This is an Invitation for Bid (IFB) document issued by the Missouri Department of Transportation (MoDOT) Central District for Cold Mix/PreMix material. The solicitation number is IFB605CD19002255 with bid responses accepted from April 4, 2019 through April 11, 2019 at 2:00:00 PM CDT. The contract requires delivery of 700 tons of Cold Mix/PreMix material each to two locations: the Fayette Maintenance Building and the Boonville Maintenance Building. All deliveries must be completed by June 1, 2019, with minimum delivery quantities of 500 tons per day during normal business hours Monday through Thursday between 7:00 AM and 4:00 PM. The contract period runs from Notice to Proceed until June 1, 2019.
Pricing must include all delivery costs FOB destination, with freight costs included in the unit bid price. Vendors must submit a bid bond, certified check, cashier's check or bank money order for 5% of the bid amount, followed by a 100% performance bond if awarded. MoDOT encourages 10% MBE and 5% WBE participation. The agency reserves the right to increase or decrease quantities, with final quantities to be furnished at the unit price bid. Liquidated damages of $500 per day per item will be assessed for late deliveries. Invoicing must be completed by June 6, 2019, with payment terms net 30 days.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number: IFB605CD19002255
Cold Mix / PreMix
MoDOT Invitation to Bid (IFBR)
MoDOT - CD
April 04, 2019 - April 11, 2019
Page:2
General Header Information
IFB605CD19002255
No. IFB605CD19002255 Title: Cold Mix / PreMix Start Date: April 04, 2019 at 11:00:00 AM CDT End Date: April 11, 2019 at 2:00:00 PM CDT Vendor Q&A Start Date:
Vendor Q&A End Date:
Estimated Total Value:
Who can respond to this bid? : All Vendors Description: The Missouri Department of Transportation, Central District is seeking bids for Cold Mix / PreMix material.
ATTENTION VENDORS: You must be a registered MissouriBUYS vendor to review all terms and conditions of this solicitation. Visit https://missouribuys.mo.gov/registration.html to obtain full access.
Delivery Terms: Free On Board Destination Payment Terms: Net 30 Days Contact Information: MoDOT - CD
Sheldon Redel 1511 Missouri Blvd Jefferson City, MO 65102 Tel: 573-751-7708
Contact Details: If you have any questions, please contact:
Sheldon Redel 1511 Missouri Blvd Jefferson City, MO 65102 Tel: 573-751-7708
Selected Categories:
Page:3
Header Custom Fields:
IFB605CD19002255
NOTICE
Vendor Responsibility
The vendor is solely responsible for ensuring timely submission of their solicitation response, whether submitting an online response or a hard copy response. Failure to allow adequate time prior to the solicitation end date to complete and submit a response to a solicitation, particularly in the event technical support assistance is required, places the vendor and their response at risk of not being accepted on time.
The State of Missouri's Privacy Policy can be accessed here.
MODOT Section Numbering
Section Numbering All section numbering contained in this solicitation is for the convenience of reference only and is not intended to define or limit the scope of any provision of this solicitation and may not be sequential.
http://www.mo.gov/privacy-policy/
Page:4
Solicitation Requirements:
IFB605CD19002255
MoDOT Instructions for Submitting a Response
Instructions for Submitting a Response
Page:5
The Missouri Department of Transportation is now posting all of its bid solicitation documents on the new
MissouriBUYS Bid Board (https://www.missouribuys.mo.gov). MissouriBUYS is the State of Missouri’s web-based statewide eProcurement system which is powered by WebProcure, through our partner, Perfect
Commerce.
For all bid solicitations, vendors now have the option of submitting their solicitation response either as an electronic response or as a hard copy response. As a means to save vendors the expense of submitting a hard copy response and to provide vendors both the ease and the timeliness of responding from a computer, vendors are encouraged to submit an electronic response. Both methods of submission are explained briefly below and in more detail in the step-by-step instructions provided at https://missouribuys.mo.gov/sites/missouribuys/files/How_To_Respond_To_A_Solicitation.pdf
Notice: The vendor is solely responsible for ensuring timely submission of their solicitation response, whether submitting an online response or a hard copy response. Failure to allow adequate time prior to the solicitation end date to complete and submit a response to a solicitation, particularly in the event technical support assistance is required, places the vendor and their response at risk of not being accepted on time.
• ELECTRONIC RESPONSES: To respond electronically to a solicitation, the vendor must first register with MissouriBUYS by going to the MissouriBUYS Home Page (https://missouribuys.mo.gov), clicking the
“Register” button at the top of the page, and completing the Vendor Registration. Once registered the vendor should log back into MissouriBUYS and edit their profile by selecting the organizational contact(s) that should receive an automated confirmation of the vendor’s electronic bid responses successfully submitted to the state.
To respond electronically to a solicitation, the vendor must login to MissouriBUYS, locate the desired solicitation on the Bid Board, and, at a minimum, the vendor must read and accept the Original Solicitation
Documents and complete pricing and any other identified requirements. In addition, the vendor should download and save all of the Original Solicitation Documents on their computer so that they can prepare their response to these documents. Vendors should upload their completed response to these downloaded documents (including exhibits, forms, and other information concerning the solicitation) as an attachment to the electronic solicitation response. Step-by-step instructions for how a registered vendor responds to a solicitation electronically are available on the MissouriBUYS system at:
https://missouribuys.mo.gov/sites/missouribuys/files/How_To_Respond_To_A_Solicitation.pdf
Vendors are encouraged to submit their entire proposal electronically; however in lieu of attaching exhibits, forms, pricing, etc. to the electronic solicitation response, a vendor may submit the exhibits, forms, pricing, etc. through mail or courier service. However, any such submission must be received prior to the solicitation’s specified end date and time. Be sure to include the solicitation/opportunity (OPP) number, company name, and a contact name on any hard copy solicitation response documents submitted through mail or courier service.
In the event a registered vendor electronically submits a solicitation response and also mails hard copy documents that are not identical, the vendor should explain which response is valid for the state's consideration. In the absence of such explanation, the state reserves the right to evaluate and award the response which serves its best interest.
https://www.missouribuys.mo.gov https://missouribuys.mo.gov/sites/missouribuys/files/How_To_Respond_To_A_Solicitation.pdf https://missouribuys.mo.gov https://missouribuys.mo.gov/sites/missouribuys/files/How_To_Respond_To_A_Solicitation.pdf
Page:6
Addendum Document: If an addendum document is subsequently issued, please follow these steps to accept the addendum document(s).
1. If you have not accepted the original solicitation document go to the Overview page, find the section titled, Original Solicitation Documents, review the solicitation document(s) then click on the box under
Select, and then click on the Accept button.
2. To accept the addendum document, on the Overview page find the section titled Addendum Document, review the addendum document(s) then click on the box under Select, and then click on the Accept button.
Note: If you submitted an electronic response prior to the addendum date and time, you should review your solicitation response to ensure that it is still valid by taking into consideration the revisions addressed in the addendum document. If a revision is needed to your solicitation response and/or to indicate your acceptance of the addendum document, you will need to retract your response and re-submit your response by following these steps:
1. Log into MissouriBUYS.
2. Select the Solicitations tab.
3. Select View Current Solicitations.
4. Select My List.
5. Select the correct Opportunity Number (Opportunity No); the Overview page will display.
6. Click on Review Response from the navigation bar.
7. Click on Retract if your response needs to be revised.
8. A message will come up asking, “Are you sure you want to retract the Bid”. Click on Continue to confirm.
9. Click on Respond and revise as applicable.
10. Click on Review Response from the navigation bar and then click on Submit to submit your response.
• HARD COPY RESPONSES: Be sure to include the solicitation/opportunity (OPP) number, company name, and a contact name on any hard copy solicitation response documents.
MoDOT STANDARD SOLICITATION PROVISIONS
1.1. Standard Provisions
The solicitation for the procurement of the supplies referenced therein, to which these Standard Bid
Provisions, General Terms and Conditions and Special Terms and Conditions, is being issued under, and governed by, the provisions of Title 7 - Missouri Department of Transportation, Division 10, Missouri
Highways and Transportation Commission, Chapter 11- Procurement of Supplies, of the Code of State
Regulations. The Missouri Highways and Transportation Commission (MHTC), acting by and through its operating arm, the Missouri Department of Transportation (MoDOT), draws the Bidders attention to said 7
CSR 10-11 for all the provisions governing solicitation and receipt of bids/quotes and the award of the contract pursuant to this solicitation.
1.2 Standard Provisions
Page:7
All bids/quotes must be submitted by a responsible officer or employee of the firm. Obligations assumed by such submission must be fulfilled.
1.3 Standard Provisions
Work is to be performed under the general supervision and direction of MoDOT and, if awarded any portion of the work, the Contractor agrees to furnish at his/her own expense all labor and equipment required to complete the work, it being expressly understood that this solicitation is for completed work based upon the price(s) specified according to the requirements and specifications detailed within the solicitation documents.
MoDOT IFB GENERAL TERMS AND CONDITIONS
2.1 Definitions
Capitalized terms as well as other terms used but not defined herein shall have the meaning assigned to them in section 7 CSR 10-11.010 Definition of Terms. Whenever the following words and expressions appear in an Invitation for Bid (IFB) document or any addendum thereto, the definition or meaning described below shall apply.
2.1.1. Addendum means a written official modification to an IFB.
2.1.2. Amendment means a written official modification to a contract.
2.1.3. Attachment applies to all forms or documents which are included with an IFB to incorporate any informational data or requirements related to the performance requirements and/or specifications.
2.1.4. Bid end date and time and similar expressions mean the exact deadline required by the IFB for the receipt of bids.
2.1.5. Exhibit applies to forms which are included with an IFB for the vendor to complete and submit with the bid prior to the specified end date and time.
2.1.6. Invitation for Bid (IFB) means the solicitation document issued to potential vendors for the purchase of equipment, supplies, and/or services as described in the document. The definition includes these Terms and Conditions as well as all Pricing Pages, Exhibits, Attachments, and Addendums thereto.
2.1.7. May means a certain feature, component, or action is permissible, but not required.
2.1.8. Must means a certain feature, component, or action is a mandatory condition. Failure to provide or comply will result in a bid being considered non-responsive.
2.1.9. Pricing page(s) applies to the form(s) which the vendor must state the price(s) applicable for the equipment, supplies, and/or services required in the IFB. Pricing page(s) must be completed and submitted by the vendor with the bid response prior to the specified bid end date and time.
2.1.10. Revised Statutes of Missouri (RSMo) refers to the body of laws enacted by the Legislature which govern the operations of all agencies of the State of Missouri.
2.1.11. Shall has the same meaning as the word must.
2.1.12. Should means that a certain feature, component and/or action is desirable but not mandatory.
2.2 Nondiscrimination
Page:8
The Contractor shall comply with all state and federal statutes applicable to the Contractor relating to nondiscrimination, including, but not limited to, Chapter 213, RSMo; Title VI and Title VII of Civil
Rights Act of 1964 as amended (42 U.S.C. Sections 2000d and 2000e, et seq.); and with any provision of the Americans with Disabilities Act (42 U.S.C. Section 12101, et seq)..
2.2.1 Sanctions for Noncompliance: In the event of the Contractor's noncompliance with the nondiscrimination provisions of this contract, MHTC shall impose such contract sanctions as it or the Federal
Highway Administration may determine to be appropriate, including, but not limited to:
2.2.1.1 withholding of payments to the Contractor under the contract until the Contractor complies, and/or,
2.2.1.2 cancellation, termination or suspension of the contract, in whole or in part.
2.3 Contract/Purchase Order
By submitting a response, the Bidder agrees to furnish any and all equipment, supplies and/or services specified in the solicitation documents, at the prices quoted, pursuant to all requirements and specifications contained therein.
2.3.1. A binding contract shall consist of: (1) the solicitation documents, amendments thereto, and/or Best and Final Offer (BAFO) request(s) with any changes/additions, (2) the Contractor's bid response, and (3) the
MHTCs acceptance of the bid by post-award contract or purchase order.
2.3.2. A notice of award does not constitute an authorization for shipment of equipment or supplies or a directive to proceed with services. Before providing equipment, supplies and/or services, the Contractor must receive a properly authorized notice to proceed and/or purchase order
2.4 Applicable Laws and Regulations
The contract shall be construed according to the laws of the State of Missouri. The Contractor shall comply with all applicable local, state, and federal laws and regulations related to the performance of the contract. The exclusive venue for any legal proceeding relating to or arising, out of the contract shall be in the Circuit Court of Cole County, Missouri.
2.4.1. The Contractor must be registered and maintain good standing with the Secretary of State of the
State of Missouri, Missouri Department of Revenue, and other regulatory agencies, as may be required by law or regulations. Prior to the issuance of a purchase order and/or notice to proceed, the Contractor may be required to submit to MHTC a copy of their current Authority Certificate from the Secretary of State of the
State of Missouri and/or a copy of their Certificate of No Tax Due from the Missouri Department of Revenue.
2.4.2. Prior to the issuance of a purchase order and/or notice to proceed, all out-of-state Contractors providing services in the state of Missouri must submit to MHTC a copy of their current Transient Employer
Certificate from the Missouri Department of Revenue, and a current Certificate of Registration from the
Secretary of State of the state of Missouri.
2.5 Open Competition and IFB Document
Page:9
It shall be the vendor's responsibility to ask questions, request changes or clarification, or otherwise advise MoDOT if any language, specifications or requirements of an IFB appear to be ambiguous, contradictory, and/or arbitrary, or appear to inadvertently restrict or limit the requirements stated in the IFB to a single source. Any and all communication from vendors regarding specifications, requirements, competitive bid process, etc., must be directed to the IFB Contact, unless the IFB specifically refers the vendor to another contact. Such e-mail, fax, or phone communication should be received at least ten calendar days prior to the official bid end date.
2.5.1. Every attempt shall be made to ensure that the vendor receives an adequate and prompt response.
However, in order to maintain a fair and equitable bid process, all vendors will be advised, via the issuance of an addendum to the IFB, of any relevant or pertinent information related to the procurement. Therefore, vendors are advised that unless specified elsewhere in the IFB, any questions received less than ten calendar days prior to the IFB end date may not be answered.
2.5.2. Vendors are cautioned that the only official position of the MHTC is that which is issued in the IFB or an addendum thereto. No other means of communication, whether oral or written, shall be construed as a formal or official response or statement.
2.5.3. The IFB is available for viewing and downloading on the MissouriBUYS Statewide eProcurement
System. Registered vendors are electronically notified of those bid opportunities that match the commodity codes for which the vendor registered in MissouriBUYS. If a registered vendors e-mail address is incorrect, the vendor must update the e-mail address themselves on the state's MissouriBUYS Statewide eProcurement System at https://missouribuys.mo.gov/.
2.5.4. MoDOT reserves the right to officially amend or cancel an IFB after issuance. It shall be the sole responsibility of the vendor to monitor the MissouriBUYS Statewide eProcurement System to obtain a copy of the addendum(s). Registered vendors who received e-mail notification of the bid opportunity when the
IFB was established and registered vendors who have responded to the IFB on-line prior to an addendum being issued, should receive e-mail notification of the addendum(s). Registered vendors who received e-mail notification of the bid opportunity when the IFB was established and registered vendors who have responded to the bid on-line prior to a cancellation being issued, should receive e-mail notification of a cancellation issued prior to the exact end date and time specified in the IFB.
2.6 Preparation of Bids
https://missouribuys.mo.gov/
Page:10
Vendors must examine the entire IFB carefully. Failure to do so shall be at the vendor's risk.
2.6.1. Unless otherwise specifically stated in the IFB, all specifications and requirements constitute minimum requirements. All bids must meet or exceed the stated specifications and requirements.
