Bridge repairs and joint replacement of 10 bridges
Solicitation number
64T43
Issued by
Henry County, Illinois

About this file

This is a Notice to Bidders and contract specification document issued by the Illinois Department of Transportation (IDOT) for bridge repairs and joint replacement work on 10 structures within Henry County along FAI Route 80 (I-80). The project, identified as Contract No. 64T43 under Project NHPP-RBDM(511), involves comprehensive bridge deck work including scarification, latex concrete overlay, and diamond grinding across all structures. Specific structures require additional work: Structures 037-0035 and 037-0036 (over Geneseo Creek) require expansion joint replacement; Structures 037-0039, 037-0040, 037-0041, and 037-0042 (over Spring Creek and E 1900th Street) require joint elimination through semi-integral abutment conversion and approach slab replacement; and Structures 037-0043 and 037-0044 (over US 6 and IAIS Railroad) require approach slab and pavement connector joint replacement. Electronic bids must be submitted through the iCX (Integrated Contractors Exchange) system no later than 12:00 p.m. on September 18, 2026, at which time bids will be publicly opened. The contract will be awarded to the lowest responsive and responsible bidder.

The project is funded through Federal-aid Highway Program (NHPP) funds and is classified as District 2 construction work. Bidders must comply with extensive federal and state requirements including prevailing wage standards, Equal Employment Opportunity (EEO) provisions, Disadvantaged Business Enterprise (DBE) participation, and Davis-Bacon Act requirements. Specific attention is required for work on Iowa Interstate Railroad (IAIS) right-of-way, including mandatory railroad protective liability insurance with $4,000,000 per occurrence limits, contractor orientation training through National Railroad Safety Services, and track protection services at $180 per hour straight time and $270 per hour overtime with a minimum eight-hour daily charge. The project includes numerous special provisions addressing traffic control, concrete quality assurance, pavement marking, and environmental requirements. All work must comply with Standard Specifications for Road and Bridge Construction adopted January 1, 2022, supplemental specifications, and recurring special provisions as outlined in the contract documents.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting September 18, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 64T43 HENRY County Section (37-(3-1,4,5,6))BRR Route FAI 80 Project NHPP-RBDM(511) District 2 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system

(iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

September 18, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 64T43 HENRY County Section (37-(3-1,4,5,6))BRR Project NHPP-RBDM(511) Route FAI 80 District 2 Construction Funds

Bridge repairs and joint replacement of 10 bridges in Henry County.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

FAI Route 80 (I-80)

Section (37-(3-1,4,5,6))BRR Henry County

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

Section (37-(3-1,4,5,6))BRR

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 X Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 X Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

Section (37-(3-1,4,5,6))BRR i

TABLE OF CONTENTS

LOCATION

DESCRIPTION

TRAFFIC CONTROL PLAN

GRANULAR BACKFILL FOR STRUCTURES

GUARDRAIL REMOVAL

PCC AUTOMATIC BATCHING EQUIPMENT

PCC QC/QA ELECTRONIC REPORTS SUBMITTAL

WORK ZONE PAVEMENT MARKING AND REMOVAL

AVAILABILITY OF ELECTRONIC FILES

ACRYLIC COATING

FLOOR DRAIN EXTENSION

CLEANING AND PAINTING EXPOSED REBAR

SLOPEWALL BREAKING

SLOPE WALL CRACK SEALING

SLOPE WALL REPAIR

SLOPE WALL SLURRY PUMPING

DRAINAGE SCUPPERS TO BE ADJUSTED

REMOVE AND REINSTALL CONCRETE HEADWALL FOR PIPE DRAIN

APPROACH SLAB REMOVAL

PREFORMED JOINT FILLER

RELOCATING NAME PLATES

RAILROAD PROTECTIVE LIABILITY INSURANCE (BDE)

CONTRACT PROVISIONS FOR WORK ON RAILROAD RIGHT-OF-WAY IOWA INTERSTATE

RAILROAD, LLC. FOR HIGHWAY WORK

JACK AND REMOVE EXISTING BEARINGS

DIAMOND GRINDING AND SURFACE TESTING BRIDGE SECTIONS

BRIDGE DECK CONSTRUCTION

BRIDGE DECK GROOVING (LONGITUDINAL)

PREFORMED PAVEMENT JOINT SEAL

BAR SPLICERS, HEADED REINFORCEMENT

BRIDGE DECK CONCRETE OVERLAYS

Section (37-(3-1,4,5,6))BRR ii

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

COMPENSABLE DELAY COSTS (BDE)

CONCRETE BARRIER (BDE)

CONCRETE SEALER (BDE)

DECK SLAB REPAIR

DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)

FUEL COST ADJUSTMENT (BDE)

GUARDRAIL (BDE)

HOT-MIX ASPHALT (BDE)

LONGITUDINAL TINING (BDE)

PAVEMENT MARKING (BDE)

PAVEMENT PATCHING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

PREFORMED PLASTIC PAVEMENT MARKING (BDE)

RAISED REFLECTIVE PAVEMENT MARKERS (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SLOPE WALL (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

SPEED DISPLAY TRAILER (BDE)

STEEL COST ADJUSTMENT (BDE)

STRUCTURAL REPAIR OF CONCRETE (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURFACE TESTING OF PAVEMENTS – IRI (BDE)

SURVEYING SERVICES (BDE)

TEMPORARY CONCRETE BARRIER (BDE)

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION . 120

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

Section (37-(3-1,4,5,6))BRR iii

WEEKLY DBE TRUCKING REPORTS (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

WORK ZONE WIDTH RESTRICTION (BDE)

WORKING DAYS (BDE)

Section (37-(3-1,4,5,6))BRR

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the “Standard Specifications for Road and Bridge Construction, adopted January 1, 2022”, the latest edition of the “Manual on Uniform Traffic Control Devices for Streets and Highways”, and the “Manual of Test Procedures for Materials” in effect on the date of invitation for bids, and the “Supplemental Specifications and Recurring Special Provisions” indicated on the Check Sheet included herein, which apply to and govern the construction of FAI Route 80 (I-80), Project NHPP-RBDM(511), Section (37-(3-1,4,5,6))BRR, Henry County, Contract No. 64T43 and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.

LOCATION

The project is located within Henry County on FAI Route 80 (I 80). Work will take place at the existing bridges, Structure Nos. 037-0035 (EB) and 037-0036 (WB) over Geneseo Creek, Structure Nos. 037-0039 (EB) and 034-0040 (WB) over Spring Creek, Structure Nos. 037-0041 (EB) and 037-0042 (WB) over E 1900th Street / TR 276, Structure Nos. 037-0043 (EB) and 037- 0044 (WB) over US 6 & IAIS RR, and Structure Nos. 037-0045 EB) and 037-0046 (WB) over Mud Creek.

DESCRIPTION

All structures shall have bridge deck scarification, latex concrete overlay, and diamond griding.

All structures, except 037-0041 and 037-0042, shall have approach slab scarification, latex concrete overlay, and diamond griding. Structure Numbers 037-0041 and 037-0042 proposed approach slabs shall have diamond griding only.

Additional work for Structure Numbers 037-0039, 037-0040, 037-0041, and 037-0042 shall consist of joint elimination through converting the existing stub abutments into semi-integral abutments and approach slab replacement. Additional work for Structure Numbers 037-0035 and 037-0036 shall consist of expansion joint replacement. Additional work for Structure Numbers 037-0043 and 037-0044 shall consist of approach slab and pavement connector joint replacement.

Section (37-(3-1,4,5,6))BRR

TRAFFIC CONTROL PLAN

Effective: January 14, 1999 Revised: January 13, 2017

Standards:

701101 701106 701201 701400 701401 701402

701406 701411 701426 701901 704001

Details:

Maintenance of Traffic Plans Work Zone Details (District Standard 34.1) Traffic Control Typical Weave (District Standard 40.1) Typical Pavement Markings (District Standard 41.1)

Signs:

“BUMP” (W8-1(O)48) signs shall be installed as directed by the Engineer.

“UNEVEN LANES” W8-11(O)48 signs shall be installed at 1 mile intervals or as directed by the Engineer.

“LOW SHOULDER” W8-9(O)48 signs shall be installed at 1 mile intervals or as directed by the Engineer.

When covering existing Department signs, no tape shall be used on the reflective portion of the sign. Contact the District sign shop for covering techniques.

Any plates or direct applied sheeting used to alter signs shall have the same sheeting as the base sign.

No more than one kind of alteration shall be used to alter a sign.

Any post stubs without a sign in place and visible shall have a reflector placed on each post.

Flaggers:

Flaggers shall comply with all requirements and signaling methods contained in the Department’s “Traffic Control Field Manual” current at the time of letting. The flagger equipment listed for flaggers employed by the Illinois Department of Transportation shall apply to all flaggers

In addition to the flaggers shown on applicable standards, on major sideroads, flaggers shall be required on all legs of the intersection. Major sideroads for this project shall be US 6.

When the mainline flagger is within 200 feet of an intersection, the sideroad flagger shall be required.

Section (37-(3-1,4,5,6))BRR

When the road is closed to through traffic and it is necessary to provide access for local traffic, all flaggers as shown on the applicable standards will be required. No reduction in the number of flaggers shall be allowed.

Pavement Marking:

All temporary pavement markings that will be operational during the winter months (December through March) shall be paint.

Short term pavement markings on a milled surface shall be paint.

Traffic Control and Protection Standard 701411:

Method of Measurement. Each ramp will be measured as a separate location and will be considered as a separate location for payment, regardless of the number of installations at that ramp.

Interstates and multi-lane divided highways where the existing speed is greater than 45 mph: The Contractor shall equip all machinery and vehicles with flashing amber lights, installed so the illumination is visible from all directions.

The median crossover will generally not be available for Contractor use. It may be used only when both lanes adjacent to the median are closed. Under no condition shall left turn lanes be made to cross the median from lanes open to traffic. Where interchanges are not available, the Contractor shall only be allowed to turn around where left turn lanes are present.

Parking of personal vehicles within the right-of-way will be strictly prohibited. Parking of construction equipment within the right-of-way will be permitted only at locations approved by the Engineer.

Maintenance of Traffic: The traffic shall generally be maintained using lane closures and lane shifts following Traffic Control and Protection Standards 701400, 701401, 701406, 701411 and 701423 and as shown in the plans.

The westbound traffic through Geneseo shall be maintained during Stage 3 using run-arounds as shown on the plans using Traffic Control and Protection Standard 701416.

The mainline shall be kept open to two-way traffic at all times during work hours and non-working hours.

Two (2) changeable message signs shall be placed on this project two (2) weeks prior to the start of work informing the public of lane closures. Location of the message signs will be determined by the Resident Engineer.

Section (37-(3-1,4,5,6))BRR

GRANULAR BACKFILL FOR STRUCTURES

Effective: April 19, 2012 Revised: July 16, 2024

Revise the third sentence of the first paragraph of Article 586.03 of the Specifications to read:

“The backfill volume shall be placed in Department acceptable lift thickness for the full width to be backfilled and shall be compacted to not less than 95 percent of the standard laboratory density.”

Delete the fourth sentence of the first paragraph of Article 586.03 of the Specifications.

GUARDRAIL REMOVAL

Effective: August 20, 1990 Revised: April 10, 2014

This work shall be done according to Section 632 of the Standard Specifications except that all removed guardrail will become the property of the Contractor.

This work will be paid for at the contract unit price per Foot for GUARDRAIL REMOVAL, measured from center-to-center of end posts.

PCC AUTOMATIC BATCHING EQUIPMENT

Effective: January 1, 2015 Revised: January 31, 2023

Portland cement concrete provided shall be produced from batch plants that conform to the requirements of Article 1103.03 (a) and (b) of the Standard Specifications for Road and Bridge Construction. Semi-automatic batching will not be allowed.

Plants shall have computerized batching interfaced with a printer. IDOT Producer Number, IDOT Design Number, Concrete Material Code, batch weights, aggregate mixtures, water added, amount of each admixture or additive, and percent variance from design shall be printed for each batch. Tickets shall state the actual water-cement ratio as batched, and the amount of water that can be added to the batch without exceeding the maximum water-cement ratio. Truck delivery tickets are still required as per Article 1020.11(a)(7) of the Standard Specifications.

PCC QC/QA ELECTRONIC REPORTS SUBMITTAL

Effective: January 1, 2015 Revised: January 31, 2023

The Contractor’s QC personnel shall be responsible for electronically submitting the following reports to the Department: PRO and IND data for BMPR MI654 “Concrete Air, Slump, and Quantity,”; PRO data for BMPR MI655 “P.C. Concrete Strength,” and PRO data for BMPR MI504 “Aggregate Gradation” reports to the Department. The format for the electronic submittals shall be the QMP package reporting program, which will be provided by the Department. Microsoft Excel 2007 or newer and Microsoft Outlook is required for this program which shall be provided by the Contractor.

Section (37-(3-1,4,5,6))BRR

WORK ZONE PAVEMENT MARKING AND REMOVAL

Effective: December 29, 2008 Revised: October 5, 2021

This work shall consist of installing and removing temporary pavement marking according to Section 703 and 783 of the Standard Specifications and the following:

All temporary paint on the final wearing surface shall be removed according to Article 1101.12 Water Blaster with Vacuum Recovery and the applicable portions of Section 783 of the Standard Specifications and as described herein.

Add the following paragraph to Article 1101.12 of the Standard Specifications.

“For the high pressure water spray, the pressure at the nozzle shall be approximately 25,000 psi with maximum flow rate of 15 gal/min. The nozzle shall be in close proximity to the pavement surface.”

AVAILABILITY OF ELECTRONIC FILES

Effective 10/16 Revised 1/29/25

Electronic files of this project will be made available to the Contractor after the contract has been awarded. This information will be provided upon request in a Bentley CONNECT Platform software format ONLY. If data is required in other formats, it will be your responsibility to make these conversions. The Contractor shall coordinate obtaining electronic files through the Project Engineer. If there is a conflict between the electronic files and the printed contract plans and documents, the printed contract plans and documents shall take precedence over the electronic files. The Contractor shall accept all risk associated with using the electronic files and shall hold the Department harmless for any errors or omissions in the electronic files and the data contained therein. Errors or delays resulting from the use of the electronic files by the Contractor shall not result in an extension of time for any interim or final completion date or shall not be considered cause for additional compensation. The Contractor shall not use, share, or distribute these electronic files except for the purpose of constructing this contract. Any claims by third parties due to use or errors shall be the sole responsibility of the Contractor. The Contractor shall include this disclaimer with the transfer of these electronic files to any other parties and shall include appropriate language binding them to similar responsibilities.

ACRYLIC COATING

Description. This item shall consist of surface preparation and painting of bridge parapets and roadway barriers at the locations shown in the plans with an acrylic coating. The limits of the painting shall be as shown in the plans and as directed by the Engineer

Materials. Acrylic Coating shall be an elastomeric, crack bridging, anti-carbonation, acrylic protective coating formulated for the protection of reinforced concrete. The Acrylic Coating shall have the following properties:

Color Gray Munsell No. 5B 7/1

Solids Content 62% by weight, 55% by volume

Section (37-(3-1,4,5,6))BRR

Tensile (ASTM 0-412 modified after 21 days cure)

Tensile Strength 200 psi Elongation at Break 625% at 730 F Tensile Strength at 00 F 1100 psi Elongation at Break at 00 F 225% Crack-Bridging (at 16 mils - 400 microns DFT) Static (at _-4 degree F) 30 mils Dynamic > 1000 cycles (at _4 degree F) 12 mils

Moisture Vapor Permeability (ASTM E-96) 14.5 Perms

Resistance to Wind Driven Rain (TT-C-555B) No passage of water through the coating

Flame Spread and Smoke Development (ASTM E-84-94)

Flame Spread: 5 Smoke Development: 5 Class Rating: A

Weathering (ASTM G-23) 10,000 hours. Excellent, no chalking or cracking

Construction Methods. Surface Preparation. All surfaces to be coated must be dry, clean, sound, and frost free with curing compound residues and any other foreign matter removed. An open textured sandpaper like surface is ideal.

Where existing surface coating is present, the surface should be prepared by blast cleaning or high pressure water jetting.

All bare concrete areas should be primed with appropriate primer as recommended by the Acrylic Coating manufacturer. Ensure that primer is thoroughly dry before over coating to prevent formation of bubbles and blisters, particularly in warmer weather.

Application. Substrate must be dry before application. Moisture content of concrete surface shall be below 5%. Minimum age of concrete or concrete patch shall be 14 days prior to application.

Acrylic Coating shall be applied with brush or roller over entire area moving in one direction.

A dry film thickness of 16 mils should be achieved.

Method of Measurement. Application of Acrylic Coating shall be measured for payment in Square Yards for the surface area of the final coat applied.

Basis of Payment. This work will be paid for at the contract unit price per square yard for ACRYLIC COATING. Surface preparation and priming will not be paid for separately, but will be included in the cost of ACRYLIC COATING

Section (37-(3-1,4,5,6))BRR

FLOOR DRAIN EXTENSION

Description. This work consists of furnishing and installing extensions on the existing bridge deck drains at locations and as detailed on the plans and as directed by the Engineer.

Construction Method. The drains shall be fabricated from material acceptable to the Engineer and is to be bent and/or formed according to the dimensions shown on the plans. The Contractor shall verify all plan dimensions prior to fabrication of the extensions. The extensions shall be braced as shown on the plans and the cost of all supporting members shall be included in the cost of floor drain extensions.

Basis of Payment. This work will be paid for at the contract unit price Each for FLOOR

DRAIN EXTENSIOSN.

CLEANING AND PAINTING EXPOSED REBAR

Description. This work shall consist of cleaning and painting all exposed reinforcement bars by the methods specified on the plans; furnishing application and protection of the paint coatings and all other work described herein.

General Requirements. All exposed rebar and adjacent concrete surfaces on the substructure and superstructure shall be cleaned and painted. All surfaces to be painted shall be power washed at 2500 psi (17,240 kPa) prior to abrasive blasting. After washing, the exposed rebar shall be abrasive blasted per SSPC-SP6 Commercial Blast Cleaning followed by the Aluminum Epoxy Mastic Paint System.

Weather Conditions. The surfaces to be painted after cleaning must remain free of moisture and other contaminants. The Contractor shall control his/her operations to ensure that dust, dirt or moisture do not come in contact with surfaces cleaned or painted that day. In addition to the paint system's manufacturer's written instructions for cleaning and painting, the following conditions shall apply. (When in conflict, the most restrictive conditions shall govern).

(1) Cleaning and painting shall be done between April 15 and November 15.

(2) The minimum temperature of the air and steel shall be 50 °F (10 °C) unless otherwise specified. Coatings shall not be applied to surfaces hotter than 130 °F (54 °C) or when the air temperature exceeds 100 °F (38 °C).

(3) The surface temperature shall be at least 5 °F (3 °C) above the dewpoint of the air surrounding the surface. In addition, the relative humidity of this air shall be less than 85%.

(4) Spray painting will not be permitted when wind velocities are greater than 15 MPH (24 kph).

Section (37-(3-1,4,5,6))BRR

These conditions will be determined by the Engineer at locations representative of the surfaces to be cleaned and painted. Work accomplished under unfavorable weather conditions will be considered unacceptable and complete recleaning and repainting of these areas will be required at the Contractor's expense.

Equipment. All cleaning and painting equipment shall include gauges capable of accurately measuring fluid and air pressures and shall have valves capable of regulating the flow of air, water or paint as recommended by the equipment manufacturer. The equipment shall be maintained in proper working order.

Spray painting and cleaning equipment shall utilize filters, traps or separators recommended by the manufacturer of the equipment and shall be kept clean to prevent oil, water, dried paint and other foreign materials from being deposited on the surface.

The filters, traps and separators shall be cleaned or drained by means, and at intervals, recommended by the manufacturer of the equipment. Paint pots shall be equipped with air operated continuous mixing devices.

Pressure type abrasive air blasting equipment shall be capable of supplying a minimum of 100 psi (690 kPa) pressure and 250 CFM (120 L/S) capacity with all air blast nozzles being used. If blast nozzle orifice sizes larger than 3/8” (9.5 mm) are being used, the minimum capacity of the equipment shall be increased according to the recommendations of SSPC Good Painting Practice, Volume 1, Chapter 2.4, Table 1.

The pressure will be measured at the blast nozzle. The equipment shall be capable of providing the minimum required pressure and volume, free of oil, water and other contaminants.

Diesel or gasoline powered equipment shall be positioned or vented in a manner to prevent deposition of combustion contaminants on any part of the structure.

Prior to beginning all painting operations, air equipment shall pass the requirements of ASTM D 4285. This test will be repeated as determined by the Engineer.

Cleaning. The Contractor shall notify the Engineer 24 hours in advance of beginning surface preparation operations. The washing shall be completed no more than 2 weeks prior to surface preparation. As directed by the Engineer, washing shall be completed on surfaces to receive second or third coats when foreign matter has accumulated on previously painted surfaces. Power washing shall be accomplished by using potable water meeting the requirements of Section 702 of the Standard Specifications with a flow rate of at least 4 gallons/minute (0.25 L/S), a nozzle fan angle between 15 and 30 degrees and a minimum pressure of 2500 psi (17,240 kPa).

Surface Preparation. The surface preparation Method is defined as outlined below:

The surface preparation shall be accomplished according to the requirements of SSPC Surface Preparation Specifications SP6, for Commercial Blast Cleaning. A Commercial Blast Cleaned surface, when viewed without magnification, shall be free of all visible oil, grease, dirt, dust, mill scale, rust, paint, oxides, corrosion products, and other foreign matter, except for staining.

Staining shall be limited to no more than 33 percent of each square inch of surface area and may consist of light shadows, slight streaks, or minor discoloration caused by stains

Section (37-(3-1,4,5,6))BRR of rust, stains of mill scale, or stains of previously applied paint. Slight residues of rust and paint may also be left in the bottoms of pits if the original surface is pitted. Unless otherwise specified, the surface preparation in these areas shall result in 1.0 to 3.5 mil (25 to 90 microns) blast profile as determined by the Engineer. The Contractor shall be careful not to damage sound paint adjacent to paint removal areas by his/her abrasive blasting operations.

Abrasive suppliers shall certify that abrasives shall not be oil contaminated and shall have a water extract pH value within the range of 6 to 8. All surfaces prepared with abrasives which are oil contaminated or have a pH outside the specified range shall be cleaned with solvent cleaner or low pressure water as directed by the Engineer and reblasted by the Contractor at his/her expense. Silica sand shall not be used as an abrasive.

All portions of the structure which could be damaged by the blast cleaning operations, shall be protected by covering or shielding. Tarpaulins, drop cloths, or other approved materials shall be employed. The Contractor shall be responsible for any damage caused to persons, vehicles, or property. Whenever the intended purposes of the protective devices are not being accomplished, as determined by the Engineer, work shall be immediately suspended until corrections are made.

Painting. All exposed rebar and surrounding concrete surfaces adjacent to the rebar shall be painted. The limits of the area to be painted shall be 3 inches (75 mm.) beyond the exposed reinforcement in all directions. Painting shall be accomplished according to these specifications and as specified in the paint manufacturer's written instructions and product data sheets for the paint system used. The prime and finish coat shall all be supplied by the same paint manufacturer.

All ingredients in any container of paint shall be thoroughly mixed by mechanical power mixers in original containers before use or mixing with other containers of paint. The paint shall be power mixed in a manner which will break up all lumps, completely disperse pigment and result in a uniform composition. Paint shall be carefully examined after mixing for uniformity and to verify that no unmixed pigment remains on the bottom of the container. Excessive skinning or partial hardening due to improper or prolonged storage will be cause for rejection of the paint, even though it may have been previously inspected and accepted. Paint shall not remain in spray pots, painters' buckets, etc.

overnight. Paint components shall not be stored at temperatures below 40 °F (4 °C). The unit weight (mass) shall be the same as the manufactured unit weight (mass) in pounds per gallon (kg/L), plus or minus 1.0 percent. If the unit weight (mass) does not fall within this range, the Contractor must take corrective action. The Contractor may try additional mixing to correct the problem. If additional mixing cannot correct the paint, it shall be rejected. Any paint that has been applied that does not meet the weight (mass) per gallon (liter) requirements shall be removed and the area shall be inspected and repainted at the Contractor's expense.

Each coat of paint shall be applied as a continuous film of uniform thickness free of pores. Each coat of paint shall be in a proper state of cure before the application of the succeeding coat. Dry film thickness shall be measured according to SSPC PA2.

Section (37-(3-1,4,5,6))BRR

Aluminum Epoxy Mastic System. All exposed rebar and surrounding concrete surfaces shall be painted with two coats of Aluminum Epoxy Mastic Paint. The dry film thickness shall be between

5.0 and 10.0 mils (125 and 250 microns) per coat. The wet film thickness shall be between 6.0 and 12.0 mils (150 and 300 microns) per coat. The total dry film thickness of the two coats shall be between 10.0 and 20.0 mils (250 and 500 microns).

Application. The aluminum epoxy mastic coating shall not be applied when the surface temperature is below 50 °F (10 °C) and shall not be applied when the ambient temperature is expected to drop below the manufacturer's minimum application temperature before the coating has cured. Curing times at various temperatures shall be provided by the paint manufacturer.

The aluminum epoxy mastic shall be applied by spray, brush or roller according to the paint manufacturer's printed instructions. Thinning of the aluminum epoxy mastic shall be according to the manufacturer's instructions. If brushes and/or rollers are used, two applications, applied at least 8 hours apart, may be required to obtain the required dry film thickness for each of the specified coats. The first application shall be tinted according to the manufacturer's guidance to produce a distinct contrast with the second application. When topcoat is applied, the recommendations of the coating manufacturer shall be followed as to surface preparation of the aluminum epoxy mastic. When the humidity exceeds 75% during the application of the epoxy mastic, the surface shall be washed off with potable water prior to application of the topcoat.

If a paint coating is too thin or if portions of the steel are not coated completely, such portions of the work shall be corrected as directed by the Engineer. If the paint coat wrinkles or shows evidence of having been applied under unfavorable conditions, or if the workmanship is poor, the Engineer may order it removed and the steel cleaned and repainted at the Contractor's expense. All areas where the paint film exceeds the maximum thickness shall be corrected by the Contractor at his/her expense using approved methods.

Aluminum Epoxy Mastic Material Requirements

The aluminum epoxy mastic paint system shall be a two component epoxy containing aluminum pigment. The aluminum epoxy mastic shall be designed as a one coat high-build complete protective coating system with excellent adhesion to rusted steel, inorganic zinc and old paint after such surfaces have been properly cleaned. The aluminum epoxy mastic shall be compatible with a wide range of topcoats including waterborne acrylics, alkyds, and polyurethanes.

The material for aluminum epoxy mastic primer shall conform to the following requirements:

(1) Pigment - The primary pigment shall be either a leafing or non-leafing aluminum pigment. Secondary pigmentation shall contain no toxic heavy metals.

(2) Vehicle - The vehicle shall be a modified epoxy and curing agent which is suitably insensitive to moisture to allow trouble free application.

Section (37-(3-1,4,5,6))BRR

(3) Packaged Components - The epoxy coating shall be supplied as a two-component material at a one-to-one volume mix ratio. It shall be well ground, free of caking, skins, gellation and excessive settling. The shelf life of each component shall be no less than twelve months.

(4) Properties Of Aluminum Epoxy Mastic

a. The mixed epoxy shall contain a minimum of 89 percent solids by weight, when tested according to ASTM D 1644, Method A, except that the sample shall be heated for 72 hours at 100 ° ± 2 °F (38 ° ± 1 °C).

b. The weight per gallon (mass/liter) of the unmixed components shall not vary more than 0.2 pounds (0.1 kg) from the weight (mass) of the original qualification samples.

c. The viscosity of the coating shall be a minimum of 90 KU at 77 ° ± 2 °F (25 ° ± 1 °C). Viscosity must be checked immediately after addition and mixing of components.

d. The pot life of the epoxy coating shall be no shorter than 2 hours at 75 °F (24 °C) or one hour at 90 °F (32 °C).

e. The epoxy coating shall air cure at a temperature of 75 °F (24 °C) or above to a hard tough film within 5 days by evaporation of solvent and chemical reaction. It shall be dry to the touch in 24 hours at 75 °F (24 °C), and be able to withstand foot traffic in 48 hours at 75°F (24 °C).

f. The mixture, when thinned per manufacturer's recommendations, shall exhibit no runs or sags when applied by conventional or airless spray to produce dry film thicknesses in the 5 to 10 mil (125 to 250 micron) range.

(5) Resistance Tests of Cured Aluminum Epoxy Mastic - Test panels of steel meeting the requirements of ASTM D 609, having dimensions of 2 X 5 X 1/8 inch (50 X 125 X 3 mm), shall be prepared by abrasive blasting all surfaces to a white metal finish according to SSPC-SP5. The cleaned panels shall then be exposed to outdoor weather for 30 days or until uniform rusting occurs. They shall then be hand cleaned with a wire brush according to SSPC-SP2. A 6 mil (150 micron) dry coating of the epoxy mastic shall then be applied in one coat according to the manufacturer's current printed instructions. The coating shall be cured as recommended by the manufacturer. Each of the following tests shall be performed on one or more test panels. Test panels to be scribed shall be prepared according to the requirements in ASTM D 1654. The material will not be accepted if any individual test panel fails any of the following tests:

(a) Fresh Water Resistance. Panels shall be scribed down to base metal with an X of at least 2 inch (50 mm) legs and shall be immersed in fresh tap water at 75 ° ± 5 °F (24 °± 3 °C). The panels shall show no rusting, blistering, or softening beyond 1/16 inch (1.5 mm) from the scribe mark, when examined after 30 days. Discoloration of the coating will be allowed.

(b) Salt Water Resistance. Panels shall be scribed down to base metal with an X of at least 2 inch (50 mm) legs and immersed in 5 percent sodium chloride at 75 ° ± 5 °F (24 °± 3 °C).

Section (37-(3-1,4,5,6))BRR

(C). The panels shall show no rusting, blistering or softening beyond 1/16 inch (1.5

mm) from the scribe mark upon examination after 7, 14 and 30 days. Discoloration of the coating will be allowed. The sodium chloride solution shall be replaced with fresh solution after each examination.

(c) Salt Fog Resistance. Panels shall be scribed down to base metal with an X of at least 2 inch (50 mm) legs. The panels shall then be tested according to ASTM B 117.

After 1,000 hours of continuous exposure, the coating shall show no loss of bond, nor shall it show rusting or blistering beyond 1/16 inch (1.5 mm) from the center of the scribed mark. Weathering Resistance. Panels shall be tested in accelerated weathering using either the light and water exposure apparatus (fluorescent UV-condensation type) as specified in ASTM G154 for 1000 hours with a cycle consisting of eight hours UV exposure at 140 °F (60 °C) followed by four hours of condensation at 104 °F (40 °C) or the weatherometer according to ASTM G154, Type D for 1000 hours beginning the test at the start of the wet cycle. After this period, the panels shall show no loss of bond, nor shall it show rusting, softening or blistering.

(6) Packaging and Labeling - The aluminum epoxy mastic coating shall be packaged in two containers. The components shall be prepackaged such that mixing in a one-to-one ratio, by volume, utilizes a complete container of each component.

Each container shall have a label on which shall be clearly shown the manufacturer and brand name of paint, the lot number, the date of manufacturer and shelf life. The label on the vehicle container shall also include complete instructions for the use of this paint. The container shall be coated, if necessary, to prevent attack by the paint components.

(7) Qualification Samples and Tests

The manufacturer shall supply to an independent test laboratory, and to the Department, duplicate samples of the aluminum epoxy mastic paint for evaluation. Prior to approval and use, the manufacturer shall submit a notarized certification of the independent laboratory, together with the results of all tests, stating that the materials meet the requirements as set forth herein. The certified test report shall state lot tested, manufacturers name, product name, and date of manufacture. New certified test results and samples for testing by the department shall be submitted any time the manufacturing process or paint formulation changes. All costs of testing (other that tests conducted by the Department) shall be borne by the manufacturer.

(8) Acceptance Samples and Certification

One quart (liter) component samples of each lot of paint produced for use on state or local agency projects shall be submitted to the Department for testing, together with a manufacturer’s certification. Their certification shall state that the formulation for the lot represented is essentially identical to that used for qualification testing. All acceptance samples shall be taken by a representative of the Illinois Department of Transportation.

The aluminum epoxy mastic paint shall not be used until all tests are completed and they have met the requirements as set forth herein.

Section (37-(3-1,4,5,6))BRR

Method of Measurement. Limits of the area to be painted are determined by the exposed reinforcement after the loose concrete has been removed. The limits of the area to be painted and measured for payment shall be 3 inches (75 mm.) beyond the exposed reinforcement in all directions.

Basis of Payment. This work shall be paid for at the contract unit price per square foot (square meter) for CLEANING AND PAINTING EXPOSED REBAR. This shall include all equipment and labor necessary to remove loose concrete.

SLOPEWALL BREAKING

Description. This work shall consist of breaking the existing concrete slopewall and leaving it in place at locations shown on the plans, as directed by the Engineer, and as herein specified.

Construction Method. The slopewall shall be broken up such that it collapses vertically thereby filling the underlying voids. The slopewall shall not be relocated nor allowed to be transported into the stream. No in stream work will be allowed.

The Contractor shall break up the concrete slopewall in pieces no larger than twelve inches (12”). Any exposed reinforcement bars or fabric will be removed or cut off to the satisfaction of the Engineer, and the removed material will be disposed of in accordance to Article 202.03.

Basis of Payment. This work will be paid for at the contract unit price per Square Yard for

SLOPEWALL BREAKING.

SLOPE WALL CRACK SEALING

Description. All open random cracks or existing joints in the existing concrete slope wall shall be cleaned and sealed. Hot Joint Sealer meeting the requirements of Article

1050.02 shall be used for slope wall repair. All cracks and joints shall be cleaned and filled with sealant according to Section 452 of the Standard Specifications. Routing of the cracks is not required.

Method of Measurement. Sealing existing cracks and joints in concrete slope wall shall be measured for payment along the linear distance of opening sealed and measured in feet. Cleaning existing cracks and joints prior to sealing will not be measured for payment but shall be considered included in the price for Slope Wall Crack Sealing.

Basis of Payment. This work will be paid for at the contract unit price per Foot for

SLOPE WALL CRACK SEALING.

Section (37-(3-1,4,5,6))BRR

SLOPE WALL REPAIR

Description - This work consists of the removal and replacement of failed sections of slope wall as shown on the Plans and as directed by the Engineer. Work shall be performed in accordance with the requirements of Section 511 of the Standard Specifications.

Materials - Materials shall meet the requirements of Article 511.02 of the Standard Specifications. Any material required to fill voids and level the supporting base shall be crushed stone meeting a CA-6 gradation.

Construction - Areas delineated for removal shall be scored with a concrete saw down to, but not through, the existing mesh reinforcement. The concrete shall be broken out and removed in such a fashion as to leave a minimum of 1 ft exposed mesh edge to tie into the new mesh. After removal of the delineated area of slope wall, any depressions or voids in the base shall be filled with crushed stone and compacted prior to placing the mesh and concrete for the slope wall repair, in order to achieve the slope wall thickness as shown in the Plans.

When shown on the Plans or as directed by the Engineer, depressions or voids shall be filled with controlled low-strength material (CLSM).

Method of Measurement - This work will be measured for payment according to Article 511.04(b) of the Standard Specifications.

CLSM placed for the repair of slope walls will be measured for payment according to the special provision for SLOPE WALL SLURRY PUMPING.

Basis of Payment - This work will be paid for at the contract unit price per square yard for SLOPE WALL REPAIR. Additional crushed stone required for the base will not be paid for separately but shall be considered as included in the work.

CLSM placed for the repair of slope walls will be paid for according to the special provision for SLOPE WALL SLURRY PUMPING.

SLOPE WALL SLURRY PUMPING

Description - This work shall consist of furnishing and placing controlled low-strength material (CLSM) in voids beneath sections of slope wall as shown in the plans, and at locations determined by the Engineer.

Materials - The material shall be CLSM according to Section 593 of the Standard Specifications.

Construction - The Contractor shall cut any necessary holes as required for the placement of the CLSM and to check for voids. The Contractor shall place forms to confine the CLSM under the slope wall. Sandbags or other means shall be used to restrict the seepage of the CLSM out of the void. The CLSM may be placed by pumping or by chute as required.

Section (37-(3-1,4,5,6))BRR

Method of Measurement - This work will be measured for payment in place and the volume computed in cubic yards. Measured volume will be the actual volume of material required to fill the voids.

Basis of Payment - This work will be paid for at the contract unit price per cubic yard for SLOPE WALL SLURRY PUMPING.

DRAINAGE SCUPPERS TO BE ADJUSTED

Description – This item of work shall consist of cleaning and adjusting the existing bridge drainage scuppers to the new elevation resulting from the latex concrete overlay as shown on the plans, as directed by the Engineer, and as specified herein. The adjustment shall be done by fabricating and installing a new adjusting ring to compensate for the elevation increase resulting from the overlay. The existing grate shall be removed and reinstalled on the new adjusting ring.

The existing scupper details are provided in the plans for information only. The Contractor shall field verify all dimensions and existing conditions prior to ordering materials.

Materials - All cast iron parts shall be gray iron conforming to the requirements of AASHTO M 105, Class 35B and AASHTO M306. Structural steel shall conform to AASHTO M 270, Grade 36.

Bolts, washers, and nuts shall conform to the requirements of AASHTO M164 Type I.

All bolts, washers, and nuts shall be galvanized according to AASHTO M 232.

Basis of Payment - Adjusting drainage scuppers shall be paid for at the contract unit price per Each for DRAINAGE SCUPPERS TO BE ADJUSTED, which price shall include full compensation for all tools, equipment, material, and labor required to complete the work as indicated on the plans, directed by the Engineer, and as specified herein.

The cost of cleaning the existing scuppers shall be included in the cost of DRAINAGE

SCUPPERS TO BE ADJUSTED.

REMOVE AND REINSTALL CONCRETE HEADWALL FOR PIPE DRAIN

Description: This work shall consist of furnishing all labor, material, and equipment necessary for the removal and reinstallation of existing concrete headwalls for pipe drains, as well as replacing any missing or damaged rodent screens at locations shown on the plan details.

This work shall be according to the applicable portions of Section 601 of the Standard Specification and as directed by the Engineer. Existing concrete headwalls for pipe drains shall be removed, stored, and reinstalled at the restored original existing location at the end of the job, or as directed by the Engineer. When the concrete headwall has been reinstalled, the existing pipe drain shall be reconnected to the headwall and sealed with a concrete collar to the satisfaction of the Engineer.

Section (37-(3-1,4,5,6))BRR

Method of Measurement: The removal and reinstallation of the concrete headwall for the pipe drains will be measured as each.

Basis of Payment: The work will be paid for at the contract unit price per each for

REMOVE AND REINSTALL CONCRETE HEADWALL FOR PIPE DRAIN.

APPROACH SLAB REMOVAL

Description. This work shall consist of the satisfactory removal and disposal of the existing approach slabs as shown on the plans. This work shall be performed according to Section 501 of the Standard Specifications.

Method of Measurement. Approach slab removal will be measured for payment.

Basis of Payment. This work will be paid for at the contract unit price per SQUARE YARD for APPROACH SLAB REMOVAL, which shall be full compensation for all labor, equipment, and materials required to complete the work.

PREFORMED JOINT FILLER

Description. This work shall consist of furnishing all labor, equipment and materials required for the installation of preformed joint fillers to the size and at the locations specified in the plans.

Materials. The materials shall be according to Section 1051.03 for bituminous preformed joint filler. The Contractor shall submit the Manufacturer’s material certification documentation stating that their materials meet the applicable requirements of this specification.

Construction Methods. The Contractor shall install the preformed joint filler to the same elevation as the top of the median curb per the manufacturer’s instructions.

Method of Measurement. This work will be measured for payment in place, in feet, along the centerline of the joint.

Basis of Payment. This work will be paid for at the contract unit price per Foot for

PREFORMED JOINT FILLER.

Section (37-(3-1,4,5,6))BRR

RELOCATING NAME PLATES

Description. This work shall consist of the removal, storage, and reinstallation of the existing bridge name plates located with portions of concrete parapets being removed and replaced as indicated in the plans.

Removal Method. Removal shall be done with hand-held tools preserving the name plate and bolts/lugs in good condition. The Contractor shall be responsible for repairing any damage caused by the removal operations to the name plate at the Contractor’s expense. If the Contractor’s operations case unrepairable damage to the existing name plate, a new name plate with identical markings and in accordance with Section 515 shall be furnished and installed at the Contractor’s expense.

The Contractor shall be responsible for storing the name plates in a secure location until reinstallation.

Reinstallation Method. On concrete structures, the name plate shall be embedded in the concrete and fastened by means of four brass or bronze bolts with countersunk heads, or four lugs cast integral with the plate. The bolts or lugs shall project at least 3 inches into the concrete beyond the back of the plate.

The name plates shall be located in accordance with Highway Standard 515001, except they shall be located a minimum of 12” between the near edge of the plate to the concrete removal line.

Basis of Payment. This work shall be paid for at the contract unit price per Each for RELOCATING…