This Addendum #1 is issued by the Board of County Commissioners of Orange County, Florida for Invitation for Bid (IFB) Y24-193 regarding Primary Canal Mowing and Maintenance Services for Stormwater Management. The addendum addresses multiple vendor questions about the solicitation, clarifies contract details, and provides important procedural information. Key dates include a public bid opening on February 28, 2024 at 9:30 EST, with bid submissions due by February 29, 2024 at 4:00 PM EST. The contract appears to be for canal mowing services with an initial 12-month period and potential for two additional 12-month option years, with the potential for acreage variations due to canal additions or removals.
The addendum clarifies that option year contracts do not include price escalation provisions, and submitted pricing for each option year must remain firm. Vendors are required to provide references demonstrating at least 4,500 acres of maintenance experience, with ongoing jobs acceptable in client references. The work involves mowing approximately 73.45 acres, with a work plan to be submitted within 10 days of contract award. Contractors must remove grass clippings from pavement, fence lines, sidewalks, curbs, and curb inlets to maintain a neat appearance. The county also references Minority/Women Business Enterprise (M/WBE) participation requirements, which can be found in Section 5 of the solicitation documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB Y24-193
Addendum #1 Page 1 of 4
February 14, 2024
BOARD OF COUNTY COMMISSIONERS
ORANGE COUNTY, FLORIDA
IFB Y24-193-MM
PRIMARY CANAL MOWING AND MAINTENANCE SERVICES FOR STORMWATER
MANAGEMENT
ADDENDUM NO. 1
This Addendum is hereby incorporated into the bid documents of the project referenced above. The following items are clarifications, corrections, additions, deletions, and/or revisions to and shall take precedence over the original documents. Additions are indicated by underlining and deletions via strikethrough.
A. QUESTIONS AND ANSWERS
1. Question: Is the acreage on the current bid sheet accurate? I noticed that the previous contract had considerably lower acreage estimates? Also, is there a list of contracted locations for this bid?
Answer: The correct acreage estimate was provided to respondents, please refer to the Bid Response Form for the quantities . Yes, a list of locations was provided with the solicitation documents.
2. Question: I wanted to see if you could please let me know the contract number prior to this contract to see what the budget looks like for the project.
Answer: The current contract is Y21-156. Please use the link below to view current pricing and information.
Vendor Service Center: OrangeBids Term Contracts (ocfl.net)
3. Question: Please explain the increase in total estimated acreage by increments of 200 in the Bid Response forms over each optional year past the base year.
Answer: The specified locations could increase due to additions of new canals or decrease due to removal of canals.
4. Question: Please explain the 4,200-acre figure provided in the fee schedule for “Mowing as specified”. The estimate provided indicates 73.45 acres.
https://apps.ocfl.net/OrangeBids/Termcontracts/listtermcontract.asp
Addendum #1 Page 2 of 4
Answer: An addendum will be issued to correct the acreage in the fee schedule.
5. Question: Please explain the 600-acre figure provided in the fee schedule for “Additional Litter Removal, as specified”.
Answer: Please refer to the answer for question #4.
6. Question: Will a list of personnel be required with initial submittal or only upon award of the contract?
Answer: A list of personnel will be required upon award of the contract.
7. Question: Does the provided list of personnel titled Manpower for Canal Mowing (Item I of the Specifications/Scope of Services) serve as minimum personnel requirements?
Answer: Yes, however, quantities may need to be adjusted according to the amount of equipment to be used in the specific area.
8. Question: To what extent can proposed personnel deviate from the provided Manpower for Canal Mowing list?
Answer: Quantities may need to be adjusted according to the amount of equipment to be used in the specific area.
9. Question: 2.1. Award and Evaluation of Options: Will price escalation be allowed between the initial 12 month period and the two additional 12 month periods of the contract, pending County approval?
Answer: Option year contracts do not include a provision for price escalations.
The County requires that submitted pricing for each option year will hold firm.
Refer to Provision 6.6 Firm Pricing.
10. Question: 2.2. License, Certification and Authorization: Please provide a list of specific licenses required for this bid.
Answer: Please refer to Section 9, Bid Response Form, Item No. 1.2, Licenses, for details on license(s) applicable to the proposed work.
11. Question: 2.11. Acceptance/Rejection/Cancellation: Please provide the terms of award to non-lowest bidder or grading scale if utilized.
Addendum #1 Page 3 of 4
Answer: Please refer to Section 2, Solicitation Terms & Conditions, Award and Evaluation Options.
12. Question: 2.15. Bid Tabulation and Recommended Award: Please verify that the public bid opening for this solicitation will be held on February 28th, 2024 at 9:30 EST.
Answer: Yes, the current public bid opening for this solicitation will be held on February 28, 2024 at 9:30 EST. Be sure to check the OpenGov portal prior to this date for any forthcoming addenda or date change to the submission deadline and bid opening.
13. Question: 2.16: Can ongoing jobs be included in client references?
Answer: Yes, ongoing employment can be included in client references.
14. Question: 2.17. Posting of Recommended Award and Protests: Please confirm a deadline of March 5th, 2024 at 5:00 PM EST for filing protest of award.
Answer: Please refer to the Protest Procedures posted on the Orange County Website, under Vendor Services.
https://www.ocfl.net/VendorServices/VendorProtestProcedures.aspx
15. Question: 8.1. Qualification: Will the 4,500 acre maintenance requirement have to be represented across only the references provided? Can the bidder’s entire book of business contribute to this requirement?
Answer: Yes. Respondent shall supply a list of at least three (3) client references for contracts successfully performed/delivered by the Respondent within the last ten (10) years, immediately preceding the due date of bids for this Invitation for Bids. Failure to provide this information may be cause for rejection of the response. Please refer to Section 9, Bid Response Form (Submittal), Item 1.1, Reference Requirements, for additional information.
16. Question: 10.4. Compliance with M/WBE Contract Requirements: Please provide M/WBE participation requirements.
Answer: Please refer to Section 5, Business Development, Bid Preference, for M/WBE participation requirements.
https://www.ocfl.net/VendorServices/VendorProtestProcedures.aspx
Addendum #1 Page 4 of 4
17. Question: Will submittal of a Work Plan be required with initial submittal or upon reward?
Answer: Please see the attached Scope of Work under Solicitation Documents in the OpenGov portal. Section C. SCHEDULE AND ROUTE, subsection 2, Work Plan states “The work plan shall be submitted within ten (10) days of notice of contract award.
18. Question: Will the requirements of item M15: Clipping Removal be fulfilled by blowing of clippings into areas besides those explicitly stated as off-limits in the scope?
Answer: All grass clippings that are not uniformly distributed and detract from the appearance of the mowing operation shall be removed from the job site by the Contractor upon completion of the mowing operation to allow for a neat and clean appearance after completion. The Contractor shall remove and dispose of all grass clippings from the pavement, fence lines, sidewalks, curbs and curb inlets located within the limits of the project.
A. ACKNOWLEDGEMENT OF ADDENDA
1. The bidder shall acknowledge receipt of this addendum by completing that applicable section in the solicitation or by completion of the acknowledgement information on the addendum. Either form of acknowledgement must be completed and returned no later than the date and time for receipt of the bid.
2. All other terms and conditions of the IFB remain the same.
3. Receipt acknowledged by: