IFB_BOILER27SB.pdf
PDF 461 KB Posted
- Attached to
- Replacement of All Water Boiler Tubes
- Solicitation number
- BPM059895
- Issued by
- Anne Arundel County, Maryland
About this file
This Invitation for Bids (IFB) is issued by the State of Maryland, State Highway Administration (SHA) for the replacement of all water boiler tubes in a Unilux Model VZ250W boiler located at the SHA Hanover Complex. The scope of work encompasses complete replacement of water tubes including labor, materials, equipment, testing, and startup services to return the boiler to safe and reliable operating condition. The work must be performed in accordance with boiler manufacturer recommendations, applicable ASME requirements, and all relevant codes. A pre-bid conference and site visit are available by appointment only at 7491 Connelley Drive, Hanover, Maryland 21076. Questions must be submitted by November 29, 2026, at noon, and bids are due by December 3, 2026, at 2:00 PM via the eMMA procurement system. The public bid opening will occur on December 3, 2026, at 2:00 PM. The contract is for a fixed-price, fixed-term engagement with a 30-day primary performance period and includes a minimum two-year warranty covering workmanship and materials.
This procurement is designated as a Small Business Reserve (SBR) procurement, limiting award eligibility to vendors certified as small businesses by the Governor's Office of Small, Minority & Women Business Affairs (GOSBA). The MBE/DBE subcontracting participation goal and VSBE participation goal are both zero percent. Bidders must meet minimum qualifications including five years of commercial boiler service experience, two Maryland-licensed commercial boiler technicians with five years of experience, current Maryland business license, $1,000,000 minimum liability insurance coverage, a current W-9, and three references for commercial boiler service work performed within the past two years. Award will be made to the responsible bidder submitting the lowest responsive bid price. The contract will not be final until the contractor submits complete documentation and the SHA executes the agreement. No federal funding is involved in this procurement, and there is no travel reimbursement authorized under the IFB.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum No. 1_BOILER27SB.pdf | ||
| Bid Price Form_BOILER27SB.pdf | ||
| IFB_BOILER27SB.pdf | ||
| Bid Price Form_BOILER27SB.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPLACEMENT OF ALL WATER BOILER TUBES
Solicitation # BPM059895
Contract No. BOILER27SB
IFB Document
IFB for Maryland State Highway Administration Hanover Complex Page 1 of 19
STATE OF MARYLAND
STATE HIGHWAY ADMINISTRATION
SHA
INVITATION FOR BIDS (IFB)
Replacement of All Water Boiler Tubes
IFB NUMBER BOILER27SB
ISSUE DATE: NOVEMBER 24, 2026
A Prospective Bidder that has received this document from a source other than eMarylandMarketplace
Advantage (eMMA) https://procurement.maryland.gov should register on eMMA https://emma.maryland.gov/
NOTICE TO BIDDERS
SMALL BUSINESS RESERVE PROCUREMENT
This is a Small Business Reserve Procurement for which the award will be limited to certified small business vendors. Only businesses that meet the statutory requirements set forth in State Finance and
Procurement Article, §§14-501—14-505, Annotated Code of Maryland, and that are certified by the
Governor’s Office of Small, Minority & Women Business Affairs (GOSBA) Small Business Reserve
Program are eligible for award of a contract. Before awarding a contract under a procurement designated as a small business reserve procurement, the Procurement Officer shall verify that the apparent awardee is certified by the GOSBA as a small business through eMMA. However, if small businesses do not show interest in this solicitation, the Procurement Officer has the right to remove the SBR designation via an
Amendment on eMMA.
https://procurement.maryland.gov/ https://emma.maryland.gov/ https://gomdsmallbiz.maryland.gov/Pages/sbr-program.aspx https://gomdsmallbiz.maryland.gov/Pages/sbr-program.aspx
IFB for Maryland State Highway Administration Hanover Complex Page 2 of 19
MINORITY BUSINESS ENTERPRISES ARE ENCOURAGED TO RESPOND TO THIS
SOLICITATION.
IFB for Maryland State Highway Administration Hanover Complex Page 3 of 19
KEY INFORMATION SUMMARY SHEET (KISS)
Invitation for Bids Service
The scope of work requires the replacement of all water tubes in the
Unilux VZ25W Boiler – Building no. 4 unit no. 2
Solicitation
Number:
BPM059895
IFB Issue Date: November 24, 2026
IFB Issuing
Office:
The Maryland State Highway Administration Facilities Operation-Office of Maintenance Hanover MD. Complex
Procurement
Officer:
Tammy Ridgeway
7491 Connelley Dr. Hanover MD. 21076
Email:
Phone Number:
tridgeway@mdot.maryland.gov
410-582-5544
Bids are to be sent to:
Submit on emma.maryland.gov under Solicitation Number:
BPM059895 – Contract no. BOILER27SB.
To submit a bid, bidders must first register on emma.maryland.gov.
We recommend registering in advance to become acquainted with the site.
Pre-Bid
Conference:
By appointment only, at 7491 Connelley Drive Hanover MD 21076
Scheduled Site
Visit
By appointment only
Site Visit Location: 7491 Connelley Drive Hanover MD 21076
Building #1 Office of Maintenance
Questions Due
Date and Time:
2 days prior to the bid opening of December 1, 2026, by noon
Bid Due (Closing)
Date and Time:
December 3, 2026, by 2:00 PM
IFB for Maryland State Highway Administration Hanover Complex Page 4 of 19
Public Bid
Opening Date, Time, and
Location
December 3, 2026, by 2:00 PM in eMMA
Facilities Operations – Office of Maintenance – OOM Library.
2:00 PM Facilities Operators – Office of Maintenance
MBE/DBE
Subcontracting
Goal:
An overall Minority Business Enterprise (MBE) or Disadvantaged
Business Enterprise (DBE) subcontract participation goal of zero percent of the total contract dollar amount, including all renewal option terms, if any, has been established for this procurement.
VSBE
Subcontracting
Goal:
This solicitation includes a VSBE participation Goal of zero percent.
Procurement
Method:
A Contract will be awarded in accordance with the Competitive Sealed
Bidding method under COMAR 21.05.02.
Multiple or
Alternate Bids:
Multiple or alternate Bids will not be accepted.
Contract Type: Fixed Price
Contract
Duration:
30 Days
Primary Place of
Performance:
Maryland State Highway Administration Hanover MD Complex
SBR Designation: Yes
Federal Funding: No
IFB for Maryland State Highway Administration Hanover Complex Page 5 of 19
1 Minimum Qualifications
1.1 Bidder Minimum Qualifications
The Bidder must document in its Bid that it satisfies the following Minimum Qualifications:
• The Contractor shall have a current and active State of Maryland Business License to operate in Maryland. The current and active State of Maryland Business License must be submitted at the time of bid submission.
• Please refer to The Comptroller of Maryland’s website at https://marylandtaxes.gov/business/types-of-business-licenses.php for TYPES OF
BUSINESS LICENSE that is applicable to the Contractor’s company/firm. The applicable business license shall be submitted at the time of bid submission.
• The Contractor shall have five (5) years of experience in the commercial boiler service industry and have available a minimum work force of two (2) State of Maryland licensed commercial boiler technicians with a minimum of five (5) years of experience in the commercial boiler service industry. The Contractor shall also employ boiler technicians with a minimum of one (1) year of experience in the commercial boiler industry and or boiler helpers to assist in various tasks. The Contractor shall provide documentation of license and commercial experience for boiler service technicians at time of bid submission.
• The Contractor shall submit a current W9 at the time of bid submission that includes the business name, mailing address, federal identification, and remit to address if different from the mailing address.
• Bidders shall submit three (3) references with their bid to provide proof of experience conducting commercial boiler service work. Evidence of commercial boiler service work submitted for the purpose of proving experience must have been performed within the past two (2) years. References shall include the name, address, telephone number, contact person, and type and duration of services provided. References may be checked prior to award. Any negative responses received may result in disqualification of the bid.
References shall be of work performed by the bidding contractor and not subcontractors or employees performing work as employees of other contractors. The Bidder shall provide its Bid "Attachment E Reference Checks".
IFB for Maryland State Highway Administration Hanover Complex Page 6 of 19
• The Contractor shall, at its own cost and expense, take out and carry in effect through the term of the contract a policy or policies of insurance with a reputable insurance company that is financially sound and authorized to conduct business in the State of Maryland and upon whom process in any suit or action or other proceeding in the courts of the State of
Maryland or of the United States may be served insuring the Contractor against all liability for injuries to persons (including wrongful death) and damages to property caused by the Contractor’s use and occupancy or otherwise caused by the Contractor’s activities and operations. The Contractor shall maintain liability insurance for One
Million Dollars ($1,000,000). The documentation is to be provided to SHA at the time of bid submission.
• The Contractor must be fully qualified to legally provide the services detailed in this
Contract within the State of Maryland. All applicable Federal, State, County, and local statutes, laws, and regulations must be followed by all parties when performing work related to this Contract. This requirement includes, but is not limited to, the standards established by the MDE, EPA, UASCE, FCWA, MOSH, OSHA, NFPA, and other relevant governmental agencies.
THE REMAINDER OF THIS PAGE IS INTENTIONALLY LEFT BLANK.
IFB for Maryland State Highway Administration Hanover Complex Page 7 of 19
2 Contractor Requirements: Scope of Work
2.1 Summary Statement
This Invitation for Bids (IFB) is issued to procure the goods or services, as specified in this Section 2, from a contract between the successful bidder(s) and the State of Maryland (“State”): It is the State’s intention to obtain goods and services, as specified in this IFB, from a contract between the selected
Bidder and the State.
SCOPE OF CONTRACTOR SERVICES
Water Tube Replacement – Unilux Model VZ250W Boiler
1. General
Provide all labor, supervision, materials, equipment, tools, rigging, temporary protection, testing, startup, and incidentals necessary to replace all water tubes in the existing Unilux Model VZ250W hot-water boiler and return the boiler to safe and reliable operating condition.
The Contractor shall perform the work in accordance with the boiler manufacturer's recommendations, applicable ASME requirements, applicable codes, and requirements of the
Authority Having Jurisdiction (AHJ).
2. Pre-Construction and Existing Conditions
Prior to beginning work, the Contractor shall:
1. Field verify the boiler manufacturer, model number, serial number, design pressure, operating pressure, tube configuration, tube quantity, tube size, tube wall thickness, and tube material.
2. Inspect existing boiler conditions and document visible deterioration, corrosion, leakage, scale accumulation, refractory damage, or other deficiencies that could affect the work.
3. Verify that replacement tubes are compatible with the existing boiler and meet the boiler manufacturer's requirements.
4. Coordinate the required boiler shutdown and outage with the Owner.
5. Identify required access, removal clearances, rigging requirements, and any temporary removal of adjacent equipment, piping, insulation, panels, or accessories necessary to complete the work.
6. Provide replacement tubes, gaskets, seals, refractory materials, and other components required for a complete installation prior to commencing the scheduled outage whenever practical.
3. Boiler Shutdown and Isolation
The Contractor shall:
1. Perform an orderly shutdown of the boiler and burner.
IFB for Maryland State Highway Administration Hanover Complex Page 8 of 19
1. Lock out and tag out electrical power, fuel supply, pumps, and other energy sources serving the boiler in accordance with applicable safety requirements.
2. Close, isolate, and secure the boiler supply and return connections as required.
3. Allow the boiler to cool to a safe working temperature.
4. Drain the boiler and manage existing boiler water in accordance with facility requirements.
5. Verify that the boiler is depressurized and safe before opening the pressure vessel or commencing tube-removal work.
4. Boiler Disassembly and Inspection
Provide the disassembly necessary to access the existing water tubes, including removal of access panels, casing components, insulation, refractory, burner components, or other components as required.
After opening the boiler:
1. Inspect the accessible fireside and waterside surfaces.
2. Inspect tube ends, tube seats, drums/headers, and accessible pressure-retaining surfaces for corrosion, erosion, cracking, pitting, scale, or other deterioration.
3. Photograph and document abnormal conditions discovered during the work.
4. Notify the Owner immediately if conditions are found that may prevent proper replacement of the tubes or indicate deterioration of the pressure vessel.
5. Do not perform repairs outside this scope without authorization from the Owner.
5. Existing Water Tube Removal
1. Remove the existing water tubes designated for replacement.
2. Perform removal using methods that minimize the potential for damage to the drums, headers, tube holes, tube seats, refractory, casing, and other boiler components.
3. Remove existing tube remnants and debris from the boiler.
4. Properly dispose of removed tubes and associated waste unless otherwise directed by the Owner.
IFB for Maryland State Highway Administration Hanover Complex Page 9 of 19
1. Do not use cutting, heating, welding, or other tube-removal methods that could damage pressure-retaining boiler components.
6. Tube Seat Preparation and Cleaning
After removal of the existing tubes:
1. Thoroughly clean tube holes and tube seating surfaces.
2. Remove corrosion products, scale, deposits, and foreign material that could interfere with installation or sealing of the replacement tubes.
3. Inspect tube holes and seating surfaces for erosion, enlargement, cracking, grooving, corrosion, or other damage.
4. Verify that tube seating surfaces are suitable for installation of the replacement tubes.
5. Report conditions requiring pressure-vessel repair to the Owner before proceeding.
7. Replacement Water Tubes
Provide new boiler tubes matching the dimensions, material, wall thickness, configuration, and pressure/temperature requirements of the existing boiler and the manufacturer's requirements.
Replacement tubes shall:
1. Be new and free of corrosion, scale, dents, cracks, laminations, or other defects.
2. Be properly cut, formed, bent, prepared, and installed for the existing boiler configuration.
3. Match the required tube diameter and wall thickness.
4. Be installed using procedures appropriate for the existing Unilux boiler construction and approved by the boiler manufacturer where required.
5. Be properly seated, expanded, rolled, welded, or otherwise terminated using the manufacturer's required installation method.
6. Be installed without excessive thinning, deformation, scoring, or damage to the tubes or tube seats.
Where tube rolling or expansion is required, the Contractor shall use properly sized equipment and procedures suitable for the tube material, diameter, wall thickness, and boiler construction.
IFB for Maryland State Highway Administration Hanover Complex Page 10 of 19
8. Internal Cleaning
Following tube installation:
1. Remove debris resulting from tube replacement activities.
2. Clean accessible waterside surfaces as required.
3. Remove loose scale, metal shavings, grinding debris, dirt, and other foreign materials introduced during the work.
4. Verify that the boiler and associated accessible waterways are clean before final closure.
Chemical cleaning or descaling of the complete boiler is not included unless specifically identified elsewhere in the Contract Documents.
9. Reassembly
After completion of the tube replacement:
1. Reinstall all boiler components removed to perform the work.
2. Replace disturbed or damaged gaskets and seals with new materials.
3. Repair or replace refractory and insulation damaged or removed as part of the Work.
4. Restore burner, access panels, casing sections, insulation, piping connections, controls, and accessories to their original operating configuration.
5. Verify that all boiler openings and connections are properly sealed.
10. Pressure and Leak Testing
After installation and prior to returning the boiler to service:
1. Fill and vent the boiler in accordance with the manufacturer's requirements.
2. Perform the required hydrostatic or pressure test in accordance with applicable code, manufacturer requirements, and the Authority Having Jurisdiction.
3. Inspect all replaced tube joints, disturbed connections, gaskets, and seals for leakage.
4. Correct leaks or deficiencies associated with the Work at no additional cost to the Owner.
5. Repeat testing as necessary until the boiler passes the required test.
IFB for Maryland State Highway Administration Hanover Complex Page 11 of 19
6. Document the final test pressure, test duration, test date, and results.
The Contractor shall not exceed the allowable test pressure established for the existing boiler.
11. Startup and Operational Testing
Upon successful completion of pressure testing:
1. Restore the boiler to normal system conditions.
2. Remove lockout/tagout devices in accordance with facility procedures.
3. Restore fuel, electrical power, and associated system components.
4. Start the boiler in accordance with the manufacturer's procedures.
5. Verify proper burner ignition and operation.
6. Check the boiler and disturbed piping/components for leakage at operating temperature and pressure.
7. Verify proper boiler water circulation.
8. Verify operation of applicable safety controls, operating controls, temperature controls, and limit controls affected by the Work.
9. Verify satisfactory boiler operation through a complete operating cycle.
10. Perform burner combustion testing and make adjustments if the burner or combustion system was disturbed during the Work.
