ILDOT 66926-042.pdf

PDF 7 MB Posted

Attached to
IL 23 Deck Replacement at Covel Creek and Bridge Replacement at Covel Creek
Solicitation number
66926
Issued by
Lasalle County, Illinois

About this file

This is a Notice to Bidders and Specifications document issued by the Illinois Department of Transportation (IDOT) for Contract No. 66926, a federal-aid highway construction project located in LaSalle County, Illinois. The project consists of rehabilitation of bridge structure number (SN) 050-0047 and removal and replacement of SN 050-0048 with a new structure (SN 050-0251) on IL Route 68 (IL 23) over Covel Creek, approximately 3.4 and 5.0 miles south of IL 71 near Ottawa. Additional work includes Hot-Mix Asphalt resurfacing, Hot-Mix Asphalt shoulders, guardrail replacement, paved ditches, and earthwork. Electronic bids must be submitted to the iCX (Integrated Contractors Exchange) system prior to 12:00 p.m. on September 18, 2026, at which time bids will be publicly opened. The contract will be awarded to the lowest responsive and responsible bidder; IDOT reserves the right to reject any or all proposals and to re-advertise the improvement. The project is designated as NHPP-UJ53(016) and is located in District 3, Section (1BR)D,(1BR-1)BR-1.

The contract is funded through National Highway Performance Program (NHPP) construction funds and is subject to Federal-aid requirements, including prevailing wage, Equal Employment Opportunity (EEO), Disadvantaged Business Enterprise (DBE) participation, and various environmental compliance obligations. The specification document includes supplemental specifications, recurring special provisions adopted January 1, 2026, and project-specific special provisions addressing work items such as bridge deck construction, bearing replacement, structural steel cleaning and painting with lead remediation, temporary traffic control and signaling, linear delineator panels, and removal and disposal of regulated substances including contaminated soil. Utility relocation coordination is required with multiple providers including Ameren, AT&T, ComEd, Nicor Gas, and fiber optic companies. The contractor is responsible for all aspects of waste collection, testing, transportation, and disposal related to hazardous materials removal, with TCLP testing required within the first week of project commencement.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting September 18, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 66926 LASALLE County Section (1BR)D,(1BR-1)BR-1 Route FAP 68 Project NHPP-UJ53(016) District 3 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

September 18, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 66926 LASALLE County Section (1BR)D,(1BR-1)BR-1 Project NHPP-UJ53(016) Route FAP 68 District 3 Construction Funds

IL 23 deck replacement (SN 050-0047) at Covel Creek 3.4 miles south of IL 71 & bridge replacement (SN 050-0048) at Covel Creek 5.0 miles south of IL 71.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

FAP Route 68 (IL 23)

Section (1BR)D,(1BR-1)BR-1 LaSalle County

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

Section (1BR)D,(1BR-1)BR-1

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 X Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 X Station Numbers in Pavements or Overlays

Section (1BR)D,(1BR-1)BR-1 i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

STATUS OF UTILITIES TO BE ADJUSTED:

TEMPORARY FENCE

MULCH METHOD 2

AGGREGATE SURFACE COURSE, TYPE B

TACK COAT

DRAINAGE MITIGATION ON MILLING AND RESURFACING PROJECTS

SHOULDER STABILIZATION AT GUARDRAIL

BRIDGE APPROACH PAVEMENT CONNECTOR (SPECIAL)

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH

REMOVE CONCRETE END SECTION

SLOPE WALL CRACK SEALING

SLOPE WALL REPAIR

PAVED DITCH (SPECIAL)

DRAINAGE STRUCTURES TO BE CLEANED

GUARDRAIL REMOVAL (SPECIAL)

DELINEATOR REMOVAL

LINEAR DELINEATOR PANELS, 4 INCH

LINEAR DELINEATOR PANELS, 6 INCH

FENCE REMOVAL AND REINSTALLATION

FURNISH PERMANENT SURVEY MARKERS

TRAFFIC CONTROL SURVEILLANCE

TEMPORARY BRIDGE TRAFFIC SIGNALS (STANDARD 701316 OR 701321)

LINEAR DELINEATION PANELS (TEMPORARY BARRIER WALL)

TEMPORARY INFORMATION SIGNING

WIDTH RESTRICTION SIGN

MODIFIED URETHANE PAVEMENT MARKING – TWO APPLICATIONS

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

JACK AND REMOVE EXISTING BEARINGS

CLEANING AND PAINTING CONTACT SURFACE AREAS OF EXISTING STEEL STRUCTURES

Section (1BR)D,(1BR-1)BR-1 ii

CLEANING AND PAINTING EXISTING STEEL STRUCTURES

CONTAINMENT AND DISPOSAL OF LEAD PAINT CLEANING RESIDUES

SLIPFORM PARAPET

BRIDGE DECK CONSTRUCTION

PREFORMED PAVEMENT JOINT SEAL

BAR SPLICERS, HEADED REINFORCEMENT

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE) 83

COMPENSABLE DELAY COSTS (BDE)

CONCRETE BARRIER (BDE)

DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)

EROSION CONTROL BLANKET (BDE)

FUEL COST ADJUSTMENT (BDE)

GUARDRAIL (BDE)

HOT-MIX ASPHALT (BDE)

HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)

PAVEMENT MARKING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

RAISED REFLECTIVE PAVEMENT MARKERS (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

RESIDENTIAL DRIVEWAY TEMPORARY SIGNAL (BDE)

SEEDING (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SLOPE WALL (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

STEEL COST ADJUSTMENT (BDE)

STRUCTURAL REPAIR OF CONCRETE (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURVEYING SERVICES (BDE)

TEMPORARY CONCRETE BARRIER (BDE)

TEMPORARY RUMBLE STRIPS (BDE)

Section (1BR)D,(1BR-1)BR-1 iii

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION . 149

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

WEEKLY DBE TRUCKING REPORTS (BDE)

WOOD SIGN SUPPORT (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

WORK ZONE WIDTH RESTRICTION (BDE)

WORKING DAYS (BDE)

SWPPP

MAINTENANCE (CORPS OF ENGINEERS NWP # 3)

LINEAR TRANSPORTATION PROJECTS (CORPS OF ENGINEERS NWP # 14)

Section (1BR)D,(1BR-1)BR-1

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of FAP Route 68 (IL 23), Project NHPP-UJ53(016), Section (1BR)D,(1BR-1)BR-1, LaSalle County, Contract No. 66926 and in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.

LOCATION OF PROJECT

The project is located at two spot locations on FAS 68 (IL 23). The locations are IL 23 over Covel Creek and IL 23 over Branch of Covel Creek just south of Ottawa, Illinois in LaSalle County.

DESCRIPTION OF PROJECT

The project consists of rehabilitation of structure number (SN) 050-0047 and the removal and replacement of SN 050-0048 with a new structure (SN 050-0251). Additional work includes Hot- Mix Asphalt resurfacing, Hot-Mix Asphalt shoulder, guardrail replacement, paved ditches, and earthwork.

Section (1BR)D,(1BR-1)BR-1

STATUS OF UTILITIES TO BE ADJUSTED:

(Effective January 1, 2007; Revised January 24, 2011)

Name & Address of Utility

Type

Location

Estimated Date Relocation Complete

Ameren 340 Raccuglia Dr.

P.O. Box 1428 LaSalle, IL 61301

Electric Ameren has overhead electric lines on the east side of Covel Creek.

These lines provide power to subdivisions to the north and south.

No conflicts are anticipated.

AT&T

1000 Commerce Drive Oak Brook, IL 60523

AT&T Ref: OT3115ZA

Communications

AT&T has buried cable along the west ROW until just north of Covel Creek.

Near the creek they have their own poles and are overhead and continue this way for some distance to the south.

AT&T does not have any facilities near the south bridge work area.

ComEd Public Relocation Dept Three Lincoln Centre, 6th floor Oakbrook Terrace, IL 60181

Electric ComEd has power poles which run along IL 23 south of the Cemetery.

They are clear of both work areas.

No conflicts.

Cornbelt 1702 West Peru Street Princeton, IL 61356

Electric Cornbelt does not have any facilities near either work area.

They have electric lines which cross IL 23 at 2450th Road which also head south along the west ROW of IL 23.

They eventually cross IL 23 and head east along 2350th Road (which is just north of the southern bridge work area).

No conflicts.

Frontier 109 E. Market Street Bloomington, IL

Telephone Frontier is clear at both bridge work areas.

No conflicts.

Section (1BR)D,(1BR-1)BR-1

Stratus Networks (purchased the iFiber) 416 N Main St, Suite 601 Peoria, IL 61612

Fiber Stratus has buried fiber along the west ROW at both bridges.

They will have a locator obtain some GPS coordinates, offsets and depth near both structures.

Mediacom (Xstream) 808 E North St Elburn, IL 60119

Communication:

Cable and Fiber

Mediacom has underground cable and fiber along the west ROW until just north of Covel Creek. At this point they are overhead over the creek and continue this way for some distance. They appear to be on AT&T poles on the west side of the Covel Creek bridge.

They also have buried fiber along the west ROW of the south bridge.

Metro Communications

P.O. BOX 555

Sullivan, IL 61951

Fiber Metro Communications has an active permit to install fiber along the west ROW of both structures. They have installed fiber north of Grand Ridge but stopped at some point. Permit Number is U-18380

Nicor 1844 Ferry Rd.

Naperville, IL 60563

Nicor Ref: SC26690

Gas From Pine hills road going south Nicor has a 2’’ gas main running along the west ROW but it ends just north of the entrance, which is just north of where the SB guardrail begins.

At the south bridge 050- 0048, Nicor has a 2” main along the east side of the existing bridge. It is approximately 28’ parallel to centerline in the SE corner of the bridge.

Nicor may have to relocate along the east side of SN 050-0048.

Section (1BR)D,(1BR-1)BR-1

The above represents the best information of the Department and is only included for the convenience of the bidder. The applicable provisions of Section 102 and Articles 105.07, 107.20, 107.37, 107.38, 107.39, 107.40, and 108.02 of the Standard Specifications for Road and Bridge Construction shall apply.

This utility relocation information reflected as of May 19, 2026.

TEMPORARY FENCE

Description. This item consists of supplying a temporary fence near the survey markers shown in the plan schedule to ensure they are separated from construction activity.

This work shall consist of constructing, maintaining, removing, and disposing of a Temporary Fence as shown on the plans and as described herein.

