Site Visit Minutes for MTA Building.pdf

PDF 45 KB Posted

Attached to
Masonry Repairs to the Former MTA Building for the Metropolitan Correctional Center (MCC) New York, NY
Solicitation number
IFBP02101100001
Issued by

View the file

Other files

File Type Posted
BidResultsMTAbuildingNYM.pdf PDF
RFI1.pdf PDF
Amendment2att1.PDF PDF
Amendment2att2.PDF PDF
Amendment2.PDF PDF
Amendment1.PDF PDF
New Compressed —
Solicitation.pdf PDF
CoverLetterBricksNYMoct2010.pdf PDF
wagerates.PDF PDF
SOW.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Visit Minutes MCC New York, NY

MTA Building at MCC New York

IFBP02101100001

November 30, 2010

On November 30, 2010, a site visit was conducted by Janice Peterson, Contracting Specialist, at FCI Fort Dix, New Jersey. The visit was conducted in an informal forum which consisted of a short meeting between staff and the contractors, followed by a guided tour of the MTA building.

Janice Peterson opened the meeting introducing herself as the person who will be administrating the contract. She introduced the Supervisory of Contracting (Lorraine Fauntleroy). The Contract Monitor will be Pat Nicholson. The following individuals were in attendance:

Janice Peterson, Contract Specialist, FCI Fort Dix Lorraine Fauntleroy, Supervisory Contract Specialist, FCI, Fort Dix Samuel Yeagley, Communication Tech, MCC New York Carol Brown, GM Foreman, MCC New York Christine Montonna, Associate Warden, MCC New York Mikeljan Agolli, NJK Contractors Nevzat Agolli, NJK Contractors Masood Bhutta, Sasco Builders Inc.

Alex Gan, Minmas Construction Corp.

Anastasia Austin, Magwood Services Inc.

Witold Szapek, V-Tech Enterprises

The site visit meeting commenced at 10:20 a.m. at the Wardens Conference Room.

Ms. Peterson began speaking to all contractors on the purpose of the meeting. She informed the contractors that this site visit is being held to familiarize the bidders with the Bureau of Prisons policies and procedures to be observed during the performance of the work; establish preliminary schedules, lines of communication and operational procedures; develop mutual understanding concerning administration of the contract; and introduce personnel associated with this project, their authority, functions, and responsibilities. It should also be noted that anything discovered or discussed at this site/pre-bid conference shall not change or alter the specifications, drawings or solicitation. Any changes will be issued by a written formal amendment. Furthermore, there is a cut-off date of Dec 2, 2010, for all questions concerning the solicitation, specs/drawings.

This should give the Government ample time to post them along with answers on www.fedbizopps.gov prior to bid opening. All questions can be faxed to Robert J. Kruskie at

(570) 547-0373 or e-mailed to rkruskie@bop.gov E-mail is the preferred method for questions.

Currently, the due date for bids is December 15, 2010, 2:00 p.m. East Coast Time (local time).

Bid opening will be conducted at the Federal Correctional Complex (FCC Allenwood Training Center, Route 15 - 2 miles north of Allenwood, Allenwood, PA 17810. Hand carried bids will be accepted up until bid opening. Facsimile bids will not be accepted. In addition to the requirements stated in the solicitation, the contractor must be registered at www.ccr.gov and complete the online representations and certifications applications (ORCA) website at mailto:rkruskie@bop.gov http://orca.bpn.gov prior to award.

Identity and Authority of Official Representatives:

C Contracting Officer - Ms. Peterson. The contracting officer has the authority to enter into, administer, and/or terminate contractual actions on behalf of the United States, this includes her duly appointed successor.

C CM - Contract Monitor - Mr. Pat Nicholson - this is the representative of the Federal Bureau of Prisons, located at the construction site, who has overall responsibility (except or contractual matters) for the administration of operation and activity at the project site.

A copy of all written correspondence must be sent to all parties.

Facilities, Carol Brown covered access to the site, working hours, Institution gate/tool policy, Construction Material Storage, Institution Code of Conduct, Tool Storage for Employees, Testing requirements, Provisions for removal of trash, Utilities, Safety/Sanitation, Escort of Contractor personnel, NCIC Requirements, and parking space.

Access to the site:

The project site will be opened to the contractors 5 days per week, Monday Through Friday, excluding Federal Holidays.

Working Hours:

The contractor will check in for work at 7::00 am to 3:00 pm, Monday through Friday, except Federal Holidays. Please note, although you are at work at 7:00 am, you will not begin work until every one is cleared to enter the institution. Allow at least 40 to 45 minutes for out processing every day. The contractor shall establish a work week schedule for the duration of the project. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer and/or CM. During a emergency situation, no work will be allowed.

Construction Material Storage:

1.) All materials will be stored at the construction site, unless prior approval is granted by the CM. Some materials can be stored at the MTA Building.

2.) The contractor is responsible for site security and storage of all construction materials and equipment.

Tool Storage for Employees:

Tools will be stored in a lock gang box, which will be supplied by the contractor, or removed nightly from the construction site. Copies of any keys to locks will be given to the CM/Locksmith. All tools will be put on a tool list for inventory. The Captain will make the determination of what can be left in a gang box in the mechanical rooms.

Institution Code of Conduct:

1.) The contractor shall inform his employees that intoxicating beverages, drugs, and weapons, cell phones, recording equipment, radios, pagers and cameras are strictly prohibited.

2.) Introduction of contraband shall be subject to the penalties prescribed by Title 18 U.S.C.-

1791.

3.) No fraternizing with inmates. If you happen to know one personally, report it immediately to any Government staff or CM.

4.) No khakis will be worn by the contractors.

Provisions for removal of trash and debris:

1.) It is the contractor’s responsibility for removal of all trash and debris from the job site.

2.) An open top container will be provided by the contractor, if required, at a location coordinated with the CM.

Outline for Escorting Prospective Contractor's through site:

The contractor will be escorted while performing under this contract. The contractor will submit to the CM a list of employees and types of equipment the contractor will be utilizing on a daily basis. The CM will coordinate all escorts.

NCIC Requirements:

1.) In order for your employees to work on the job site they have to be NCIC cleared.

2.) Forms will be handed out to the contractor.

3.) It will take a minimum of 72 hours for an employee to be NCIC approved. Once approved the contractor will be immediately notified by the CM. Any of the contractor’s employees not cleared by NCIC will not be allowed on the premises.

Once employees are cleared, there is a 4 hour contractor course they must attend in order to obtain a badge to enter the institution. The cost of the time related to this course is the responsibility of the contractor.

The Captain has the final say on all individuals entering the institution. If an employee is denied no reason will be given. Denial does not mean the individual has a criminal history, it could be a multitude of reasons (ie. Relative in institution).

Parking Space: There are no reserved parking spaces. Contractor is responsible for parking their own vehicles and must obey all parking laws, we are not exempt.

Other Information:

OSHA - Even on Federal sites OSHA applies. In addition you will have inmates watching you and they have been known to call OSHA and report unsafe conditions. Make sure all your employees obey all applicable laws & rules.

Please ensure to tell your sub-contractors and delivery personnel of the NCIC requirements/All procedures. It is your responsibility.

Before concluding the meeting, Janice Peterson, Contracting Officer asked the contractors was there any questions. She also informed the contractors that all bids are due December 15, 2010.

Note; these minutes are provided for informational purposes only and any changes made to the solicitation shall be made by formal amendment.

Janice Peterson, Contract Specialist, FCI Ft. Dix Date