11. Record final combustion readings when combustion testing is performed.
12. Closeout Documentation
At completion of the Work, provide:
• Replacement tube manufacturer and material information.
• Final quantity, size, and specification of tubes installed.
• Photographs showing conditions before, during, and after tube replacement.
• Hydrostatic/pressure test report.
• Documentation of any deficiencies identified during boiler inspection.
• Combustion test report, where applicable.
IFB for Maryland State Highway Administration Hanover Complex Page 12 of 19
• Startup and operational test documentation.
• Documentation of any manufacturer or authorized service representative involvement.
• Warranty information for replacement materials and workmanship.
13. Contractor Qualifications
Tube replacement shall be performed by personnel experienced in repair of commercial/industrial watertube boilers.
Work shall be performed by an organization holding the appropriate National Board "R"
Certificate of Authorization and shall be documented in accordance with applicable National Board and ASME requirements.
The Contractor shall determine permitting, inspection, certification, and authorized-inspector requirements before commencing pressure-retaining repairs.
14. Warranty
Provide a minimum two-year warranty from the date of acceptance covering workmanship, leakage of replaced tube joints, and Contractor-furnished materials. Correct deficiencies attributable to the tube replacement work at no additional cost to the Owner during the warranty period.
15. Owner Coordination
Maintain the boiler outage for the shortest practical duration. Coordinate shutdown, draining, testing, startup, and return to service with the Owner.
The Contractor shall immediately notify the Owner of conditions that could:
• Extend the scheduled outage;
• Require additional pressure-vessel repairs;
• Affect boiler safety or reliability; or
• Prevent successful completion of the tube replacement.
This is a single award IFB. See IFB Section 4.21 Bid Evaluation Criteria and Award Basis for more
Contract award information.
Contractor Responsibilities and Tasks
I. GENERAL
A. Project Requirements:
1. The Contractor shall have no less than five years of technical experience in providing maintenance service to commercial boilers.
2. The Contractor shall be responsible for all administration, labor, and equipment required to complete the work of this Statement of Work:
IFB for Maryland State Highway Administration Hanover Complex Page 13 of 19
3. Vendor shall adhere to all OSHA and MOSH required safety and Personal
Protective Equipment directives and have this in place during the work period:
(eye protection, respirators, etc.). More information on safety regulations can be found at http://www.dllr.md.gov/labor/mosh/.
Vendors shall have employees covered by worker’s compensation insurance and submit documentation for such coverage.as outlined in this IFB.
B. References: Work, and performance of work, shall conform to standards stated for maintaining and repairing Buildings and Building components in accordance with latest published requirements of the following standard setting agencies, organizations and associations:
1. BOCA: Building Officials & Code Administrators;
2. IBC: International Building Code;
3. NEC: National Electric Code;
C. Job Conditions: All work on this project shall conform to the IBC, Maryland
Building Code, Local codes and regulations, and the Special Provisions included in this Invitation For Bid (IFB).
1. Coordinate and schedule all activities on site with the Facilities Maintenance
Division (FMD) representative, or Project Manager;
2. Coordinate with all Contractors and building trades that may be working concurrently in a space.
1) Not all project tasks may require meetings.
D. Safety and Protection:
1. All necessary precautions and care shall be used to prevent accidental fire:
a. Furnish two fully charged and operable ABC fire extinguishers, readily visible within 25 feet of all operations at all times. THIS WILL BE
STRICTLY ENFORCED.
2.2 Supplemental Category of Work Requirements and Responsibilities
Submittals with Bid:
Current Copy of the Maryland Business Licenses
Proof of Workman’s Comp and Liability Insurance
At least three Business References with commercial boiler service work.
Current W9 http://www.dllr.md.gov/labor/mosh/
IFB for Maryland State Highway Administration Hanover Complex Page 14 of 19
3 Standard Terms and Conditions
3.1 Contract Initiation Requirements
Once all approvals have been obtained and the Contract is fully executed, the Procurement Officer may schedule a kickoff meeting to be held prior to commencement of Contract performance.
3.2 End of Contract Transition
The Contractor shall cooperate in the orderly transition of services from it to a subsequent contractor at the end of the contract term or upon receipt of a Notice of Termination from the State. Transition shall be provided in a prompt and timely manner and shall proceed in accordance with the schedule provided to the Contractor by the State in the Notice of Transition. Additional instructions regarding transition services may be provided in the event of a Notice of Termination issued by the State.
3.3 Invoicing
Submission of an invoice constitutes the Contractor’s verification that the information in the invoice is accurate as of the time of submission.
An invoice not satisfying the requirements of a Proper Invoice (as defined in COMAR 21.06.09) will not be processed for payment. To be considered a Proper Invoice, invoices must include the following information, without error:
A. Contractor name and address;
B. Remittance address;
C. Federal taxpayer identification (FEIN) number, social security number, as appropriate;
D. Invoice period (i.e. time period during which services covered by invoice were performed);
E. Invoice date;
F. Invoice number;
G. State assigned Contract number;
H. State assigned (Blanket) Purchase Order number(s);
I. Goods or services provided;
J. Amount due; and
K. Any additional documentation required by regulation or the Contract.
Invoices that contain both fixed price and labor hour or time and material items shall clearly identify each item as either fixed price, and labor hour, or time and material billing.
The State reserves the right to reduce or withhold Contract payment in the event the Contractor does not provide all required deliverables within the time frame specified in the Contract or otherwise breaches the terms and conditions of the Contract until such time as the Contractor brings itself into full compliance with the Contract.
IFB for Maryland State Highway Administration Hanover Complex Page 15 of 19
The State is generally exempt from federal excise taxes, Maryland sales and use taxes, District of
Columbia sales taxes and transportation taxes. The Contractor, however, is not exempt from such sales and use taxes and may be liable for the same.
Invoices for final payment shall be clearly marked as “FINAL” and submitted when all work requirements have been completed and no further charges are to be incurred under the Contract. In no event shall any invoice be submitted later than 60 calendar days from the Contract termination date.
3.3.1 Invoice Submission Schedule
The Contractor shall submit invoices in accordance with the following schedule:
A. For items of work for which there is one-time pricing (see Attachment B –The Price
Form), those items shall be billed in the month following the acceptance of the work by the State.
B. Invoices for work performed on a labor hour or time and materials basis shall be submitted on or before the 10th business day of the month following the end of the invoice period.
3.3.2 Travel Reimbursement
Travel will not be reimbursed under this IFB.
3.4 Liquidated Damages
3.4.1 Problem Escalation Procedure
No later than ten (10) Business Days after notice of recommended award or after the date of the
Notice to Proceed, whichever is earlier, the Contractor must provide, and thereafter, maintain a
Problem Escalation Procedure (PEP) for both routine and emergency situations. The PEP must state how the Contractor will address problem situations as they occur during the performance of the Contract, especially problems that are not resolved to the satisfaction of the State within appropriate timeframes and must include:
A. Contact information
B. The process for establishing the existence of a problem;
C. Names, titles, and contact information for progressively higher levels of personnel in the Contractor’s organization who would become involved in resolving a problem;
D. For each individual listed in the Contractor’s PEP, the maximum amount of time a problem will remain unresolved with that individual before the problem escalates to the next contact person listed in the Contractor’s PEP;
E. Expedited escalation procedures and any circumstances that would trigger expediting them;
F. The method of providing feedback on resolution progress, including the frequency of feedback to be provided to the State;
G. Contact information for persons responsible for resolving issues after normal business hours (e.g., evenings, weekends, holidays) and on an emergency basis; and
H. A process for updating and notifying the Contract Monitor of any changes to the PEP.
I. The PEP must be updated within ten (10) Business Days after any change in circumstance which changes the PEP but not less than annually within ten (10)
Business Days after the start of each Contract year .
IFB for Maryland State Highway Administration Hanover Complex Page 16 of 19
Nothing in this section shall be construed to limit any rights of the Contract Monitor or the
State which may be allowed by the Contract or applicable law.
3.5 Payments by Electronic Funds Transfer
By submitting a Bid in response to this solicitation, the Bidder, if selected for award:
Agrees to accept payments by electronic funds transfer (EFT) unless the State Comptroller’s
Office grants an exemption. The successful Bidder shall register using the COT/GAD X-10
Vendor Electronic Funds (EFT) Registration Request Form.
Any request for exemption must be submitted to the State Comptroller’s Office for approval at the address specified on the COT/GAD X-10 form, must include the business identification information as stated on the form, and must include the reason for the exemption. The COT/GAD
X-10 form may be downloaded from the Comptroller’s website at:
http://comptroller.marylandtaxes.com/Vendor_Services/Accounting_Information/Static_Files/GA
DX10Form20150615.pdf.
3.6 Prompt Payment Policy
This procurement and the Contract(s) to be awarded pursuant to this solicitation are subject to the
Prompt Payment Policy Directive issued by the Governor’s Office of Small, Minority & Women
Business Affairs (GOSBA) and dated August 1, 2008. Promulgated pursuant to Md. Code Ann., State Finance and Procurement Article, §§ 11-201, 13-205(a), and Title 14, Subtitle 3, and
COMAR 21.01.01.03 and 21.11.03.01, the Directive seeks to ensure the prompt payment of all subcontractors on non-construction procurement contracts. The Contractor shall comply with the prompt payment requirements outlined in the Contract; Section 31 “Prompt Pay Requirements”
Additional information is available on GOSBA’s website at:
http://www.gomdsmallbiz.maryland.gov/documents/legislation/promptpaymentfaqs.pdf.
3.7 Conflict of Interest Affidavit and Disclosure
The Bidder shall complete and sign the Conflict of Interest Affidavit and Disclosure (Attachment I) and submit it with its Bid. By submitting a Conflict of Interest Affidavit and Disclosure, the
Contractor shall be construed as certifying all Contractor Personnel and subcontractors are also without a conflict of interest as defined in COMAR 21.05.08.08A.
Additionally, a Contractor has an ongoing obligation to ensure that all Contractor Personnel are without conflicts of interest prior to providing services under the Contract. For policies and procedures applying specifically to Conflict of Interests, the Contract is governed by COMAR
21.05.08.08.
3.8 Maryland Healthy Working Families Act Requirements
On February 11, 2018, the Maryland Healthy Working Families Act went into effect. All Bidders should be aware of how this Act could affect your potential contract award with the State of
Maryland. See the Department of Labor, Licensing and Regulations website for Maryland
Healthy Working Families Act Information: https://dllr.state.md.us/paidleave/.
https://dllr.state.md.us/paidleave/
IFB for Maryland State Highway Administration Hanover Complex Page 17 of 19
3.9 The State of Maryland’s Commitment to Purchasing Environmentally
Preferred Products and Services (EPPs)
Maryland’s State Finance & Procurement Article §14-410 defines environmentally preferable purchasing as “the procurement or acquisition of goods and services that have a lesser or reduced effect on human health and the environment when compared with competing goods or services that serve the same purpose.” Accordingly, Bidders are strongly encouraged to offer EPPs to fulfill this contract, to the greatest extent practicable.
