About this file

This Invitation for Bids (IFB) is issued by the Housing Authority of the City of Pawtucket (PHA), Rhode Island, for the St Germain Manor Site Walkway and Staircase Repair project located in Pawtucket, Rhode Island. The scope of work includes re-pavement of existing walkways, replacement of two precast concrete stairs, and concrete work at the St. Germain Manor facility. The IFB was issued on November 5, 2026, with a pre-bid meeting scheduled for November 17, 2026, at 10:00 AM at the project site (401 Mineral Spring Avenue, Pawtucket, RI). A deadline for submitting questions was set for November 19, 2026, with an addendum to be issued on November 20, 2026. Sealed bids are due electronically through Housing Agency Marketplace by December 8, 2026, at 10:00 AM EST, with the bid opening occurring immediately thereafter. Bidders must be registered on SAM.gov and hold an active UEI number in good standing. The contractor must commence work on dates specified in the contract documents and complete all work within the established contract period, with liquidated damages of $300 per calendar day assessed for delays beyond the contract completion date.

Bid security in the form of a bid bond, certified check, or cashier's check equal to 5 percent of the bid amount must accompany each bid. The successful bidder must furnish a 100 percent performance bond and 100 percent labor and material payment bond within 10 calendar days of bid acceptance notification. The contract is subject to Davis-Bacon prevailing wage requirements (Wage Decision RI20260002 Modification 2), with certified payroll submissions required weekly. The PHA will award the contract to the lowest responsible and responsive bidder meeting all qualifications. The contractor must maintain comprehensive liability, auto, and workers' compensation insurance naming the PHA as an additional insured, along with builder's risk insurance on all work in place and stored materials. The contractor is responsible for all labor, materials, equipment, permits, site safety compliance with OSHA requirements, debris removal, and restoration of work areas to pre-construction condition at no additional cost to the PHA. Minority and women-owned businesses are encouraged to submit bids, and the contractor must make positive efforts to expend at least 20 percent of the contract dollar amount with certified minority and women-owned business enterprises as subcontractors and suppliers.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION FOR BIDS (IFB)

St Germain Manor - Site Walkway and Staircase Repair

ISSUE DATE: November 5, 2026

BID DUE DATE: December 8, 2026

BY 10:00 AM EST

Alissa Stipa Capital Projects Coordinator astipa@pawthousing.org

The Housing Authority of the City of Pawtucket 214 Roosevelt Ave Pawtucket RI 02860 www.pawthousing.org mailto:your%20email@PROVHOUSING.ORG http://www.pawthousing.org/

The Housing Authority of the City of Pawtucket

TABLE OF CONTENTS

BID OVERVIEW AND INSTRUCTIONS

• INVITATION FOR BIDS

• PHA BACKGROUND

• PHA 2026 HOLIDAY SCHEDULE

• PHA 2027 HOLIDAY SCHEDULE

• PHA INSTRUCTIONS TO BIDDERS

• CONTRACTOR RESPONSIBILITIES

• BID PACKAGE REQUIREMENTS

• BID EVALUATION

• FORM HUD-5369: INSTRUCTIONS TO BIDDERS FOR CONTRACTS

• FORM HUD-5370: GENERAL CONDITIONS FOR CONSTRUCTION

CONTRACTS

• PHA SPECIAL INSTRUCTIONS THAT PERTAIN TO FORM HUD-5370

APPENDIX A: SAMPLE DOCUMENTS

• PAWTUCKET HOUSING AUTHORITY CERTIFICATE OF INSURANCE SAMPLE

APPENDIX B: EEO AND DAVIS BACON REQUIREMENTS

• LAWS ENFORCED BY E.E.O.

• DAVIS-BACON ACT WAGE DECISION #RI20260001 MOD 4

• CERTIFIED PAYROLL FORM WH-347 {SAMPLE}

• INSTRUCTIONS FOR COMPLETING PAYROLL FORM, WH-347

• FORM HUD 11 - RECORD OF EMPLOYEE INTERVIEW INSTRUCTIONS {SAMPLE}

APPENDIX C: SCOPE OF WORK

• SCOPE OF WORK

APPENDIX D: FORMS TO BE SUBMITTED TO PHA WITH THE BID PACKAGE

• BID SUBMISSION FORM

• HUD FORM 5369-A: REPRESENTATION, CERTIFICATIONS, AND OTHER STATEMENTS

OFBIDDERS,PUBLIC AND INDIAN HOUSING PROGRAMS

• COMPANY PROFILE FORM

• NON-COLLUSIVE AFFIDAVIT (Notarized)

• PAWTUCKET HOUSING AUTHORITY CERTIFICATE OF INSURANCE SAMPLE

• VENDOR DISCLOSURE AGREEMENT

• PREVIOUS PARTICIPATION - HUD FORM 2530

• CLIENT REFERENCES FORM

• LIST OF SUBCONTRACTORS

• CERTIFICATION FOR CONTRACT, GRANT, LOAN, AND COOPERATIVE AGREEMENT

• FAIR EMPLOYMENT PRACTICE STATEMENT

• CERTIFICATION OF DAVIS BACON PREVAILING WAGE

• COPY OF RHODE ISLAND CONTRACTOR’S LICENSE

INVITATION FOR BIDS

The Housing Authority of the City of Pawtucket (“PHA”) Rhode Island is accepting electronic, sealed bids from qualified vendors for St Germain Manor - Site Walkway and Staircase Repair located in Pawtucket, RI. Detailed information regarding the work encompassed under this project is provided in the Scope of Work section of this Invitation for Bids.

The key milestone dates from the publication of the bid to the bid submission deadline are outlined below:

Invitation For Bids Issued November 5, 2026

Pre-Bid Meeting November 17, 2026 at 10:00am

Deadline for Submitting Questions November 19, 2026 addendum issued November 20, 2026

Bid Submission Due Date December 8, 2026 by 10:00am

Bid Opening Date December 8, 2026 at 10:00am

Electronic Submission Only Microsoft Teams link is below to join the bid opening:

Details for each milestone date could be found under PHA INSTRUCTIONS TO BIDDERS.

It shall be the responsibility of any and all bidders to consult the Pawtucket Housing website at https://www.pawthousing.org/bidding-opportunities/ for the complete Invitation for Bids, to be aware of and to abide by all dates, times, conditions, requirements, and specifications set forth in this IFB and any addendum, RFI response, Pre-bid meeting agenda and notes issued by the PHA, prior to submitting their bids.

Please note that bids will be submitted through Housing Agency Marketplace. Bidders will need an active account on Housing Agency Marketplace dedicated to Pawtucket Housing Authority. If you already have an account, you will only be able to submit RFI questions and bids if you are dedicated to Pawtucket Housing Authority. If you need to change your dedication, please email support@internationalprocurement.com and ask for your dedication to be changed. Please ensure you have done this prior to submitting a bid to fix any issues that might arise.

By virtue of completing, signing, and submitting the completed documents, the bidder is stating his/her agreement to comply with all conditions and requirements set forth within those documents. The PHA:

• Will not accept bids submitted by fax or email.

• Will not be responsible for the receipt of bids not properly submitted.

• Will not accept bids received after the above deadline.

Minority and Woman-Owned Businesses are encouraged to submit bids. Bidders will be required to make positive efforts to use small and minority-owned businesses and to offer employment, training, and contracting opportunities in accordance with Section 3 of the Housing and Urban Development Act of 1968 (24 CFR Part 75).

Individuals requiring interpreter services for the hearing-impaired should notify the Facilities Management Department by calling (401) 709-2201 seventy-two (72) hours prior to any event.

Microsoft Teams Link:

https://teams.microsoft.com/meet/2793924499431543?p=rcywdEDf0zwQXPeMaP https://www.pawthousing.org/bidding-opportunities/ https://www.ecfr.gov/current/title-24/subtitle-A/part-75

PHA BACKGROUND

The Housing Authority of Pawtucket is a public entity that was formed in 1937 to provide federally subsidized housing and housing assistance to low-income families, within the City of Pawtucket, RI. The Agency is headed by an Executive Director (ED) and is governed by a seven-person board of commissioners and is subject to the requirements of Title 24 of the Code of Federal Regulations and the Agency’s procurement policy. Though brought into existence by a Resolution of the City of Pawtucket, it is a separate entity from the City.

Currently, the Agency owns, manages and/or is in partnership for: (a) 6 developments totaling 784 units of HUD Public Housing; and (b) administrates a total of 800 Section 8 Housing Choice Vouchers. The Agency currently has 50 employees.

In keeping with its mandate to provide efficient and effective services, the Agency is now soliciting proposals from qualified, licensed and insured entities to provide the above noted services to the Agency. All proposals submitted in response to this solicitation must conform to all of the requirements and specifications outlined within this document and any designated attachments in its entirety.

Vision Statement: The Pawtucket Housing Authority serves as a facilitator in promoting the health, safety, and progress of our families and the overall community.

Mission Statement: The Mission of the Pawtucket Housing Authority is to provide safe, decent, and affordable housing and to establish programs that will educate, enhance, and empower the lives of all the people in the community we serve.

Pawtucket Housing Authority

2026 Holiday Schedule

Day Date Holiday

Thursday 01/01/2026 New Year’s Day

Monday 01/19/2026 Martin Luther King

Monday 02/16/2026 President's Day

Monday 05/25/2026 Memorial Day

Friday 06/19/2026 Juneteenth

Friday 07/03/2026 Independence Day

Monday 08/10/2026 Victory Day

Monday 09/07/2026 Labor Day

Monday 10/12/2026 Columbus Day

Wednesday 11/11/2026 Veteran's Day

Wednesday 11/25/2026 Thanksgiving Eve - 1/2 Day

Thursday 11/26/2026 Thanksgiving Day

Friday 11/27/2026 Day after Thanksgiving

Thursday 12/24/2026 Christmas Eve - 1/2 Day

Friday 12/25/2026 Christmas Day Thursday 12/31/2026 New Year's Eve - 1/2 Day

Pawtucket Housing Authority

2027 Holiday Schedule

Date Holiday

Friday, January 1st, 2027 New Year’s Day

Monday, January 18, 2027 Martin Luther King Jr Day

Monday, February 15, 2027 Presidents’ Day

Monday, May 31, 2027 Memorial Day

Friday, June 18, 2027 Juneteenth

Monday, July 5, 2027 Independence Day

Monday, August 9, 2027 Victory Day

Monday, September 6, 2027 Labor Day

Monday, October 11th, 2027 Columbus Day

Thursday, November 11, 2027 Veterans Day

Wednesday, November 24th, 2027 Thanksgiving Eve ~ ½ Day

Thursday, November 25, 2027 Thanksgiving Day

Friday, November 26, 2027 Day After Thanksgiving

Thursday, December 23, 2027 Christmas Eve(Obs.) ~ ½ Day

Friday, December 24, 2027 Christmas Day (Observed)

Thursday, December 30, 2027 New Year’s Eve(Obs.) ~ ½ Day

ADVERTISEMENT TO BID

Section 00 11 13 - Page 1 of 1 © THE ROBINSON GREEN BERETTA CORPORATION – 7033

SECTION 00 11 13 – ADVERTISEMENT TO

BID Pawtucket Housing Authority - St

Germain Site Walkway and Staircase Repair

October 29, 2026

SECTION 00 11 13 – ADVERTISEMENT TO BID

Pawtucket Housing Authority

ADVERTISEMENT FOR BIDS

St Germain Site Walkway and Staircase Repair

Sealed bids for the Pawtucket Housing Authority – Repaving and concrete work Project will be received at the Pawtucket Housing Authority (PHA) 214 Roosevelt Avenue Pawtucket, RI 02860 until 12/8/26 by 10:00am . Each sealed bid needs to be marked on the outside of the envelope “Pawtucket Housing Authority - St Germain Site Walkway and Staircase Repair”. This project is subject to prevailing wage rates. Minority and women owned businesses are encouraged to submit bids.

The Pawtucket Housing Authority – Repaving and concrete, Project work encompassed under this Contract shall include, but not limited to; re-pavement of existing walkways, replacement of (2) precast concrete stairs and concrete work at St. Germain Manor Pawtucket RI.

The Bidder must agree to commence work and fully complete the work of this Contract on the dates specified in the contract documents. The Bidder must agree also to pay liquidated damages for each consecutive calendar day thereafter as hereinafter provided in the Contract and General Conditions.

BID SECURITY in the form of bid bond, certified check, treasurer's check or cashier's check in the amount of 5(%) percent of the bid amount must accompany each Bid. No bidder may withdraw his Bid within 90 days after the actual date of the opening thereof.

Email goliveira@rgb.net for a copy of the Plans and Bid Documents starting on or after 10/29/26. Plans and Bid Documents are also available on or after 10/29/26 at https://www.pawthousing.org/bids.aspx.

There will be a non-mandatory pre-bid conference on 11/17/26 at 10:00am at St Germain Manor located at 401 Mineral Spring Ave. Pawtucket, RI 02860.

Successful bidder must furnish 100% Performance Bond and 100% Labor and Material Payment Bond and the required insurance certificates and execute the Agreement within (10) calendar days following notification of the Acceptance of his/her Bid.

The Pawtucket Housing Authority reserves the right to reject any and all bids, to waive any technical or legal deficiencies, to accept individual bid items and excluding others, and to accept any a bid that it may deem to be in the best interest and most responsive of the Owner.

Attention of the bidders is particularly called to the requirements as to conditions of employment to be observed and minimum wage rates to be paid under the Contract. In conformity with the Provisions of Chapter 13 of Title 37, General Laws, Rhode Island, 1956, as amended, the minimum wages for a day's work paid to craftsmen, teamsters and laborers shall be not less than the customary and prevailing rate of wages for a day's work in the locality where the work is undertaken. Such a schedule of wages has been established on a minimum hourly basis and is on file in the office of the State Department of Labor.

All questions shall be submitted to George Oliveira, Project manager at RGB Architects, 401-272-1730. email:

goliveira@rgb.net by 11/19/26. Upon receipt of any written questions, an addendum will be issued to all bidders on 11/20/26.

END OF SECTION 00 11 13

https://sam.gov/content/home mailto:rmessier@verdantas.com

Work Schedule:

• Daily Schedule: Monday – Friday 7:30 AM to 3:30 PM except for PHA holidays. The holiday schedule is included in this bid package after "PHA Background."

Logistics:

• Limited space for vehicles, storage, construction equipment

• Other details to be determined at pre-construction meeting

CONTRACTOR RESPONSIBILITIES

General:

• The contractor must be sam.gov certified and be able to provide an active UEI number in goodstanding.

• The Contractor shall supply all labor, materials, equipment, tools, construction equipment,machinery, water, heat, utilities, transportation and other facilities and services necessary for theproper execution and completion of the work.

• The Contractor shall obtain any permits required to perform work as outlined in the biddocuments. The PHA does not pay / get charged permit fees by the city.

• Work is to be performed in accordance with this IFB, scope of work, specifications, andamendments, if any.

• The PHA only recognizes one contractor as party to this Contract.

• The Contractor shall promptly submit written notice, within five (5) business days of discovery, tothe PHA of any observed variance of contract documents from legal requirements.

• The Contractor shall comply with all applicable laws, ordinances, and codes of the State andlocal governments, and shall commit no trespass on any public or private property in performingany of the work embraced by this Contract.

• The Contractor shall not make any substitutions for materials without prior written authorizationfrom the PHA.

• The Contractor shall be responsible for all their material, equipment, and other items onsite.

• The Contractor shall notify the PHA of any long lead time items that may impact completiondates.

• Contractor’s Project Manager or Site Supervisor shall participate in project meetings with thePHA.

• The Contractor shall submit a “pencil requisition” on an AIA form to Verdantas for approval.

Once the invoice is approved and signed, Verdantas will send the form to the PHA, for review and approval prior to submitting an invoice for payment.

Personnel:

• All employees of the Contractor, subcontractors, or other representatives shall be skilled in the type of work for which they are employed on the project and shall work under the direction of a competent superintendent.

• All employees of the Contractor, subcontractors, and/or other representatives shall be licensed as required by local, state, and/or federal law and regulations to perform the type of work for which they are employed on the project.

• All employees of the Contractor, subcontractors, or other representatives shall be legally authorized to work in the United States.

• The Contractor is responsible for all personnel involved in the work, including those of its direct employ, its sub-contractors and suppliers of materials and equipment and/or labor.

• The Contractor shall enforce strict discipline and good order among employees.

• Should the PHA deem anyone employed in the work incompetent or unfit for their duties, the

Contractor shall remove such employee from the work and shall not re-employ them for work within the PHA on this project without prior written permission from the PHA. The Contractor shall select and employ the replacement personnel.

• All personnel shall be neat in appearance and shall conduct their work in a professional manner.

• The Contractor shall not park their vehicles on grassy areas of the properties without prior written authorization from the PHA.

Apprentices:

See attached HUD 5370 for additional detailed information regarding Apprentices.

• Apprentices will be permitted to work at less than the predetermined rate noted in Davis Bacon Wage Decision under specific circumstances:

1. They are employed pursuant to and individually registered in a bona fide apprenticeship program registered with the US Department of Labor (USDOL).

2. The allowable ratio of apprentices to journeymen shall not be greater than the ratio permitted to the employer as to the entire work force under the approved program.

3. If the State or USDOL withdraws approval of an apprenticeship program, the Contractor will no longer be permitted to utilize apprentices. All employees must then be paid the full Davis Bacon Wage Rate.

Site Safety & Precautions:

• All work performed pursuant to this Contract must conform and comply with all applicable local, state, and federal codes, statutes, laws, and regulations.

• The Contractor shall follow all applicable OSHA safety requirements.

• The Contractor shall supply all safety or warning signs, equipment, plastic covers, barricades, and any other specialty items that may be required.

• The Contractor shall provide adequate protection for all persons and all PHA personnel within the working area.

• The Contractor shall not, at any time, leave work in an unsafe condition or any conditions that might cause personal injury or property damage, but shall continue to work until work is in a safe space to stop.

• The Contractor shall keep the working area sufficiently clear of equipment, material, and implements of service to prevent endangering persons and damage to the PHA property and to avoid an unsightly condition. Removal of such items shall be performed promptly upon completion of work.

• The Contractor shall ensure that clear, safe, passage remains available for access of tenants in the building if applicable.

• The Contractor shall be responsible for removing and protecting any equipment that may interfere with construction operations. Immediately upon completion of construction activities in each area, the Contractor shall return the area to a pre-construction state satisfactory to the

PHA.

Damage to the PHA Property:

• The Contractor shall be responsible for repair of any damage to the PHA property and restoration of any area disturbed by Contractors or subcontractor’s work to the satisfaction of the PHA’s Authorized Representative prior to final payment.

• Any repair and/or restoration of the damaged area shall be performed at no cost to the PHA.

Debris Removal:

• The Contractor shall be responsible for the physical removal and lawful disposal of all debris generated during construction of this project in accordance with all local, state, and federal requirements. These costs shall be factored into the pricing submitted by the Contractor.

• The Contractor shall not use the PHA facilities for disposal of debris and waste material, whether hazardous or non-hazardous. The trash receptacles on site are not to be used for disposal of construction debris.

Sub-Contracting:

• Unauthorized sub-contracting is prohibited. The successful proposer shall not assign any right, nor delegate any duty for the work proposed pursuant to this IFB (including, but not limited to, selling, or transferring the contract) without the prior written consent of the PHA.

• Any purported assignment of interest or delegation of duty without the prior written consent of the PHA shall be void and may result in the cancellation of the contract or may result in the full or partial forfeiture of funds paid to the successful proposer as a result of the proposed contract.

Delivery, Storage, and Handling:

• All materials shall be delivered to the jobsite in new, dry, unopened, and clearly marked containers with the product and manufacturer’s name.

• All materials shall be delivered in sufficient quantity to allow for continuity of work.

• All plastic packing shrouds must be removed.

• All materials shall be covered with a secure canvas tarp from top to bottom.

• All materials shall be handled to avoid bending, tearing, or other damage during transportation and installation.

• Equipment shall be selected and operated so it will not damage existing construction or any new materials.

• All materials and equipment shall be handled in accordance with the manufacturer’s guidelines.

• Any damage to materials or existing construction caused by the Contractor’s failure to protect such, shall be repaired or replaced at no additional expense to the PHA.

Keys And Access:

• The Contractor and a member of the PHA shall ensure all PHA facilities & materials are secured at the close of each day.

• The Contractor shall coordinate with the PHA a minimum of three (3) days prior to any work performed for tenant unit access.

• The Contractor, if issued an electronic fob, shall maintain strict control of it for the duration of the project.

• The Contractor shall immediately notify the PHA if the key card has been lost.

• The Contractor shall return the key card to the PHA at the close of the project.

BID PACKAGE REQUIREMENTS

The The Housing Authority of The City of Pawtucket is seeking qualified vendors for the St Germain Manor - Site Walkway and Staircase Repair, located in Pawtucket, RI.

The selected Contractor shall provide all labor and materials needed to complete the project in a workmanlike manner. Work shall be done in strict accordance with terms and conditions in this Invitation for Bids (IFB); and the Specifications included in this IFB.

Please refer to APPENDIX C: SCOPE OF WORK for project details.

Since the PHA will not be aware of all who may submit bids, it is the responsibility of all bidders to inquire after any amendment(s) issued to this bid solicitation prior to their bid submittal. Bidders are responsible for reviewing in-depth the entire bid package, scope of work, plans and specifications, amendments (if any), and any other information contained in the Invitation for Bids. All bids are considered final and must be submitted before the deadline.

The bid package, as submitted, shall include the following documents (as listed below). The PHA will not be responsible for the receipt of bids not properly submitted.

1. Bid Form

2. Letter of Surety

3. Bid Bond

4. HUD Form 5369-A

5. Company Profile Form

6. Non-Collusive Affidavit (Notarized)

7. Vendor Disclosure Agreement

8. Client References Form, Minimum of three (3) references of similar projects

9. List of all Subcontractors (All subcontractors subject to review and approval by the PHA)

10. Certification for Contracts, Grants, Loan, and Cooperative Agreement

11. Contingent Fees Statement

12. Fair Employment Practice Statement

13. Certification of Davis Bacon Prevailing Wage Rates

14. Copy of Rhode Island Contractor’s License

Note: The "Previous Participation Certificate" indicated in Clause 12 of the Representations, Certifications, and Other Statements of Bidders (HUD Form 5369-A), need not be included.

By completing, executing, and submitting a bid, the bidder is thereby agreeing to abide by all terms and conditions pertaining to this IFB as issued by the PHA, including the contract Terms and Conditions included in APPENDIX A. Accordingly, the PHA has no responsibility to conduct after the submittal deadline any negotiations pertaining to the contract clauses already published.

Additional Bidder Credentials:

• Contractor shall be registered on Sam.gov ( https://sam.gov/content/home ).

• Contractor shall not be barred from doing business with HUD / receiving Federal Funds.

Insurance:

• The winning bidder will be required to name the PHA as an additional insured and maintain the insurance for the duration of the Contract.

• The winning bidder will be required to provide a certificate of comprehensive liability / auto / workers compensation insurance. Please refer to the included Pawtucket Housing Authority Certificate of Insurance Sample for required insurance amounts and verbiage to match.

• The winning bidder shall furnish the PHA a Certificate of Insurance evidencing that, Builder's Risk (Fire and Extended Coverage) Insurance on all work in place and / or materials stored at the construction site, including foundations, and building equipment, is in force.

• Proof of such coverage must be presented to the PHA upon request.

• Failure to maintain insurance as required during the term(s) of this Contract shall constitute a material breach thereof.

• The Contractor is responsible for the full cost of any loss.

Licenses & Permits:

• The Contractor will ensure all required licensing requirements are met.

• The Contractor and Contractor’s employees and agents shall secure and maintain in force such licenses and permits as are required by law and shall conform to all Federal, State, and local laws, ordinances, and regulations covering the work under the Contract.

• The Contractor shall provide to the PHA copies of these and any other required licenses.

• Failure to maintain licenses in current status during this Contract shall constitute a material breach.

• The Contractor is responsible for complying with all governmental licensing requirements and associated business regulations whether Local, State or Federal. It is the responsibility of the Contractor to determine the applicability of any rule, regulation or other training or certification requirement.

• The PHA is exempt from the payment of any and all taxes and fees to the State of Rhode Island and City of Pawtucket.

Wage Requirements:

• Davis Bacon prevailing wages apply on all phases of the project. The wages are as follows:

o St Germain Manor - Residential Wages RI20260002 Mod 2

• Wage determinations are effective by operation of law even where they have been mistakenly omitted from a contract.

o The PHA has the power to retroactively modify contracts to include missing or corrected Davis Bacon Wage Decisions and contract clauses o The Contractor will have an opportunity to adjust their payroll fees, for AFFECTED wage classifications when the clauses and/or Davis Bacon Wage Decisions are retroactively incorporated. Changes must be submitted to the PHA by the deadline provided by the PHA.

https://sam.gov/content/home

• The Contractor will be required to post the wage rates on jobsite, visible to all employees of the project.

• Wage Rate Interviews will be conducted with the workers to ensure Davis Bacon Wage Rate compliance.

• Compliance with Davis Bacon Wage Decision is required at time of Contract Execution and for full duration of the project.

• The Contractor is responsible for ensuring all subcontractors comply with Davis Bacon Wage Decisions.

• Failure to abide by Davis Bacon Prevailing Wage requirements shall constitute a material breach of contract.

• All employees performing labor at the project jobsite(s) must be paid wages no lower than found in the most recent prevailing wages decision of the U.S. Department of Labor (DOL), Davis-Bacon Act Wage Decision Residential: No. RI20260002, Modification 02, Dated May 18, 2026 or as amended ten (10) days prior to bid opening.

Change of Davis Bacon Wage Determination {October 2023}:

Davis Bacon Wage Determinations shall be updated after signing the contract under the below circumstances:

• The contract was changed to include additional, substantial construction not within the original scope of work.

• The contract was changed to require the contractor to perform work for an additional time period not originally obligated, including when an option is exercised on a contract.

• Long-term contracts requiring construction over a period of time, that are not tied to the completion of any particular project, long-term operations and maintenance contracts wage decisions shall be updated annually.

Certified Payroll Requirements:

• Certified payroll documents must be submitted weekly to the PHA via certified mail to:

o Alissa Stipa

Pawtucket Housing Authority 175 Broad St Pawtucket, RI 02860

• Certified Payroll must be completed using the latest U.S. DOL Form WH-347.

• Contractor shall be responsible for compliance by any subcontractors, agents or assigns to

Davis-Bacon and Related Acts (“DBRA”) requirements.

o Contractor shall confirm all proper wages and benefits are being paid correctly and in accordance with DBRA requirements.

o Contractor shall be liable for the non-compliance of its employees, subcontractors, agents, and assigns.

o Contractor shall be required to pay back wages on behalf of their subcontractors, agents, and assigns.

o Contractor may be subject to debarment in appropriate circumstances due to subcontractor’s violations.

• Contractor and its subcontractors shall maintain DBRA contracts, subcontracts, and related documents, as well as worker telephone numbers and email addresses.

• Contractor and its subcontractors shall maintain all required records for a minimum of three (3) years after all the work on the Contract and Project is completed.

• Statements or notices containing a breakdown of the fringe benefit rate(s) without sufficient supporting documentation are not acceptable forms of verification.

o Contractor’s own administrative costs are not creditable as fringe benefits even when the Contract pays a third party to perform such tasks. However, costs incurred by third parties directly related to administration and delivery of bona fide fringe benefits to Contractor’s laborers and mechanics may be creditable. If uncertain, the Contractor shall contact the U.S. Dept. of Labor’s Wage and Hour Division (“WHD”) for review.

• All Contractors who have apprentices on the job will be required to provide WHD verification and any other verification required by WHD or HUD regulations.

o Any apprentices noted on payroll forms in excess of the allowable ratio permitted under the registered program shall be paid NOT less than the applicable Davis Bacon Wage Rate.

o Every apprentice must be paid no less than the rate specified in the registered program for the apprentice’s level of progress.

o Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program.

If the program does NOT specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the Davis Bacon Wage Rate All apprenticeship programs must follow the ratio and wage rate standards established for Rhode Island, regardless of where their company’s main office is located.

• Failure to provide payroll reports and benefit statements on a weekly basis shall constitute a material breach of the Contract.

• Refer to the following website for a video demonstrating the process of filling out a certified payroll report https://www.youtube.com/watch?v=7IyNLL7wgBY.

Labor Violations:

• Contractors submitting a bid shall provide with the bid on the company letterhead a list of any work practice and/or labor violations received by OSHA, EPA, U.S. Dept. of Labor, and state departments of labor and/or Attorneys General within the last five years, for all States where the Contractor is registered.

• Contractors failing to disclose violations with the bid will have their bid rejected.

• The PHA reserves the right to reject any bid based on the severity and number of violations received.

Cost Incurred in Responding:

• All costs directly or indirectly related to preparation of a response to this Invitation for Bids, or any oral presentation required to supplement and/or clarify the submittal which may be required by the PHA shall be the sole responsibility of and shall be borne by the Offeror.

• By submitting their bid, each firm waives any claim for liability against the PHA as to loss, injury and costs or expenses, which may be incurred as a consequence of its response to this document.

Contract Compliance Statement:

• The Bidder shall state their compliance with all applicable laws, rules and regulations of Federal, State and Local governing entities and that they are not excluded from Federal procurement programs. Bidders must state compliance with the terms of this Invitation for Bids (see attachments).

https://www.youtube.com/watch?v=7IyNLL7wgBY

• The Bidder must demonstrate that the bid meets all applicable laws, rules, regulations, permitting, registration, and licensing requirements, whether Local, State or Federal. It is the responsibility of the Bidder to determine the applicability of any law, rule, regulation, or other requirement.

Equal Employment Opportunity:

• The Bidder shall affirm that it does not have or subscribe to any personnel policy which permits or allows for discrimination in the employment promotion, demotion, dismissal or laying off of any individual due to their race, creed, color, national origin, age, gender, gender identity, disability, or any other protected class, and that it has not been charged or found guilty of such discriminatory practices.

Assistance to Small and Other Businesses:

Required Efforts

Consistent with Presidential Executive Orders 11625, 12138, and 12432, and Section 3 of the HUD Act of 1968, all feasible efforts shall be made to ensure that small and minority-owned businesses, women’s business enterprises, and other individuals or firms located in or owned in substantial part by persons residing in the area of the AHA project are used when possible. Such efforts shall include, but shall not be limited to:

• Including such firms, when qualified, on solicitation mailing lists;

• Encouraging their participation through direct solicitation of bids or proposals whenever they are potential sources;

• Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by such firms;

• Establishing delivery schedules, where the requirement permits, which encourage participation by such firms;

• Using the services and assistance of the Small Business Administration and the Minority Business

• Development Agency of the Department of Commerce;

• Including in contracts, to the greatest extent feasible, a clause requiring contractors, to provide opportunities for training and employment for lower income residents of the project area and to award subcontracts for work in connection with the project to business concerns which provide opportunities to low-income residents, as described in 24 CFR Part 75 (so-called Section 3 businesses); and

• Requiring prime contractors, when subcontracting is anticipated, to take the positive steps listed above.

Goals shall be established periodically for participation by small businesses, minority-owned businesses, women-owned business enterprises, labor surplus area businesses, and Section 3 business concerns in AHA prime contracts and subcontracting opportunities.

The PHA’s Reservation of Rights:

• Right to retain all bids submitted in response to this IFB, and no firm shall be allowed to withdraw said bid after the deadline for receiving bids without the written consent of the PHA’s Project Manager.

• Right to Reject, Waive, or Terminate this IFB. Reject any or all bids, waive any informality in this IFB process, or terminate the IFB process at any time, if deemed by the PHA to be in its best interests.

• Right to Not Award. Not to award a contract pursuant to this IFB.

• Right to Terminate. Terminate a contract awarded pursuant to this IFB, at any time for its convenience upon ten (10) days written notice to the successful Bidder(s).

• Right to Determine Time and Location. Determine the days, hours, and locations that the successful Bidders(s) shall provide the services called for in this IFB.

• Right to Negotiate. Negotiate the fees proposed by the Bidder’s entity.

• Right to Reject Any Proposal. Reject and do not consider any bid that does not meet the requirements of this IFB, including but not necessarily limited to incomplete bids and / or bids offering alternate or non-requested services.

• No Obligation to Compensate. Have no obligation to compensate any Bidder for any costs incurred in responding to this IFB.

BID EVALUATION

All bids received by the date and time of receipt specified in this solicitation will be publicly opened and read aloud by Alissa Stipa, Capital Projects Coordinator of the PHA. The time and place of opening will be as specified in this solicitation. Bidders and other interested people may be present.

• At the bid opening day the PHA will only disclose company name of each bidder; and calculated total bid amount as well as any deduct alternates specified in the bid specifications.

• A copy of the bid tabulation or recap recorded will be made available to each member of the public attending such opening and to anyone who requests such afterwards.

• The bids will not be made available for inspection by anyone at this time. The PHA will, at a later time, review all bids in detail and will, in a timely manner (typically within 5 days), notify all bidders of any bidder that is, as a result of the more detailed inspection of bids submitted, ruled to be non-responsive or not-responsible. Bidders who are not awarded will receive a formal regret letter within 5 (five) days of the bid submission.

• Award of a contract will be to the lowest responsible and responsive bidder.

• Bidders must meet the qualifications stated in the bid package and Scope of Work.

• Bidders will be required to demonstrate their ability to perform the work based on their understanding of the project’s requirements – including seeing first-hand existing conditions at the non-mandatory Pre-Bid Meeting, prior work history, previous experience, satisfactory references, technical proficiency, and ability to provide qualified manpower.

• The PHA reserves the right to reject the low bid price, if, in the opinion of the PHA, that bidder is determined not to be the best-qualified bidder or to be deficient in experience, understanding of the project’s requirements, technical proficiency or unable to provide qualified manpower to meet the specification.

• The PHA may waive any informalities in the bids and may reject any or all bids.

• All prices are considered firm.

• No bid may be withdrawn after the date of the bid opening.

• The final determination of the winning bidder will be at the sole discretion of the PHA.

• Any and all persons having ownership interest in a bidder entity or familial (including in-laws) and/or employment relationships (past or current) with principals and/or employees of a bidder entity will be excluded from participation in the evaluation of the bid.

• Depending on the amount of the award, it is possible that the PHA may take such contract award to the PHA’s Board of Commissioners (BOC) for approval of the award prior to executing a contract with the apparent successful bidder.

• The PHA considers all amounts final. Change Orders will be scrutinized and will not be considered for existing conditions that are known or that Bidder should have known. This includes but is not limited to conditions present at the Pre-Bid Meeting.

Responsive Evaluation:

After the public opening, the “hard copy” bid submittals received will be evaluated in private for responsiveness (i.e., meets the minimum of the requirements). Firms not meeting the minimum that are deemed to be non-responsive will be notified of such in writing by the PHA in a timely manner (in any case, in no less than 5 days after such determination is made).

Responsible Evaluation:

The PHA will evaluate each bid submitted as to responsibility (i.e., a firm that is qualified, responsible and able to provide to the PHA the required services). If the PHA ascertains that such firm has the required ability, capability, experience, knowledge, licensing, insurance and resources to provide the required services, the PHA may proceed with award.

If the PHA determines that such firm is deemed to be not responsible, such firm will be notified of such in writing by the PHA in a timely manner (in any case, in no less than 5 days after such determination is made); in such case the PHA may proceed with the noted Responsive and Responsible Evaluations with the next lowest bidder.

PHA SPECIAL INSTRUCTIONS THAT PERTAIN TO FORM HUD-5370

The parties agree that the following additional terms and conditions supplement and are incorporated into the Contract’s General Conditions. If any provision of this document conflicts with any provision of any other pertinent contract or document, then the provision required by HUD, and/or that is most beneficial to The Housing Authority of The City of Pawtucket (“PHA”), shall govern.

1. Definitions:

(d)(i) “Subcontractor” means the person or other entity entering into a contract with the Contractor to perform any of the work required under the Contract. (ii). “Subcontractor” also means the person or other entity entering into a contract with a Subcontractor to perform any of the work required under a subcontract. Contractor shall be fully liable for the actions and/or inactions of all subcontractors and fully releases PHA of any liability. Remedies for any actions and/or inactions of subcontract(s) shall be the full responsibility of Contractor, not the PHA.

(k) “In writing” / “written” refers to email communication and/or print format, but not texts.

2. Contractor’s Responsibility for Work:

(i) Before commencing any work, the Contractor shall submit in writing to the Contracting Officer the name of the superintendent to be employed. Written approval of the superintendent by PHA is required. While remaining in the Contractor’s employ, the superintendent shall not be replaced for the duration of the work, except with prior written approval of the Contracting Officer. If the PHA, in its sole discretion, requests that Contractor replace the superintendent, Contractor shall do so within ten (10) calendar days.

(j) Confine storage of materials and equipment to suitable portion of building or site. Relocate stored materials and equipment as required or as directed. If Contractor desires partial payment for off-site storage of contract-related materials, Contractor shall submit to the PHA written request and justification for each storage location and type of material.

(k) The Contracting Officer will assign space, if available, for a temporary field office and storage of supplies and equipment. If no space is available, Contractor shall provide such space in the form of trailers or temporary structures that sufficiently secures and protects said materials. If the PHA desires a job office, the Contractor shall provide at no cost a plan desk and working telephone for Contracting Officer.

(l) Contractor and subcontractors shall: manage project and trades’ work to avoid any delay(s);

cooperate with all concerned to expedite work; afford other contractors and trades every reasonable opportunity to progress with work; minimize conflicts with all personnel; coordinate necessary adjustments in work locations; work with diligence and keep as large a force at work as is compatible with safe, rapid work progress; and cause material to be delivered to site to ensure uninterrupted progress of work.

(m) Because the premises, or portions thereof, are occupied, Contractor shall: cause work to be done as safely and expeditiously as possible, minimizing inconvenience to occupants; maintain unobstructed ingress and egress along roadways, walks, lobbies, and corridors except as approved in writing by Contracting Officer; follow all pertinent safety protocols; schedule work as agreed to in writing by Contracting Officer.

(n) Contractor shall: take every reasonable precaution to minimize injury to persons and property due to inclement weather of any type; repair or replace damage caused to any part of work or site to the complete satisfaction of Contracting Officer at no cost to Contracting Officer. The Contractor shall be fully and exclusively liable for any damage to the person(s) and/or property.

(o) Contractor shall not use the PHA’s containers for the disposal of excess waste materials or rubbish, unless Contractor obtains prior written consent from Contracting Officer.

6. Construction Progress Schedule:

(d) Contractor shall honor all time constraints stated in the specifications. Breach of this provision shall be grounds for termination for convenience by the PHA.

9. Specifications and Drawings for Construction:

(j) Contractor shall provide to the PHA one (1) print and one (1) electronic copy of all shop drawings for prior approval by the PHA of all work and materials.

(k) Contractor shall provide to the PHA one (1) copy of contract drawings and specifications and one

(1) electronic copy of additional instructions at no cost to the PHA. Additional copies, if requested by the PHA, shall be provided at Contractor’s cost.

(l) Contractor shall: carefully review plans and shall not be relieved of any duty/ies due to furnish / install item(s) due to missing written specifications; it is Contractor’s duty to ask the PHA if Contractor is uncertain about any detail; Contractor shall provide items such as attachments, hangers, screws, bolts, and the like that are necessary but may not be specifically indicated.

11. Material and Workmanship:

(d) Contractor shall: perform all work in compliance with all applicable laws, municipal codes, industry best practices, regulations, licensure and the like, including compliance with applicable specifications; install work plumb and level, true to line, secured and braced rigidly in accordance with best practices; provide supports and fastenings as required; and employ only licensed, in good standing, qualified personnel.

(e) Contractor shall be responsible for, and shall warrant, all necessary cutting and patching for trades.

(f) Installers of materials shall: first examine conditions under which their work is to be done; notify the Contractor of conditions detrimental to proper and/or timely completion of work; and shall not proceed with work until unsatisfactory conditions have been corrected. Commencing work is evidence that Contractor/installer accepts such conditions and liability.

(g) Contractor shall: thoroughly protect all work and materials; provide and use boards, cloths, planks, waterproof paper, canvas, and/or other approved protection as necessary to prevent damage;

replace or rectify work or materials damaged by any cause to the full satisfaction of the PHA, at no cost to the PHA.

12. Permits and Codes:

(c) The PHA is exempt from the payment of any taxes or fees to the State of Rhode Island or any subdivision thereof; as a public body, the PHA has no exemption certification number.

(d) Contractor shall not display signs or advertising of any type on-site except with prior written approval from Contracting Officer.

15. Availability and Use of Utility Services:

(c) PHA will pay the worksite-related cost of water and electrical power only if it can reasonably be made available to the Contractor.

27. Payments:

(l) Contractor shall submit a “pencil-requisition” to architect (if applicable) and to PHA for review and approval. Once Contractor has received approval on pencil-requisition, Contractor shall submit a notarized payment requisition to architect for architect’s notarized signature. The architect shall forward the notarized approved pay application to PHA for final approval within seven (7) days of architect’s receipt of same from Contractor. Once approved, PHA shall process same for payment.

Final Payment of retainage shall be held until the project has received final approval from PHA and/or Municipal Authority (i.e.- Certificate of Occupancy, Sign off from Fire Dept., and the like), and/or all so-called “punch list” items have been completed to the PHA’s reasonable satisfaction.

(m) No error, omission, or act of forbearance by the PHA in verifying or certifying the accuracy of the amounts indicated on the Periodical Estimates for Partial Payment shall relieve the Contractor from any responsibility under the Contract. Without prejudice to any other right or remedy, the PHA may decline to certify payments of a Periodical Estimate for Partial Payment or, due to subsequently-discovered evidence or observations, may nullify the whole or any part of any Periodical Estimate for Partial Payment previously approved or paid to such extent as may be necessary to protect the PHA from loss due to: damage to the PHA; defective work not remedied; Contractor’s failure to carry out the work in accordance with the Contract documents; reasonable evidence, in the PHA’s sole discretion, that the work cannot be completed for the unpaid balance of the Contract Sum;

and/or reasonable evidence, in the PHA’s sole discretion, that the work will not be completed within the Contract Time.

(n) When the grounds listed above are remedied to the PHA’s satisfaction, payment will be made for amounts withheld due to said grounds. If the PHA, in its sole discretion, chooses to accept defective or non-conforming work, the PHA may do so instead of requiring its removal and correction and a Change Order shall be issued to reflect the reduced Contract Sum that is appropriate and equitable per the PHA’s sole discretion. Such reduction shall be executed whether or not final payment has been made. Each Periodical Estimate for Partial Payment shall be accompanied by a Certificate and Release of Prime Contractor and/or Certificate and Release of Subcontractor and/or Material Supplier forms, attached, fully executed as of the date of the Periodical Estimate by the Contractor and subcontractors and major materials suppliers.

29. Changes:

(k) The Indirect Costs noted in subparagraph (f)(2) shall not exceed ten percent (10%) of the Direct Costs, and the Profit noted in subparagraph (f)(3) shall not exceed five percent (5%) of the Total of the Direct and Indirect Costs.

30. Suspension of Work:

(d) To be entitled to delay damages, the Contractor must show each/all of the following elements to the jurisdiction’s prevailing legal burden of proof standard and using the reasonable person standard:

(1) contract performance was in fact delayed by the PHA;

(2) the cause of delay was within the PHA’s/ Contracting Officer’s control;

(3) the delay continued for an unreasonable period of time;

(4) the delay injured the Contractor in the form of additional expenses or loss damages;

(5) Contractor met its legal duty to mitigate damages in a competent and expedient manner; and

(6) such expense or delay has a direct causal relationship to damages incurred.

31. Disputes:

(g) All claims, disputes, and other matters in question arising out of or relating to this Contract or the performance or interpretation thereof shall be submitted to arbitration as provided for per state law, unless the PHA selects mediation as a more expedient first step. If mediation fails, then the matter shall be arbitrated.

33. Liquidated Damages:

(d) Because actual damages due to delay in completion of the work are impossible to determine, the Contractor and its Sureties shall be liable for and shall pay to the PHA the sum of three hundred

(300) dollars and 00/100 agreed as liquidated damages for each calendar day of delay beyond the Contract Period until the work is complete to the PHA’s sole satisfaction. Such sums may be withheld from payments due the Contractor or collected from the Contractor in any manner provided by law. Any costs incurred by the PHA in such collections/breach, including reasonable attorneys’ fees, shall be paid by the Contractor.