Materials. Temporary fence shall be a minimum of 4 ft. (1.2 m) in height and shall be a high visibility orange snow fence. Fence stakes shall meet the requirements of Article 1081.15(b) of the Standard Specifications.

The Contractor shall remove the temporary fence at the completion of the project.

Method of Measurement. The temporary fence will be measured for payment in place in feet (meters) along the top of the fence.

Basis of Payment. The temporary fence will be paid for at the contract unit price per foot (meter) for TEMPORARY FENCE, which price shall include the cost of the fence and fence stakes.

MULCH METHOD 2

(Effective August 1, 1994; Revised January 1, 2007)

Article 251.03 Method 2 Procedure 1 of the Standard Specifications shall be required for this improvement.

AGGREGATE SURFACE COURSE, TYPE B

(Effective January 1, 2007)

Add the following to Article 402.07 of the Standard Specifications:

The top layer shall be given a final rolling with a roller meeting the requirements of Article 1101.01.

Section (1BR)D,(1BR-1)BR-1

TACK COAT

(Effective December 10, 2025)

Replace the application rate table in Article 406.05 (c)(1) of the Standard Specifications with the following:

Type of Surface to be Tacked Residual Asphalt Rate lb/sq ft Concrete, Existing HMA, and Milled HMA .05 New HMA and Brick .05

DRAINAGE MITIGATION ON MILLING AND RESURFACING PROJECTS

(Effective January 1, 2022)

Milling operations on this project have the potential to cause water encroachment on the travel lanes during and after a rainfall event. The Contractor shall schedule the milling and resurfacing operations to minimize the potential for the encroachment. The Contractor shall be responsible for mitigating any encroachments as directed by the Engineer. Mitigation may include, but not be limited to constructing lateral ditches through shoulders and modifying then repairing curb inlets to provide drainage.

The work associated with drainage mitigation will be included in the cost of the Hot-Mix Asphalt Surface Removal pay item.

SHOULDER STABILIZATION AT GUARDRAIL

(Effective February 7, 2013)

Replace the last sentence of the second, third and fourth paragraphs of Article 630.06 with the following:

The void around each post shall be backfilled with earth or aggregate and capped with 3 in.

of grout.

BRIDGE APPROACH PAVEMENT CONNECTOR (SPECIAL)

Description. This work shall consist of constructing a bridge approach pavement connector according to the details shown on the plans. This work shall also be performed in accordance with the applicable portions of Section 420 of the Standard Specifications and Highway Standard 420401.

Method of Measurement. The bridge approach pavement connector will be measured for payment in place and the area computed in square yards for the pay limits shown in the plans.

Basis of Payment. This work will be paid for at the contract unit price per square yard for BRIDGE APPROACH PAVEMENT CONNECTOR (SPECIAL). Subbase granular material beneath the Bridge Approach Pavement Connector (Special) will not be paid for separately, but will be included in the cost of BRIDGE APPROACH PAVEMENT CONNECTOR (SPECIAL).

Welded wire reinforcement will be paid for at the contract unit price per square yard for WELDED

WIRE REINFORCEMENT.

Section (1BR)D,(1BR-1)BR-1

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH

Description. This work shall include all labor, materials, and equipment necessary for the removal and disposal of the existing hot-mix asphalt pavement at variable depths as shown in the plans and as directed by the Engineer. Work shall be in accordance with Section 202 and Section 440 of the Standard Specifications and as noted herein.

The intent of this work is to provide variable hot-mix asphalt surface removal and/or to provide transitions between the proposed changes in resurfacing thickness throughout the project.

Method of Measurement. This work will be measured for payment in square yards with no adjustments made for the variations in the depth of the material removed.

Basis of Payment. The work shall be paid for at the contract unit price per square yard for

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH.

REMOVE CONCRETE END SECTION

Description. This work shall consist of the removal and disposal of existing concrete end sections at locations shown on the plans, in accordance with the applicable portions of Section 551 of the Standard Specifications, and as directed by the Engineer.

Method of Measurement. Removal of existing concrete end sections will be measured for payment in units of each at the locations designated on the plans.

Basis of Payment. This work will be paid for at the contract unit price per each for REMOVE

CONCRETE END SECTION.

SLOPE WALL CRACK SEALING

Description. All open random cracks or existing joints in the existing concrete slope wall shall be cleaned and sealed as shown on the plans and as directed by the Engineer. Hot-poured Joint Sealer meeting the requirements of Article 1050.02 shall be used for slope wall repair. All cracks and joints shall be cleaned and filled with sealant according to Section 452 of the Standard Specifications. Routing of the cracks is not required.

Method of Measurement. Sealing existing cracks and joints in concrete slope wall shall be measured for payment along the linear distance of opening sealed and measure in feet. Cleaning existing cracks and joints prior to sealing will not be measured for payment but shall be considered include in the price for SLOPE WALL CRACK SEALING.

Basis of Payment. Cleaning and sealing cracks shall be paid for at the contract unit price per foot for SLOPE WALL CRACK SEALING.

Section (1BR)D,(1BR-1)BR-1

SLOPE WALL REPAIR

Description. The work consists of the repair of existing slope walls as shown on the plans, directed by the Engineer. Work shall be performed in accordance with the requirements of Sections 501 and 511 of the Standard Specifications. This work shall include removal and replacement of existing deteriorated concrete slope wall areas with new concrete slope walls and, if required, filling the voids beneath the slope wall. Existing slope wall reinforcing shall be incorporated into new slope wall repair. New slope wall repair shall match existing slope wall thickness.

Materials. Materials shall meet the requirements of Article 511.02 of the Standard Specifications.

Any material required to fill voids and level the supporting base shall be crushed stone meeting a CA-6 gradation or Controlled Low-Strength Material (CLSM) meeting the requirements of Section 1019 of the Standard Specifications.

Construction. Areas delineated for removal shall be scored with a concrete saw down to, but not through, the existing mesh reinforcement. The concrete shall be broken out and removed in such a fashion as to leave a minimum of 1 ft exposed mesh edge to tie into the new mesh. After removal of the delineated area of slope wall, any depressions or voids in the base shall be filled with crushed stone and compacted prior to placing the mesh and concrete for the slope wall repair to achieve the slope wall thickness as shown in the Plans. When shown on the Plans or as directed by the Engineer, depressions or voids shall be filled with CLSM, in accordance with the applicable portions of Section 593 of the Standard Specifications.

Method of Measurement. This work will be measured for payment in square yards, complete and in place.

Basis of Payment. This work will be paid for at the contract unit price per SQUARE YARD for SLOPE WALL REPAIR, which price shall include removing, disposing of, and replacing the damaged slope wall. Controlled Low-Strength Material or Crushed Stone as required for the base of the repaired slope wall areas will not be paid for separately but shall be included in the work.

PAVED DITCH (SPECIAL)

Description. This work shall be performed in accordance with Section 606 of the Standard Specifications, this Special Provision, and as detailed in the plans. This work shall include all labor, materials, and equipment required to construct the paved ditch (special), including but not limited to concrete finishing, jointing pattern, joints, connections to existing paved ditches, and all reinforcement.

The channel bottom should be 2 feet in width for paved ditch (special) as designated in the plans.

The Contractor shall ensure that the paved ditch existing and proposed flowlines allow for the conveyance of water.

Method of Measurement. The work shall be measured in place per foot along the flowline of the paved ditch (special).

Basis of Payment. This work will be measured and paid for at the contract unit price per foot for

PAVED DITCH (SPECIAL).

Section (1BR)D,(1BR-1)BR-1

DRAINAGE STRUCTURES TO BE CLEANED

Description. All existing storm sewers, pipe culverts, manholes, catch basins and inlets shall be considered as drainage structures insofar as the interpretation of this special provision is concerned. When specified for payment, the location of drainage structures to be cleaned will be determined in the field by the Engineer.

All existing drainage structures labeled for cleaning in the plans shall be cleaned according to Article 602.15 of the Standard Specifications. This work will be paid for in accordance with Article

602.16 of the Standard Specifications.

All other existing drainage structures which are specified to be cleaned by the Engineer will be cleaned according to Article 602.15 of the Standard Specifications.

Basis of Payment. This work will be paid for at the contract unit price EACH for DRAINAGE STRUCTURES TO BE CLEANED, and at the contract unit price per FOOT for PIPE CULVERTS TO BE CLEANED, of the diameter specified.

GUARDRAIL REMOVAL (SPECIAL)

Description. In addition to the requirements of Section 632 of the Standard Specifications, this work shall include the removal of any concrete encasements of the posts and any additional items attached to the guardrail or posts.

Method of Measurement. This work will be measured for payment according to Article 632.03 of the Standard Specifications.

Basis of Payment. This work shall be paid for at the contract unit price per foot for GUARDRAIL

REMOVAL (SPECIAL).

DELINEATOR REMOVAL

Description. This work shall include the complete removal of the existing delineator posts and reflectors. Disposal shall be in accordance with Article 202.03 of the Standard Specifications.

Method of Measurement. This work will be measured for payment for delineator posts removed to the satisfaction of the Engineer on an Each basis.

Basis of Payment. This work shall be paid for at the contract unit price Each for DELINEATOR REMOVAL, which price shall include all labor, material, and equipment necessary to complete the work as specified, including disposal, and no additional compensation will be allowed.

Section (1BR)D,(1BR-1)BR-1

LINEAR DELINEATOR PANELS, 4 INCH

(Effective January 1, 2022)

Description. This work shall consist of furnishing and installing linear delineators on steel plate beam guardrail at locations shown in the plans.

CONSTRUCTION REQUIREMENTS

General. Linear delineator panels shall be attached to steel plate beam guardrail as shown on plan details and as directed by the Engineer. These panels shall be either white or yellow, matching the color of the adjacent pavement marking edge line. They should be spaced at a minimum of 80 ft centers horizontally, with a minimum of two linear delineator per guardrail run.

Linear delineators shall not be place on guardrail terminal sections. Linear delineator spacing through horizontal curves where the normal speed limit is reduced, the spacing of the linear delineators shall be reduced to 40 ft centers. Existing steel plate beam guardrail that contain existing linear delineator panels shall have any damaged or missing panels removed and replaced as directed by the Engineer.

When securing the linear delineator panels to steel plate beam guardrail, the Contractor may use a linear delineation system panel and bracket mounting method approved by the Engineer. Linear delineation system panel and bracket including installation methods shall be according to the manufacture’s recommendations.

The Contractor shall be responsible for testing the durability and strength of the method used to ensure permanent adhesion of the linear delineator panel to the bridge rail. Drilling into metal bridge rail or other metal surfaces to secure the linear delineator panels will not be permitted.

When removing and replacing missing or damaged linear delineator panels, the existing linear delineator panels and any adhesive or bracket when used to secure the existing linear delineator panels shall be removed to the satisfaction of the Engineer. All cost and labor associated with the removal and cleanup of the existing linear delineator panels shall not be paid for separately but shall be included in the cost of this work.

Each panel shall not be less than 34 in. in length and 4.0 in. in width. The panels shall be constructed of cube-corner retroreflective material in standard highway colors permanently bonded to an aluminum substrate. The lateral edges of each panel shall be hemmed. The panel assembly shall have a repeating raised lateral ridge every 2.25 in. Each ridge shall be 0.34 in.

high with a 45° profile and a 0.28 in. radius top.

Daytime color requirements shall be determined from measurement of the retroreflective sheeting applied to aluminum test panels. Daytime color shall be measured instrumentally using a spectrophotometer employing annular 45/0 (or equivalent 0/45) illuminating and viewing geometry. Measurements shall be made in accordance with ASTM E1164 for ordinary colors or ASTM E2153 for fluorescent colors. Chromaticity coordinates shall be calculated for CIE Illuminant D65 and the CIE 1931 (2o) Standard Colorimetric Observer in accordance with ASTM E308 for ordinary colors or ASTM E2152 for fluorescent colors.

Section (1BR)D,(1BR-1)BR-1

Chromaticity Limits for White x y x y x y x y Limit Y (%) Min Max

White 0.303 0.287 0.368 0.353 0.340 0.380 0.274 0.316 40 -

Chromaticity Limits for Fluorescent Yellow

Total

Luminance x Y x Y x y x y Factor YT (%) Min

Fluor.

Yellow 0.521 0.424 0.557 0.442 0.479 0.520 0.454 0.491 40

Inspection of Linear Delineator Panels. The linear delineator panels installed under this contract will be inspected following installation. In addition, they will be inspected following a winter performance period that extends 180 days from December 30th.

Within 15 calendar days after the end of the winter performance period, a final performance inspection will be made. If this inspection discloses any work which is not visibly intact and serviceable, the Contractor shall, within 30 calendar days, completely repair or replace such work to the satisfaction of the Engineer.

Measured in its entirety, the work shall be 97 percent intact.

Upon completion of the final performance inspection, or after satisfactory completion of any necessary corrections, the Engineer shall notify the Contractor in writing of the date of such final performance inspection and release him/her from further performance responsibility.

This delay in performance inspection and performance acceptance of the linear delineator panels shall not delay acceptance of the entire project and final payment due if the contractor requires and receives from the subcontractor a third party “performance” bond naming the Department as obligee in the full amount of all linear delineator panels listed in the contract, multiplied by the contract unit price. The bond shall be executed prior to acceptance and final payment of the non-linear delineator panel items and shall be in full force and effect until final performance inspection and performance acceptance of the linear delineator panels. Execution of the third-party bond shall be the option of the Contractor.

Basis of Payment. This work will be paid for at the contract unit price per each for LINEAR

DELINEATOR PANELS, 4 INCH.

Section (1BR)D,(1BR-1)BR-1

LINEAR DELINEATOR PANELS, 6 INCH

(Effective April 28, 2017)

Description. Linear delineator panels shall be placed on each parapet wall 6 in. down from the top. Panels shall also be placed on structures containing bridge rail as directed by the Engineer.

These panels shall be either white or yellow, matching the color of the adjacent pavement marking edge line. They should be spaced at a minimum of 80 ft centers horizontally, with the first and last panel located within 20 ft of the parapet wall ends. Structures that contain existing linear delineator panels shall have any damaged or missing panels removed and replaced as directed by the Engineer.

When attaching linear delineator panels to concrete, the panels shall be secured using an anchor bolt method approved by the Engineer that will anchor the entire panel securely, but also facilitate removal of the panel by maintenance operations if damaged or weathered in the future. The Contractor shall also sufficiently cover the back side of the linear delineator panel, to the satisfaction of the Engineer, with an adhesive caulking system to aid in the permanent adhesion and alignment of the panels prior to drilling through the pre-drilled linear delineation system holes.

When securing the linear delineator panels to metal bridge rail or any other metal surfaces, the Contractor may use a linear delineation system panel and bracket mounting method approved by the Engineer. The Contractor may also use an adhesive caulking method to sufficiently cover the back side of the linear delineator panel to the satisfaction of the Engineer. The Contractor shall be responsible for testing the durability and strength of the method used to ensure permanent adhesion of the linear delineator panel to the bridge rail. Drilling into metal bridge rail or other metal surfaces to secure the linear delineator panels will not be permitted.

When removing and replacing missing or damaged linear delineator panels, the existing linear delineator panels and any adhesive used to secure the existing linear delineator panels shall be removed to the satisfaction of the Engineer. All cost and labor associated with the removal and cleanup of the existing linear delineator panels shall be included in the unit price of the pay item

LINEAR DELINEATOR PANELS, 6 INCH.

Each panel shall not be less than 34 in. in length and 6.0 in. in width. The panels shall be constructed of cube-corner retroreflective material in standard highway colors permanently bonded to an aluminum substrate. The lateral edges of each panel shall be hemmed. The panel assembly shall have a repeating raised lateral ridge every 2.25 in. Each ridge shall be 0.34 in.

high with a 45° profile and a 0.28 in. radius top.

Daytime color requirements shall be determined from measurement of the retroreflective sheeting applied to aluminum test panels. Daytime color shall be measured instrumentally using a spectrophotometer employing annular 45/0 (or equivalent 0/45) illuminating and viewing geometry. Measurements shall be made in accordance with ASTM E1164 for ordinary colors or ASTM E2153 for fluorescent colors. Chromaticity coordinates shall be calculated for CIE

Section (1BR)D,(1BR-1)BR-1 x y x y x y x y Limit Y (%)

Yellow x Y x Y x y x y Factor YT (%) Min

Fluor.

Yellow 0.521 0.424 0.557 0.442 0.479 0.520 0.454 0.491 40

Inspection of Linear Delineator Panels. The linear delineator panels installed under this contract will be inspected following installation, but no later than December 30th. In addition, they will be inspected following a winter performance period that extends 180 days from December 30th.

Within 15 calendar days after the end of the winter performance period, a final performance inspection will be made. If this inspection discloses any work which is not visibly intact and serviceable, the Contractor shall, within 30 calendar days, completely repair or replace such work to the satisfaction of the Engineer.

Measured in its entirety, the work shall be 97 percent intact.

Upon completion of the final performance inspection, or after satisfactory completion of any necessary corrections, the Engineer shall notify the Contractor in writing of the date of such final performance inspection and release him/her from further performance responsibility.

This delay in performance inspection and performance acceptance of the linear delineator panels shall not delay acceptance of the entire project and final payment due if the contractor requires and receives from the subcontractor a third party “performance” bond naming the Department as obligee in the full amount of all linear delineator panels listed in the contract, multiplied by the contract unit price. The bond shall be executed prior to acceptance and final payment of the non-linear delineator panel items and shall be in full force and effect until final performance inspection and performance acceptance of the linear delineator panels. Execution of the third party bond shall be the option of the Contractor.

Basis of Payment. This work will be paid for at the contract unit price per each for LINEAR

DELINEATOR PANELS, 6 INCH.

Section (1BR)D,(1BR-1)BR-1

FENCE REMOVAL AND REINSTALLATION

Description. This work shall consist of the removal and reinstallation of portions of existing fence and its appurtenances at locations shown in the plans or as directed by the Engineer. This work shall be completed according to the applicable portions of Section 201, Section 664, and Section 665 of the Standards Specifications and as noted herein.

Fence posts shall be set vertically and true in alignment, and post spacing shall match the existing fence post spacing as closely as possible.

Prior to beginning this work, the Contractor shall report any existing fence or appurtenances damage to the Engineer. Any fence, posts, railing, etc. damaged during the removal, storage, or reinstallation of the fence shall be repaired or replaced by the Contractor as directed by the Engineer. No additional compensation will be provided for the repair or replacement of fence damaged during removal, storage, or reinstallation.

Method of Measurement. This work will be measured in place in units of foot, along the base of the existing fence to be removed.

Basis of Payment. This work will be paid for at the contract unit price per foot for FENCE

REMOVAL AND REINSTALLATION.

FURNISH PERMANENT SURVEY MARKERS

(Effective May 28, 2025)

Description. Survey markers shall be in general accordance with Highway Standard 667101, except they shall be bronze instead of aluminum and shall have a diameter of 3.5 inches. They shall be stamped “SECTION CORNER” as a circular row of text inside the words “ILLINOIS DEPARTMENT OF TRANSPORTATION” and shall have a “+” stamped in the center instead of a dimpled triangle.

The Engineer will supply a Professional Land Surveyor and equipment for installation of the survey markers. The Contractor shall supply traffic control for installation of the survey markers by the Engineer.

Basis of Payment. This work will be paid for at the contract unit price per each for FURNISH

PERMANENT SURVEY MARKERS.

TRAFFIC CONTROL SURVEILLANCE

(Effective January 1, 2016)

Revise the first sentence of Article 701.10 of the Standard Specifications to read:

701.10 Surveillance. When open holes, broken pavement, trenches over 3 in. deep and 4 in.

wide, or other hazards are present within 8 ft of the edge of an open lane; when opposing directions of traffic are separated by barrier wall; or on a closed road from the time a structure is removed until the time the structure has been replaced, the Contractor shall furnish traffic control surveillance during all hours when the Contractor is not engaged in construction operations.

Section (1BR)D,(1BR-1)BR-1

TEMPORARY BRIDGE TRAFFIC SIGNALS (STANDARD 701316 OR 701321)

(Effective July 1, 1999; Revised January 1, 2022)

Description. This work shall be done according to Sections 701 and 862 of the Standard Specifications, Standard 701316 or 701321, and modified as described herein.

Microwave detectors shall be installed instead of the induction loop detectors shown on Standard 701316 or Standard 701321.

Materials. The controller shall provide actuated operation for the number of phases required with full menu driven format for ease of data entry. The controller shall show all the timers operating simultaneously.

A standard uninterruptable power supply (UPS) shall be required for the traffic signal cabinet with controller.

All signal heads shall be LED’s.

The microwave detector shall be a motion and presence sensor that provides vehicle detection that is not affected by temperature, humidity, color, or background variations and shall meet the approval of the Engineer. It shall be capable of tracking multiple moving and stationary vehicles.

It shall have an adjustable hold time on stationary objects from 0 to 15 minutes. The microwave detector shall be designed to detect moving vehicles at a maximum range of 300 ft. The microwave detector shall have an ability to accurately discriminate between vehicles arriving and departing. The Contractor shall supply the type of lead-in cable recommended by the manufacturer for his microwave detector.

Construction Requirements. The Contractor shall mount a metal arm to each near right signal post (an arm for a light fixture would be acceptable). The arm shall be reasonably stationary to prevent false calls on the microwave sensor. The final mounting height of the microwave detector shall be 17.5 ft plus or minus 0.5 ft. The microwave detector shall be horizontally positioned somewhere between the center of the driving lane and 2 ft from the edge of the driving lane. The microwave detector shall be aimed to a 6 ft height at the stop bar at the center of the driving lane.

The microwave detector voltage shall be the highest allowed by the manufacturer.

At the time of inspection and programming of the controller, one of the Contractor's employees or representatives at the inspection shall be capable of doing all cabinet wiring or controller programming necessary to accomplish the type of operation desired or to modify the cabinet for any unusual conditions.

The UPS shall be installed adjacent to the controller cabinet and mounted according to Article 701.18(b)(2)d.

No vehicle, trailer, or other large object may be parked between the microwave detector and 500 ft in the direction of approaching traffic.

Where there is an intersecting street or driveway within the limits of the stage construction stop bars, the following specifications shall also apply:

Section (1BR)D,(1BR-1)BR-1

Material. Each signal for an intersecting street or driveway shall consist of one red ball section, one yellow ball section, one green left arrow section, and one green right arrow section with backplate.

Construction Requirements. Signal heads shall be located as shown on the plans.

Detection for the side road and driveway shall consist of a microwave detector. The microwave detector shall be mounted 14 to 18 ft high on the near right post for the side road and driveway.

Each approach of a side road and driveway shall be a separate phase.

When the green proceeds from one side of the bridge to the other, the controller shall time a programmable long all red period. Approaches on the same side of the bridge shall be able to cycle between each other without incurring the long all red time but a shorter programmable time.

The Contractor shall supply and install two (one near right; one far left) NO TURN ON RED signs for each sideroad and driveway approach.

The Contractor shall supply and install two (one near right; one far left) STOP HERE ON RED signs for each sideroad and driveway approach to be placed adjacent to the stop bar.

The Contractor shall be required to remove and store or securely cover any conflicting existing signs.

The Contractor shall supply and erect a SIGNAL AHEAD sign for each side road.

The Contractor shall be required to restore all original traffic control when the temporary bridge signals are removed.

Basis of Payment. This work, including the UPS, will be included in the contract unit price each for TEMPORARY BRIDGE TRAFFIC SIGNALS.

LINEAR DELINEATION PANELS (TEMPORARY BARRIER WALL)

(Effective March 30, 2023)

Description. This work shall consist of placing linear delineation panels on temporary concrete barrier wall.

Materials. Each panel shall not be less than 34 inches in length and 6 inches in width. The panels shall be constructed of cube-corner retroreflective material in standard highway colors permanently bonded to an aluminum substrate. The lateral edges of each panel shall be hemmed. The panel assembly shall have a repeating raised lateral ridge every 2.25 inches. Each ridge shall be 0.34 inches high with a 45° profile and a 0.28 inch radius top.

Daytime color requirements shall be determined from measurement of the retroreflective sheeting applied to aluminum test panels. Daytime color shall be measured instrumentally using a spectrophotometer employing annular 45/0 (or equivalent 0/45) illuminating and viewing geometry. Measurements shall be made in accordance with ASTM E1164 for ordinary colors or ASTM E2153 for fluorescent colors. Chromaticity coordinates shall be calculated for CIE

Section (1BR)D,(1BR-1)BR-1

X y x y x y x y Limit Y (%)

Orange x y x y x y x y Factor Y (%) Min

Fluor. 0.595 0.351 0.645 0.355 0.583 0.416 0.542 0.403 30 Orange

Construction Requirements Two (2) panels shall be placed on each section of temporary concrete barrier wall 24 inches up from the bottom of the wall to the top of the panel. These panels shall be alternating white and fluorescent orange and have a spacing of 28 inches apart and centered horizontally on each section of barrier wall. These panels shall be used in lieu of the Type C reflectors shown on Standard 704001.

Each panel shall be attached to the temporary concrete barrier wall according to the manufacturer’s specifications.

Basis of Payment. The Linear Delineation Panels will not be paid for separately but shall be considered included in the cost of the Temporary Concrete Barrier.

TEMPORARY INFORMATION SIGNING

(Effective September 24, 2013; Revised July 31, 2020)

Description. This work shall consist of the furnishing, installation, maintenance, and removal of temporary information signs.

Materials. Materials shall be according to the applicable portions of Section 701 of the Standard Specifications and as shown on the plans.

Construction Requirements. The temporary information signs shall be in place at least one week prior to the beginning of construction activities that impact traffic flow and shall remain in place until the completion of the project. If all lanes are open for an extended period of time during the project, the Contractor shall cover the signs until lane closures resume. If the project is shut down for the winter, the signs shall read “Road Work Resumes Spring XXXX.”

Signs shall be installed according to the requirements of Section 701.

Section (1BR)D,(1BR-1)BR-1

Method of Measurement. This work will be measured for payment in square feet in place. The auxiliary sign panel will not be measured for payment.

Basis of Payment. This work will be paid for at the contract unit price per square foot for

TEMPORARY INFORMATION SIGNING.

WIDTH RESTRICTION SIGN

Width restriction signs, as shown in District 3 Standard 701-6 Width Restriction Signing Details shown in the plan details, shall be used on this project. They shall be placed as shown in the plans.

The cost of supplying, installing, maintaining, and removing width restriction signs shall be included in the cost of the traffic control and protection pay items.

MODIFIED URETHANE PAVEMENT MARKING – TWO APPLICATIONS

(Effective March 30, 2023)

Description. This work consists of furnishing and applying modified urethane pavement marking according to Section 780 of the Standard Specifications except that the modified urethane shall be applied in two applications.

Materials. Each application shall meet the requirements of Article 780.12 of the Standard Specifications.

CONSTRUCTION REQUIREMENTS

General. The first application shall be allowed to cure for a minimum of 14 days prior to placing the second application over the first. The Contractor shall not place one thick application in lieu of two regular applications.

Basis of Payment. Each application will be measured and paid for.

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

Description. This work shall consist of the removal and disposal of regulated substances according to Section 669 of the Standard Specifications as revised below.

Contract Specific Work Areas. For stationing, the lateral distance is measured from centerline and the farthest distance is the offset distance or construction limit, whichever is less.

The following contract specific work areas shall be monitored by the Environmental Firm for soil contamination and workers protection.

Section (1BR)D,(1BR-1)BR-1

ISGS Site 4326A-4– Bridge (S.N. 050-0047), IL 23 over Covel Creek, North of Grand Ridge, LaSalle County, Illinois

• Station 620+48 to Station 622+49 (CL IL-23), from 0 to 25 feet LT. The Engineer has determined this material shall be managed in accordance with Article 669.05(a)(1).

Contaminant of concern sampling parameter: total lead, TCLP lead and SPLP lead.

• Station 622+49 to Station 624+35 (CL IL-23), from 0 to 50 ft LT. The Engineer has determined this material in the vicinity of the station and offset meets the criteria of and shall be managed in accordance with 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 624+35 to Station 625+55 (CL IL-23), from 0 to 60 ft LT. The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05b(1). Contaminant of concern sampling parameter: pH..

• Station 619+00 to Station 620+48 (CL IL-23), from 0 to 25 ft RT. The Engineer has determined this material in the vicinity of the station and offset meets the criteria of and shall be managed in accordance with 669.05(c). Contaminants of concern sampling parameters include: Iron.

• Station 627+27 to Station 628+35 (CL IL-23), from 0 to 60 ft RT. The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05b(1). Contaminant of concern sampling parameter: pH..

• Station 629+73 to Station 631+03 (CL IL-23), from 0 to 50 ft RT. The Engineer has determined this material in the vicinity of the station and offset meets the criteria of and shall be managed in accordance with 669.05(a)(1). Contaminants of concern sampling parameters include: Iron.

Work Zones Three distinct OSHA HAZWOPER work zones (exclusion, decontamination, and support) shall apply to projects adjacent to or within sites with documented leaking underground storage tank (LUST) incidents, or sites under management in accordance with the requirements of the Site Remediation Program (SRP), Resource Conservation and Recovery Act (RCRA), or Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), or as deemed necessary. For this project, the work zones apply for the following ISGS PESA Sites:

None.

Additional information on the above sites collected during the Phase I Engineering process is available through the District’s Environmental Studies Unit (DESU).

JACK AND REMOVE EXISTING BEARINGS

Effective: April 20, 1994 Revised: April 13, 2018

Description: This work consists of furnishing all labor, tools and equipment for jacking and supporting the existing beams/slab while removing the bearing assembly. The Contractor is responsible for the complete design of the bridge lifting procedures and the materials used. The Contractor shall furnish and place all bracing, shoring, blocking, cribbing, temporary structural steel, timber, shims, wedges, hydraulic jacks, and any other materials and equipment necessary for safe and proper execution of the work. The Contractor shall remove and dispose of the bearings according to Article 501.05 of the Standard Specifications.

Section (1BR)D,(1BR-1)BR-1

Construction Requirements: The Contractor shall submit details and calculations of his/her proposed jacking systems and temporary support procedures for approval by the Engineer before commencing work. If unforeseen field conditions preclude the execution of the approved jacking plan, the Engineer may require the Contractor to provide additional supports or measures. All changes to the jacking plan shall be approved by the Structural Engineer that sealed the jacking plan.Neither added precautions nor the failure of the Engineer to order additional protection will in any way relieve the Contractor of sole responsibility for the safety of lives, equipment and structure.

(a) Jack and Remove Existing Bearings with bridge deck in place.

This is the start of the file's text. The full file is on GovTribe.