This document is an Invitation for Bids (IFB) issued by the Maryland Department of Public Safety and Correctional Services/Maryland Correctional Enterprises (DPSCS/MCE) to procure Welding Supplies for a period of one (1) year with a one (1) year renewal option. The Welding Supplies will be delivered to three MCE facilities located in Hagerstown, Jessup, and Westover, Maryland. The estimated quantities represent an anticipated combined need for a one (1) year period. Bids are due by August 21, 2020 at 10:00 AM local time, and there is no pre-bid conference scheduled. The contract will be awarded to the responsible bidder submitting the responsive bid determined to be the most advantageous to the State based on price and delivery time.
Pricing terms include that all prices shall remain firm for 90 days from the effective date of the contract, and any proposed price increase must be provided with 30 days' notice and is subject to MCE approval. There are no Minority Business Enterprise (MBE) or Veteran-Owned Small Business Enterprise (VSBE) participation goals for this solicitation. The contract will be funded entirely by state funds, and payment terms include the potential for late payment interest if certain conditions are met.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF MARYLAND
DEPARTMENT OF PUBLIC SAFETY
CORRECTIONAL SERVICES
INVITATION FOR BIDS (IFB)
Welding Supplies for
Maryland Correctional Enterprises
BPM020430
ISSUE DATE: 7/24/20
NOTICE
A Prospective Bidder that has received this document from a source other than eMarylandMarketplaceAdvantage (eMMA) should register on eMMA. See Section 4.2.
Welding Supplies
Solicitation #: BPM020430 IFB Document
IFB for Maryland Correctional Enterprises Page ii of 55
NO BID NOTICE/VENDOR FEEDBACK FORM
To help us improve the quality of State solicitations, and to make our procurement process more responsive and business friendly, please provide comments and suggestions regarding this solicitation.
Please return your comments with your response. If you have chosen not to respond to this solicitation, please email or fax this completed form to the attention of the Procurement Officer (see Key
Information Summary Sheet below for contact information).
Title: Welding Supplies
Solicitation No: BPM020430
1. If you have chosen not to respond to this solicitation, please indicate the reason(s) below:
Other commitments preclude our participation at this time
The subject of the solicitation is not something we ordinarily provide
We are inexperienced in the work/commodities required
Specifications are unclear, too restrictive, etc. (Explain in REMARKS section)
The scope of work is beyond our present capacity
Doing business with the State is simply too complicated. (Explain in REMARKS section)
We cannot be competitive. (Explain in REMARKS section)
Time allotted for completion of the Bid is insufficient
Start-up time is insufficient
Bonding/Insurance requirements are restrictive (Explain in REMARKS section)
Bid requirements (other than specifications) are unreasonable or too risky (Explain in
REMARKS section)
MBE or VSBE requirements (Explain in REMARKS section)
Prior State of Maryland contract experience was unprofitable or otherwise unsatisfactory.
(Explain in REMARKS section)
Payment schedule too slow
Other: __________________________________________________________________
2. If you have submitted a response to this solicitation, but wish to offer suggestions or express concerns, please use the REMARKS section below. (Attach additional pages as needed.)
REMARKS:
Vendor Name: ________________________________ Date: _______________________
Contact Person: _________________________________ Phone (____) _____ - _________________
Address: ______________________________________________________________________
E-mail Address: ________________________________________________________________
IFB for Maryland Correctional Enterprises Page iii of 55
STATE OF MARYLAND
MARYLAND CORRECTIONAL ENTERPRISES (MCE)
KEY INFORMATION SUMMARY SHEET
Invitation for Bids Welding Supplies for Maryland Correctional Enterprises
Solicitation Number: BPM020430
IFB Issue Date: 7/24/20
IFB Issuing Office: Maryland Correctional Enterprises (MCE or the "Department")
Procurement Officer: Michelle Baldwin
7275 Waterloo Road, Jessup, MD 20794 e-mail:
Office Phone:
Dlmce-procurement_dpscs@maryland.gov
410-540-5419 Fax: 410-540-5580
Bids are to be sent to: Maryland Correctional Enterprises
Attention: Purchasing Department
7275 Waterloo Rd
Jessup, MD 20794
Via fax, FedEx, UPS, hand delivery, email or USPS. Originals required prior to award.
Pre-Bid Conference: n/a
Questions Due Date and Time 8/14/2020 at 10:00 AM Local Time
Bid Due (Closing) Date and
Time:
8/21/2020 at 10:00 AM Local Time
Bidders are reminded that a completed Feedback Form is requested if a no-bid decision is made (see page iv).
Public Bid Opening Date, Time and Location
8/21/2020 at 10:00 AM Local Time
7275 Waterloo Rd, Jessup, MD 20794
MBE Subcontracting Goal: 0%
VSBE Subcontracting Goal: 0%
Contract Type: Firm Fixed price
Contract Duration: One (1) year contract with a one (1) year renewal option
SBR Designation: No
Federal Funding: No mailto:Dlmce-procurement_dpscs@maryland.gov
IFB for Maryland Correctional Enterprises Page iv of 55
TABLE OF CONTENTS – IFB
1 GENERAL INFORMATION
1.1 SUMMARY
2 SCOPE OF WORK
2.1 Scope of Work
3 Contractor Requirements: General
3.1 Contract Initiation Requirements
3.2 End of Contract Transition
3.3 Invoicing
3.4 Liquidated Damages
3.5 Insurance Requirements
3.6 Security Requirements
3.7 Problem Escalation Procedure
4 Procurement Instructions
4.1 Pre-Bid Conference
4.2 eMaryland Marketplace Advantage (eMMA)
4.3 Questions
4.4 Procurement Method
4.5 Bid Due (Closing) Date and Time
4.6 Multiple or Alternate Bids
4.7 Receipt, Opening and Recording of Bids
4.8 Confidentiality of Bids / Public Information Act Notice
4.9 Award Basis
4.10 Tie Bids
4.11 Duration of Bids
4.12 Revisions to the IFB
4.13 Cancellations
4.14 Incurred Expenses
4.15 Protest/Disputes
4.16 Bidder Responsibilities
4.17 Acceptance of Terms and Conditions
4.18 Bid/Proposal Affidavit
IFB for Maryland Correctional Enterprises Page v of 55
4.19 Contract Affidavit
4.20 Compliance with Laws/Arrearages
4.21 Verification of Registration and Tax Payment
4.22 False Statements
4.23 Payments by Electronic Funds Transfer
4.24 Prompt Payment Policy
4.25 Electronic Procurements Authorized
4.26 MBE Participation Goal
4.27 VSBE Goal
4.28 Federal Funding Acknowledgement
4.29 Conflict of Interest Affidavit and Disclosure
4.30 Non-Disclosure Agreement
4.31 HIPAA - Business Associate Agreement
4.32 Nonvisual Access
4.33 Mercury and Products That Contain Mercury
4.34 Location of the Performance of Services Disclosure
4.35 Department of Human Services (DHS) Hiring Agreement
4.36 Small Business Reserve (SBR) Procurement
4.37 Maryland Healthy Working Families Act Requirements
5 Bid Format
5.1 One Part Submission
5.2 Labeling
5.3 Bid Price Form
5.4 Required Bid Submission
5.5 Delivery
5.6 Documents Required upon Notice of Recommendation for Contract Award
6 Bid Evaluation and Award
6.1 Bid Evaluation Criteria
6.2 Reciprocal Preference
6.3 Award Determination
6.4 Documents Required upon Notice of Recommendation for Contract Award
7 IFB ATTACHMENTS AND APPENDICES
Attachment A. Pre-Bid Conference Response Form
IFB for Maryland Correctional Enterprises Page vi of 55
Attachment B. Bid Instructions & Form
Attachment C. Bid/Proposal Affidavit
Attachment D. Minority Business Enterprise (MBE) Forms
Attachment E. Veteran-Owned Small Business Enterprise (VSBE) Forms
Attachment F. Maryland Living Wage Affidavit of Agreement for Service Contracts
Attachment G. Federal Funds Attachments
Attachment H. Conflict of Interest Affidavit and Disclosure
Attachment I. Non-Disclosure Agreement (Contractor)
Attachment J. HIPAA Business Associate Agreement
Attachment K. Mercury Affidavit
Attachment L. Location of the Performance of Services Disclosure
Attachment M. Contract
Attachment N. Contract Affidavit
Attachment O. DHS Hiring Agreement
Appendix 1. – Abbreviations and Definitions
Appendix 2. – Bidder Information Sheet
IFB for Maryland Correctional Enterprises Page 1 of 55
1 GENERAL INFORMATION
1.1 SUMMARY
The Maryland Department of Public Safety and Correctional Services/Maryland Correctional Enterprises
(DPSCS/MCE) is soliciting bids to procure Welding Supplies for a period of one (1) year with a one (1) year renewal option. The Welding Supplies will be delivered to:
Maryland Correctional Enterprises, Metal Plant, Maryland Correctional Institution -
Hagerstown, 18601 Roxbury Road, Hagerstown, MD 21746, Maryland Correctional Enterprises, Tag Plant, Jessup Correctional Institution, 7800 MD
House of Corrections Road, Jessup, MD 20794, and
Maryland Correctional Enterprises, Furniture Restoration Plant, Eastern Correctional
Institution, 30420 Revells Neck Road, Westover, MD 21890.
THE REMAINDER OF THIS PAGE IS INTENTIONALLY LEFT BLANK.
IFB for Maryland Correctional Enterprises Page 2 of 55
2 SCOPE OF WORK
2.1 Scope of Work
2.1.1 The estimated quantities represent an anticipated combined need for a one (1) year period and should not be construed as a fixed amount neither warranty nor guarantee by the State of
Maryland for this contract period.
2.1.2 Orders against this contract will be by verbal request by the Plant Supervisor on an as-need basis.
2.1.3 All contracts could be renewed for a single period of one (1) year by mutual consent of vendor and MCE.
2.1.4 Price Changes: All prices contained in the award as a result of bid shall remain firm for a period of ninety (90) days from the effective date of the contract. No proposed price increase without bonafide documentation will be considered. A thirty (30) day notice for a price increase must be given in writing in order for a price increase to be considered. MCE reserves the right to accept or reject any request for a price increase. MCE reserves the right to terminate the contract for cause or due to non-performance by the vendor. In the event of a price decrease, either by market changes or other conditions, MCE will be notified and receive the decrease.
2.1.5 Freight Charges: There are to be no freight or any other type of additional charges. The cost of shipping is to be included in the cost of the item being shipped.
2.1.6 The materials in the bid or proposal shall be delivered FOB destination.
2.1.7 Deliveries: Deliveries are to be made between the hours of 8:00 AM to 10:30 AM and/or 12:00
PM to 2:15 PM Monday thru Thursday (unless otherwise noted), except State and Federal holidays. The Plant Supervisor must be notified a day in advance in order to make arrangements;
otherwise, the shipment may be refused.
IFB for Maryland Correctional Enterprises Page 3 of 55
3 Contractor Requirements: General
3.1 Contract Initiation Requirements
THIS SECTION IS INAPPLICABLE TO THIS IFB.
3.2 End of Contract Transition
THIS SECTION IS INAPPLICABLE TO THIS IFB.
3.3 Invoicing
3.3.1 General
a) The Contractor shall mail OR e-mail the original of each invoice to the MCE AP, 7275
Waterloo Road, Jessup, MD 20794 or dlmceap_dpscs@maryland.gov.
All invoices for services shall be verified by the Contractor as accurate at the time of submission.
An invoice not satisfying the requirements of a Proper Invoice (as defined in COMAR 21.06.09) cannot be processed for payment. To be considered a Proper Invoice, invoices must include the following information, without error:
1) Contractor name and address;
2) Remittance address;
3) Federal taxpayer identification (FEIN) number, social security number, as appropriate;
4) Invoice period (job report and invoice per floor)
5) Invoice date;
6) Invoice number;
7) State assigned Contract number;
8) Amount due; and
9) Any additional documentation required by regulation or the Contract.
The Department reserves the right to reduce or withhold Contract payment in the event the Contractor does not provide the Department with all required services within the time frame specified in the Contract or otherwise breaches the terms and conditions of the Contract until such time as the Contractor brings itself into full compliance with the Contract.
Any action on the part of the Department, or dispute of action by the Contractor, shall be in accordance with the provisions of Md. Code Ann., State Finance and Procurement Article §§ 15-215 through 15-223 and with COMAR 21.10.04.
The State is generally exempt from federal excise taxes, Maryland sales and use taxes, District of
Columbia sales taxes and transportation taxes. The Contractor, however, is not exempt from such sales and use taxes and may be liable for the same.
Invoices for final payment shall be clearly marked as “FINAL” and submitted when all work requirements have been completed and no further charges are to be incurred under the Contract. In no event shall any invoice be submitted later than 60 calendar days from the Contract termination date.
mailto:dlmceap_dpscs@maryland.gov
IFB for Maryland Correctional Enterprises Page 4 of 55
3.3.2 For the purposes of the Contract an amount will not be deemed due and payable if:
a) The amount invoiced is inconsistent with the Contract;
b) The proper invoice has not been received by the party or office specified in the Contract;
c) The invoice or performance is in dispute or the Contractor has failed to otherwise comply with the provisions of the Contract;
d) The services have not been accepted;
e) The services do not meet the quality requirements of the Contract;
f) If the Contract provides for progress payments, the proper invoice for the progress payment has not been submitted pursuant to the schedule;
g) The Contractor has not submitted satisfactory documentation or other evidence reasonably required by the Procurement Officer or by the Contract concerning performance under the
Contract and compliance with its provisions.
3.3.3 Travel Reimbursement
Travel will not be reimbursed under this IFB.
3.4 Liquidated Damages
3.4.1 MBE Liquidated Damages
Inapplicable because there is no MBE goal for this IFB.
3.4.2 Liquidated Damages other than MBE
THIS SECTION IS INAPPLICABLE TO THIS IFB.
3.5 Insurance Requirements
The Contractor shall maintain, any minimum requirements established by law, for the duration of the
Contract, including option periods, if exercised:
3.5.1 The following type(s) of insurance and minimum amount(s) of coverage if required:
a) Commercial General Liability - of $1,000,000 combined single limit per occurrence for bodily injury, property damage, and personal and advertising injury and $2,000,000 annual aggregate. The minimum limits required herein may be satisfied through any combination of primary and umbrella/excess liability policies.
b) Errors and Omissions/Professional Liability - $1,000,000 per combined single limit per claim and $2,000,000 annual aggregate.
c) Crime Insurance/Employee Theft Insurance - to cover employee theft with a minimum single loss limit of $1,000,000 per loss, and a minimum single loss retention not to exceed
$10,000. The State of Maryland and the Department should be added as a “loss payee.”
3.6 Security Requirements
THIS SECTION IS INAPPLICABLE TO THIS IFB.
3.6.1 Security Clearance / Criminal Background Check
A security clearance is not required for Contractor Personnel assigned to the Contract.
IFB for Maryland Correctional Enterprises Page 5 of 55
3.6.2 On-Site Security Requirement
THIS SECTION IS INAPPLICABLE TO THIS IFB.
3.7 Problem Escalation Procedure
THIS SECTION IS INAPPLICABLE TO THIS IFB.
IFB for Maryland Correctional Enterprises Page 6 of 55
4 Procurement Instructions
4.1 Pre-Bid Conference
No Pre-Bid conference will be held.
4.2 eMaryland Marketplace Advantage (eMMA)
4.2.1 eMMA is the electronic commerce system for the State of Maryland. The IFB, Conference summary and attendance sheet, Bidders’ questions and the Procurement Officer’s responses, addenda, and other solicitation-related information will be made available via eMMA.
4.3 Questions
4.3.1 All questions shall identify in the subject line the Solicitation Number and Title (BPM020430 –
Welding Supplies) and shall be submitted in writing via e-mail to the Procurement Officer at least seven (7) days prior to the Bid due date. The Procurement Officer, based on the availability of time to research and communicate an answer, shall decide whether an answer can be given before the Bid due date.
4.3.2 Answers to all questions that are not clearly specific only to the requestor will be distributed via the same mechanism as for IFB amendments, and posted on eMMA.
4.3.3 The statements and interpretations contained in responses to any questions, whether responded to verbally or in writing, are not binding on the Department unless it issues an amendment in writing.
4.4 Procurement Method
A Contract will be awarded in accordance with the Competitive Sealed Bidding method under COMAR
21.05.02.
4.5 Bid Due (Closing) Date and Time
4.5.1 Bids, in the number and form set forth in Section 5 Bid Format, must be received by the
Procurement Officer no later than the Bid due date and time indicated on the Key Information
Summary Sheet in order to be considered.
4.5.2 Requests for extension of this date or time shall not be granted.
4.5.3 Bidders submitting Bids should allow sufficient delivery time to ensure timely receipt by the
Procurement Officer. Except as provided in COMAR 21.05.02.10, Bids received after the due date and time listed in the Key Information Summary Sheet will not be considered.
4.5.4 The date and time of an e-mail submission is determined by the date and time of arrival in the e-mail address indicated on the Key Information Summary Sheet.
4.5.5 Bids may be modified or withdrawn by written notice received by the Procurement Officer before the time and date set forth in the Key Information Summary Sheet for receipt of Bids.
4.5.6 Bids may be submitted by mail, hand-delivery, e-mail, or facsimile. Bids will be opened publicly at the date and time indicated on the Key Information Summary Sheet. Original signatures are required before an award can be made.
IFB for Maryland Correctional Enterprises Page 7 of 55
4.5.7 Potential Bidders not responding to this solicitation are requested to submit the “No Bid
Notice/Vendor Feedback” form, which includes company information and the reason for not responding (e.g., too busy, cannot meet mandatory requirements).
4.6 Multiple or Alternate Bids
Multiple or alternate Bids will not be accepted.
4.7 Receipt, Opening and Recording of Bids
4.7.1 Upon receipt, each Bid and any timely modification(s) to a Bid shall be stored in a secure place until the time and date set for bid opening. Before Bid opening, the State may not disclose the identity of any Bidder.
4.7.2 Bids shall be opened publicly, at the time, date and place designated in the IFB Key Information
Summary Sheet (near the beginning of the solicitation, after the Title Page and Notice to
Vendors). The name of each Bidder, the Total Bid Price, and such other information as is deemed appropriate shall be read aloud or otherwise made available and recorded at the time of bid opening.
4.8 Confidentiality of Bids / Public Information Act Notice
4.8.1 The Bidder should give specific attention to the clear identification of those portions of its Bid that it considers confidential and/or proprietary commercial information or trade secrets, and provide justification why such materials, upon request, should not be disclosed by the State under the Public Information Act, Md. Code Ann., General Provisions Article, Title 4. This information should be identified by page number and placed in the Transmittal Letter with the Bid.
4.8.2 The Bids shall be tabulated or a Bid abstract made. The opened Bids shall be available for public inspection at a reasonable time after Bid opening, but in any case before contract award, except to the extent the Bidder designates trade secrets or other proprietary data to be confidential as set forth in this solicitation. Material so designated as confidential shall accompany the Bid and shall be readily separable from the Bid in order to facilitate public inspection of the non-confidential portion of the Bid, including the Total Bid Price.
4.8.3 For requests for information made under the PIA, the Procurement Officer shall examine the Bids to determine the validity of any requests for nondisclosure of trade secrets and other proprietary data identified in writing. Nondisclosure is permissible only if approved by the Office of the
Attorney General.
4.9 Award Basis
4.9.1 A Contract shall be awarded to the responsible Bidder(s) submitting a responsive Bid(s) determined to be the most advantageous to the State (as referenced in COMAR 21.05.02.13) for providing the goods and services as specified in this IFB. See IFB Section 6 for Bid evaluation and award information.
4.9.2 Award of this contract will not be final and complete until after: (1) the Contractor submits complete and satisfactory documentation required under the Contract and/or documentation required by the Procurement Officer; and (2) the Contract is signed by the Department following any required approvals of the Contract, including approval by the Board of Public Works, if such approval is required.
IFB for Maryland Correctional Enterprises Page 8 of 55
4.10 Tie Bids
Tie Bids will be decided pursuant to COMAR 21.05.02.14.
4.11 Duration of Bids
Bids submitted in response to this IFB are irrevocable for the latest of the following: 120 days following the Bid due date and time or the date any protest concerning this IFB is finally resolved. This period may be extended at the Procurement Officer’s request only with the Bidder’s written agreement.
4.12 Revisions to the IFB
4.12.1 If the IFB is revised before the due date for Bids, the Department shall post any addenda to the
IFB on eMMA and shall endeavor to provide such addenda to all prospective Bidders that were sent this IFB or are otherwise known by the Procurement Officer to have obtained this IFB. It remains the responsibility of all prospective Bidders to check eMMA for any addenda issued prior to the submission of Bids.
4.12.2 Bidders shall acknowledge the receipt of all addenda to this IFB issued before the Bid due date.
4.12.3 Failure to acknowledge receipt of an addendum does not relieve the Bidder from complying with the terms, additions, deletions, or corrections set forth in the addendum, and may cause the Bid to be deemed not responsive.
4.13 Cancellations
4.13.1 The State reserves the right to cancel this IFB, accept or reject any and all Bids, in whole or in part, received in response to this IFB and to waive or permit the cure of minor irregularities.
4.13.2 In the event a government entity proposes and receives the recommendation for award, the procurement may be cancelled and the award processed in accordance with COMAR
21.01.03.01.A(4).
4.13.3 If the services that are the subject of the IFB are currently being provided under an interagency agreement with a public institution of higher education and the State determines that the services can be provided more cost effectively by the public institution of higher education, then the IFB may be cancelled in accordance with Md. Code Ann., State Finance and Procurement Art., § 3-
207(b)(2).
4.14 Incurred Expenses
The State will not be responsible for any costs incurred by any Bidder in preparing and submitting a Bid or performing any other activities related to submitting a Bid in response to this solicitation.
4.15 Protest/Disputes
Any protest or dispute related to this solicitation or the Contract award shall be subject to the provisions of COMAR 21.10 (Administrative and Civil Remedies).
4.16 Bidder Responsibilities
4.16.1 Bidders must be able to provide all goods and services and meet all of the requirements requested in this solicitation and the successful Bidder shall be responsible for Contract performance including any subcontractor participation.
IFB for Maryland Correctional Enterprises Page 9 of 55
4.16.2 If the Bidder is the subsidiary of another entity, all information submitted by the Bidder, including but not limited to references, financial reports, or experience and documentation (e.g.
insurance policies, bonds, letters of credit) used to meet minimum qualifications, if any, shall pertain exclusively to the Bidder, unless the parent organization will guarantee the performance of the subsidiary. If applicable, the Bidder’s Bid shall contain an explicit statement, signed by an authorized representative of the parent organization, stating that the parent organization will guarantee the performance of the subsidiary.
4.16.3 A parental guarantee of the performance of the Bidder under this Section will not automatically result in crediting the Bidder with the experience or qualifications of the parent under any evaluation criteria pertaining to the actual Bidder’s experience and qualifications. Instead, the
Bidder’s responsibility will be assessed to the extent to which the State determines that the experience and qualifications of the parent are applicable to and shared with the Bidder, any stated intent by the parent to be directly involved in the performance of the Contract, and the value of the parent’s participation as determined by the State.
4.17 Acceptance of Terms and Conditions
By submitting a Bid in response to this IFB, the Bidder, if selected for award, shall be deemed to have accepted the terms and conditions of this IFB and the Contract, attached hereto as Attachment M. Any exceptions to this IFB or the Contract must be raised prior to Bid submission. Changes to the solicitation, including the Bid Form or Contract, made by the Bidder may result in Bid rejection.
4.18 Bid/Proposal Affidavit
A Bid submitted by the Bidder must be accompanied by a completed Bid/Proposal Affidavit. A copy of this Affidavit is included as Attachment C of this IFB.
4.19 Contract Affidavit
All Bidders are advised that if a Contract is awarded as a result of this solicitation, the successful Bidder will be required to complete a Contract Affidavit. A copy of this Affidavit is included for informational purposes as Attachment N of this IFB. This Affidavit must be provided within five (5) Business Days of notification of recommended award. For purposes of completing Section “B” of this Affidavit
(Certification of Registration or Qualification with the State Department of Assessments and Taxation), a business entity that is organized outside of the State of Maryland is considered a “foreign” business.
4.20 Compliance with Laws/Arrearages
By submitting a Bid in response to this IFB, the Bidder, if selected for award, agrees that it will comply with all federal, State, and local laws applicable to its activities and obligations under the Contract.
By submitting a response to this solicitation, each Bidder represents that it is not in arrears in the payment of any obligations due and owing the State, including the payment of taxes and employee benefits, and shall not become so in arrears during the term of the Contract if selected for Contract award.
4.21 Verification of Registration and Tax Payment
Before a business entity can do business in the State, it must be registered with the State Department of
Assessments and Taxation (SDAT). SDAT is located at State Office Building, Room 803, 301 West
Preston Street, Baltimore, Maryland 21201. For registration information, visit https://www.egov.maryland.gov/businessexpress.
IFB for Maryland Correctional Enterprises Page 10 of 55
It is strongly recommended that any potential Bidder complete registration prior to the Bid due date and time. The Bidder’s failure to complete registration with SDAT may disqualify an otherwise successful
Bidder from final consideration and recommendation for Contract award.
4.22 False Statements
Bidders are advised that Md. Code Ann., State Finance and Procurement Article, § 11-205.1 provides as follows:
4.22.1 In connection with a procurement contract a person may not willfully:
a) Falsify, conceal, or suppress a material fact by any scheme or device.
b) Make a false or fraudulent statement or representation of a material fact.
c) Use a false writing or document that contains a false or fraudulent statement or entry of a material fact.
4.22.2 A person may not aid or conspire with another person to commit an act under Section 4.22.1.
4.22.3 A person who violates any provision of this section is guilty of a felony and on conviction is subject to a fine not exceeding $20,000 or imprisonment not exceeding five (5) years or both.
4.23 Payments by Electronic Funds Transfer
By submitting a Bid in response to this solicitation, the Bidder, if selected for award:
4.23.1 Agrees to accept payments by electronic funds transfer (EFT) unless the State Comptroller’s
Office grants an exemption. Payment by EFT is mandatory for contracts exceeding $200,000. The successful Bidder shall register using the COT/GAD X-10 Vendor Electronic Funds (EFT)
Registration Request Form.
4.23.2 Any request for exemption must be submitted to the State Comptroller’s Office for approval at the address specified on the COT/GAD X-10 form, must include the business identification information as stated on the form, and must include the reason for the exemption. The COT/GAD
X-10 form may be downloaded from the Comptroller’s website at:
http://comptroller.marylandtaxes.com/Vendor_Services/Accounting_Information/Static_Files/GA
DX10Form20150615.pdf.
4.24 Prompt Payment Policy
This procurement and the Contract(s) to be awarded pursuant to this solicitation are subject to the
Prompt Payment Policy Directive issued by the Governor’s Office of Small, Minority & Women
Business Affairs (GOSBA) and dated August 1, 2008. Promulgated pursuant to Md. Code Ann., State
Finance and Procurement Article, §§ 11-201, 13-205(a), and Title 14, Subtitle 3, and COMAR
21.01.01.03 and 21.11.03.01, the Directive seeks to ensure the prompt payment of all subcontractors on non-construction procurement contracts. The Contractor shall comply with the prompt payment requirements outlined in the Contract, Section 31 “Prompt Pay Requirements” (see Attachment M).
Additional information is available on GOSBA’s website at:
http://www.gomdsmallbiz.maryland.gov/documents/legislation/promptpaymentfaqs.pdf.
4.25 Electronic Procurements Authorized
4.25.1 Under COMAR 21.03.05, unless otherwise prohibited by law, the Department may conduct procurement transactions by electronic means, including the solicitation, proposing, award, execution, and administration of a contract, as provided in Md. Code Ann., Maryland Uniform
Electronic Transactions Act, Commercial Law Article, Title 21.
IFB for Maryland Correctional Enterprises Page 11 of 55
4.25.2 Participation in the solicitation process on a procurement contract for which electronic means has been authorized shall constitute consent by the Bidder to conduct by electronic means all elements of the procurement of that Contract which are specifically authorized under the solicitation or Contract. In the case of electronic transactions authorized by this IFB, electronic records and signatures by an authorized representative satisfy a requirement for written submission and signatures.
4.25.3 “Electronic means” refers to exchanges or communications using electronic, digital, magnetic, wireless, optical, electromagnetic, or other means of electronically conducting transactions.
Electronic means includes facsimile, e-mail, internet-based communications, electronic funds transfer, specific electronic bidding platforms (e.g., https://emaryland.buyspeed.com/bso/), and electronic data interchange.
4.25.4 In addition to specific electronic transactions specifically authorized in other sections of this solicitation (e.g., IFB § 4.23 describing payments by Electronic Funds Transfer), the following transactions are authorized to be conducted by electronic means on the terms as authorized in
COMAR 21.03.05:
a) The Procurement Officer may conduct the procurement using eMMA, e-mail, or facsimile to issue:
1) The IFB;
2) Any amendments;
3) Pre-Bid conference documents;
4) Questions and responses;
5) Communications regarding the solicitation or Bid to any Bidder or potential Bidder;
6) Notices of award selection or non-selection; and
7) The Procurement Officer’s decision on any Bid protest or Contract claim.
The Bidder or potential Bidder may use e-mail to:
8) Submit Bids (originals are required before an award can be made);
9) Ask questions regarding the solicitation;
10) Reply to any material received from the Procurement Officer by electronic means that includes a Procurement Officer’s request or direction to reply by e-mail or facsimile, but only on the terms specifically approved and directed by the
Procurement Officer and;
11) Submit a "No Bid Notice/Vendor Feedback Form" to the IFB.
The Procurement Officer, the Contract Monitor, and the Contractor may conduct day-to-day Contract administration, except as outlined in Section 4.25.5 of this subsection, utilizing e-mail, facsimile, or other electronic means if authorized by the Procurement Officer or Contract Monitor.
4.25.5 The following transactions related to this procurement and any Contract awarded pursuant to it are not authorized to be conducted by electronic means:
A. Filing of bid protests;
B. Filing of Contract claims;
C. Submission of documents determined by the Department to require original signatures (e.g., Contract execution, Contract modifications); or https://emaryland.buyspeed.com/bso/
IFB for Maryland Correctional Enterprises Page 12 of 55
D. Any transaction, submission, or communication where the Procurement Officer has specifically directed that a response from the Contractor or Bidder be provided in writing or hard copy.
4.25.6 Any facsimile or e-mail transmission is only authorized to the facsimile numbers or e-mail addresses for the identified person as provided in the solicitation, the Contract, or in the direction from the Procurement Officer or Contract Monitor.
4.26 MBE Participation Goal
There is no MBE subcontractor participation goal for this procurement.
4.27 VSBE Goal
There is no VSBE participation goal for this procurement.
4.28 Federal Funding Acknowledgement
This Contract does not contain federal funds.
4.29 Conflict of Interest Affidavit and Disclosure
4.29.1 The Bidder shall complete and sign the Conflict of Interest Affidavit and Disclosure
(Attachment H) and submit it with its Bid.
4.29.2 By submitting a Conflict of Interest Affidavit and Disclosure, the Contractor shall be construed as certifying all Contractor Personnel and subcontractors are also without a conflict of interest as defined in COMAR 21.05.08.08A.
4.29.3 Additionally, a Contractor has an ongoing obligation to ensure that all Contractor Personnel are without conflicts of interest prior to providing services the Contract. For policies and procedures applying specifically to Conflict of Interests, the Contract is governed by COMAR 21.05.08.08.
4.29.4 Participation in Drafting of Specifications: Disqualifying Event: Bidders are advised that Md.
Code Ann. State Finance and Procurement Article §13-212.1(a) provides generally that “an individual who assists an executive unit in the drafting of specifications, an invitation for bids, a request for proposals for a procurement, or the selection or award made in response to an invitation for bids or a request for proposals, or a person that employs the individual, may not:
(1) submit a bid or proposal for that procurement; or (2) assist or represent another person, directly or indirectly, who is submitting a bid or proposal for that procurement.” Any Bidder submitting a Bid in violation of this provision shall be classified as “not responsible.”
4.30 Non-Disclosure Agreement
4.30.1 Non-Disclosure Agreement (Bidder)
A Non-Disclosure Agreement (Bidder) is not required for this procurement.
4.30.2 Non-Disclosure Agreement (Contractor)
A Non-Disclosure Agreement (Contractor) is not required for this procurement.
4.31 HIPAA - Business Associate Agreement
A HIPAA Business Associate Agreement is not required for this procurement.
IFB for Maryland Correctional Enterprises Page 13 of 55
4.32 Nonvisual Access
This solicitation does not contain Information Technology (IT) provisions requiring Nonvisual Access.
4.33 Mercury and Products That Contain Mercury
This solicitation does not include the procurement of products known to likely include mercury as a component.
4.34 Location of the Performance of Services Disclosure
This solicitation does not require a Location of the Performance of Services Disclosure.
4.35 Department of Human Services (DHS) Hiring Agreement
This solicitation does not require a DHS Hiring Agreement.
4.36 Small Business Reserve (SBR) Procurement
This solicitation is not designated as a Small Business Reserve (SBR) Procurement.
4.37 Maryland Healthy Working Families Act Requirements
On February 11, 2018, the Maryland Healthy Working Families Act went into effect. All offerors should be aware of how this Act could affect your potential contract award with the State of Maryland.
See the Department of Labor, Licensing and Regulations web site for Maryland Healthy Working
Families Act Information: http://dllr.maryland.gov/paidleave/.
http://dllr.maryland.gov/paidleave/
IFB for Maryland Correctional Enterprises Page 14 of 55
5 Bid Format
5.1 One Part Submission
Each Bidder shall submit its Bid with all Required Bid Submissions (see IFB Section 5.4) in a single sealed package.
5.2 Labeling
Each Bidder is required to label the sealed Bid with the IFB title and number, name and address of the
Bidder, and closing date and time for receipt of the Bids.
5.3 Bid Price Form
The Bid shall contain all price information in the format specified on the Bid Form. The Bidder shall complete the Bid Form only as provided in the Bid Pricing Instructions and the Bid Form. Do not amend, alter, or leave blank any items on the Bid Form or include additional clarifying or contingent language on or attached to the Bid Form. Failure to adhere to any of these instructions may result in the Bid being determined to be non-responsive and rejected by the Department.
5.4 Required Bid Submission
A Bidder shall include the following with its Bid:
5.4.1 Bidder Information Sheet (see Appendix 2)
5.4.2 Acknowledgement of all addenda to this IFB.
5.4.3 Minimum Qualifications Documentation. The Bidder shall submit any Minimum
Qualifications documentation that may be required, as set forth in IFB Section 1. If references are required in IFB Section 1, those references shall be submitted in this section and shall contain the information described in both Section 1.
5.4.4 Completed Required Attachments. Submit one (1) copy of each with original signatures:
1) Completed Bid Form (Attachment B).
2) Completed Bid Affidavit (Attachment C).
3) Additional Document *If Required. Submit one (1) copy of each with original signatures, if required. *See appropriate IFB section to determine whether the document is required for this procurement.
4) Completed Conflict of Interest Affidavit and Disclosure (Attachment H) *see IFB section 4.30
5.5 Delivery
5.5.1 Bidders may either mail, hand-deliver, e-mail or facsimile Bids. Original signatures are required before an award can be made.
5.5.2 For U.S. Postal Service deliveries, any bid that has been received at the appropriate mail room, or typical place of mail receipt for the respective procuring unit by the time and date listed in the IFB will be deemed to be timely. If a Bidder chooses to use the U.S. Postal Service for delivery, the Department recommends that it use Express Mail, Priority Mail, or Certified Mail or another form for which both the date and time of receipt can be independently verified by the
Department. It could take several days for an item sent by first class mail to make its way by normal internal mail to the procuring unit and a Bidder using first class mail will not be able to prove a timely delivery at the mailroom.
IFB for Maryland Correctional Enterprises Page 15 of 55
5.5.3 Hand-delivery includes delivery by commercial carrier acting for the Bidder. For any type of direct (non-mail) delivery, a Bidder is advised to secure a dated, signed, and time-stamped (or otherwise indicated) receipt of delivery.
5.6 Documents Required upon Notice of Recommendation for Contract Award
Upon receipt of a notification of recommendation for contract award, the following documents shall be completed and submitted by the recommended awardee, unless noted otherwise. Submit one (1) copy of each of the following documents:
A. Signed contract (Attachment M),
b. Completed Contract Affidavit (Attachment N).
IFB for Maryland Correctional Enterprises Page 16 of 55
6 Bid Evaluation and Award
6.1 Bid Evaluation Criteria
The Bids will be evaluated based on the given Specifications, Total Bid Price, and Delivery Time as per
COMAR 21.02.13.
6.2 Reciprocal Preference
6.2.1 Although Maryland law does not authorize procuring agencies to favor resident Bidders in awarding procurement contracts, many other states do grant their resident businesses preferences over Maryland contractors. COMAR 21.05.01.04 permits procuring agencies to apply a reciprocal preference under the following conditions:
a) The Maryland resident business is a responsible Bidder;
b) The lowest responsive Bid is from a responsible Bidder whose principal office, or principal base of operations is in another state;
c) The other state gives a preference to its resident businesses through law, policy, or practice;
and
d) The preference does not conflict with a federal law or grant affecting the procurement
Contract.
6.2.2 The preference given shall be identical to the preference that the other state, through law, policy, or practice gives to its resident businesses.
6.3 Award Determination
Award will be made to the responsible Bidder who submits to the State the responsive Bid that is determined to be the most advantageous to the State based on price and delivery time.
6.4 Documents Required upon Notice of Recommendation for Contract Award
Upon receipt of a Notification of Recommendation for Contract award, the apparent awardee shall complete and furnish the documents and attestations as directed in Table 1 of Section 7 – IFB
Attachments and Appendices.
IFB for Maryland Correctional Enterprises Page 17 of 55
7 IFB ATTACHMENTS AND APPENDICES
Instructions Page
A Bid submitted by the Bidder must be accompanied by the completed forms and/or affidavits identified as “with Bid” in the “When to Submit” column in Table 1 below. All forms and affidavits applicable to this IFB, including any applicable instructions and/or terms, are identified in the “Applies” and “Label” columns in Table 1.
For documents required as part of the Bid:
1. For e-mail submissions, submit one (1) copy of each with signatures.
2. For paper submissions, submit one (1) copy of each with original signatures. All signatures must be clearly visible.
All Bidders are advised that if a Contract is awarded as a result of this solicitation, the successful Bidder will be required to complete certain forms and affidavits after notification of recommended award. The list of forms and affidavits that must be provided is described in Table 1 below in the “When to Submit” column.
For documents required after award, submit one (1) copy of each document within the appropriate number of days after notification of recommended award, as listed in Table 1 below in the “When to
Submit” column.
Table 1: IFB ATTACHMENTS AND APPENDICES
A p p li es
When to Submit
L a b el
Attachment Name
N Before Bid A Pre-Bid Conference Response Form
Y With Bid B Bid Instructions and Form
Y With Bid C Bid/Proposal Affidavit (see link at http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/AttachmentC-
Bid_Proposal-Affidavit.pdf)
N With Bid D MBE Forms D-1A
N 10 Business Days after recommended award
D MBE Forms D-1B, D-1C,D-2, D-3A, D-3B
N As directed in forms D MBE Forms D-4A, D-4B, D-5
N With Bid E Veteran-Owned Small Business Enterprise (VSBE)
Form E-1A
N 5 Business Days after recommended award
E VSBE Forms E-1B, E-2, E-3
N With Bid F Maryland Living Wage Requirements for Service
Contracts and Affidavit of Agreement
N With Bid G Federal Funds Attachments http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/AttachmentC-Bid_Proposal-Affidavit.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/AttachmentC-Bid_Proposal-Affidavit.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/AttachmentC-Bid_Proposal-Affidavit.pdf
IFB for Maryland Correctional Enterprises Page 18 of 55
A p p li a
Y With Bid H Conflict of Interest Affidavit and Disclosure (see link at https://procurement.maryland.gov/wp-content/uploads/sites/12/2018/05/AttachmentH-Conflict-of-InterestAffidavit.pdf)
N 5 Business Days after recommended award –
However, suggested with Bid
I Non-Disclosure Agreement (Contractor)
N 5 Business Days after recommended award –
However, suggested with Bid
J HIPAA Business Associate Agreement
N With Bid K Mercury Affidavit
N With Bid L Location of the Performance of Services Disclosure
Y 5 Business Days after recommended award
M Sample Contract (included in this IFB)
Y 5 Business Days after recommended award
N Contract Affidavit (see link at http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Attachment-N-
ContractAffidavit.pdf)
N 5 Business Days after recommended award
O DHS Hiring Agreement
Appendices p li a
Y n/a 1 Abbreviations and Definitions (included in this IFB)
Y With Bid 2 Bidder Information Sheet (see link at http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Appendix2-
Bidder_OfferorInformationSheet.pdf)
N Before Bid, as directed in the IFB.
3 Non-Disclosure Agreement (Bidder)
N 5 Business Days after
Evidence of meeting insurance requirements (see
Section 3.6); 1 copy https://procurement.maryland.gov/wp-content/uploads/sites/12/2018/05/AttachmentH-Conflict-of-InterestAffidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2018/05/AttachmentH-Conflict-of-InterestAffidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2018/05/AttachmentH-Conflict-of-InterestAffidavit.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Attachment-N-ContractAffidavit.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Attachment-N-ContractAffidavit.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Attachment-N-ContractAffidavit.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Appendix2-Bidder_OfferorInformationSheet.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Appendix2-Bidder_OfferorInformationSheet.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Appendix2-Bidder_OfferorInformationSheet.pdf
IFB for Maryland Correctional Enterprises Page 19 of 55 p li a
N 10 Business Days after
PEP; 1 copy
IFB for Maryland Correctional Enterprises Page 20 of 55
Attachment A. Pre-Bid Conference Response Form
A pre-bid conference will not be held for this solicitation.
IFB for Maryland Correctional Enterprises Page 21 of 55
Attachment B. Bid Instructions & Form
B-1 Bid Instructions
In order to assist each Bidder in the preparation of its Bid and to comply with the requirements of this solicitation, Bid Instructions and a Bid Form have been prepared. Each Bidder shall submit its Bid on the
Bid Form in accordance with the instructions on the Bid Form and as specified herein. Do not alter the
Bid Form or the Bid may be determined to be not reasonably susceptible of being selected for award. The
Bid Form is to be signed and dated, where requested, by an individual who is authorized to bind the
Bidder to the prices entered on the Bid Form.
The Bid Form is used to calculate the Bidder’s TOTAL BID PRICE. Follow these instructions carefully when completing your Bid Form:
A) All Unit and Extended Prices must be clearly entered in dollars and cents, e.g., $24.15. Make your decimal points clear and distinct.
B) All Unit Prices must be the actual price per unit the State will pay for the specific item or service identified in this IFB and may not be contingent on any other factor or condition in any manner.
C) All calculations shall be rounded to the nearest cent, e.g., .344 shall be .34 and .345 shall be .35.
D) Any goods or services required through this IFB and proposed by the vendor at No Cost to the
State must be clearly entered in the Unit Price, if appropriate, and Extended Price with $0.00.
E) Every blank in every Bid Form shall be filled in. Any changes or corrections made to the Bid
Form by the Bidder prior to submission shall be initialed and dated.
F) Except as instructed on the Bid Form, nothing shall be entered on or attached to the Bid Form that alters or proposes conditions or contingencies on the prices. Alterations and/or conditions may render the
Bid not reasonably susceptible of being selected for award.
G) It is imperative that the prices included on the Bid Form have been entered correctly and calculated accurately by the Bidder and that the respective total prices agree with the entries on the Bid
Form. Any incorrect entries or inaccurate calculations by the Bidder will be treated as provided in
COMAR 21.05.03.03.F, and may cause the Bid to be rejected.
H) If option years are included, Bidders must submit pricing for each option year. Any option to renew will be exercised at the sole discretion of the State and comply with all terms and conditions in force at the time the option is exercised. If exercised, the option period shall be for a period identified in the IFB at the prices entered in the Bid Form.
I) All Bid prices entered below are to be fully loaded prices that include all costs/expenses associated with the provision of services as required by the IFB. The Bid price shall include, but is not limited to, all: labor, profit/overhead, general operating, administrative, and all other expenses and costs necessary to perform the work set forth in the solicitation. No other amounts will be paid to the
Contractor. If labor rates are requested, those amounts shall be fully-loaded rates; no overtime amounts will be paid.
J) Unless indicated elsewhere in the IFB, sample amounts used for calculations on the Bid Form are typically estimates for evaluation purposes only. Unless stated otherwise in the IFB, the Department does not guarantee a minimum or maximum number of units or usage in the performance of the Contract.
K) Failure to adhere to any of these instructions may result in the Bid being determined not reasonably susceptible of being selected for award.
IFB for Maryland Correctional Enterprises Page 22 of 55
B-1 Bid Form
The Bid Form shall contain all price information in the format specified on these pages. Complete the Bid
Form only as provided in the Bid Instructions. Do not amend, alter or leave blank any items on the Bid
Form. If option years are included, Bidders must submit pricing for each option year. Failure to adhere to any of these instructions may result in the Bid being determined not reasonably susceptible of being selected for award.
CONTRACTOR SHALL PROVIDE WELDING SUPPLIES AS REQUIRED BY THE DEPARTMENT
IN ACCORDANCE TO THE SPECIFICATIONS PROVIDED IN THE SCOPE OF WORK SECTION I
AND THE STANDARD SPECIFICATIONS. THE CONTRACTOR SHALL PROVIDE A BID FOR
ALL SIZES. NO ADDITIONAL CHARGES.
P.O. ITEM QUOTATION TO INCLUDE DELIVERY OF FOLLOWING ITEMS F.O.B. DESTINATION. QUANTITY UNIT
NET UNIT
PRICE
SAFETY ITEMS:
1 3M PARTICLE MASK, #8500 1,200 EA _________
2…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .