- Removal and replacement of the structure (SN 101-0109) carrying IL 75 over the Rock River
- Solicitation number
- 64E09
- Issued by
- Rock Island County, Rosewood Heights CDP, Illinois
About this file
This is a Notice to Bidders and Special Provisions document issued by the Illinois Department of Transportation (IDOT) for Contract No. 64E09, a Federal-aid highway construction project in Winnebago County. The project involves complete bridge replacement of structure SN 101-0109 with new structure SN 101-0230 carrying Illinois Route 75 over the Rock River in Rockton. The work includes roadway reconstruction, multi-use path additions, drainage improvements, lighting enhancements, pavement marking and signing, erosion control, landscaping, guardrail improvements, and miscellaneous related work along a 733.94-foot project segment. Electronic bids must be submitted to the iCX (Integrated Contractors Exchange) system by 12:00 p.m. on November 6, 2026, at which time bids will be publicly opened. The project completion date is November 18, 2027, with a completion date plus working days provision allowing 15 additional working days for cleanup and punch list items. The road closure and detour must begin no earlier than February 1, 2027, and end no later than November 18, 2027, with continuous, uninterrupted closure required.
The contract will be awarded to the lowest responsive and responsible bidder in conformance with established terms and conditions. This is a Federal-aid construction contract subject to state and federal certification requirements, including EEO compliance, DBE participation requirements, and Project Labor Agreement provisions. The contractor is required to obtain 30 Stateline Mass Transit District credits to provide alternate pedestrian access during the bridge closure. Key specifications include PCC automatic batching equipment requirements, quality control and assurance procedures, concrete mix design provided by the Department, electrical system installation per NEC and OSHA standards, and comprehensive testing protocols for lighting, telecommunications, and fiber optic systems. Special provisions address traffic control, temporary information signing, utility adjustments, maintenance transfer procedures, and removal and disposal of regulated substances at identified PESA sites with documented contamination concerns including SVOCs, manganese, and pH issues.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Letting November 6, 2026
Notice to Bidders, Specifications and Proposal
Contract No. 64E09 WINNEBAGO County Section 77BR Route FAP 505 Project BR-MJPV(881) District 2 Construction Funds
Prepared by F
Checked by
(Printed by authority of the State of Illinois)
NOTICE TO BIDDERS
1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.
November 6, 2026 at which time the bids will be publicly opened from the iCX SecureVault.
2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the
Invitation for Bids as:
Contract No. 64E09 WINNEBAGO County Section 77BR Project BR-MJPV(881) Route FAP 505 District 2 Construction Funds
Removal and replacement of the structure (SN 101-0109) carrying IL 75 over the Rock River in Rockton.
3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.
(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.
4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.
By Order of the Illinois Department of Transportation
Gia Biagi, Secretary
FAP Route 505 (IL 75)
Section 77B-1 Winnebago County
INDEX
FOR
SUPPLEMENTAL SPECIFICATIONS
AND RECURRING SPECIAL PROVISIONS
Adopted January 1, 2026
This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.
ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)
SUPPLEMENTAL SPECIFICATIONS
Std. Spec. Sec. Page No.
109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires
1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment
Section 77B-1
RECURRING SPECIAL PROVISIONS
The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:
CHECK SHEET # PAGE NO.
1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)
3 X EEO
4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 X Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes
10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 X Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 X Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays
Section 77B-1 i
TABLE OF CONTENTS
LOCATION OF WORK
DESCRIPTION OF WORK
TRAFFIC CONTROL PLAN
TEMPORARY INFORMATION SIGNING
STATUS OF UTILITIES TO BE ADJUSTED
COMPLETION DATE PLUS WORKING DAYS
DETOUR RESTRICTIONS
COORDINATION WITH ADJACENT AND/OR OVERLAPPING CONTRACTS
GRANULAR BACKFILL FOR STRUCTURES
GUARDRAIL REMOVAL
PCC AUTOMATIC BATCHING EQUIPMENT
PCC QC/QA ELECTRONIC REPORTS SUBMITTAL
AVAILABILITY OF ELECTRONIC FILES
INLETS (SPECIAL)
ATTACHING TELESCOPING STEEL SIGN SUPPORTS TO BRIDGE RAILING
GUARDRAIL DELINEATORS/REFLECTORS
BARRIER WALL DELINEATORS/REFLECTORS
SOLAR POWERED FLASHING BEACON ASSEMBLY (COMPLETE)
POWDER COATING OF PARAPET RAILING AND BRIDGE FENCE RAILING
BENCHES
FLAGPOLES
RELOCATING COMMEMORATIVE PLAQUES
STATELINE MASS TRANSIT DISTRICT CREDITS
REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES
GENERAL ELECTRICAL REQUIREMENTS
PAINT MAST ARM AND POLE
ELECTRIC UTILITY SERVICE CONNECTION
ELECTRIC SERVICE INSTALLATION
UNDERGROUND RACEWAYS
UNIT DUCT
WIRE AND CABLE
HIGH LOAD MULTI-ROTATIONAL BEARINGS
Section 77B-1 ii
CONCRETE WEARING SURFACE
SLIPFORM PARAPET
BRIDGE DECK CONSTRUCTION
METALLIZING OF STRUCTURAL STEEL
DRILLED SHAFTS
CONSTRUCTION REQUIREMENTS
CROSSHOLE SONIC LOGGING TESTING OF DRILLED SHAFTS
BAR SPLICERS, HEADED REINFORCEMENT
AGGREGATE SUBGRADE IMPROVEMENT (BDE)
CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)
COMPENSABLE DELAY COSTS (BDE)
CONCRETE SEALER (BDE)
DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)
ENGINEER’S FIELD OFFICE (BDE)
EROSION CONTROL BLANKET (BDE)
FUEL COST ADJUSTMENT (BDE)
GUARDRAIL (BDE)
INLET FILTERS
PAVEMENT MARKING (BDE)
PREFORMED PLASTIC PAVEMENT MARKING (BDE)
REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)
SIGN PANELS AND APPURTENANCES (BDE)
SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)
STEEL COST ADJUSTMENT (BDE)
SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)
SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)
SUBMISSION OF BIDDERS LIST INFORMATION (BDE)
SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)
SURVEYING SERVICES (BDE)
TRAINING SPECIAL PROVISIONS (BDE)
IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION 128
VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)
WEEKLY DBE TRUCKING REPORTS (BDE)
Section 77B-1 iii
WORK ZONE TRAFFIC CONTROL DEVICES (BDE)
WORK ZONE WIDTH RESTRICTION (BDE)
PROJECT LABOR AGREEMENT
Section 77B-1
STATE OF ILLINOIS
SPECIAL PROVISIONS
The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction, Adopted January 1, 2022", the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways", and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the "Supplemental Specifications and Recurring Special Provisions" indicated on the Check Sheet included herein, which apply to and govern the construction of FAP Route 505 (IL 75), Project BR-MJPV(881), Section 77B-1, Winnebago County, Contract No. 64E09 and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.
LOCATION OF WORK
The project is located along FAP Route 505 (IL 75) in Rockton, from River Street to Hawick Street while going over the Rock River; in Winnebago County.
The net length of the project measures approximately 733.94 feet (0.139 miles) along the centerline of FAP Route 505 (IL 75).
DESCRIPTION OF WORK
The proposed improvements consist of complete bridge replacement of the existing structure SN 101-0109 with a new structure SN 101-0230 that will carry two lanes of traffic (one in each direction) along with a sidewalk on the west side and a new multi-use path on the east side. Other improvements include roadway reconstruction approaching both sides of the new bridge, addition of multi-use path on the east side of IL 75, drainage improvements, lighting improvements, pavement marking & signing, erosion control & landscaping, guardrail improvements, and other miscellaneous work as necessary.
Section 77B-1
TRAFFIC CONTROL PLAN
Effective: January 14, 1999 Revised: January 13, 2017
Standards:
701006 701011 701301 701311 701501 701701 701801 701901
Details:
Detour Route District Standard WORK ZONE SIGN DETAILS (DIST STD. 34.1)
District Standard TRAFFIC CONTROL FOR ROAD CLOSURE (DIST STD. 40.1)
Signs:
When covering existing Department signs, no tape shall be used on the reflective portion of the sign. Contact the District sign shop for covering techniques.
Any plates or direct applied sheeting used to alter signs shall have the same sheeting as the base sign.
No more than one kind of alteration shall be used to alter a sign.
Any post stubs without a sign in place and visible shall have a reflector placed on each post.
Devices:
A minimum of 3 drums spaced at 4 feet shall be placed at each return when the sideroad is open.
Flaggers:
Flaggers shall comply with all requirements and signaling methods contained in the Department’s “Traffic Control Field Manual” current at the time of letting. The flagger equipment listed for flaggers employed by the Illinois Department of Transportation shall apply to all flaggers
In addition to the flaggers shown on applicable standards, on major sideroads, flaggers shall be required on all legs of the intersection. Major sideroads for this project shall be River Street and Hawick Street.
Pavement Marking:
All temporary pavement markings that will be operational during the winter months (December through March) shall be paint.
Short term pavement markings on a milled surface shall be paint.
Section 77B-1
District Standard Application:
Traffic Control for Road Closure: This work shall be done according to the Road Closure Standard and Section 701 of the Standard Specifications.
The contractor shall provide information warning signs for oversized loads regarding the road closure. These signs shall be 4’ x 8’ as shown on the sign design and shall read “NO OVERSIZE- OVERWEIGHT XX MILES AHEAD” and the distance from the cross roads as noted. The contractor shall erect these signs near the intersection of IL 75 and IL 70 (14 MILES AHEAD).
“ROAD CLOSED AHEAD” (W20-3(O)-48) with flasher and the appropriate arrow plate (W1-6(O)- 36x18 or W1-7(O)-36x18) shall be required on all side roads within the limits of the mainline “ROAD CLOSED AHEAD” signs.
The Contractor shall notify the Department via email at DOT.D2.TrafficNotice@illinois.gov. This request shall be submitted a minimum of three weeks (21 days) and no earlier than four weeks (28 days) prior to the anticipated closure date to allow the State adequate time to re-route oversized loads.
Signing and devices required to close the road, according to the Traffic Control for Road Closure detail and contained herein, shall be the responsibility of the Contractor. Detour signing required to detour traffic to alternate routes shall be the responsibility of the Contractor. The day the detour signing begins, the detour will be in effect when the Contractor has notified the Resident Engineer or personnel on the project. No detour shall be erected on Friday, Saturday or Sunday. The road shall not be closed until the detour signing is completely installed, verified, and ready to accept traffic.
The “ROAD CLOSED” sign on the Type III barricades shall be unobstructed and visible to traffic at all times. No equipment, debris, or other materials shall be stored within 20 feet of the first set of Type III barricades, unless approved by the Engineer.
The Contractor shall not drive around the outside of the Type III barricades, but shall relocate the barricades temporarily for access. When it is necessary for the barricades to be moved for access, the Contractor shall move the devices into the left lane and/or left shoulder area behind barricades that are to remain in place. At no time shall the barricades be turned parallel to traffic flow for access purposes.
If a path becomes evident around the outside of the barricades, the Contractor shall be required to place additional Type III barricades to prevent driving around the existing barricades. Additional barricades shall be included in the cost of applicable Traffic Control Standards
This work shall be paid for at the contract lump sum price for TRAFFIC CONTROL AND
PROTECTION, (SPECIAL).
Road Closure – Closures within Closures: The road closure shall be completed using Type III barricades in compliance with Standards 701901, and signing according to Traffic Control for Road Closure detail. Two flashers shall be installed above each Type III barricade. The "ROAD CLOSED" (R11-2) or “ROAD CLOSED TO THRU TRAFFIC” (R11-4) signs shall be placed as shown in Standard 701901. Flashers shall be installed above all warning signs involving a night time road closure. If a portion of the road is completely closed between a sideroad and any entrances, the roadway will be kept open to local access in the other direction between that closure and the next road.
Section 77B-1
The Contractor shall be required to notify the Bureau of Project Implementation and affected residents prior to a complete closure.
All cost involved in conforming with this provision shall be considered a part of TRAFFIC
CONTROL AND PROTECTION, (SPECIAL).
Maintenance of Traffic:
When the roadway is not closed, the road shall be kept open to one-way traffic at all times during working hours and two-way traffic during non-working hours.
The Contractor shall notify the Village of Rockton, the corresponding Township Commissioner, city municipality, emergency response agencies (i.e.: fire, ambulance, police), school bus companies and the Department of Transportation (Bureau of Project Implementation) regarding any changes in traffic control.
The road shall be closed for reconstruction using the detour from Wagon Wheel Road to IL 2.
Access to the residential property at STA 933+73 within the closed section of road shall be provided at all times throughout the duration of the project.
All construction activities shall be halted for the duration of Rockton’s Old Settler’s Day event typically held the third week of June every year.
TEMPORARY INFORMATION SIGNING
Description. This work shall consist of the furnishing, installation, maintenance, and removal of temporary information signs.
Materials. Materials shall be according to the applicable portions of Section 701 of the Standard Specifications and as shown on the plans.
Construction Requirements. The temporary information signs shall be in place at least one week prior to the beginning of construction activities that impact traffic flow and shall remain in place until the completion of the project.
Signs shall be installed according to the requirements of Section 701.
Method of Measurement. This work will be measured for payment in square feet edge to edge (horizontally and vertically). All hardware, posts or skids, supports, bases for ground mounted signs, connections, which are required for mounting these signs will be included as part of this pay item.
Basis of Payment. This work will be paid for at the contract unit price per square foot for
TEMPORARY INFORMATION SIGNING.
Section 77B-1
STATUS OF UTILITIES TO BE ADJUSTED
LIST OF UTILITIES TO BE ADJUSTED
Type Utility Contact Telephone # JULIE Member
Telephone Frontier Mr. Kalin Hinshaw 112 W. Elm Street
Sycamore, IL 60178
815-895-1515 Yes
Gas & Electric Rock Energy Cooperative
Mr. Rod Magnuson PO Box 126
15229 Willowbrook Rd South Beloit, IL 61808
866-752-4550 Yes
Water & Sewer Village of Rockton Mr. Gordy Nygren 110 E. Main Street Rockton, IL 61072
815-624-7600 No
Communications Charter Communications
Mr. Keith Stewart 1837 Park Avenue Beloit, WI 53511
608-365-3382 Yes
Communications Kentucky Data Link, Inc.
Mr. James Kustuch 13935 Bishops Drive Brookfield, WI 53005
414-313-9032 No
The above represents the best information of the Department and is only included for the convenience of the bidder. The applicable provisions of Sections 102 and 103, and Articles
105.07 and 107.20 of the Standard Specifications for Road and Bridge Construction shall apply.
If any utility adjustment or removal has not been completed when required by the Contractor's operation, the Contractor should notify the Engineer in writing. A request for an extension of time will be considered to the extent the Contractor's operations were affected.
COMPLETION DATE PLUS WORKING DAYS
Effective: December 29, 2006 Revised: April 22, 2019
Revise Article 108.05(b) of the Standard Specifications to read:
“(b) Completion Date Plus Working Days. When a completion date plus working days is specified, the Contractor shall complete all contract items to safely open all roadways to traffic by 11:59 p.m.
on or prior to November 18th, 2027, except as specified herein.
The Contractor will be allowed 15 working days after the completion date for opening the roadway to traffic to complete clean-up work and punch list items. Miscellaneous items may be completed within the working days allowed for clean-up work and punch list items if approved by the Engineer. Temporary lane closures for this work may be allowed at the discretion of the Engineer.”
Section 77B-1
DETOUR RESTRICTIONS
The IL 75 Closure/Detour shall adhere to the following restrictions
• Start date of the IL 75 Closure/Detour shall be no earlier than February 1st , 2027
• End date of the IL 75 Closure/Detour shall be no later than November 18th , 2027
• The Closure/Detour shall be continuous in duration, and not intermittent
• Under no circumstances shall the IL 75 Closure/Detour be allowed to extend over a winter shutdown
COORDINATION WITH ADJACENT AND/OR OVERLAPPING CONTRACTS
This contract abuts and/ or overlaps with other concurrent and future Village of Rockton Contracts as listed below.
Each contract may include work items requiring close coordination between the various Contractors regarding the sequence and timing for execution of work items in accordance with Article 105.08 of the Standards Specifications and as herein noted.
The adjacent and/or overlapping Contracts will be (but not limited to):
• Village of Rockton’s recreational bike path along the east side of Old River Rd, and East
River St, from University Pkwy to IL75 Contract or Job Number: C-92-024-23 Start Date/Duration: Spring 2027 / 1 year
• Winnebago County’s resurfacing of Old River Rd from Roscoe Rd to IL75.
Contract or Job Number: 85800 Start Date/Duration: Spring 2027 / 1 year
Basis of Payment. All expenses incurred by the Contractor by reason of compliance with these requirements shall be considered as included in and completely covered by the contract unit prices for the various items included in the contract.
GRANULAR BACKFILL FOR STRUCTURES
Effective: April 19, 2012 Revised: July 16, 2024
Revise the third sentence of the first paragraph of Article 586.03 of the Specifications to read:
“The backfill volume shall be placed in Department acceptable lift thickness for the full width to be backfilled and shall be compacted to not less than 95 percent of the standard laboratory density.”
Delete the fourth sentence of the first paragraph of Article 586.03 of the Specifications.
Section 77B-1
GUARDRAIL REMOVAL
Effective: August 20, 1990 Revised: April 10, 2014
This work shall be done according to Section 632 of the Standard Specifications except that all removed guardrail will become the property of the Contractor.
This work will be paid for at the contract unit price per Foot for GUARDRAIL REMOVAL, measured from center-to-center of end posts.
PCC AUTOMATIC BATCHING EQUIPMENT
Effective: January 1, 2015 Revised: January 31, 2023
Portland cement concrete provided shall be produced from batch plants that conform to the requirements of Article 1103.03 (a) and (b) of the Standard Specifications for Road and Bridge Construction. Semi-automatic batching will not be allowed.
Plants shall have computerized batching interfaced with a printer. IDOT Producer Number, IDOT Design Number, Concrete Material Code, batch weights, aggregate mixtures, water added, amount of each admixture or additive, and percent variance from design shall be printed for each batch. Tickets shall state the actual water-cement ratio as batched, and the amount of water that can be added to the batch without exceeding the maximum water-cement ratio. Truck delivery tickets are still required as per Article 1020.11(a)(7) of the Standard Specifications.
PCC QC/QA ELECTRONIC REPORTS SUBMITTAL
Effective: January 1, 2015 Revised: January 31, 2023
The Contractor’s QC personnel shall be responsible for electronically submitting the following reports to the Department: PRO and IND data for BMPR MI654 “Concrete Air, Slump, and Quantity,”; PRO data for BMPR MI655 “P.C. Concrete Strength,” and PRO data for BMPR MI504 “Aggregate Gradation” reports to the Department. The format for the electronic submittals shall be the QMP package reporting program, which will be provided by the Department. Microsoft Excel 2007 or newer and Microsoft Outlook is required for this program which shall be provided by the Contractor.
AVAILABILITY OF ELECTRONIC FILES
Effective 10/16 Revised 1/29/26
Electronic files of this project will be made available to the Contractor after the contract has been awarded. This information will be provided upon request in a Bentley CONNECT Platform software format ONLY. If data is required in other formats, it will be your responsibility to make these conversions. The Contractor shall coordinate obtaining electronic files through the Project Engineer. If there is a conflict between the electronic files and the printed contract plans and documents, the printed contract plans and documents shall take precedence over the electronic files. The Contractor shall accept all risk associated with using the electronic files and shall hold
Section 77B-1 the Department harmless for any errors or omissions in the electronic files and the data contained therein. Errors or delays resulting from the use of the electronic files by the Contractor shall not result in an extension of time for any interim or final completion date or shall not be considered cause for additional compensation. The Contractor shall not use, share, or distribute these electronic files except for the purpose of constructing this contract. Any claims by third parties due to use or errors shall be the sole responsibility of the Contractor. The Contractor shall include this disclaimer with the transfer of these electronic files to any other parties and shall include appropriate language binding them to similar responsibilities.
INLETS (SPECIAL)
This work shall be in accordance with Section 602 of the Standard Specifications for Road and Bridge Construction and the for Inlets, Special Detail included in the Plans.
This item includes all materials (concrete, reinforcement, frames, lids, etc.), labor and equipment necessary to construct to the lines and grades shown within the Plans.
This work shall be paid for at the contract unit price per EACH for INLETS, SPECIAL..
ATTACHING TELESCOPING STEEL SIGN SUPPORTS TO BRIDGE RAILING
This work shall consist of installing telescoping steel sign support(s) at the locations shown in the plans and as directed by the Engineer.
Materials shall meet the requirements of the POWDER COATING OF PARAPET RAILING AND BRIDGE FENCE RAILING specification and conform to the standards for sign panel mounting, sign panel erection, and telescoping steel sign support.
The vertical telescoping steel sign support shall be attached to the outside of the bicycle railing at the nearest post location to the station listed in the plans for the sign to be installed using hardware to secure the support to the outside of the post. No drilling of holes into the railing shall be allowed.
Any damage to the powder coating finish shall be repaired by the Contractor at their own expense.
This work will not be paid for separately and shall be considered included with the cost of TELESCOPING STEEL SIGN SUPPORT, which price shall include furnishing, erecting, and installing supports, and any other necessary hardware.
GUARDRAIL DELINEATORS/REFLECTORS
The reflector shall be the STRAIGHT, DOUBLE SIDED style and shall be in compliance with Illinois Department of Transportation Standard Specifications for Road and Bridge Construction Section 1097 and the following. The retroreflective sign sheeting used on the reflector shall meet Article 1097.02 (c)(2). Guardrail Delineators/Reflectors shall be a minimum of 13 inches tall and 3 inches wide, with a minimum reflective area of at least 12 square inches. The bodies of the markers shall be made from high-impact, weatherable engineering rigid PVC .090 thick (min). The markers shall be capable of retaining its original shape after being hit repeatedly.
Section 77B-1
Guardrail Delineators/Reflectors may be mounted directly to a wood, plastic or metal guardrail block out or metal delineator post, using 2 – 16 DG nails and 2 – 3/16” washers or 2 galvanized screws 2-1/2” in length or 2 – self tapping screws, in the pre-drilled holes. (When mounting on a metal delineator post, use 2 – 10/24 X 1-1/2 bolts with washer and nuts.).
Basis of payment: The Delineator or Marker shall be paid for per EACH for GUARDRAIL REFLECTORS, TYPE C (SPECIAL) as shown in District Standard 55.1.
BARRIER WALL DELINEATORS/REFLECTORS
The Barrier Wall Reflectors Special shall be installed according to District Standard
REFLECTORS (SPECIAL) 55.1
The Barrier Wall Reflector Special shall be paid for at the contract unit price per EACH for Barrier Wall Reflectors (Special), which price shall also include screws, washers, or approved bonding agent. Reflectors installed on two lane roads shall be double sided and both sides shall be Crystal. Reflectors installed on center barrier wall shall be double sided and both sides shall be Amber. Reflectors installed on divided highways along the outside of the highway shall be double sided and both sides shall be Crystal. Spacing for reflectors shall be according to Standard 782006, unless otherwise noted in the plans.
SOLAR POWERED FLASHING BEACON ASSEMBLY (COMPLETE)
Effective: August 18, 2025
This pay item includes all necessary work to install the Post Mounted Solar Powered Flashing Beacon Assembly (Complete) as follows:
This work will consist of the installation of solar-powered flashing beacon assemblies (complete), at locations shown in the plans and approved by Kristie Nyderek (815/284-5469) of the Illinois Department of Transportation, two weeks prior to installation.
Overview: This specification is for a solar powered 24-hour flashing beacon. The system shall consist of a self-contained light engine containing all electronics, batteries & solar panels. No additional cabinet is required. The light engine shall connect to an ITE compliant 12” lens with visor and backplate, and mount with the included bracket set to a 4x6 wood post, unless otherwise specified in the plans. Flashers mounted above yellow warning signs shall consist of a yellow lens beacon and the flashers mounted above red regulatory signs shall consist of a red lens beacon.
The flashers shall be installed one (1) foot above the sign.
1.0 Mechanical Specifications
The flasher shall meet the requirements of Section 800 of the Standard Specifications for Road and Bridge Construction. The light engine shall be constructed from aluminum, with a yellow power-coated finish, and shall be no greater in size than 6” x 17” x 26”. Solar panels shall be integrated to the light engine, and all batteries and electronics shall be located internally, with no external control cabinet required. The weight of the light engine shall not exceed 52 pounds. The light engine must be able to rotate 360 degrees and tilt 60 degrees for maximum solar energy collection. Batteries shall be field replaceable.
Section 77B-1
Enclosure. The controller shall be housed in a vandal-resistant, aluminum, NEMA 3R pole mounted cabinet with a lockable, hinged door.
Power. The controller unit shall be available in solar 12 VDC, 35 AHr versions, each equipped with a 40W solar panel. Solar-powered systems shall provide a minimum of 15 days of back-up batter power in the absence of sunlight while operating at full brightness and at standard usage levels. The battery shall have a life span of a minimum of 5 years and be field replaceable.
The signal housing shall be constructed of yellow polycarbonate material, and must be adjustable independently from the bracket for lens alignment. The signal housings shall meet the equipment standard of the Institute of Transportation Engineers Vehicle Traffic Control Signal Heads (VTCSH) Chapter 2 and Sections 880 and 882 of the Standard Specifications for Road and Bridge Construction. The lens shall be an ITE complaint 12” yellow or red lens.
The bracket kit must be constructed of cast aluminum or steel, and shall be designed according to MASH safety standards. The bracket shall be designed to fit new or existing wood post or 4” OD pole supports, such that existing signs shall not be affected.
2.0 Operation Profile
The flash pattern and flash sequence shall comply with the Manual of Uniform Traffic Control Devices (MUTCD), Chapter 4K.
The light shall flash at a rate of 56.6 flashes per minute, 24 hours per day. The light shall flash with a 50% duty cycle (0.53s on time/ 0.53s off time). The light shall operate at 124, 250 or 400 candela (user configurable).
When set at 124 candela by day, and 35 by night, the light shall have a minimum operating autonomy of 40 days. The light shall automatically reduce light output in case of low battery situations, reducing risk that the light will fail entirely under conditions of poor solar insulation.
If shown in the plans, when two (2) flashers are for the same direction of travel, at the same location, the flashers must communicate and flash in a wig-wag pattern. The communication must be wireless.
3.0 Environmental Specifications
The light should be able to withstand and operate at temperature extremes of -40° F to +122° F.
The system shall be designed and constructed to withstand 178 KM\h (110 mph) wind loads in conformance with the requirements of the AASHTO publication, “Standard Specifications for Structural Supports of Highway Signs, Luminaries and Traffic Signals”, 4th Edition 2001.
4.0 Quality Assurance
The light, including batteries, panels and all components, shall be guaranteed for a minimum of three years.
If radio components are shown in the design plans the product must be FCC certified to comply with all 47 CFR FCC Part 15 Subpart B Emission requirements.
Section 77B-1
5.0 Existing Equipment
When indicated in the plans, existing solar flashers shall be carefully removed and stored for the Department. They shall remain the property of the Department. Traffic Operations shall be contacted to schedule pickup of the existing electrical equipment.
6.0 Basis of Payment
This work will be paid for at the contract unit price Each for SOLAR POWERED FLASHING BEACON ASSEMBLY (COMPLETE), which price shall be payment in full for furnishing all parts and labor for the installation of the solar unit. No additional compensation will be allowed.
POWDER COATING OF PARAPET RAILING AND BRIDGE FENCE RAILING
Description: This work shall include surface preparation, vinyl, polyolefin or powder type painted finish application and packaging of new galvanized railing and fence system assemblies. All work associated with applying the painted finish shall be performed at the manufacturing facility for the fence system assembly or railing assembly or at a painting facility approved by the Engineer. After installation of railing or fence system in the field, the color of all visually exposed surfaces of all connector hardware shall be touched up using material as recommended by the galvanizer and the powder coating supplier to match the black powder coating that was applied to all other metal elements of the railing systems.
This work shall conform to Section 509 of the Standard Specifications with the additional work specified herein and as shown on the plans.
Materials: Materials shall meet the requirements of Article 509.02 of the Standard Specifications, and as specified below.
Fence Fabric: The fabric shall be woven in 2 inch mesh with 0.148 inch diameter wire meeting the requirements of AASHTO M181, Type IV, Class B (polyvinyl chloride PVC) or ASTM F668 Class 2b (polyvinyl chloride PVC or polyolefin elastomer) coated steel.
Fence Coating: The tension wire and fabric ties shall be vinyl or polyolefin coated.
Galvanizing: The posts, post tops, base and cap plates, railings, braces, stretcher bars, fittings and hardware shall be powder coated. All materials to be powder coated shall be hot dipped galvanized in accordance with Articles 1006.27, 1006.28 and 1006.34 of the Standard Specifications and ASTM A123 with a minimum zinc coating of 0.90 ounces per square foot (G90) after fabrication and prior to vinyl, polyolefin, or powder coating. Vent holes for galvanizing shall be placed in the posts and rails at locations that will not allow the accumulation of moisture in the members. Only the dry-kettle (pre-fluxing) process shall be used. The material shall not be water or chromate quenched. Galvanized materials to be powder coated shall be air cooled only. An American Galvanizers Association trained Master Galvanizer shall be on the premises during the hot dipped galvanizing process.
Powder: Powder coating material shall be a thermosetting, durable, TGIC polyester powder of a degassing grade. Such coating powder must be recommended by its manufacturer for use over hot dipped galvanizing. The coating powder’s particle size distribution shall be recommended by
Section 77B-1 its manufacturer to produce the best results for powder coating components under this specification.
Surface Preparation. All primary components of railing systems: posts, post tops, base and cap plates, railings, braces, stretcher bars, and fittings shall receive a pre-treatment process that cleans and prepares the galvanized surface to assure complete adhesion of the powder coating after drilling and layout, to ensure maximum corrosion protection. The zinc surface shall be prepared for powder coat application using a multistage system employing appropriate cleaners and imparting a phosphate conversion coat to provide an appropriate substrate for the powder coat material. During the cleaning process, water rinses shall be used as appropriate between stages to clean the items and prepare them for the subsequent stages. Water for the rinses, unless specified elsewhere shall be potable with a hardness not to be more than 250 ppm as CaCO3 and a combined chloride and sulfate level less than 100 ppm.
Surface Defects: All weld flux and other contaminates shall be mechanically removed. All drainage spikes, tears, high spots, protrusions or other surface defects shall be removed using hand or power tools in accordance with the manufacturer’s specifications. Such operations shall not remove the galvanized coating below the thickness allowed by ASTM A123. Thickness of the galvanizing shall be verified using a properly calibrated magnetic thickness gauge as per ASTM E376. Any item falling below the required zinc thickness, before or after removal of any high spots, shall be repaired in accordance with Practice A780.
Surface Cleaning: The galvanized surface shall be clean and free of oils and grease before they are powder coated. These shall be removed by use of an aqueous alkaline solution and/or hand or power tool cleaning. Subsequent to alkaline/power cleaning, trace zinc oxide will be removed by a mild acidic solution.
• An alkaline solution, pH in the range of 11 to 12 may be used to remove traces of oil, grease, or dirt. The alkaline solution shall not have a pH exceeding 13. After cleaning the piece shall be rinsed thoroughly in water under pressure.
• Hand or power tool cleaning may be used to clean light deposits of zinc reaction products such as wet storage stain, as specified to SSPC Surface Preparation Specification 2 or 3 as appropriate.
• An acidic solution with a pH of 3.5 to 4.5 shall be sprayed onto the item to remove residual zinc oxide.
Surface Profiling: The galvanized surface shall be profiled to promote proper powder coating adhesion. This shall be accomplished by applying a phosphate treatment to create a protective crystalline phosphate conversion coating on the zinc surface. The coating shall have a coating weight between 20 to 70 mg/ft2.
Final Rinse: To ensure the most optimum performance possible, a final rinse of de-mineralized water shall be applied as a final rinse prior to pre-baking. This stage will remove any un-reacted phosphate and other contaminants.
Powder Coat Application. The finish color shall be one of the manufacturer's standard colors and shall be as selected by the local agency responsible for paint costs. The Contractor shall confirm, in writing, the color selection with the local responsible agency and provide a copy of the approval to the Engineer and a copy of the approval shall be included in the material catalog submittal. The City desires a smooth powder black finish.
Section 77B-1
Color: The color of all vinyl, polyolefin or polyester powder coatings on fence metal fabric, posts, post tops, base and cap plates, railings, braces, stretcher bars, fittings, hardware, and accessories shall be a smooth powder black finish.
Pre-baking: Following phosphating all items to be powder coated shall be placed in an oven capable of maintaining a temperature of 500°F. Specimens shall be baked at a temperature 25°F above the normal cure temperature for the powder that will be employed. The specimens shall remain in the oven for a minimum of 20 minutes after having equalized to the temperature of the oven to remove any residual moisture from the preparation phase, and insure expulsion of any entrapped gases or moisture. Typically, specimens are pre-baked for one hour.
Powder Coat Application: Polyester powder shall be applied through electrostatic/tribomatic application guns. The powder shall be applied in multiple coats. The first coat shall have a thickness of 1.5 to 3 mils. Each intermediate coat shall be partially cured at a temperature of 350°F to insure adhesion. Subsequent coats shall be then applied in 1.5 to 3 mil increments to bring the specimen to its final (cured) thickness as required by the customer specification. In no case will the final (cured) thickness be less than 5 mils.
Cure: The powder coating shall be cured by heating the coated specimens to a temperature and duration specified by the powder coat material manufacturer to insure sufficient curing of the powder coating material. The resulting coating shall be uniform in color and free of pinholes, blisters, and other surface defects. Correct cure shall be checked by a solvent rub test.
Properties of Cured Coating:
Minimum film thickness TGIC 5.0 mils (120μm) Direct impact ASTM D 2794 160 in./lb (9.0 m/kg) Reverse impact ASTM D 2794 160 in./lb (9.0 m/kg) Pencil hardness (scratch/gouge) ASTM D 383 2H Flexibility (Mandrel test) ASTM D 522 1/8 in. (3m mm) Minimum adhesion ASTM D 3359 5A,5B (100% crosshatch) Salt spray ASTM B 117 + 1000 hrs < 2mm
Repair of Powder Coated Material:
• Damage shall be defined as exposed galvanized coating.
• Damaged coatings less than ½ of 1% of the surface area shall be acceptable for repair.
Damage greater than that amount shall be recoated. Final finish shall be damage free FOB the plant.
• Coatings to be repaired shall be touched up as recommended by the galvanizer and the powder coating supplier. Touch up and/or field repair can be accomplished using either powder coating material or paint. Typically acrylic based paint as recommended by the powder coating material manufacturer, applied either by spray or brushed on liquid is used for touch up and repair of the powder coating.
Any damage to the finish after leaving the manufacturer's facility shall be repaired to the satisfaction of the Engineer using a method approvable by the Engineer and manufacturer. If while at the manufacturer's facility the finish is damaged, the finish shall be re-applied.
Packaging: Prior to shipping, the new railing and fence system assemblies including fence metal fabric, posts, post tops, base and cap plates, railings, braces, stretcher bars, fittings, hardware, and accessories shall be wrapped in ultraviolet-inhibiting plastic foam or rubberized foam.
Section 77B-1
Submittals. In addition to the requirements of Article 509.04 of the Standard Specifications, the Contractor shall provide certification for the following:
• The galvanized element surfaces were properly prepared for adhesion of powder coat.
• The connector hardware was properly prepared for adhesion of field-applied paint.
• Polyester Powder was applied at a rate of 1.5 to 3 mils and properly cured per the manufacturer’s recommendations.
Warranty: The Contractor shall furnish in writing to the Engineer, the paint manufacturer's standard warranty and certification that the paint system has been properly applied.
Basis of Payment. This work shall be paid for at the contract Lump Sum price for POWDER COATING OF PARAPET RAILING AND BRIDGE FENCE RAILING, which shall be payment in full for surface preparation and powder coat application to all galvanized metal elements of the railing systems including posts, post tops, base and cap plates, railings, braces, stretcher bars, fittings, hardware, and accessories. This payment shall also include vinyl or polyolefin coat application to fence metal fabric and the packaging of new railing and fence system assemblies as described in this specification.
BENCHES
Description: This work shall include:
1. Furnishing, assembling and installing decorative metal benches (“benches”) at the positions and grades designated on the construction drawings.
2. Furnishing and installing the appurtenant materials required for the installation of the benches as shown on the construction drawings.
General Requirements: The contractor shall comply with manufacturer’s recommendations for transportation, installation and approved submittals. All benches shall be installed level and true and in proper relation to adjacent surfaces.
Submittal Requirements: Submit following for review and approval.
1. Product Data: Manufacturer’s standard product literature.
2. Shop Drawings: Indicating size, connections, materials, etc.
3. Installation Instructions
4. Maintenance Instructions
5. Warranty Information
Material Requirements: Materials used for bench construction shall comply with the following.
1. Decorative Metal Site Bench: Meeting the following specifications:
a. Basis of Design Product: Bench 58 by DuMor, inc.
b. Manufacturer Contact: https://dumor.com/products/bench-58
c. Dimension: 6’ Length
d. Configuration: Backed with End Armrest
e. Frame Material: Cast Iron and Steel
Section 77B-1
f. Frame Finish: Zinc Rich Epoxy then finished with Polyester Powder Coating, Provide Manufacturer standard color options for selection.
g. Mounting: Anchored to concrete slab, using Manufacturer recommended mount brackets.
h. Manufacturer’s Warranty: Three (3) years from date of invoice against defects in materials and workmanship, to be held by the Village of Rockton.
2. The contractor shall submit manufacturer’s product literature, including color charts and installation details for approval.
3. Benches must be supplied by a single manufacturer having the resources to provide consistent quality in appearance and physical properties.
4. Benches are to be packaged and shipped and as per manufacturer’s recommendations.
5. All products are to be free from cracks, chips, defects and surface blemishes.
Construction Requirements: Installation of benches shall comply with the following:
1. Benches are to be installed as per manufacturer’s instructions.
2. Benches are to be surface mounted to concrete slabs where indicated in a manner which does not compromise the integrity of, crack, chip or discolor the slab.
3. Benches to be anchored to concrete slab using Manufacturer recommended hardware.
This work will be paid for at the contract unit price per Each for BENCHES, which price shall include all labor, materials, surface mount brackets, and equipment necessary to complete the work specified herein.
FLAGPOLES
This work shall consist of installing a new flag pole located in the pedestrian bump out on the new bridge as directed by the Engineer.
The new flag pole shall be six inches (6”) in diameter, 0.188” wall thickness and have an exposure height of thirty feet (30’) for the pole. The pole shall have the following features:
• All poles shall be aluminum and powder coated black in color
• All poles shall be of the internal halyard type with winch
• All poles shall be equipped with up-down solar powered flagpole LED lighting units
Catalog shop drawings shall be submitted to the Engineer for approval prior to ordering the flag pole.
This work will be paid for at the contract unit price per EACH for FLAGPOLES which price shall be full compensation for all equipment, labor and materials.
Section 77B-1
RELOCATING COMMEMORATIVE PLAQUES
Description. This work shall consist of the removing, cleaning, storing, and reinstalling existing bridge commemorative plaques as identified on the plans and as directed by the Engineer.
Existing commemorative plaques shall be removed from their existing locations and cleaned.
Removal shall be done with handheld tools preserving the plaques and bolts/lugs in good condition. The Contractor shall be responsible for repairing any damage to the plaques caused by the removal operations at their expense. If the Contractor’s operations cause unrepairable damage to the existing plaques, a new plaque with identical markings and in accordance with Section 515 shall be furnished and installed at the Contractor’s expense. The Contractor shall be responsible for storing the plaques in a secure location until reinstallation. Installation in the proposed locations shall be according to the Article 515.04 of the Standard Specifications.
Installation locations shall be per the Design Plans and the recommendations of the Engineer.
Basis of Payment. This work will be paid for at the contract unit price per EACH for RELOCATING
COMMEMORATIVE PLAQUES.
STATELINE MASS TRANSIT DISTRICT CREDITS
For the purpose of providing alternate pedestrian access route for the duration of the IL-75 bridge closure, The Contractor is required to obtain 30 STATELINE MASS TRANSIT DISTRICT CREDITS from the Village of Rockton. The Village to Rockton will manage these credits in order to purchase both full-fare tickets and mobile passes to distribute to pedestrians who request SMTD shuttle services.
One STATELINE MASS TRANSIT DISTRICT CREDITS is equivalent to one full-fare SMTD ticket.
This is an on demand service, and the Contractor shall acknowledge that additional credits may be required throughout the duration of the contract. Prior to the Contractor initiating full closure of the IL-75 bridge, proof of the purchase of STATELINE MASS TRANSIT DISTRICT CREDITS shall be provided to the Resident Engineer.
If there are any questions, comments or concerns about this Special Provision, please contact the district 2 designer, Andrew Dewey, at 815-284-5358 or Happy Welch at 815-624-7600.
Village of Rockton SMTD Coordinator:
Happy Welch Village Administrator 110 E. Main St. Rockton, IL 61072 Email: hwelch@rocktonil.gov Phone: 815-624-7600 ext. 2277
For the Contractors information:
SMTD fare prices @ https://www.smtd.biz/fares Please bid accordingly.
If there are any questions, comments or concerns about this Special Provision, please contact the District 2 Environmental Studies Supervisor at 815-284-5460.
Section 77B-1
Basis of Payment. Stateline mass transit district credits will be paid for at the contract unit price per EACH for STATELINE MASS TRANSIT DISTRICT CREDITS. If this pay item is not present in the advertised summary of quantities, payment will be processed per art. 109.05 of the Standard Specifications for Road and Bridge Construction.
REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES
Description. This work shall consist of the removal and disposal of regulated substances according to Section 669 of the Standard Specifications as revised below.
Contract Specific Work Areas. For stationing, the lateral distance is measured from the centerline, and the farthest distance is the offset distance or construction limit, whichever is less.
The following contract-specific work areas shall be monitored by the Environmental Firm for soil contamination and workers'…