Statement of Work Summary
This Statement of Work (SOW) details the ADA Door Opener Projects for Kayenta Health Center in Kayenta, Arizona, dated December 10, 2025, under the Kayenta Service Unit. The project involves installation and modification of twenty-seven ADA door opener locations throughout the health facility, which serves approximately 20,000 people in a remote area and provides ~200 patient visits daily with 24/7 emergency room services.
The contractor must prepare a comprehensive proposal with an accurate project timeline and perform all work to completion, including modifications and replacements while maintaining fire/smoke door ratings (NFPA compliance), furnishing UL-certified hardware, removing existing door closures, preparing doors for new ADA openers, ensuring existing electronic access systems remain functional, and installing new ADA door openers with two push buttons per location. Installation locations include single and double doors across multiple departments (G-Wing, Physical Therapy, ED, Radiology, Pharmacy, Patient Registration, Outpatient, Conference, Administration, Human Resources, and Inpatient areas). The contractor must maintain existing door ratings and specifications per FGI (Federal Guideline Institute) standards, use well-known reliable door opener brands, test and certify all openers with electronic access control systems, and dispose of debris at EPA-approved locations. Work must comply with NFPA criteria, The Joint Commission standards, and safety protocols, conducted Monday through Friday, 8:00 AM to 5:00 PM, excluding federal holidays, with coordination through facility management and security. The contractor provides a one-year workmanship warranty and manufacturer warranties with finish certificates. KSU Maintenance will provide 120-volt power installation, and the contractor must obtain facility ID badges, minimize disruption to patient care operations, maintain a clean work area, and submit equipment submittals prior to installation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IHS IEE Representation Form_Jan 2022_508 Compliant.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
KAYENTA HEALTH CENTER
ADA DOOR OPENER PROJECTS
AT
KAYENTA HEALTH CARE CENTER
KAYENTA, ARIZONA
December 10, 2025
KAYENTA SERVICE UNIT
1. Introduction:
1.1. Kayenta Health Center (KHC) is located south of Arizona State Highway 160 at milepost 364.3. The nearest town is a two hour drive. The Kayenta Service Unit serves a population of ~20,000 people spread across a remote and sparsely populated area. Services are provided to ~200 patients each day. KHC provides walk-in clinics and a 24 hour, 7 days per week emergency room. KHC requires professional services and expertise to perform the following work:
a. Installation of twenty-seven ADA door locations
2. PROJECT BACKGROUND
2.1. Kayenta Health Center currently have need for ADA door openers throughout building.
2.2. Some doors are fire/smoke door rated and need to comply with NFPA.
2.3. This health facility project requires the expertise of a responsible contractor.
2.4. Some door entries may require two sets of ADA door openers at double door location.
3. PROJECT DESCRIPTION:
3.1. The contractor shall prepare a proposal, and upon award, shall provide an accurate timeline to complete project and following will perform the work to completion.
3.2. The project includes the following work:
a. Modifications and/or replacements need to maintain and not degrade the fire or smoke rating of the door.
b. All hardware and door replacements need to be tested and certified (Ex. UL certified)
c. Existing doors have panic hardware, handicap door handles, electronic mechanical access systems (striker), and magnet locks.
d. Doors that need to be replaced will require same or higher grade, and solid core or metal doors need to be replaced with same type.
e. Contractor is to dispose of debris at approved EPA disposal location.
f. Fire and smoke door installation/modifications need to pass fire and smoke door criteria inspections.
g. Remove door closures as needed, ADA door openers have built in door closures.
h. Prepare existing door to place new Handicap Door Openers
i. Existing electronic door access must work with new ADA door opener.
j. Existing doors are lockable and some doors will need striker or solenoid to work with ADA opener.
k. KSU Maintenance to install 120-volt power to Handicap Door Opener location
l. Contractor to furnish and install new Handicap Door Openers with two push buttons.
i. Doors are either single door or double door, double doors require two ADA door openers.
m. Test and certify Handicap Door Openers that will work with electronic access control.
n. Test and certify doors open and close properly.
4. CRITERIA:
4.1. Codes and Standards: the contractor shall perform work in accordance with best common practices and standards;
a. Safety and Hazard Awareness (PPE, jobs specific hazards, Electrical isolation).
b. NFPA criteria
c. The Joint Commission standards and regulations
d. Door specification must meet government FGI, Federal Guideline Institute.
e. Door opener must be a well known reliable brand.
5. GENERAL REQUIREMENTS:
5.1. Contractor shall develop a set plan and accurate timeline to present to KHC project representative prior to the project start date.
5.2. Contractor is responsible for furnishing tools, materials and equipment to complete the project.
5.3. A report and walk through of the work area will be necessary after completion of project.
5.4. Work area should be well kept and free of trash and debris after work days.
5.5. Finished work/product needs to function properly, be pristine and professional.
5.6. The contractor shall perform work between the hours of 8:00am and 5:00pm Monday through Friday excluding Federal Holidays, weekend work and afterhours work may be necessary.
5.7. Work hours need to be discussed and agreed upon with facility (contract officer, facility manager, security and
ETC.).
5.8. The contractor shall furnish a schedule of the dates agreed upon with the project officer and the facility manager at least two weeks in advance.
5.9. Any foreseen or unplanned costs, workhours or changes that will affect or incur extra costs to KSU, needs to be brought to the attention of the KHC project representative before proceeding with this matter.
5.10. The Contractor must be mindful of keeping normal business and patient care activities uninterrupted.
5.11. Contractor is expected to be professional and efficient with his work.
6. SPECIAL REQUIREMENTS
6.1. Proper demolition, and construction work methods in a health facility environment is needed to minimize construction and demolition material contamination to the department and facility.
6.2. HVAC vents, exhaust hoods, and openings need to be covered and sealed to prevent fumes, dust, odors and other construction related activity contamination from escaping.
6.3. Fire safety systems such as sprinklers and smoke alarms need to be blocked, covered and/or protected to prevent damage and activation.
6.4. Contractor is required to obtain an identification badge (ID) before starting work at KSU.
6.5. Contractor shall wear ID badge on KSU premises and check in with security every day.
6.6. Contractor must have knowledge of fire door installation.
6.7. Contractor must submit submittals of equipment to be installed.
7. ATTACHEMENTS
7.1. ADA Door Opener List
7.2. Doors 1G-202
7.3. Doors 1G-203
7.4. Doors 2C-201
7.5. Doors 1D-220
7.6. Door Location Floor Plan.
8. Period of Performance
8.1. The period of performance shall commence immediately upon award.
9. Warranty
10.1 Workmanship warranty one years.
10.2 Equipment warranty by manufacture, finish certificates.
7.1 Door Improvement List
Room # Door Tag
Fire Door
Electronic Door Access
P-Panic H-Handle C-Closure S-Electric Strike M-Mag Lock T-Vertical Rod Latch
Door Work Request
1 1G-203 G-Wing West X P, C, ADA Opener-Double 2 1G-203B G-Wing West C ADA Opener-Double 3 1G-202 G-Wing 166399 2 Hour X P, H, C, M, T ADA Opener-Double 4 1A-201 Physical T. H, C ADA Opener Single 5 1B-202A Physical T. 166314 2 Hour X H, C, S ADA Opener-Single 6 1C-205B Navajo Nation X H, C, S ADA Opener-Single 7 1C-021 OEHE Entrance X H, C, S ADA Opener-Single 8 1D-220 ED Entrance 166359 1 Hour X P, C, M ADA Opener-Double 9 1D-220B ED Entrance 166366 1 Hour H, C ADA Opener-Double 10 1D-203 Radiology 166355 1 Hour X H, C, S ADA Opener-Single 11 1D-402 Pharmacy
Waiting 1 Hour X P, C, M, T ADA Opener-Double
1E-201 Patient Reg. 166343 1 Hour X P, C, M, T ADA Opener-Double
13 1F-201 Outpatient 166333 1 Hour X P, C, M, T ADA Opener-Double 14 1F-202 Outpatient X P, H, C, S ADA Opener-Single 15 1F-210 Outpatient X P, H, C, S ADA Opener-Single 16 2E-202 Conference 1 Hour X P, C, M, T ADA Opener-Double 17 2E-201 Conference 1 Hour X P, C, M, T ADA Opener-Double 18 2D-210 Inpatient 166261 2 Hour X P, C, M, T ADA Opener-Double 19 2B-001 Exec. Conf. X H, C, S ADA Opener-Single 20 2C-201 Administration 166307 1 Hour X P, H, C, S ADA Opener-Single 21 2C-201A Administration X H, C, S ADA Opener-Single 22 2C-017 Human
Resources X P, H, C, S ADA Opener-Single
23 2C-010 Human Resource
X H, C, S ADA Opener-Single
24 2D-212B Inpatient 166267 2 Hour X P, C, M, T ADA Opener-Double 25 2D-214 Inpatient 166243 1 Hour P, C, T ADA Opener-Double 26 2D-215 Inpatient C ADA Opener-Double 27 1D-209 ED Waiting 163357 1 Hour X H, P, C, T ADA Opener-Double
7.2 Doors 1G-202
7.3 Doors 1G-203
7.4 Doors 2C-201
7.5 Doors 1D-220
Figure 7.6: Door Location Floor Plans: