IFB Solicitation - NP-BLRI 1M20.pdf

PDF 3 MB Posted

Attached to
Roanoke River Bridge Federal contract opportunity
Solicitation number
693C73-21-B-000008
Issued by
Department of Transportation Federal Highway Administration

About this file

This federal solicitation seeks sealed bids for the rehabilitation of the Roanoke River Bridge near milepost 115.0 in Roanoke County, Virginia. The work includes installing drainage systems, replacing asphalt and concrete surfaces, repairing bridge structures, and other miscellaneous tasks. The project will be split into multiple schedules and contract options, with pricing expected to range from $1,000,000 to $5,000,000. Bids are due by the date specified on the SF1442 form. This opportunity is set aside for small businesses only. Interested vendors must register at beta.sam.gov to receive notifications. Annual representations and certifications must be completed online at sam.gov. Form VETS-4212 filing is also required annually at dol.gov. All questions should be sent to eflhd.contracts@dot.gov. Prospective contractors must register in the SAM database. The Department of Transportation Federal Highway Administration seeks to award this contract.

View the file

Other files for this federal contract opportunity

Other files attached to Roanoke River Bridge, newest first.
File Type Posted
Results of Bid Opening - NP-BLRI 1M20.pdf PDF
Amendment 0002 - NP-BLRI 1M20.pdf PDF
Amendment 0001 - NP-BLRI 1M20.pdf PDF
Report 1_NEPA CE - NP-BLRI 1M20.pdf PDF
VETS 4212 Form.pdf PDF
ADV_Bidders Qualifications Form.doc DOC document
FP14_Eng.pdf PDF
Plans - NP-BLRI_1M20.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract No.

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

NP-BLRI 1M20

ROANOKE RIVER BRIDGE

REHABILITATION OF ROANOKE RIVER BRIDGE NEAR MP 115.0

CONTRACTOR:

ADDRESS:

PMIS# 175115

SOLICITATION

IFB No. 693C73-21-B-000008

This Contract Cites

STANDARD SPECIFICATIONS (FP-14)

STATE Virginia

COUNTY Roanoke

PARK Blue Ridge Parkway

TYPE OF IMPROVEMENT

Rehabilitation of Roanoke River Bridge and reconstruction of the bridge approaches including grading, embankment repair, placement of aggregate base and asphalt concrete pavement, application of a waterproofing membrane to the bridge deck, drainage improvement, and other miscellaneous work.

Project Length Totals

0.33 0.66

For Parking Areas, Lane Miles is calculated as SQFT/1 lft (nominal) lane

Parking Roadway / Parking Area / Other Stations / SQFT Linear Route Lane

Schedule Area Feet Miles Miles

A □ Roanoke River Bridge 811 To 1839 1,028 0.19 0.38

B □ Blue Ridge Parkway- South Roadway 300 To 811 511 0.10 0.20 Approach

B □ Blue Ridge Parkway- North Roadway 1839 To 2030 191 0.04 0.08 Approach

TABLE OF CONTENTS

Page

Notice to Bidders 1 through 2

Checklist for Bid Submission 1 through 2

*SF-1442 Solicitation, Offer, and Award 1 through 4

Bid Schedule Instructions 1 through 3

*Bid Schedule B-1 through B-9

*SF-24 Bid Bond C-1 through C-2

FEDERAL ACQUISITION REGULATION & TRANSPORTATION ACQUISITION

REGULATION SOLICITATION PROVISIONS & CONTRACT CLAUSES

Index to Federal and Transportation Acquisition Regulations 1 through 7

Representations and Certifications (SAMs online) D-1 through D-2

Instructions to Bidders E-1

*Socioeconomic Program Requirements F-1 through F-4

Minimum Wage Schedule F-5 through F-13

*General Contract Requirements G-1 through G-9

Construction Contract Requirements H-1 through H-5

Special Contract Requirements J-1 through J-70

Section K K-1 through K-3

Permits Obtained for this Project 1 through 12

SPECIFICATIONS On CD

Plans 1 through 101

Categorical Exclusion Report (NEPA) 1 through 7

* Bidder’s Qualifications Form 1 through 7

* Federal Contractor Veterans’ Employment Report VETS-4212 1 through 5

*BOLD FACED ITEMS ARE TO BE INCLUDED WITH THE BID SUBMITTAL PACKAGE

NOTICE TO BIDDERS

CONTRACT FORMAT:

Bidders should note that the format of this contract is in accordance with Federal Acquisition Regulations (FAR), promulgated by the General Services Administration (GSA), effective April 1, 1984, including all applicable revisions. Applicable FAR provisions and clauses are incorporated in this contract by reference or full text as indicated in the INDEX before the D-pages in this booklet.

FAR provisions and clauses incorporated by reference can be accessed on the Internet website at https://www.acquisition.gov/. Bidders are encouraged to review the documents thoroughly before submitting a bid.

PROPOSAL BOOKLET AND OFFER SUBMITTAL:

It is the responsibility of the Bidder to verify that this proposal is complete as listed in the Table of Contents. The Bidder is responsible for submitting all required forms and documents with the bid.

Bidders should use the Checklist for Bid Submission included in this booklet to check that their bids are complete.

CONSTRUCTION CONTRACTS:

Additional guidance is given in FAR Subpart 35.005 where the majority of the project work is complex and specialized such as restoration work, bridge painting, and proprietary construction techniques (i.e. proprietary Cintec arch strengthening.) There are exceptions and they will be reviewed on a case-by-case basis.

HAZARDOUS MATERIALS IDENTIFICATION AND MATERIAL SAFETY DATA:

As required by FAR Clause 52.223-3, Hazardous Materials Identification and Safety Data, the apparent low Bidder must submit prior to award a Material Safety Data Sheet (MSDSs) for all hazardous materials that the Bidder identifies in paragraph (b) of this clause in Section G of this booklet. Failure to submit MSDSs may render the Bidder ineligible for award of contract. The apparent low Bidder should submit their MSDSs within two weeks after bid opening.

INTERNET BASED DATA BASES - REQUIRED INPUT:

According to FAR Subpart 4.1102 contractors are required to be registered in the System for Award Management (SAM) at the time a bid is submitted. Access the following web site to register: https://www.sam.gov/.

According to FAR Subpart 4.1201 contractors are required to complete electronic annual representations and certifications in SAM accessed via https://www.sam.gov/ as a part of required registration.

According to FAR Subpart 22.1302 (b) federal contractors and sub-contractors MUST complete the required annual Vets-4212 Form in order to be eligible for a contract award. It can be completed on-line at http://www.dol.gov/vets/vets4212.htm. The annual filing period for Form VETS-4212 is August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS-4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.

PAYMENT:

Bidders are advised to review the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP), subsection 109.05, concerning direct and indirect payment included under a pay item in the bid schedule.

https://www.sam.gov/ https://www.sam.gov/ http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212 http://www.dol.gov/vets/vets4212.htm

NOTICE TO BIDDERS

PROGRESS PAYMENTS:

ALL payments will be made via Electronic Funds Transfer (EFT) as such; the payment information in SAM must be accurate in order for contractors' invoices to be considered proper invoices for the purpose of prompt payment under DOT contracts. Contractors must input and maintain (update as necessary) their EFT information in the SAM database. Bidders are advised that under FAR Clause 52.232-5, Payments Under Fixed Price Construction Contracts, upon request, progress payments will include premiums paid by the Contractor to obtain performance and payment bonds as required under this contract. These payments shall not be made in addition to the contract price. As specified in the FP, “Section 151 - MOBILIZATION", payments for performance and payment bond premiums shall be included in mobilization.

WELFARE-TO-WORK INITIATIVE:

The President’s Welfare Reform Bill was initiated to assist welfare recipients and hopefully aid welfare recipients to find gainful employment. In support of this bill, Contractors are encouraged to hire welfare recipients whenever possible and to use welfare recipients in performance of duties on Government contracts.

INCREASING SEAT BELT USE IN THE UNITED STATES:

The President’s Executive Order 13043 dated April 16, 1997, was issued to increase the use of seat belts in the United States. In support of this Order, contractors and subcontractors are encouraged to adopt and enforce on-the-job seat belt policies for their employees when operating company-owned, rented, or personally owned vehicles.

OBTAINING BID DOCUMENTS:

Invitation For Bid (IFB) documents will not be mailed. All solicitation documents are available for direct download from the Contract Opportunities website: https://beta.sam.gov/. Contractors are encouraged to register on the website (for this specific project) in order to receive automatic notifications when a document is added or updated for this specific project. All questions about this construction project must be emailed to the following address:

eflhd.contracts@dot.gov.

THE CONTRACTOR IS SOLELY RESPONSIBLE FOR MONITORING THE WEB PAGES

NOTED ABOVE FOR ALL CHANGES TO THE SOLICITATION AND ACTING ON

THOSE CHANGES.

PLEASE NOTE: For security reasons, individuals requiring access to all government buildings must present a valid photo ID and be escorted to their destination by a Government employee. All visitors attending bid openings are urged to arrive at least 1 hour prior to a scheduled bid opening. All visitors must sign in at the main entrance of the Quantum Park facility and wait to be escorted by a Government employee to Eastern Federal Lands Highway Division (EFLHD) in Suite 200. Visitors must then register with the EFLHD Receptionist. A Government employee will collect all bids. Prior to the bid opening, a Government employee will escort all bidders to the bid opening. Unescorted visitors will be denied entry and no exceptions will be made.

https://beta.sam.gov/ mailto:eflhd.contracts@dot.gov

CHECKLIST FOR BID SUBMISSION

The following is a checklist of items included in the proposal/bid package that are required to be completed and returned (or filled in on-line) to the address in Block 7 of the Standard Form 1442, Solicitation, Offer, and Award (page 1). This checklist is for informational purposes only and is not required to be filled out by the bidder. Failure to submit a complete bid may be cause to reject your bid.

1. Bid Envelope:

a. Addressed as shown in Block 7 of SF-1442

b. In the lower left corner, indicate the following: Solicitation No., Project Name & Number, and mail to Suite E2-3-300, ATTENTION: ACQUISITIONS. If bids are hand-delivered, bring them to the main entrance of Quantum Park, and ask for the Federal Highway Administration (EFLHD) Receptionist to be contacted and an EFLHD representative will come to collect the bid.

2. Standard Form 1442: Solicitation, Offer and Award

a. Block 14: Name and Address of Bidder.

b. Block 15: Telephone Number of Bidder.

c. Block 16: Remittance Address if different from Block 14.

d. Block 19: All Amendments Acknowledged, with dates of Amendments.

e. Block 20: Bid is signed and dated.

3. Bid Schedule - (Pages B-1 through B-9)

a. Unit bid price and bid amount provided for each pay item in numbers.

b. Corrections initialed.

4. Standard Form 24, Bid Bond (Pages C-1 through C-2) (Required if bid guarantee is bid bond)

a. Date executed

b. Legal name and address of bidder.

c. Type of organization.

d. State of incorporation (if applicable).

e. Name and business address of Treasury approved surety.

f. Penal sum of bond (not less than 20% of bid total).

g. Bid identification.

h. Signature of Bidder

i. Seal, if corporation

j. Signature of Surety

k. Seal, if corporation

BIDS RECEIVED WITHOUT A VALID BID BOND WILL BE REJECTED.

5. Power of Attorney.

a. Dated on or before execution date of bond

b. Power has original signature of surety, or is embossed with surety's seal in the certification section

BIDS RECEIVED WITHOUT A VALID POWER OF ATTORNEY WILL BE REJECTED.

CHECKLIST FOR BID SUBMISSION

6. Bidder's Qualifications form (provided separately as part of the Bid Documents Package).

Form completed, signed and submitted with bid

7. System for Award Management (SAM): The contractor is currently registered in the System For Award Management (SAM) database at https://www.sam.gov/ at the time the bid is submitted. If the contractor elects to not have its active SAM registration viewable by the public, then the contractor must submit a copy with the bid.

8. Online Representations and Certifications Application: The contractor's Representations and Certifications have been input online via the electronic database at https://www.sam.gov/.

9. VETS – 4212 Reporting: The contractor has completed the annual reporting requirement online at http://www.dol.gov/vets/vets4212.htm.

The annual filing period for Form VETS-4212 is August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS- 4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.

NOTE: THE CONTRACTOR IS FULLY RESPONSIBLE TO VERIFY THAT ALL

DATA IN THE ABOVE DATABASES IS CORRECT EACH TIME A BID PACKAGE IS

SUBMITTED. FAILURE TO PROPERLY INPUT AND/OR UPDATE YOUR DATA

PRIOR TO BID SUBMISSION MAY CAUSE THE BID TO BE REJECTED.

https://www.sam.gov/ https://www.sam.gov/SAM/ http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

693C73

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

SUITE E2-3-300

ATTN: ACQUISITION BRANCH

ASHBURN VA 20147

See Block 7

JOHNNIE ORDONEZ

See Block 10 x

12/07/2020

693C7321B000008

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

This Invitation for Bids is for the Blue Ridge Parkway, Project No. NP-BLRI 1M20, located in Roanoke County, Virginia in strict accordance with the

Solicitation/Contract instructions, notices, clauses, provisions, items listed below, and for the quantities of work actually performed at the unit prices as bid in the Bid Schedule, including all applicable Federal, State, and local taxes.

FP - Standard Specification for Construction of Roads & Bridges on Federal Highway Projects.

Bid Schedule, Section B - pages B-1 through B-9.

Special Contract Requirements, Section J - pages J-1 through J-70

Plans, Sheets 1 through 101

Categorical Exclusion Report (NEPA), pages 1 through 7

Permits Obtained for this Project, pages 1 through 12

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 280 calendar days and complete it within ________________ ________________ calendar days after receiving

01/06/2021

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d) eflhd.contracts@dot.gov

�����./�0::/303�#73//5�20�9/3:03;�2./�=03D�3/AB83/>�#2�2./�9384/5�59/48:8/>�$/60=�81�523842�#4403>#14/�=82.�2./�2/3;5�0:�2.85�5068482#2801?�8:�2.85�0::/3�85�#44/92/>

$@�2./��0E/31;/12�81�=382817�=82.81�--------------------�4#6/1>#3�>#@5�#:2/3�2./�>#2/�0::/35�#3/�>B/����������

�%(��
�)��
�������
���
����� �������������������
���

�����./�0::/303�#73//5�20�:B3185.�#1@�3/AB83/>�9/3:03;#14/�#1>�9#@;/12�$01>5�

0��#������ ��2�

������������
H������

������� �)4��

3�2���%����

�����"��� � ��������
�������������
��" ��������������
�������������"���

����������3 4��� '5 '6 �--����7��

3�2���%���

�����������������������
H������

������� )4������ �$���� �� �4������

����2�� #��0 ��2�����

�)��������� )�&4'��������������� ������������ &4'���������������

�"������&��*���G��'����, Block 26

Federal Highway Administration Eastern Federal Lands Highway Division ATTN: Construction Branch Quantum Park 22001 Loudoun County Parkway Suite E2-2-200 Ashburn, VA 20147

Federal Highway Administration Eastern Federal Lands Highway Division A/P Branch, AMZ-150 P.O. Box 25710 or E-MAIL

9-AMC-AMZ-EFLINVOICES@FAA.GOV

Oklahoma City, OK 73125

EFLHD-CO

peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text

CONTINUATION OF SF 1442

Block 2:

This project is RESTRICTED - Bids will be accepted from all eligible Small Business concerns.

This procurement falls under North American Industry Classification System (NAICS) code 237310 - Highway, Street, and Bridge Construction (see FAR Subpart 19.10)

Facsimile and electronic bids will not be accepted.

PHYSICAL DATA AVAILABLE FOR REVIEW

1. Manual on Uniform Traffic Control Devices for Streets and Highways, 2009 Edition, published by the Federal Highway Administration. http://mutcd.fhwa.dot.gov.

2. National Park Service Sign Manual, revised - January 1988, United States Department of the Interior. http://flh.fhwa.dot.gov/resources/design/library

3. Categorical Exclusion Report (NEPA).

4. Permits

Block 9:

In accordance with FAR Provision 52.236-27, Site Visit, a Government representative can be available to show the project to prospective bidders. All requests for site visits see Section E of the solicitation and e-mail all questions concerning this construction project to the following e-mail address eflhd.contracts@dot.gov. Interested parties must provide the Solicitation Number and the relevant project name with all requests and questions.

∗Block 11:

Maximum Time Allowed if Schedule A + B are Awarded at the Same Time

If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 280 calendar days.

Maximum Time Allowed for Each Schedule of Work if Awarded Separately

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 250 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 135 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

See Completion of Work section of the B-Pages – Bid Schedule Instructions for further information. The completion time for the contract is not to exceed the maximum time above.

Work restrictions can be found in SCR Sections 108 and 156.

http://flh.fhwa.dot.gov/resources/design/library

CONTINUATION OF SF 1442

Notice to Proceed will be issued within 30 days following receipt of acceptable performance and payment bonds. (Actual Notice to Proceed date will be 10 days from issuance or the date specified in the Notice.)

Bidders are to assume that the award of the contract and approval of the Contractor’s Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228- 15) may result in the start of construction activities to be no earlier than March 2021. See Subsection 108.01 of the SCR’s for additional details.

Block 12A:

Furnish performance and payment bonds in accordance with FAR Clause 52.228-15.

Block 13:

A bid guarantee in the amount of not less than 20 percent of the bid price or $3 million, whichever is less, is required with this bid. If the bidder fails to provide the required bid guarantee, such failure may require rejection of the bid. Reference FAR Provision 52.228-1, Bid Guarantee.

Block 17:

Amounts should be completed as follows:

Schedule A - $ Schedule B (Option 1) - $

Other:

The estimated price is expected to fall within the price range of $1,000,000 to $5,000,000.

Responsibility of bidders shall be evaluated in accordance with the information provided on the Bidder's Qualification Form, which can be downloaded from the Contract Opportunities website located at http://beta.SAM.gov. FP-03 or FP-14 versions can be downloaded at the FHWA web site located at http://flh.fhwa.dot.gov/resources/specs/.

http://beta.sam.gov/ http://flh.fhwa.dot.gov/resources/specs/

BID SCHEDULE INSTRUCTIONS

PROJECT: NP-BLRI 1M20

BIDDERS PLEASE NOTE: Before preparing the bid, carefully read the Instructions to

Bidders. While preparing the bid, comply with the following:

COMPLETING THE BID SCHEDULE

Complete the Bid Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places, for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit Bid Price and Amount Bid for the pay item. Determine the Bid Total for each specific individual Schedule of Work by adding the amounts of the listed items, and show in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.

To be eligible for award, bidders must submit prices for each pay item.

Review Subsection 109.05 of the FP (standard specifications book) regarding scope of payment for direct and indirect payment work.

Fill in the Bid Total(s) for each individual Schedule of Work as directed on the Bid Summary page. Fill in the Evaluation Total Price of Project in the space provided on the Bid Summary page.

The amount in Block 17 of the SF 1442 should be completed as follows:

Schedule A - $ .

Schedule B - $ .

SCHEDULES OF WORK

The Bid Schedule is comprised of the following separate schedules and options of work:

Schedule A (Base Contract) - Pages B-1 thru B-3

Schedule B (Government Option 1) - Pages B-4 thru B-8

The Government will award the project as a Base Contract (Schedule A) with the option to award Schedule B (Government Option 1); see FAR Clauses 52.217-4 and 52.217-5.

The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price, by proper utilization of programmed funds and upon receipt of any additional funds required to award the contract. If complete funding is in place at the time of award of Schedule A (Base Contract), the Government may award Schedule B (Government Option 1) at that time. If additional funding is required for the award of Schedule B (Government Option 1), and is received after the award of Schedule A (Base Contract), the Government has the right to exercise Schedule B (Government Option 1) at the unit prices bid no later than the contract completion date for Schedule A (Base Contract).

COMPLETION OF WORK

The Government has estimated the number of calendar days necessary to complete all contract work from the effective date of the Notice to Proceed to contract completion for the various contract award scenarios. The maximum number of calendar days allowed (i.e., the contract performance period) is shown in Block 11 of the SF-1442 and described below.

If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 280 calendar days.

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 250 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 135 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

In developing a construction schedule to determine the number of calendar days, the Government considered and included the work limitations shown in Sections 108 and 156 of the FP and Special Contract Requirements (SCR’s). Specific work limitations may be (but are not limited to): National legal holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items are (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc). The Government also considered time required for preparing material and drawing submittals, and the allowable Government review times for those submittals (Subsection 104.03 of the FP and SCR’s).

Bidders are to assume that the award of the contract and approval of the Contractor’s Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-15) may result in the start of construction activities to be no earlier than March 2021. See Subsection 108.01 of the SCR’s for additional details.

BASIS FOR AWARD

The contract will be awarded to the responsive, responsible bidder with the lowest Evaluation Total Price of Project, which is defined as:

Schedule A (Base Contract) Bid Total + Schedule B (Government Option 1) Bid Total.

B - 1

Item No. Pay Item No. Description Quantity Unit Unit Price Amount

A1000 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

A1020 15201-0000 CONSTRUCTION SURVEY AND STAKING

ALL LPSM $___LPSM_____ $____________

A1040 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

A1060 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

650 LNFT $____________ $____________

A1080 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION

12 EACH $____________ $____________

A1100 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

1 EACH $____________ $____________

A1120 25102-0300 PLACED RIPRAP, METHOD A, CLASS 3

120 TON $____________ $____________

A1140 40101-0200 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL

MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL (PG 64-22, TYPE IV

PAVEMENT ROUGHNESS)

340 TON $____________ $____________

A1160 41301-0400 ASPHALT PAVEMENT MILLING, 1 1/2-INCH DEPTH (MICRO MILLING)

3,000 SQYD $____________ $____________

A1180 55220-0000 REPAIR CONCRETE (BOTTOM OF DECK)

15 SQYD $____________ $____________

A1200 55220-0000 REPAIR CONCRETE (PIERS)

50 SQYD $____________ $____________

A1220 55220-0000 REPAIR CONCRETE (TOP OF DECK)

50 SQYD $____________ $____________

A1240 55901-0000 MEMBRANE WATERPROOFING (THREE COAT SYSTEM)

3,000 SQYD $____________ $____________

Bid Schedule Schedule:A Schedule Type:Base

Project No:NP-BLRI 1M20

Project Name:Rehabilitation of Roanoke River Bridge near MP 115.0

B - 2

A1260 56001-0000 REMOVAL OF CONCRETE BY HYDRODEMOLITION (REMOVAL OF

REMAINING ASPHALT AND WATERPROOFING MEMBRANE)

3,000 SQYD $____________ $____________

A1280 56101-0000 STRUCTURAL CONCRETE INJECTION AND CRACK REPAIR (TOP AND

BOTTOM OF DECK AND PIERS)

40 LNFT $____________ $____________

A1300 56301-2000 PAINTING, STEEL STRUCTURE

ALL LPSM $___LPSM_____ $____________

A1320 56320-0000 CONTAINMENT SYSTEM AND WORKER PROTECTION PLAN

ALL LPSM $___LPSM_____ $____________

A1340 60510-0400 4-INCH OUTLET PIPE (SCUPPER EXTENSION)

70 LNFT $____________ $____________

A1360 60515-0000 UNDERDRAIN CLEANOUT (WEEPHOLE FILTER)

4 EACH $____________ $____________

A1380 60706-0000 CLEANING DRAINAGE STRUCTURE (SCUPPER & JOINT DRAINAGE PAN

CLEANING)

12 EACH $____________ $____________

A1400 61901-2100 FENCE, CHAIN LINK, 96-INCH HEIGHT (WITH GATE)

440 LNFT $____________ $____________

A1420 63401-2300 PAVEMENT MARKINGS, TYPE L, SOLID

1,000 LNFT $____________ $____________

A1440 63401-2400 PAVEMENT MARKINGS, TYPE L, BROKEN

600 LNFT $____________ $____________

A1460 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM

50 EACH $____________ $____________

A1480 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

100 EACH $____________ $____________

Bid Schedule Schedule:A Schedule Type:Base

B - 3

A1500 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

8 EACH $____________ $____________

A1520 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

155 LNFT $____________ $____________

A1540 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE

1,050 LNFT $____________ $____________

A1560 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

4,000 SQFT $____________ $____________

A1580 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:A Schedule Type:Base

B - 4

Item No. Pay Item No. Description Quantity Unit Unit Price Amount

B1000 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

B1020 15201-0000 CONSTRUCTION SURVEY AND STAKING

ALL LPSM $___LPSM_____ $____________

B1040 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

B1060 15705-1300 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL

260 LNFT $____________ $____________

B1080 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

420 LNFT $____________ $____________

B1100 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION

3 EACH $____________ $____________

B1120 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

1 EACH $____________ $____________

B1140 20103-0000 CLEARING AND GRUBBING

2,550 SQYD $____________ $____________

B1160 20220-1000 REMOVAL, INDIVIDUAL TREE

6 EACH $____________ $____________

B1180 20301-1400 REMOVAL OF INLET

1 EACH $____________ $____________

B1200 20301-2800 REMOVAL OF STRUCTURES AND OBSTRUCTIONS (BAFFLE)

1 EACH $____________ $____________

B1220 20302-0600 REMOVAL OF CURB, STONE

150 LNFT $____________ $____________

B1240 20302-0700 REMOVAL OF FENCE

150 LNFT $____________ $____________

B1260 20302-1200 REMOVAL OF GUARDRAIL

245 LNFT $____________ $____________

Bid Schedule Schedule:B Schedule Type:Options

B - 5

B1280 20302-2100 REMOVAL OF PIPE CULVERT

80 LNFT $____________ $____________

B1300 20302-2600 REMOVAL OF PAVEMENT MARKINGS

600 LNFT $____________ $____________

B1320 20303-1200 REMOVAL OF PAVED WATERWAY, ASPHALT

28 SQYD $____________ $____________

B1340 20315-0000 SAWCUTTING PAVEMENT

80 LNFT $____________ $____________

B1360 20401-0000 ROADWAY EXCAVATION

1,400 CUYD $____________ $____________

B1380 20701-0200 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE B

600 SQYD $____________ $____________

B1400 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E

1,330 SQYD $____________ $____________

B1420 20703-0000 GEOGRID (TYPE V)

1,900 SQYD $____________ $____________

B1440 25110-0200 GROUTED RIPRAP, METHOD A, CLASS 2

15 CUYD $____________ $____________

B1460 25501-1000 MECHANICALLY STABILIZED EARTH WALL, WELDED WIRE FACE

700 SQFT $____________ $____________

B1480 25510-0000 SELECT GRANULAR BACKFILL

940 CUYD $____________ $____________

B1500 30101-4000 AGGREGATE BASE GRADING C OR D

400 TON $____________ $____________

B1520 30202-1000 ROADWAY AGGREGATE, METHOD 1

5 TON $____________ $____________

B1540 30210-0000 BEDDING AND BACKFILL AGGREGATE (BEDDING MATERIAL)

75 CUYD $____________ $____________

Bid Schedule Schedule:B Schedule Type:Options

B - 6

B1560 31302-0400 AGGREGATE-TOPSOIL COURSE, 4-INCH DEPTH

230 SQYD $____________ $____________

B1580 40101-0200 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL

MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL (PG 64-22, TYPE IV

PAVEMENT ROUGHNESS)

105 TON $____________ $____________

B1600 40101-1000 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/4-INCH NOMINAL

MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL (PG 64-22)

175 TON $____________ $____________

B1620 41202-0000 TACK COAT

55 GAL $____________ $____________

B1640 60201-0400 12-INCH PIPE CULVERT

40 LNFT $____________ $____________

B1660 60201-0600 18-INCH PIPE CULVERT

100 LNFT $____________ $____________

B1680 60401-0000 MANHOLE

1 EACH $____________ $____________

B1700 60403-1800 INLET, FLH TYPE 6A MODIFIED

1 EACH $____________ $____________

B1720 60602-0500 PIPE ANCHOR ASSEMBLY, 18-INCH

5 EACH $____________ $____________

B1740 60815-0500 RECONDITION PAVED WATERWAY, TYPE 5

80 SQYD $____________ $____________

B1760 60901-5900 CURB, STONE, TYPE 2, 16-INCH DEPTH

155 LNFT $____________ $____________

B1780 61701-4000 GUARDRAIL SYSTEM SBTB

40 LNFT $____________ $____________

Bid Schedule Schedule:B Schedule Type:Options

B - 7

B1800 61702-0100 TERMINAL SECTION, TYPE SBT-BAT

2 EACH $____________ $____________

B1820 61702-0510 TERMINAL SECTION, TYPE SBT-FAT

1 EACH $____________ $____________

B1840 61707-2000 STRUCTURE TRANSITION RAILING, SBT SYSTEM

100 LNFT $____________ $____________

B1860 61901-0000 FENCE (TIMBER)

145 LNFT $____________ $____________

B1880 62028-1000 REMOVE AND RESET STONE MASONRY HEADWALL

1 EACH $____________ $____________

B1900 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (ARCHAEOLOGICAL

MONITORING)

ALL LPSM $___LPSM_____ $____________

B1920 62401-0700 FURNISHING AND PLACING TOPSOIL, 12-INCH DEPTH

525 SQYD $____________ $____________

B1940 62502-0000 TURF ESTABLISHMENT

750 SQYD $____________ $____________

B1960 62901-1000 ROLLED EROSION CONTROL PRODUCT, TYPE 3.B

520 SQYD $____________ $____________

B1980 63308-3000 OBJECT MARKER, TYPE 3

1 EACH $____________ $____________

B2000 63316-1000 REMOVE AND RESET SIGN

1 EACH $____________ $____________

B2020 63401-2300 PAVEMENT MARKINGS, TYPE L, SOLID

1,340 LNFT $____________ $____________

B2040 63401-2400 PAVEMENT MARKINGS, TYPE L, BROKEN

60 LNFT $____________ $____________

Bid Schedule Schedule:B Schedule Type:Options

B - 8

B2060 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE

1,775 LNFT $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:B Schedule Type:Options

B – 9

BID SUMMARY

Project NP-BLRI 1M20

(1) Schedule A (Base Contract) Bid Total (from Page B-3) = (1) $____________________

(2) Schedule B (Government Option 1) Bid Total (from Page B-8) = (2) $____________________

Total Price of Project (for evaluation purposes only)

EVALUATION TOTAL PRICE OF PROJECT = (1) + (2) $____________________

Maximum Time Allowed for the Contract if Schedules A and B are Awarded at the Same Time

If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 280 calendar days.

Maximum Time Allowed for Each Schedule of Work if Awarded Separately

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 250 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 135 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

BID BOND

(See instructions on reverse)

OMB Control Number: 9000-0045 Expiration Date: 8/31/2022

PRINCIPAL (Legal name and business address) TYPE OF ORGANIZATION ("X" one)

STATE OF INCORPORATION

SURETY(IES) (Name and business address)

PERCENT

OF BID

PRICE

PENAL SUM OF BOND

AMOUNT NOT TO EXCEED

MILLION(S) THOUSAND(S) HUNDRED(S) CENTS

BID IDENTIFICATION

BID DATE INVITATION NUMBER

PRINCIPAL

SIGNATURE(S)

NAME(S) &

TITLE(S)

(Typed)

1.

1. 2.

2.

3.

3.

(Seal) (Seal) (Seal) Corporate Seal

INDIVIDUAL SURETY(IES)

SIGNATURE(S)

NAME(S)

(Typed)

1.

1.

2.

2.

(Seal) (Seal)

CORPORATE SURETY(IES)

NAME &

ADDRESS

STATE OF INCORPORATION LIABILITY LIMIT ($)

SIGNATURE(S)

NAME(S) &

TITLE(S)

(Typed)

1.

1.

2.

2. Corporate Seal

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is NOT usable

STANDARD FORM 24 (REV. 8/2016)

Prescribed by GSA - FAR (48 CFR) 53.228(a)

FOR (Construction, Supplies or Services)

OBLIGATION:

We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.

CONDITIONS:

The Principal has submitted the bid identified above.

THEREFORE:

The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.

Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government.

Notice to the surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.

WITNESS:

The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.

DATE BOND EXECUTED (Must not be later than bid opening date)

Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0045. We estimate that it will take 1 hour to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.

JOINT VENTURE

OTHER (Specify)

PARTNERSHIPINDIVIDUAL

CORPORATION

INSTRUCTIONS

1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.

2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.

3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).

4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the LIABILITY LIMIT block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.

(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "CORPORATE SURETY(IES)." In the space designated "SURETY(IES)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.

(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond.

The Government may require the surety to furnish additional substantiating information concerning its financial capability.

5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals.

6. Type the name and title of each person signing this bond in the space provided.

7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and "offeror."

NAME &

ADDRESS

STATE OF INCORPORATION LIABILITY LIMIT ($)

SIGNATURE(S)

NAME(S) &

TITLE(S)

(Typed)

1.

1.

2.

2. Corporate Seal

Corporate Seal

LIABILITY LIMIT ($)STATE OF INCORPORATION

2.

2.

1.

1.NAME(S) &

TITLE(S)

(Typed)

SIGNATURE(S)

NAME &

ADDRESS

Corporate Seal

LIABILITY LIMIT ($)

2.

2.

STATE OF INCORPORATION

1.

1.

NAME(S) &

TITLE(S)

(Typed)

SIGNATURE(S)

NAME &

ADDRESS

Corporate Seal

LIABILITY LIMIT ($)

2.

2.

STATE OF INCORPORATION

1.

1.

NAME(S) &

TITLE(S)

(Typed)

SIGNATURE(S)

NAME &

ADDRESS

Corporate Seal

LIABILITY LIMIT ($)

2.

2.

STATE OF INCORPORATION

1.

1.

NAME(S) &

TITLE(S)

(Typed)

SIGNATURE(S)

NAME &

ADDRESS

Corporate Seal

LIABILITY LIMIT ($)

2.

2.

STATE OF INCORPORATION

1.

1.

NAME(S) &

TITLE(S)

(Typed)

SIGNATURE(S)

NAME &

ADDRESS

STANDARD FORM 24 (REV. 8/2016) BACK

CONTRACT CLAUSES INDEX

FEDERAL ACQUISITION REGULATION (FAR) TRANSPORTATION ACQUISITION REGULATION (TAR)

(Updated thru FAC 2021-02 on 11/23/2020)

FAR & TAR CLAUSES INCORPORATED BY REFERENCE

CLAUSE TITLE DATE REMARKS

52.202-1 DEFINITIONS Jun-20 52.203-3 GRATUITIES Apr-84 52.203-5 COVENANT AGAINST CONTINGENT FEES May-14 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT Jun-20 52.203-7 ANTI-KICKBACK PROCEDURES Jun-20 52.203-8 CANCEL & RECOVER OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY May-14 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY May-14

52.203-11

CERTIFICATION AND DISCLOSURE REGARDING PAYMENTS TO INFLUENCE CERTAIN FEDERAL

TRANSACTIONS Sep-07

52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS Jun-20 52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT Jun-20 52.203-14 DISPLAY OF HOTLINE POSTER(S) Jun-20 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER May-11 52.204-7 SYSTEM FOR AWARD MANAGEMENT Oct-18 Contractor Mandatory Internet Data Input 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS Jun-20 Contractor Mandatory Internet Data Input 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE Oct-18 Contractor Mandatory Internet Data Input 52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS Oct-16 Contractor Mandatory Internet Data Input 52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING Aug-20 52.204-17 OWNERSHIP OR CONTROL OF OFFEROR Aug-20 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE Aug-20 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS Dec-14 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS Jun-16

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED OR PROPOSED FOR DEBARMENT Jun-20

52.209-11

REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A FELONY

CONVICTION UNDER ANY FEDERAL LAW Feb-16

52.214-5 SUBMISSION OF BIDS Mar-97 52.214-19 CONTRACT AWARD -- SEALED BIDDING-CONSTRUCTION Aug-96 52.214-26 ALT 1 AUDIT AND RECORDS -- SEALED BIDDING (ALT 1 - (MAR 09)) Jun-20 52.214-27 PRICE REDUCTION FOR DEFECTIVE COST OR PRICING DATA - MODIFICATIONS - SEALED BIDDING Jun-20 52.214-28 SUBCONTRACTOR COST OR PRICE DATA -- MODIFICATIONS--SEALED BIDDING Aug-20 52.214-29 ORDER OF PRECEDENCE - SEALED BIDDING Jan-86 52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE Apr-91 52.214-35 SUBMISSION OF OFFERS IN THE U.S. CURRENCY Apr-91

52.252-2 Clauses Incorporated By Reference (Feb 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. The full text of a clause may be accessed electronically at this address: www.acquisition.gov

(End of Clause)

(Updated thru FAC 2021-02 on 11/23/2020)

52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE Nov-20 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS Oct-18 52.219-9 ALT 1 SMALL BUSINESS SUBCONTRACTING PLAN (ALT 1 - (Nov 16)) Jun-20 Large Business Mandatory Submittal Requirement 52.219-14 LIMITATIONS ON SUBCONTRACTING Mar-20 52.219-16 LIQUIDATED DAMAGES - SUBCONTRACTING PLAN Jan-99 52.219-31 NOTICE OF SMALL BUSINESS RESERVE Mar-20 52.219-32 ORDERS ISSUED DIRECTLY UNDER SMALL BUSINESS RESERVES Mar-20 52.219-33 NONMANUFACTURER RULE Mar-20 52.222-3 CONVICT LABOR Jun-03 52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS -- OVERTIME COMPENSATION May-18 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS - SECONDARY SITE OF THE WORK May-14 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS Aug-18 Contractor Mandatory Wage Rates Posting 52.222-7 WITHHOLDING OF FUNDS May-14 52.222-8 PAYROLLS AND BASIC RECORDS Aug-18 Contractor Weekly Payroll Submittals 52.222-9 APPRENTICES AND TRAINEES Jul-05 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS Feb-88 52.222-11 SUBCONTRACTS (LABOR STANDARDS) May-14 52.222-12 CONTRACT TERMINATION -- DEBARMENT May-14 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS May-14 52.222-14 DISPUTES CONCERNING LABOR STANDARDS Feb-88 52.222-15 CERTIFICATION OF ELIGIBILITY May-14 52.222-19 CHILD LABOR - COOPERATION WITH AUTHORITIES AND REMEDIES Mar-20 52.222-21 PROHIBITION OF SEGREGATED FACILITIES Feb-99 52.222-26 EQUAL OPPORTUNITY Sep-16 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION Apr-15 52.222-32 CONSTRUCTION WAGE RATE REQUIREMENTS - PRICE ADJUSTMENT (ACTUAL METHOD) Aug-18

52.222-35 EQUAL OPPORTUNITY FOR SPECIAL DISABLED VETERANS, VETERANS OF THE VIETNAM ERA, & OTHER ELIGIBLE VETERANS Jun-20

52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES Jun-20 52.222-37 EMPLOYMENT REPORTS ON VERTERANS Jun-20 52.222-38 COMPLIANCE WITH VETERANS' EMPLOYMENT REPORTING REQUIREMENTS Feb-16 Contractor Annual Mandatory Reporting Requirement 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT Mar-15 52.222-50 COMBATING TRAFFICKING IN PERSONS Oct-20 52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 Nov-20 52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 Jan-17 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS Sep-13 http://www.biopreferred.gov 52.223-5 POLLUTION PREVENTION AND RIGHT TO KNOW INFORMATION May-11 52.223-6 DRUG-FREE WORKPLACE May-01 Contractor Annual Contractor Reporting Reqt 52.223-10 WASTE REDUCTION PROGRAM May-11 52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION CONTRACTS Aug-18 Mandatory 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING Jun-20 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES Jun-08 52.227-1 AUTHORIZATION AND CONSENT Jun-20 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT Jun-20 52.227-4 PATENT INDEMNITY-CONSTRUCTION CONTRACTS Dec-07 52.227-14 RIGHTS IN DATA - GENERAL May-14 52.227-17 RIGHTS IN DATA - SPECIAL WORKS Dec-07 52.228-1 BID GUARANTEE Sep-96 52.228-2 ADDITION BOND SECURITY Oct-97 Contractor Submittal Requirement http://www.biopreferred.gov/

(Updated thru FAC 2021-02 on 11/23/2020)

52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION Jan-97 52.228-11 PLEDGES OF ASSETS Aug-18 52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS May-14 52.228-14 IRREVOCABLE LETTER OF CREDIT Nov-14 Contractor Submittal Requirement 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION Jun-20 52.229-3 FEDERAL, STATE, AND LOCAL TAXES Feb-13 52.230-2 COST ACCOUNTING STANDARDS Jun-20 52.230-3 DISCLOSURE AND CONSISTENCY OF COST ACCOUNTING PRACTICES Aug-20 52.230-6 ADMINISTRATION OF COST ACCOUNTING STANDARDS Jun-10 Contractor Submittal Requirement 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS May-14 52.232-13 NOTICE OF PROGRESS PAYMENTS Apr-84 52.232-16 PROGRESS PAYMENT Jun-20 52.232-17 INTEREST May-14 52.232-18 AVAILABILITY OF FUNDS Apr-84 52.232-23 ASSIGNMENT OF CLAIMS May-14 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS Jan-17 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD MANAGEMENT Oct-18 52.232-39 UNINFORCEABILITY OF UNAUTHORIZED OBLIGATIONS Jun-13 52.233-1 ALT 1 DISPUTES (ALT-1, DEC-91) May-14 52.233-3 PROTEST AFTER AWARD Aug-96 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM Oct-04 52.236-2…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .