to be jacked according to Article 552.04.

Trenches under or within 2 ft of the proposed slopewall shall be backfilled with trench backfill.

Pipe ends shall be capped as approved by the Engineer with the intent to prevent flow through and piping along the culverts yet facilitate future removal of the caps.

Areas disturbed by culvert installation shall be graded and seeded to restore the ditches flowing to the existing culverts. Ditches shall be lined with erosion control blanket to a depth of 4 ft or top of backslope, whichever is less.

Method of Measurement. This work will be measured for payment in place in feet, regardless of method of installation, except the length measured will not exceed the length shown on the plans or authorized in writing by the Engineer.

Basis of Payment. This work will be paid for at the contract unit price per FOOT for PIPE CULVERTS, CLASS A (JACKED) of the diameter specified. Pipe end caps, sheeting, shoring or bracing, excavation, backfill, and trench backfill, surface restoration, including seeding, mulch, and erosion control blanket will not be paid for separately.

SECTION (84-2HB-1) R, BR

PIPE UNDERDRAINS 4” (SPECIAL)

Description. This work shall consist of the removal and replacement of the pipe underdrains along the inside lane of I-55 and along both outside lanes of northbound and southbound I-55 near the Sudduth Road bridge. Pipe underdrains shall be removed as needed for the removal of the center pier, the construction of the new pier, and for the removal of the outside piers. New pipe underdrains shall be laid in accordance with Section 601 of the Standard Specifications once pier construction is complete and prior to re-constructing the inside shoulder, inside lane of traffic, and outside shoulder work.

Basis of Payment. This work will be paid for at the contract unit price per FOOT for PIPE UNDERDRAIN 4” (SPECIAL), which shall include the removal of the existing pipe underdrains.

REMOVE AND REINSTALL IMPACT ATTENUATORS

Description. This work shall consist of the removing, storing, and reinstalling existing sand module impact attenuators at the median pier of the Sudduth Road bridge over I-55. Work shall be according to Section 643 of the Standard Specifications and Standard 643001, except as modified herein.

After the temporary concrete barrier has been placed along I-55 and prior to removal of the median pier, existing attenuator barrels shall be emptied of sand, carefully removed, and stored outside the right of way. Prior to removal of the temporary concrete barrier along I-55, the attenuators shall be reinstalled at the new pier on new attenuator bases and properly filled with new sand.

Materials. Existing attenuators damaged by carelessness or improper storage shall be replaced with new attenuators at no additional cost to the Department.

Method of Measurement. This work will be measured for payment per each barrel.

Basis of Payment. This work will be paid for at the contract unit price per EACH for REMOVE

AND REINSTALL IMPACT ATTENUATORS.

REMOVE ATTENUATOR BASE

Description. This work shall consist of the complete removal and satisfactory disposal of the existing PCC impact attenuator base as shown in the plans. This work shall be performed according to applicable portions of Section 440 of the Standard Specifications and shall include all materials, labor, and equipment to remove and dispose of the existing impact attenuator base.

Basis of Payment. This work will be paid for at the contract unit price per EACH for REMOVE

ATTENUATOR BASE.

SECTION (84-2HB-1) R, BR

REMOVE AND REINSTALL HIGH TENSION CABLE MEDIAN BARRIER

Description. This work shall consist of the removal of the high-tension cable median barrier as shown in the plans for the removal of the center pier and construction of the new pier. This work includes the reinstallation of the high-tension cable median barrier to its original configuration once the pier construction and I-55 shoulder and pavement work are complete.

Materials. The existing high tension cable median barrier shall be inspected by the Engineer and reused if possible.

Basis of Payment. This work will be paid for at the contract unit price per FOOT for REMOVE

AND REINSTALL HIGH TENSION CABLE MEDIAN BARRIER.

REMOVAL OF EXISTING STRUCTURE (SPECIAL)

Description. This work shall consist of the complete removal of SN 084-0100 according to Section 501 of the Standard Specifications, except as specified herein.

Construction Requirements. The Contractor shall be required to salvage five steel beams, located between splice No. 2 and splice No. 3 (Span 3 over northbound I-55), as shown in the plans. The beams shall be removed from the structure without damage, detached from splice plates, and delivered to the Illinois Department of Transportation Day Labor Yard.

The Contractor shall remove all bolts and connection plates at splice locations and diaphragm connections. No rough cutting will be allowed. The beams shall be free of adhered concrete or other residual materials.

Delivery. The salvaged beams shall be delivered to:

IDOT Day Labor Yard 505 North MacArthur Boulevard Springfield, IL 62702

The Contractor shall contact Jeff Rhodes (217-299-5273) at least 14 days prior to delivery to coordinate transport, receiving hours, and placement at the yard.

Basis of Payment. This work will be paid for at the contract unit price per EACH for REMOVAL OF EXISTING STRUCTURE (SPECIAL). Payment shall include removal, protection, salvage, cleaning, transport, coordination, and delivery of the beams to the specified location, along with all incidental work necessary to meet these requirements.

SECTION (84-2HB-1) R, BR

PAVEMENT STATIONING NUMBERS AND PLACEMENT

Reviewed: April 14, 2020

The Contractor shall provide labor and materials required to imprint pavement station numbers in the finished surface of the pavement and /or overlay. The numbers shall be approximately ¾ inch wide, 5 inches high and 5/8 inch deep.

The pavement station numbers shall be installed as specified herein:

Interval – 250 feet (English stationing) or 100 meters (metric stationing)

Bottom of Numbers – 6 inches from the inside edge of the pavement marking and/or resurfacing joint.

Location:

• 2-Lane Pavements – At center line in direction of increasing stations.

• 3 and 5-Lane Pavements – Left edge of center lane in direction of increasing stations.

• Multi-Lane Divided Roadways – Outside edge of pavement in both directions.

• Ramps – Along baseline edge of pavement.

Position – Stations shall be placed so they can be read from the adjacent shoulder.

Format – English [Metric] pavement stations shall use this format (XX+XO [XOO]) where X represents the pavement station.

This work will not be paid for separately but shall be included in the cost of the associated pavement and/or overlay pay items.

SECTION (84-2HB-1) R, BR

SLIPFORM PARAPET

Effective: June 1, 2007 Revised: April 15, 2022

The following shall be added to the end of Article 503.16(b) of the Standard Specifications.

(3) Slipforming parapets. Unless otherwise prohibited herein or on the plans, at the option of the

Contractor, concrete parapets on bridge decks may be constructed by slipforming in lieu of the conventional forming methods. Slipforming will not be permitted for curved parapets on a radius of 1500 ft (457 m) or less.

The slipform machine shall be self-propelled and have automatic horizontal and vertical grade control. For 34 in. (864 mm) and 39 in. (991 mm) tall parapets the machine shall be equipped with a minimum of four (4) vibrators. For 42 in. (1.067 m) and 44 in. (1.118 m) tall parapets the machine shall be equipped with a minimum of five (5) vibrators. The equipment shall be approved by the Engineer before use.

If the Contractor wishes to use the slipform parapet option for 42 in. (1.067 m) or 44 in. (1.118

m) tall parapets he/she shall construct an acceptable test section in a temporary location to demonstrate his/her ability to construct the parapets without defect. The test section shall be constructed under similar anticipated weather conditions, using the same means and methods, equipment, equipment vibrator settings, travel speed, operator, concrete plant, concrete mix design, and slump as proposed for the permanent slipform parapets.

The test section shall be at least 30 feet (9 meters) in length and shall be of the same cross section shown on the plans. The contractor shall place all of the reinforcement embedded in the parapet as shown on the plans. Upon completion of the test section, the Contractor shall saw cut the test section into 2 ft (600 mm) segments and separate the segments for inspection by the Engineer. Test sections containing segments showing voids adjacent to a reinforcement bar, 1/4 square inch (160 square millimeters) or more in area and extending along the reinforcement bar into the section, or showing excessive voids not adjacent to reinforcement bars 1/4 square inch (160 square millimeters) or more in area, or showing cracking extending through a segment, shall be considered unacceptable.

The test section shall demonstrate to the satisfaction of the Engineer that the Contractor can slipform the parapets on this project without defects. The acceptance of the test section does not constitute acceptance of the slipform parapets in place.

The concrete mix design may combine two or more coarse aggregate sizes, consisting of CA- 7, CA-11, CA-13, CA-14, and CA-16, provided a CA-7 or CA-11 is included in the blend in a proportion approved by the Engineer.

The slipform machine travel speed shall not exceed the lesser of 3 ft (0.9 m) per minute, or the speed used to construct the acceptable test section. Any time the speed of the machine drops below 0.5 ft (150 mm) per minute will be considered a stoppage of the slipforming operation, portions of parapet placed with three or more intermittent stoppages within any 15 ft (4.6 m) length will be rejected. The contractor shall schedule concrete delivery to maintain

SECTION (84-2HB-1) R, BR

a uniform delivery rate of concrete into the slipform machine. If delivery of concrete from the truck into the slipforming machine is interrupted by more than 15 minutes, the portion of the wall within the limits of the slipform machine will be rejected.

If the Contractor elects to slipform, the parapet cross-sectional area and reinforcement bar clearances shall be revised according to the details for the Concrete Parapet Slipforming Option. In addition, if embedded conduit(s) are detailed, then the contractor shall utilize the alternate reinforcement as detailed.

The use of cast-in-place anchorage devices for attaching appurtenances and/or railings to the parapets will not be allowed in conjunction with slipforming of parapets. Alternate means for making these attachments shall be as detailed on the plans or as approved by the Engineer.

All reinforcement bar intersections within the parapet cross section shall be 100 percent tied utilizing saddle ties, wrap and saddle ties, or figure eight ties to maintain rigidity during concrete placement. At pre-planned sawcut joints in the parapet, Glass Fiber Reinforced Polymer (GFRP) reinforcement shall be used to maintain the rigidity of the reinforcement cage across the proposed joints as detailed for the Concrete Parapet Slipforming Option.

Glass Fiber Reinforced Polymer (GFRP) reinforcement shall be subject to approval by the Engineer. Other non-ferrous reinforcement may be proposed for use but shall be subject to approval by the Engineer. GFRP reinforcement shall be tied the same as stated in the previous paragraph.

The Contractor may propose supplemental reinforcement for stiffening to prevent movement of the reinforcement cage and/or for conduit support subject to approval by the Engineer.

Clearances for these bars shall be the same as shown for the required bars and these bars shall be epoxy coated. If the additional reinforcement is used, it shall be at no additional cost to the Department.

For projects with plan details specifying parapet joints spaced greater than 20 ft (6 m) apart, additional sawcut joints, spaced between 10 ft (3 m) and 20 ft (6 m), shall be placed as directed by the Engineer. The horizontal reinforcement extending through the proposed joints shall be precut to provide a minimum of 4 in. (100 mm) gap, centered over the joint, between rebar ends. The ends of the reinforcement shall be repaired according to Article 508.04.

After the…