U.S. Department of Justice

Federal Bureau of Prisons Administrative Division

Field Acquisition Office Grand Prairie, Texas 75051

May 5, 2015

ATTN: ALL BIDDERS

RE: Clarification Set Number One

Solicitation IFBP04181500005 FCC Terre Haute, Indiana Replace DA Surge Tanks

Dear Bidders, In reference to the above solicitation, enclosed are clarifications to questions that have been submitted. These clarifications are for informational purposes only.

If you have any questions, feel free to contact me at (972) 352-4641 or e-mail at dpatton@bop.gov

Sincerely, Douglas V. Patton Contracting Officer Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, Texas 75051

Enclosure cc: File

SCS, FCC Terre Haute COR, FCC Terre Haute Facility Manager, FCC Terre Haute Regional Facilities Administrator, NCRO

CLARIFICATION SET NUMBER ONE

IFBP04181500005

REPLACE DA SURGE TANKS

FCC TERRE HAUTE, INDIANA

l . Question: Downtime – Are there any limits to downtime of the tank:

Answer: In the summer we have a little flexibility with regard to downtime, but very limited in the wintertime if this proceeds to that time frame. The switch over is to be as quick as possible to maintain orderly running of the facility.

2. Question: Electricity - Are we to use existing electrical hook ups and are there any changes to be made electrically?

Answer: Yes, you are to use existing hookup and this will basically just be a switch out of the existing tank and tie in of new tank to the existing electricity that is already in place.

3. Question: Tie in for temporary DA Tank - The question was posed about a tie in for temporary DA tank.

Answer: Yes. A temporary Tie in is required and that it would be the responsibility of the contractor as stated in the statement of work.

4. Question: There was a question posed about a vent valve vs. a fixed orifice.

Answer: In the drawing it is a valve not a fixed orifice.

5. Question: About chemical injection points.

Answer: Chemical injection points will be on both ends below the water line as per drawings.

END OF CLARIFICATION