3.10 Insurance Requirements
The Contractor shall maintain, at a minimum, the insurance coverages outlined below, or any minimum requirements established by law if higher, for the duration of the Contract, including option periods, if exercised:
3.10.1 The following type(s) of insurance and minimum amount(s) of coverage are required:
A. Commercial General Liability - One million dollars ($1,000,000) combined single limit per occurrence for bodily injury, property damage, and personal and advertising injury and three million dollars ($3,000,000) annual aggregate. The minimum limits required herein may be satisfied through any combination of primary and umbrella/excess liability policies.
B. Worker’s Compensation - The Contractor shall maintain such insurance as necessary or as required under Workers’ Compensation Acts, the Longshore and Harbor Workers’
Compensation Act, and the Federal Employers’ Liability Act, to not be less than. one million dollars ($1,000,000) per occurrence (unless a state’s law requires a greater amount of coverage). Coverage must be valid in all states where work is performed.
3.10.2 The State shall be listed as an additional insured on the faces of the certificates associated with the coverages listed above, including umbrella policies, excluding Workers’
Compensation Insurance and professional liability.
3.10.3 All insurance policies shall be endorsed to include a clause requiring the insurance carrier to provide the Procurement Officer, by certified mail, not less than 30 days’ advance notice of any non-renewal, cancellation, or expiration. The Contractor shall notify the
Procurement Officer in writing, if policies are canceled or not renewed within five (5) days of learning of such cancellation or nonrenewal. The Contractor shall provide evidence of replacement insurance coverage to the Procurement Officer at least 15 days prior to the expiration of the insurance policy then in effect.
3.10.4 Any insurance furnished as a condition of the Contract shall be issued by a company authorized to do business in the State.
3.10.5 The recommended awardee must provide current certificate(s) of insurance with the prescribed coverages, limits and requirements set forth in this section within five (5)
Business Days from notice of recommended award. During the period of performance for multi-year contracts, the Contractor shall provide certificates of insurance annually, or as otherwise directed by the Contract Monitor.
3.10.6 No sub-contractors for this work unless approved by the Contract Monitor.
https://trackbill.com/bill/maryland-house-bill-629-environmentally-preferable-procurement-maryland-green-purchasing-committee/647077/
IFB for Maryland State Highway Administration Hanover Complex Page 18 of 19
If approved by the contract monitor, the Contractor shall require any subcontractors to obtain and maintain comparable levels of coverage and shall provide the Contract Monitor with the same documentation as is required of the Contractor Bid Submission Information and Instructions.
IFB for Maryland State Highway Administration Hanover Complex Page 19 of 19
4 Bid Submission Information and Instructions
4.1 eMaryland Marketplace Advantage (eMMA) eMMA is the electronic commerce system for the State of Maryland. The IFB, Pre-Bid Conference
(Conference)summary and attendance sheet, Bidders’ questions and the Procurement Officer’s responses, addenda, and other solicitation-related information will be made available via eMMA.
To receive a contract award, a vendor must be registered on eMMA. Go to emma.maryland.gov, click on “New Vendor? Register Now” to begin the process, and then follow the prompts.
4.2 Electronic Means
The following transactions related to this procurement and any Contract awarded pursuant to it are not authorized to be conducted by electronic means; any transaction, submission, or communication where the Procurement Officer has specifically directed that a response from the Contractor or
Offeror be provided in writing or hard copy. Any e-mail transmission is only authorized to the email addresses for the identified person as provided in the solicitation, the Contract, or in the direction from the Procurement Officer or Contract Monitor.
4.3 Pre-Bid Conference
If a Conference will be held, the date, time, and location is indicated on the Key Information
Summary Sheet. Attendance at the Conference is not mandatory, but all interested parties are encouraged to attend to facilitate better preparation of their Bids.
If there is a need for sign language interpretation or other special accommodations due to a disability, please notify the Procurement Officer at least five (5) Business Days prior to the Conference date.
Reasonable efforts will be made to provide such special accommodation. If the Conference is in person, attendees should bring a copy of the solicitation and a business card to help facilitate the sign-in process.
4.4 Questions
All questions, including concerns, shall identify in the subject line the Solicitation Number and Title for this IFB and must be submitted in writing via e-mail or eMMA to the Procurement Officer no later than the date and time specified in the Key Information Summary Sheet. The Procurement
Officer, based on the availability of time to research and communicate an answer, shall decide whether an answer can be given before the Bid due date.
4.4.1 Answers to all questions that are not clearly specific only to the requestor will be distributed via the same mechanism as for IFB amendments and posted on eMMA.
4.4.2 The statements and interpretations contained in responses to any questions, whether responded to verbally or in writing, are not binding on the State unless it issues an amendment to the solicitation in writing.
4.5 Bid Due (Closing) Date and Time
Bids must be received by the Procurement Officer no later than the Bid due date and time indicated on the Key Information Summary Sheet to be considered. Except as provided in COMAR
21.05.02.10. Bids received after that date will not be considered. Requests for an extension of this date or time shall not be granted.
https://emma.maryland.gov/page.aspx/en/usr/login?ReturnUrl=%2fpage.aspx%2fen%2fbuy%2fhomepage
IFB for Maryland State Highway Administration Hanover Complex Page 20 of 19
Bids may be modified or withdrawn by written notice received by the Procurement Officer before the time and date set forth in the Key Information Summary Sheet for receipt of Bids.
4.6 Receipt, Opening and Recording of Bids
Upon receipt, each Bid and any timely modification(s) to a Bid shall be stored in a secure place until the time and date set for Bid opening. Before Bid opening, the State may not disclose the identity of any Bidder. Bids shall be opened publicly at the time, date and place designated in the Key
Information Summary Sheet. The name of each Bidder, the Total Bid Price, and such other information as is deemed appropriate shall be read aloud or otherwise made available and recorded at the time of Bid opening.
4.7 Duration of Bids
Bids submitted in response to this IFB are irrevocable for the latest of the following: 120 days following the Bid due date and time or the date any protest concerning this IFB is finally resolved.
This period may be extended at the Procurement Officer’s request only with the Bidder’s written agreement.
4.8 Revisions to the IFB
4.8.1 All revisions to the IFB before the due date for Bids will be published in an addendum to the IFB and posted on eMMA and reasonable effort will be made to provide such addenda to all prospective Bidders that were sent this IFB or are otherwise known by the
Procurement Officer to have obtained this IFB. It is the responsibility of all prospective
Bidders to check eMMA for any addenda issued prior to the submission of Bids.
4.8.2 Bidders shall acknowledge in the Bid the receipt of all addenda to this IFB issued before the Bid due date.
4.8.3 Failure to acknowledge receipt of an addendum does not relieve the Bidder from complying with the terms, additions, deletions, or corrections set forth in the addendum, and may cause the Bid to be deemed not responsive.
4.9 Cancellations
4.9.1 This IFB may be cancelled as provided in COMAR 21.06.02.02
4.9.2 The State reserves the right to cancel this IFB, accept or reject any and all Bids, in whole or in part, received in response to this IFB and to waive or permit the cure of minor irregularities.
4.9.3 In the event a government entity proposes and receives the recommendation for award, this procurement may be canceled, and the award processed in accordance with COMAR
21.01.03.01.A(4).
4.9.4 If the services that are the subject of the IFB are currently being provided under an interagency agreement with a public institution of higher education and the State determines that the services can be provided more cost effectively by the public institution of higher education, then the IFB may be canceled in accordance with Md.
Code Ann., State Finance and Procurement Art., § 3-207(b)(2).
IFB for Maryland State Highway Administration Hanover Complex Page 21 of 19
4.10 Incurred Expenses
The State will not be responsible for any costs incurred by any Bidder in preparing and submitting a
Bid or performing any other activities related to submitting a Bid in response to this solicitation.
4.11 Protest/Disputes
Any protest or claim related to this IFB, or the Contract award hereunder shall be subject to the provisions of COMAR 21.10 (Administrative and Civil Remedies).
4.12 Bidder Responsibilities
4.12.1 A Bidder, either directly or through its subcontractor(s), must be able to provide all goods and services and meet all of the requirements requested in this solicitation and the successful Bidder (the Contractor) shall remain responsible for Contract performance regardless of subcontractor participation in the work.
4.12.2 If the Bidder is the subsidiary of another entity, all information submitted by the Bidder, including but not limited to references, financial reports, or experience and documentation (e.g., insurance policies, bonds, letters of credit) used to meet minimum qualifications, if any, shall pertain exclusively to the Bidder, unless the parent organization will guarantee the performance of the subsidiary. If applicable, the Bidder’s
Bid shall contain an explicit statement, signed by an authorized representative of the parent organization, stating that the parent organization will guarantee the performance of the subsidiary.
4.12.3 A parental guarantee of the performance of the Bidder under this section will not automatically result in crediting the Bidder with the experience or qualifications of the parent under any evaluation criteria pertaining to the actual Bidder’s experience and qualifications. Instead, the Bidder’s responsibility will be assessed to the extent to which the State determines that the experience and qualifications of the parent are applicable to and shared with the Bidder, any stated intent by the parent to be directly involved in the performance of the Contract, and the value of the parent’s participation as determined by the State.
4.13 Acceptance of Terms and Conditions
By submitting a Bid in response to this IFB, the Bidder, if selected for award, is deemed to have accepted the terms and conditions of this IFB and the Contract, attached hereto as:
Sample-Short-form-Contract-for-Small-Procurements-fillable.pdf
Any questions or exceptions to this IFB or the Contract must be submitted by the “Questions
Due Date and Time” prior to Bid submission. Changes to the solicitation, including the Bid
Form or Contract, made by the Bidder may result in Bid rejection.
https://procurement.maryland.gov/wp-content/uploads/sites/12/2025/05/Sample-Short-form-Contract-for-Small-Procurements-fillable.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2025/05/Sample-Short-form-Contract-for-Small-Procurements-fillable.pdf
IFB for Maryland State Highway Administration Hanover Complex Page 22 of 19
4.14 Compliance with Laws/Arrearages
By submitting a Bid in response to this IFB, the Bidder, if selected for award, agrees that it will comply with all federal, State, and local laws applicable to its activities and obligations under the
Contract. By submitting a response to this solicitation, each Bidder represents that it is not in arrears in the payment of any obligations due and owing the State, including the payment of taxes and employee benefits, and shall not become so in arrears during the term of the Contract if selected for
Contract award.
4.15 Verification of Registration and Tax Payment
Before a business entity can do business in the State, it must be registered with the State Department of Assessments and Taxation (SDAT). SDAT is located at State Office Building, Room 803, 301
West Preston Street, Baltimore, Maryland 21201. For registration information, visit https://egov.maryland.gov/BusinessExpress/.
It is strongly recommended that any potential Bidder complete registration prior to the Bid due date and time. The Bidder’s failure to complete registration with SDAT may disqualify an otherwise responsive successful Bidder from final consideration and recommendation for Contract award.
4.16 False Statements
Bidders are advised that Md. Code Ann., State Finance and Procurement Article, § 11-205.1 provides as follows:
In connection with a procurement contract a person may not willfully:
A. Falsify, conceal, or suppress a material fact by any scheme or device.
B. Make a false or fraudulent statement or representation of a material fact; or
C. Use a false writing or document that contains a false or fraudulent statement or entry of a material fact.
A person may not aid or conspire with another person to commit an act under this section. A person who violates any provision of this section is guilty of a felony and on conviction is subject to a fine not exceeding $20,000 or imprisonment not exceeding five (5) years or both.
4.17 Confidentiality of Bids / Public Information Act Notice
The Bidder should give specific attention to the clear identification of those portions of its Bid that it considers to contain confidential and/or proprietary commercial information or trade secrets, and provide justification for why such materials, upon request, should not be disclosed by the State under the Public Information Act, Md. Code Ann., General Provisions Article, Title 4. This information should be identified by page number and placed in the Transmittal Letter with the Bid.
For requests for information made under the PIA, the Procurement Officer shall examine the Bids to determine the validity of any requests for nondisclosure. Nondisclosure is permissible only if approved by the Office of the Attorney General.
4.18 Use of Bidder’s Form Not Binding on State
The Bidder may not substitute, modify, or provide any other document in lieu of the documents provided with this Bid. Only those forms and documents provided with this solicitation and by the
Procurement Officer will be considered acceptable as bid submission.
https://egov.maryland.gov/BusinessExpress/
IFB for Maryland State Highway Administration Hanover Complex Page 23 of 19
4.19 Attachments and Documents Required with the Bid (Table A)
A Bidder shall include the following Attachments with its Bid as a single Bid Package:
TABLE A - Attachments and Documents Required with the Bid
Attachment Attachment Name
A
Bid/Proposal Affidavit
A Bid submitted by the Bidder must be accompanied by a completed Bid/Proposal
Affidavit.
https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf
B
The Price Form (as specified within eMMA)
Do not alter this Price Form or the Bid may be determined to be not responsive.
The Price Form must be signed and dated, where requested, by an individual who is authorized to bind the Bidder to the prices entered on the Bid Form.
(See Appendix 2 for specific Price Form Instructions.)
C
Conflict of Interest Affidavit and Disclosure https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-I.-Conflict-of-Interest-Affidavit.pdf
Note: If this solicitation will result in the “selection of a contractor who will assist a unit in the formation, evaluation, selection, award, or execution of another State contract” the Bidder shall provide this Affidavit and other times as requested by the Procurement Officer.
D
Mercury Affidavit https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-J.-Mercury-Affidavit.pdf
E
Reference Checks
(Each reference shall be from a customer for whom the Bidder has provided goods or services within the most recent past five years) https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-L.-Reference-Checks.pdf
Additional Required Documents with the Bid
Minimum Qualifications Documentation. The Bidder shall submit any Minimum Qualifications documentation that may be required, as set forth in IFB Section 1. If references are required in IFB
Section 1, those references shall be included in Attachment E. Reference Checks.
https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-I.-Conflict-of-Interest-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-I.-Conflict-of-Interest-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-J.-Mercury-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-J.-Mercury-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-L.-Reference-Checks.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-L.-Reference-Checks.pdf
IFB for Maryland State Highway Administration Hanover Complex Page 24 of 19
Acknowledgement of all addenda to this IFB.
4.20 Bid Delivery Instructions
Each Bidder shall submit its Bid Package as specified below.
Bids shall only be accepted via the State’s internet-based electronic procurement system, eMMA.
Bidders shall provide their Bids in one submission through eMMA following the Quick Reference
Guides (QRG) labeled “4 - eMMA QRG Responding to Solicitations (IFB)” for single envelope submissions.
4.21 Bid Evaluation Criteria and Award Basis
The Bids will be evaluated based on the Total Bid Price, as per COMAR 21.05.02.13. All Bids will be ranked from the lowest (most favorable) to the highest (least favorable) price based on the Total
Bid Price as submitted in its Bid. A Contract shall be awarded to the responsible Bidder(s) submitting a responsive Bid with the most favorable Bid Price or most favorable evaluated Bid Price for providing the goods and services as specified in this IFB. The award for this solicitation will be made to the responsive and responsible Vendor with the lowest price, as determined by the Procurement
Officer to be in the best interests of the State of Maryland.
Vendor shall submit a bid price based on product description (specification) and unit of measure specified on each line. Award of this contract will not be final and complete until after: (1) the
Contractor submits complete and satisfactory documentation required under the Contract and/or documentation required by the Procurement Officer; and (2) the Contract is signed by the State
Highway Administration following any approvals of the Contract required by law or regulation.
4.22 Tie Bids
Tie Bids will be decided pursuant to COMAR 21.05.02.14.
4.23 Reciprocal Preference
Although Maryland law does not authorize procuring agencies to favor resident Bidders in awarding procurement contracts, many other states do grant their resident businesses preferences over Maryland contractors. COMAR 21.05.01.04 permits procuring agencies to apply a reciprocal preference under the following conditions:
A. The Maryland resident business is a responsible Bidder.
B. The lowest responsive Bid is from a responsible Bidder whose principal office, or principal base of operations, is in another state.
C. The other state gives a preference to its resident businesses through law, policy, or practice; and https://procurement.maryland.gov/emma-qrgs/ https://procurement.maryland.gov/emma-qrgs/
IFB for Maryland State Highway Administration Hanover Complex Page 25 of 19
D. The preference does not conflict with a federal law or grant affecting the procurement
Contract.
The preference given shall be identical to the preference that the other state, through law, policy, or practice gives to its resident businesses.
PAGE INTENTIONALLY LEFT BLANK
File details come from the government source that posted it. Updated .