2.6.2. Unless otherwise specifically stated in the IFB, any manufacturer names, trade names, brand names, information and/or catalog numbers listed in a specification and/or requirement are for informational purposes only and are not intended to limit competition. The vendor may offer any brand which meets or exceeds the specification for any item, but must state the manufacturer's name and model number for any such brands in the bid. In addition, the vendor shall explain, in detail, (1) the reasons why the proposed equivalent meets or exceeds the specifications and/or requirements and (2) why the proposed equivalent should not be considered an exception thereto. Bids which do not comply with the requirements and specifications are subject to rejection without clarification.
2.6.3. Bids lacking any indication of intent to bid an alternate brand or to take an exception shall be received and considered in complete compliance with the specifications and requirements as listed in the IFB.
2.6.4. In the event that the vendor is an agency of state government or other such political subdivision which is prohibited by law or court decision from complying with certain provisions of an IFB, such vendor may submit a bid which contains a list of statutory limitations and identification of those prohibitive clauses.
The vendor should include a complete list of statutory references and citations for each provision of the IFB, which is affected by this paragraph. The statutory limitations and prohibitive clauses may (1) be requested to be clarified in writing or (2) be accepted without further clarification if the statutory limitations and prohibitive clauses are deemed acceptable. If MHTC determines clarification of the statutory limitations and prohibitive clauses is necessary, the clarification will be conducted in order to agree to language that reflects the intent and compliance of such law and/or court order and the IFB.
2.6.5. All equipment and supplies offered in a bid must be new, of current production, and available for marketing by the manufacturer unless the IFB clearly specifies that used, reconditioned, or remanufactured equipment and supplies may be offered.
2.6.6. Prices shall include all packing, handling and shipping charges FOB destination, freight prepaid and allowed unless otherwise specified in the IFB.
2.6.7. Bids, including all pricing therein, shall remain valid for 90 days from bid opening unless otherwise indicated. If the bid is accepted, the entire bid, including all prices, shall be firm for the specified contract period.
2.6.8. Any foreign vendor not having an Employer Identification Number assigned by the United States
Internal Revenue Service (IRS) must submit a completed IRS Form W-8 prior to or with the submission of their bid in order to be considered for award.
2.7 Submission of Bids
Page:11
Registered vendors may submit bids electronically through the MissouriBUYS Statewide eProcurement System at https://missouribuys.mo.gov/ or by delivery of a hard copy to the Contact address shown on the Solicitation General Header Information. Vendors that have not registered on the MissouriBUYS Statewide eProcurement System may submit bids hard copy to the Contact address shown on the Solicitation General Header Information. Delivered bids must be sealed in an envelope or container, and received in the required location no later than the exact end date and time specified in the IFB. All bids must (1) be submitted by a duly authorized representative of the vendors organization, (2) contain all information required by the IFB, and (3) be priced as required. It shall be the responsibility of the vendor to ensure their bid is in the required location no later than the exact end date and time specified in the IFB.
2.7.1. The sealed envelope or container containing a bid should be clearly marked on the outside with (1) the official IFB number and (2) the official end date and time. Different bids should not be placed in the same envelope, although copies of the same bid may be placed in the same envelope.
2.7.2. A bid submitted electronically by a registered vendor may be modified on-line prior to the official end date and time. A bid which has been delivered to the Purchasing office may be modified by signed, written notice which has been received in the required location prior to the official end date and time specified. A bid may also be modified in person by the vendor or its authorized representative, provided proper identification is presented before the official end date and time. Telephone or telegraphic requests to modify a bid shall not be honored.
2.7.3. A bid submitted electronically by a registered vendor may be retracted on-line prior to the official end date and time. A bid which has been delivered to the required location may only be withdrawn by a signed, written document on company letterhead transmitted via mail, e-mail, or facsimile which has been received at the required location prior to the official end date and time specified. A bid may also be withdrawn in person by the vendor or its authorized representative, provided proper identification is presented before the official end date and time. Telephone or telegraphic requests to withdraw a bid shall not be honored.
2.7.4. A bid may also be withdrawn after the bid opening through submission of a written request by an authorized representative of the vendor. Justification of withdrawal decision may include a significant error or exposure of bid information that may cause irreparable harm to the vendor.
2.7.5. When submitting a bid electronically, the registered vendor indicates acceptance of all IFB requirements, terms and conditions by clicking on the Review and Submit button on the Response Review tab.
2.7.6. Faxed bids shall not be accepted. However, faxed and e-mail no-bid notifications shall be accepted.
2.8 Bid Opening
Bid openings are public on the end date and at the opening time specified on the IFB document.
Names and prices of the respondents shall be read at the bid opening. All vendors may view the same bid response information on the MissouriBUYS Statewide eProcurement System. Purchasing will not provide prices or other bid information via the telephone.
2.8.1. Bids which are not received in the Purchasing office prior to the official end date and time shall be considered late, regardless of the degree of lateness, and normally will not be opened.
https://missouribuys.mo.gov/
Page:12
2.9 Evaluation and Award
Page:13
Any clerical error, apparent on its face, may be corrected by the buyer before contract award. Upon discovering an apparent clerical error, the buyer shall contact the vendor and request clarification of the intended bid. The correction shall be incorporated in the notice of award. Examples of apparent clerical errors are: 1) misplacement of a decimal point; and 2) obvious mistake in designation of unit.
2.9.1. Any pricing information submitted shall be subject to evaluation if deemed to be in the best interest of the MHTC.
2.9.2. The vendor is encouraged to propose price discounts for prompt payment or propose other price discounts that would benefit the MHTC. However, unless otherwise specified in the IFB, pricing shall be evaluated at the maximum potential financial liability to the MHTC.
2.9.3. Awards shall be made to the vendor whose bid (1) complies with all mandatory specifications and requirements of the IFB and (2) is the lowest and best bid, considering price, responsibility of the vendor, and all other evaluation criteria specified in the IFB and (3) complies with all applicable Missouri statutes and Executive Orders.
2.9.4. In the event all vendors fail to meet the same mandatory requirement in an IFB, MHTC reserves the right, at its sole discretion, to waive that requirement for all vendors and to proceed with the evaluation. In addition, MHTC reserves the right to waive any minor irregularity or technicality found in any individual bid.
2.9.5. MHTC reserves the right to reject any and all bids. When all bids are non-responsive or otherwise unacceptable and circumstances do not permit a rebid, MHTC may negotiate for the required supplies.
2.9.6. When evaluating a bid, the MHTC reserves the right to consider relevant information and fact, whether gained from a bid, from a vendor, from vendor references, or from any other source.
2.9.7. Any information submitted with the bid, regardless of the format or placement of such information, may be considered in making decisions related to the responsiveness and merit of a bid and the award of a contract.
2.9.8. Any award of a contract shall be made by notification to the successful vendor. MHTC reserves the right to make awards by item, group of items, or an all or none basis unless otherwise identified in the solicitation. The grouping of items awarded shall be determined based upon factors such as item similarity, location, administrative efficiency, or other considerations in the best interest of the MHTC.
2.9.9. All bids and associated documentation which were submitted on or before the official end date and time will be considered open records pursuant to section 610.021, RSMo, following the official opening of bids.
2.9.10. The MHTC posts all bid results on the MissouriBUYS Statewide eProcurement System website for all vendors to view for a reasonable period of time after bid award.
2.9.11. The MHTC reserves the right to request clarification of any portion of the vendor response in order to verify the intent of the vendor. The vendor is cautioned, however, that its response may be subject to acceptance or rejection without further clarification.
2.9.12. Any bid award protest must be received within ten (10) business days after the date of award in accordance with the requirements of 7 CSR 10-11.020 (9).
Page:14
2.9.13. The final determination of contract award(s) shall be made by the MHTC.
2.10 Executive Order
The Contractor shall comply with all the provisions of Executive Order 07-13, issued by the
Honorable Matt Blunt, Governor of Missouri, on the sixth (6th) day of March, 2007. This Executive
Order, which promulgates the State of Missouri's position to not tolerate persons who contract with the state engaging in or supporting illegal activities of employing individuals who are not eligible to work in the United States, is incorporated herein by reference and made a part of this Agreement.
2.10.1. The Contractor hereby certifies that any employee of the Contractor assigned to perform services under the contract is eligible and authorized to work in the United States in compliance with federal law.
2.10.2. In the event the Contractor fails to comply with the provisions of the Executive Order 07-13, or in the event the Commission has reasonable cause to believe that the contractor has knowingly employed individuals who are not eligible to work in the United States in violation of federal law, the Commission reserves the right to impose such contract sanctions as it may determine to be appropriate, including but not limited to contract cancellation, termination or suspension in whole or in part or both.
2.10.3. The Contractor shall include the provisions of this paragraph in every subcontract. The Contractor shall take such action with respect to any subcontract as the Commission may direct as a means of enforcing such provisions, including sanctions for noncompliance.
2.11 Preferences
In the evaluation of bids/quotes, preferences shall be applied in accordance with 7 CSR 10-
11.020(7). Contractors should apply the same preferences in selecting subcontractors.
2.11.1. Bidders are encouraged to obtain minority business enterprise (MBE) and women business enterprise (WBE) participation in this work through the use of subcontractors, suppliers, joint ventures, or other arrangements that afford meaningful participation for M/WBEs. Bidders are encouraged to obtain 10%
MBE and 5% WBE participation.
2.12 Cancellation of Contract
The MHTC may cancel the Contract at any time for a material breach of contractual obligations or for convenience by providing Contractor with written notice of cancellation. Should the MHTC exercise its right to cancel the contract for such reasons, cancellation will become effective upon the date specified in the notice of cancellation sent to the Contractor.
2.13 Bankruptcy or Insolvency
Upon filing for any bankruptcy or insolvency proceeding by or against the Contractor, whether voluntarily, or upon the appointment of a receiver, trustee, or assignee, for the benefit of creditors, the Commission reserves the right and sole discretion to either cancel the Agreement or affirm the Agreement and hold the
Contractor responsible for damages.
2.14 Warranty
Page:15
The Contractor expressly warrants that all equipment, supplies, and/or services provided shall: (1) conform to each and every specification, drawing, sample or other description which was furnished to or adopted by the MHTC, (2) be fit and sufficient for the purpose expressed in the solicitation documents, (3) be merchantable, (4) be of good materials and workmanship, and (5) be free from defect. Such warranty shall survive delivery and shall not be deemed waived either by reason of the MHTC's acceptance of or payment for said equipment, supplies, and/or services.
2.15 Status of Independent Contractor
The Contractor represents itself to be an independent Contractor offering such services to the general public and shall not represent itself or its employees to be an employee of the MHTC. Therefore, the Contractor shall assume all legal and financial responsibility for taxes, FICA, employee fringe benefits, workers compensation, employee insurance, minimum wage requirements, overtime, etc., and agrees to indemnify, save and hold the MHTC, its officers, agents and employees harmless from and against any and all losses
(including attorney fees) and damage of any kind related to such matters.
2.16 Non-Waiver
If one of the parties agrees to waive its right to enforce any term of this Contract, that party does not waive its right to enforce such term at any other time or to enforce any or all other terms of this Contract.
2.17 Indemnification
The Contractor shall defend, indemnify and hold harmless MHTC, including its members and department employees, from any claim or liability whether based on a claim for damages to real or personal property or to a person for any matter relating to or arising out of the Contractor's performance of its obligations under the contract awarded pursuant to this solicitation.
2.18 Right of Acceptance and/or Rejection
MoDOT reserves the right to reject any responses, and to accept or reject any items thereon, and to waive technicalities. In case of error in the extension of prices in the response, unit prices will govern.
2.19 Inspection and Acceptance
No equipment, supplies, and/or services received by MoDOT pursuant to a contract shall be deemed accepted until MoDOT has had reasonable opportunity to inspect said equipment, supplies, and/or services.
2.19.1. All equipment, supplies, and/or services which do not comply with the specifications and/or requirements or which are otherwise unacceptable or defective may be rejected. In addition, all equipment, supplies, and/or services which are discovered to be defective or which do not conform to any warranty of the contractor upon inspection (or at any later time if the defects contained were not reasonably ascertainable upon the initial inspection) may be rejected.
2.19.2. The MHTC reserves the right to return any such rejected shipment at the contractor's expense for full credit or replacement and to specify a reasonable date by which replacements must be received.
2.19.3. The MHTCs right to reject any unacceptable equipment, supplies, and/or services shall not exclude any other legal, equitable or contractual remedies the MHTC may have.
2.20 Invoicing and Payment
Page:16
The statewide financial management system has been designed to capture certain receipt and payment information. For each purchase order received, an invoice must be submitted that references the purchase order number and must be itemized in accordance with items listed on the purchase order. Failure to comply with this requirement may delay processing of invoices for payment.
2.20.1. The contractor shall not transfer any interest in the contract, whether by assignment or otherwise, without the prior written consent of the MHTC.
2.20.2. Payment for all equipment, supplies, and/or services required herein shall be made in arrears unless otherwise indicated in the IFB.
2.20.3 The MHTC assumes no obligation for equipment, supplies, and/or services shipped or provided in excess of the quantity ordered. Any unauthorized quantity is subject to the state's rejection and shall be returned at the contractor's expense.
2.20.4. The State of Missouri reserves the right to purchase goods and services using the state purchasing card.
2.21 Conflict of Interest
Elected or appointed officials or employees of the State of Missouri or any political subdivision thereof, serving in an executive or administrative capacity, must comply with sections 105.452 and
105.454, RSMo, regarding conflict of interest.
2.21.1. The contractor hereby covenants that at the time of the submission of the bid the contractor has no other contractual relationships which would create any actual or perceived conflict of interest. The contractor further agrees that during the term of the contract neither the contractor nor any of its employees shall acquire any other contractual relationships which create such a conflict.
2.22 Tax Exempt Status
MHTC is exempt from paying Missouri Sales Tax, Missouri Use Tax and Federal Excise Tax. However, the
Contractor may themselves be responsible for the payment of taxes on materials they purchase to fulfill the contract.
MoDOT IFB SPECIAL TERMS AND CONDITIONS
3.2 Bid Guaranty/Contract Bond
Page:17
Each bid shall be accompanied by one of the following: a Bid Bond, Certified Check, Cashier's Check, or
Bank Money Order payable to Director of Revenue - Credit State Road Fund for an amount equal to Five
Percent (5%) of the amount of the bid submitted. This is to act as a guarantee that the bidder, if awarded the contract, will furnish an acceptable performance and payment bond (Contract Bond) or a cashier's check, a bank money order or a certified check made payable to "Director of Revenue - Credit State Road
Fund" in an amount equal to One Hundred Percent (100%) of the contract price. Vendors submitting an electronic response must attach a COPY of the Bid Bond, Certified Check, Cashier's Check or Bank Money
Order to the electronic bid response along with proof the bond instrument has been mailed to the bid contact prior to the bid deadline date and time. Failure to receive the ORIGINAL hardcopy bond instrument within
FIVE (5) calendar days of bid opening, may render the bid as non-responsive.
3.2.1. If a BID BOND is used (in lieu of a certified check, cashier's check, or bank money order), it must be in the form provided and executed by the bidder as principal and by a surety company authorized to do business in the State of Missouri as surety. The agent executing the same on behalf of the surety company must attach a current Power of Attorney setting forth his authority to execute the bond involved.
3.2.2. Certified Checks, Cashier's Checks or Bank Money Orders of unsuccessful bidders will be returned upon execution of the awarded contract. The checks or bank money orders of the successful bidder(s) will be retained until the contract is executed and a satisfactory Performance and Payment (Contract Bond) is furnished. Bid Bonds will not be returned except on specific request of the bidder.
3.2.3. Failure to execute the contract and file acceptable performance payment (Contract Bond) or cashier's check, bank money order or certified check within 15 days after the contract has been transmitted to the bidder shall be just cause for the cancellation of the award and the forfeiture of the proposal guaranty.
Award may then be made to the next lowest responsible bidder, or the work may be re-advertised and performed under contract or otherwise, as the Commission may decide. No contract shall be considered effective until it has been executed by all parties thereto.
3.3 Subcontracting
It is specifically understood that no portion of the material or any interest in the contract, shall be subcontracted, transferred, assigned or otherwise disposed of, except with the written consent of MHTC.
Request for permission to subcontract or otherwise dispose of any part of the work shall be in writing to
MHTC and accompanied by documentation showing that the organization which will perform the work is particularly experienced and equipped for such work.
3.3.1. Consent to subcontract or otherwise dispose of any portion of the work shall not be construed to relieve the Contractor of any responsibility for the production and delivery of the contracted work and the completion of the work within the specified time.
3.3.2. All payments for work performed by a subcontractor shall be made to the Contractor to whom the contract was awarded and the purchase order issued.
3.7 Permits, Licenses and Safety Issues
The contract price shall include any necessary permits and licenses required by law incidental to the work.
Local ordinances requiring building permits are not applicable to state agencies.
3.8 Delivery-Additional Requirements
Page:18
The Contractor shall furnish the Missouri Department of Transportation with a planned delivery schedule at least 2 Business Days before starting delivery.
3.8.1. Notification should be during the normal workday preceding the day on which the Contractor desires to initiate delivery.
3.8.2. A representative of the Missouri Department of Transportation must be present when items are delivered.
3.8.3. No material will be accepted that has been dumped in the absence of the department representative.
3.8.4. Unless otherwise specified, deliveries will be a minimum of 500 Tons Per Day. No deliveries will be made during the period from 30 minutes before sundown to sunrise. No deliveries will be made on
Saturdays, Sundays and holidays unless specifically authorized by the department representative.
3.8.5. The following days shall be construed as official holidays under the terms of the contract:
3.8.5.1. January 1 - New Year's Day
3.8.5.2. Third Monday in January - Martin Luther King, Jr.s Birthday
3.8.5.3. February 12-Lincoln's Birthday
3.8.5.4. Third Monday in February - Washington's Birthday
3.8.5.5. May 8 - Truman's Birthday
3.8.5.6. Last Monday in May-Memorial Day
3.8.5.7. July 4 - Independence Day
3.8.5.8. First Monday in September - Labor Day
3.8.5.9. Second Monday in October-Columbus Day
3.8.5.10. November 11 - Veteran's Day
3.8.5.11. Fourth Thursday in November - Thanksgiving Day
3.8.5.12. December 25 - Christmas Day
3.8.6. When any of the above holidays falls on a Sunday, the holiday will be observed on the following
Monday; when any of the above holidays falls on a Saturday, the holiday will be observed on the immediately preceding Friday.
3.8.7. Contractor will not be required to provide dozers, loaders, motor graders, or other equipment for shaping of stockpiles, constructing ramps or runways, or leveling of the top of a completed lift, unless otherwise noted herein.
3.8.8. During construction/maintenance seasons, many maintenance buildings work four day, ten hour shifts and deliveries may not be made on the off days for those buildings.
3.9 Temporary Suspension of Work
Page:19
Any authorized department representative shall have authority to suspend work wholly or in part for such period or periods as may be deemed necessary when weather or other conditions are such that in the opinion of the department representative, the work may be done at a later time with advantage to MoDOT or for failure on the part of the Contractor to comply with any of the provisions of the Contract.
3.9.1. If MoDOT suspends the work for its own advantages and not because of the Contractor's failure to comply with the Contract, the Contractor will be allowed an equal number of calendar days after the completion date for the completion of the work. MoDOT may at its discretion give the Contractor an extension of time for completing the work where the Contractor incurs delays for causes beyond his control.
3.9.2. Normal rainfall is not considered a cause qualifying for an extension of time. Claim for extension of time for all causes must be submitted by the Contractor in writing within 30 Days after the claimed cause for the delay has ceased to exist.
3.11 Liquidated Damages
In the event the successful Contractor fails to deliver the material within the time specified, the Department and the public will sustain damages because of such delay in delivery, the exact extent of which would be difficult to ascertain, and in order to liquidate such damage in advance it is agreed that the sum of $500.00 per day, per item, for each assessable calendar day on which the delivery has not been completed, is reasonable and the best estimate which the parties can arrive at as liquidated damages, and it is therefore agreed that said amount will be withheld from payments due the Contractor or otherwise collected from the
Contractor as liquidated damages.
3.11.1 Saturdays, Sundays, holidays and days whereas the Department has suspended work shall not be assessable days.
3.14 Increase or Decrease Quantities
The quantities listed are MoDOT's best estimate of needs at the time of the solicitation posting. MoDOT reserves the right to increase or decrease quantities. The final quantity ordered by MoDOT shall be furnished at the unit price bid.
Required Specifications
4.1 Required Specifications
Page:20
4.1.1 The Contractor shall provide MoDOT with Cold Mix/Pre-Mix Material.
4.1.2 All Material must meet specifications as described in sections 401 through 402 of the 2017
Missouri Standard Specifications for Highway Construction and any revisions thereto.
4.1.3 MoDOT may request samples from the apparent low bidder(s) prior to award. Samples will be tested for adherence to the listed specifications.
4.1.4 Ticket Requirements:
a. The Contractor's printer shall be capable of keeping and printing cumulative totals for each item number in the contract. The Contractor shall produce a ticket to accompany each truckload and shall be furnished to the MoDOT representative. The ticket shall show the following:
Gross, tare and net weights (masses)
Identification of the vehicles
Current date and time
MoDOT's purchase order number
Unique ticket number (may be pre-printed on the ticket)
Item, specification designation and location
4.2 Delivery Requirements
4.2.1 Prices shall include the delivery cost of the material; the Contractor agrees to pay all transportation charges on the material for FOB - Destination. Freight costs must be included in the unit price bid.
4.2.2 All deliveries must be complete by June 1, 2019.
4.2.3 Deliveries will be accepted Monday - Thursday 7:00 a.m. - 4:00 p.m. Unless other arrangements are made with the maintenancne supervisor. A minumu of 500 tons shall be delivered per day.
4.2.4 Deliveries many begin following the Notice to Proceed.
4.3 Invoicing and Payment Requirements
4.3.1 The Contractor shall submit an itemized invoice by June 6, 2019.
4.3.2 The invoices shall be itemized in accordance with items listed on the purchase order and/or contract.
4.3.3 The Contractor shall be paid in accordanace with the firm, fixed price stated on the pricing page of this bid after completion of the deliverables specificied herein and acceptance by MoDOT.
4.4 Contract Period
The contract shall commence from the date of Notice to Proceed unitl June 1, 2019.
Page:21
Page:22
Questionnaire:
IFB605CD19002255
Cooperative Procurement Description: The Missouri Department of Transportation (MoDOT) is interested in assisting Missouri counties, cities, special road districts, etc. in purchasing equipment, various materials and supplies that meet the MoDOT specifications. It is understood MoDOT will not issue purchase orders, accept delivery nor make payment for these items ordered by any of these agencies. It is further understood the price is based on meeting the MoDOT specifications. Any added options, deletions, or extra freight costs would be negotiated between the local agency and the successful vendor. If the response is No to the first question, simply respond "N/A" in any additional required response fields below.
Is your firm willing to offer such cooperative purchasing for Missouri counties, cities or other political entities?
Type YES/NO Is Required Y
If the price varies throughout the state because of different delivery destinations, please indicate the price FOB Shipping Point.
Type TEXT Is Required Y
Indicate the deadline date orders will be accepted.
Type TEXT Is Required Y
M/WBE Participation Description: Bidders are encouraged to obtain minority business enterprise (MBE) and women business enterprise (WBE) participation in this work through the use of subcontractors, suppliers, joint ventures, or other arrangements that afford meaningful participation for M/WBEs. Bidders are encouraged to obtain 10% MBE and 5% WBE.
List all certified M/WBE vendors utilized in the fulfillment of this bid.
Include percentage of participation for subcontractors and identify the M/WBE certifying agency. If not applicable, enter N/A in the required field.
Type TEXT Is Required Y
SDV/E Preference
Page:23
Description: Service-Disabled Veteran (SDV) is defined as any individual who is disabled as certified by the appropriate federal agency responsible for the administration of veterans affairs. A Service- Disabled Veteran Business (SDVE) is defined as a business whereby not less than fifty-one (51) percent of which is owned by one or more service-disabled veterans or, in the case of any publicly owned business, not less than fifty-one (51) percent of the stock of which is owned by one or more service-disabled veterans; and the management and daily business operations of which are controlled by one or more service-disabled veterans.
List the names and addresses of an SDV or SDVE providing products or services in relation to this bid. If not applicable, enter N/A in the required field.
Type TEXT Is Required Y
Domestic Products Description: If any or all of the goods or products offered in the attached bid which the bidder proposes to supply to the MHTC are not manufactured or produced in the United States, or imported in accordance with a qualifying treaty, law, agreement, or regulation, list below, by item or item number, the country other than the United States where each good or product is manufactured or produced.
For all items offered which are not manufactured or produced in the USA, list the item number and location of where the item is manufactured or produced. If not applicable, enter N/A in the required field.
Type TEXT Is Required Y
Page:24
Documents:
Anti-Collusion and Bid Bond.docx
Affidavits - Exhibit A and B.pdf
Page:25
Item Specifications
No. Item Alternative Supplier Part No Mfr.
Name
Mfr. No Del
Date
Unit Unit Bid Qty. Total
1 Cold Mix / PreMix - Fayette
Maintenance ton (us);
or short ton
(uk/us);
700.00
Item Specification for Cold Mix / PreMix - Fayette Maintenance
Description: Cold Mix / PreMix delivered to the Fayette Maintenance Building
Delivery Address: 871 State Hwy 240
Fayette, MO 65248
Desired Delivery Date: Jun 01, 2019
Allow Vendor to Enter Negative Value : No
Exclude Line Item from Bid Total : No
2 Cold Mix / PreMix -
Boonville Maintenance ton (us);
or short ton
(uk/us);
700.00
Item Specification for Cold Mix / PreMix - Boonville Maintenance
Description: Cold Mix / PreMix delivered to the Boonville Maintenance building
Delivery Address: 16803 Hwy 5
Boonville, MO 65233
Desired Delivery Date: Jun 01, 2019
Allow Vendor to Enter Negative Value : No
Exclude Line Item from Bid Total : No