RFI1.pdf
PDF 29 KB Posted
- Attached to
- Masonry Repairs to the Former MTA Building for the Metropolitan Correctional Center (MCC) New York, NY
- Solicitation number
- IFBP02101100001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BidResultsMTAbuildingNYM.pdf | ||
| Amendment2att1.PDF | ||
| Amendment2att2.PDF | ||
| Amendment2.PDF | ||
| Site Visit Minutes for MTA Building.pdf | ||
| Amendment1.PDF | ||
| New Compressed | — | |
| Solicitation.pdf | ||
| CoverLetterBricksNYMoct2010.pdf | ||
| wagerates.PDF | ||
| SOW.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request For Information (RFI) 1
IFBP02101100001
Masonry Repairs on Former MTA Building MCC New York
1. Name of Company on Site Visit Minutes "Minmas" , should be corrected as " Minhas".
ANSWER: WE APOLOGIZE FOR THE TYPING ERROR; HOWEVER, THE MINUTES
HAVE BEEN POSTED AND WILL NOT BE CHANGED.
2. How material submittal process will work on this project?
Should be ALL submitals mailed to PA?
ANSWER: ALL SUBMITTALS SHOULD BE MAILED TO THE DESIGNATED ON-SITE
CONTRACT MONITOR AT OR AFTER THE PRE-CONSTRUCTION CONFERENCE.
3. The Sidewalk Bridge will be required (by NYC) to perform this work. So, will personal of MCC provide an assistance to coordinate (and specially with relocation of parking cars) with adjacent agencies?
ANSWER: THE BUREAU OF PRISONS WILL PROVIDE ASSISTANCE WITH
PARKING CONTROL ON CARDINAL HAYES PLACE.
4. Should Contractor Provide a Security Guard (including booth) while sidewalk bridge erected, to avoid any intrusion in the building?
ANSWER: NO SECURITY GUARD WILL BE REQUIRED.
5. Corner Replacement: Should contractor follow a regular 2' by 2' (return) Corner Replacement Detail ([http://source.nycsca.org/ae/aes/d04/dwgs/0452002a.pdf] http://source.nycsca.org/ae/aes/d04/dwgs/0452002a.pdf), including a control joint or just repair brick along the crack according standard Brick Stitching Repair Detail ([http://source.nycsca.org/ae/aes/d04/dwgs/0452000a.pdf] http://source.nycsca.org/ae/aes/d04/dwgs/0452000a.pdf)?
ANSWER: REPAIR BRICK ALONG CRACKS ACCORDING TO STANDARD BRICK
STITCHING REPAIR DETAIL.
6. Should we include in proposal a new stucco coating at highest portion of South Wall at Cardinal Hayes Place?
ANSWER: NO. THE WORK WILL BE LIMITED TO THE CURRENT STATEMENT OF
WORK.
7. Prior to F&I of new Metal Coping as per detail ([http://source.nycsca.org/ae/aes/d07/dwgs/0760014a.pdf] http://source.nycsca.org/ae/aes/d07/dwgs/0760014a.pdf )we remove and dispose existing concrete coping stone?
ANSWER: REMOVE AND DISPOSE OF EXISTING CONCRETE COPING STONE WHEN
NECESSARY TO MEET THE CURRENT STATEMENT OF WORK.
8. Should we considered to provide a temporary fencing (as per NYC) for material storage and portable bathroom at Park Row Side?
ANSWER: FOLLOW ALL LOCAL CODES AND GUIDELINES.