This is a solicitation for repair of the Bisley Road Landslide on El Yunque National Forest in Rio Grande, Puerto Rico. The work includes slide repair, reshaping road slopes, constructing rolling dips, placing riprap and aggregate, installing culverts and drains, and installing gates. The estimated value is between $500,000 and $1,000,000. Questions are due by March 23, 2022 and award will be made to the lowest priced responsive and responsible offeror. The successful contractor must complete all work within 90 days of notice to proceed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No: 12445221B0001 Project Name: Bisley Road Landslide Repair on El Yunque National Forest
NOTICE TO BIDDERS
1442 INFORMATION
Item 8: LOCATION OF PUBLIC BID OPENING: A public bid opening will be conducted electronically via Microsoft Teams at the time and date stated in Item 13A. To participate in the bid opening, send an email request to Jose Allende at Jose.Allende@usda.gov NLT than 30 minutes prior to the designated date and time as stated in Item 13A and a link will be provided.
Item 11: COMPLETION DATE: Work shall be completed on or before the date specified in
FAR 52.211-10.
Item 12A: PERFORMANCE AND PAYMENT BONDS: See FAR Clause 52.228-15 Performance and Payment Bonds-Construction.
Item 13B: BID BOND AMOUNT: See FAR Provision 52.228-1 Bid Guarantee All bid guarantees must be a scanned original, showing signatures with original corporate seals.
Item 14: NAME AND ADDRESS OF OFFEROR: SAM Unique Entity ID shall be included in addition to the name and address.
Item 19: ACKNOWLEDGMENT OF AMENDMENTS: FAILURE TO ACKNOWLEDGE
AMENDMENTS, IN ITEM 19 OF THE SF-1442, BY THE DESIGNATED DATE AND
HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR
BID. If amendments are issued, they will be posted to www.sam.gov.
Item 24: SUBMITTING INVOICES: Invoices must be comply with FAR 52.232-5, Payments under Fixed Price Construction Contracts, and submitted electronically using the Invoice Processing Platform (IPP) via www.IPP.gov.
I. PRE-BID INFORMATION
ELECTRONIC BID SUBMISSION. Submit an electronic copy of your bid package to Jose.Allende@usda.gov with the following documents:
SF-1442, Solicitation, Offer & Award, Pages 1, 2 and 3.
Bid Schedule Page 6, and 7 Provide a price for CLIN’s 0001, 0002 and the total combined price.
Buy American Act & Hazardous Materials, Attachment A.
Bid Guarantee (see FAR Clause 52.228-1). Bid bonds must be scanned and show the original signatures and corporate seals. An acceptable bid bond must be submitted. Failure to submit an acceptable bid bond will make your bid non-responsive.
Complete the VETS-4212 declaration contained below
Annual Representations and Certifications (FAR Provision 52.204-8), Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (FAR Provision 52.204-24), and Certification Regarding Responsibility Matters (FAR Provision 52.209-5). Section K of this solicitation.
This solicitation and the subsequent contract are governed by the Federal Acquisition Regulations (FAR), agency supplemental regulations, and the drawings, specifications, and data attached. Applicable FAR provisions and clauses in this IFB are incorporated by reference or full text. FAR provisions and clauses incorporated by reference can be accessed on the Internet at: https://www.acquisition.gov/browse/index/far.
It is the responsibility of the bidder to verify that this solicitation document, including the plans, are complete as listed in the table of contents and the index to sheets. Plan sheets can be found at http://www.SAM.gov and viewed by individual sections, downloaded by individual sections, or the entire plan set downloaded in a zip file.
Notice of SAM Registration – bidders must be registered in the System for Award Management (SAM) prior to submission of a bid in response to this solicitation. Failure to register prior to submission of a bid may require award to the next successful registered offeror. See FAR Subpart 4.1102. Register online at www.sam.gov. (SAM is an official website of the U.S. government. There is no cost to use SAM. You can use this site for FREE to register to do business with the U.S. government.).
Representations and Certifications – This solicitation is issued under NAICS 237310 – Highway, Street & Bridge Construction with a small business size standard of $39.5 million. If your average annual gross receipts for the past 3 years are above $39.5 million, your organization is considered a large business for the purposes of this solicitation; if they are below $39.5 million your organization is considered a small business for the purposes of this solicitation. Please complete the certification listed in paragraph (b) of FAR Provision 52.204-8 Annual Representation and Certifications. Offerors must certify small business status for NAICS 237310 in SAM. Before submitting a bid, please ensure you have completed annual representations and certifications electronically in SAM at www.sam.gov.
Modifications to Bids - Bids may be modified or withdrawn by electronic commerce (email) if such notice is received prior to the time specified for receipt of bids. The Government will not be responsible for ANY failure attributable to the transmission or receipt of electronic commerce (email) data. For all modifications, the Government STRONGLY ENCOURAGES bidders to resubmit the entire bid schedule with a unit price and amount for every bid item, and a Schedule
Total (See FAR Provision 52.214-5, Submission of Bids). Modifications which make the bid ambiguous, indefinite, or uncertain as to any essential requirement of the contract will cause the bid to be rejected as nonresponsive. Email Address to submit modifications to bids for this project is Jose.Allende@usda.gov.
Vets-4212 Reporting - Bidders must complete the following report, if required. See reporting requirements at: https://www.dol.gov/agencies/vets/programs/vets4212.
☐ My firm had a qualifying Federal Contract in 2020 and has complied with the reporting requirements.
☐ My firm did not have a qualifying Federal Contract in 2020 and is therefore exempt from the reporting requirements.
Bid Guarantee – Follow the requirements of FAR Clause 52.228-1 Bid Guarantee. Bid bonds must be scanned originals showing signatures and corporate seals. A SF 24 can be found at: https://www.gsa.gov/forms-library/bid-bond
Accuracy and Completeness of Bid- The Contractor is fully responsible to verify that all data is correct when an offer is submitted. Failure to properly update your data may cause the offer to be rejected.
Site Visit—See Section L, 452.237-71 Pre-Bid/ Pre-Proposal Conference (FEB (1988), for information about the site visit. This is an opportunity for prospective bidders to see the site. Questions/clarifications will need to be submitted in writing.
**QUESTIONS REGARDING THIS SOLICITATION WILL NOT BE ACCEPTED
AFTER 4:00 P.M. ON March 23, 2022
Questions can be submitted to Jose.Allende@usda.gov. Questions and answers will be posted at https://sam.gov
Table of Contents
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
B.2 SCHEDULE NOTES
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.2 PROJECT LOCATON
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
C.4 TECHNICAL SPECIFICATIONS
SECTION D--PACKAGING AND MARKING
D-1 PACKING AND MARKING
D-2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
G.2 OTHER REQUIREMENTS
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
H.2 OTHER REQUIREMENTS
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
J.1 ATTACHMENTS
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND
OTHER STATEMENTS OF OFFERORS OR RESPONDENTS
K.1 PROVISIONS
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
L.1 PROVISIONS
SECTION M--EVALUATION FACTORS FOR AWARD
M.1 AWARD
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
Line Item 0001 – Bisley Road Landslide Repair on El Yunque National Forest
12445221R0058- Schedule of Items (SOI) - Bisley Rd
LINE
ITEM
DESCRIPTION QTY UNITS
UNIT
PRICE
TOTAL
PRICE
151.0
1 MOBILIZATION 1.00 CQ-LS
152.0
CONSTRUCTION SURVEY AND STAKING
METHOD 1 TOLERANCE A 1.00 CQ-LS
157.0
TEMPORARY EROSION CONTROL PLAN
AND IMPLEMENTATION. INCLUDES 200 SY.
AEC PREMIER COCONUT MAT, 150 FT. X 9
IN. STRAW WATTLES, AND STRAW BALES
AT CULVERTS 1.00 CQ-EACH
201.0
CLEARING AND GRUBBING- HEAVY
DISPOSE BY SCATTERING INCLUDES
VEGETATION AND BAMBOO 1.10 CQ-ACRE
201.0
CLEARING OF ROAD (OPTIONAL ITEM)-
HEAVY DISPOSE BY SCATTERING
EXISTING VEGETATION AND BAMBOO
WITHIN THE ROAD, BETWEEN RESEARCH
STATION #3 AND Q5. 0.30 CQ-ACRE
203.0
REMOVAL OF STRUCTURES AND
OBSTRUCTIONS, INCLUDES EXISTING
WOOD AND PLASTIC DRAINAGE
FEATURES, WOOD SIGNS, 40 FT.
CONCRETE PIPE (AT SLIDE), EXISTING
GATE AND ALL GATE POSTS 10.00 CQ-CY
204.0
EXCAVATION AND EMBANKMENT-SLIDE
REPAIR, INCLUDES MATERIAL
EXCAVATION REMOVAL AND WASTE
DISPOSAL
900.0
0 CQ-CY
212.0
LINEAR GRADING-RESHAPE 2%
INSLOPE/OUTSLOPE, INCLUDES DITCH
REHAB, CLEANING OUT 10 EXISTING
CONCRETE DRAIN PIPES, INCLUDING
INLET AND OUTLET, REHABILITATE 3
EXISTING LIVE-STREAM CULVERTS 1.15
CQ-LANE
MILE
212.0
LINEAR GRADING-CONSTRUCT 15 ROLLING
DIPS, INCLUDES GEOTEXTILE CLASS (1)
TYPE (A) (Mirafi 180N OR EQUIVALENT)
PLACEMENT AND 1 CY. OF CLASS 3 (8"-27")
RIP RAP PER DIP 15.00
CQ-LANE
MILE
251.0
RIPRAP CLASS 3 (8"-27"): MACHINE PLACED
COMMERCIAL SOURCE-SLIDE FACE
REPAIR INLUDES GEOTEXTILE CLASS (1)
TYPE (A) (Mirafi 180N OR EQUIVALENT)
PLACEMENT
250.0
0 CQ-CY
301.0
CRUSHED AGGREGATE (6 IN. DEPTH) :
TABLE 703-2 (3 IN. MINUS), GRADATION (A)
COMPACTION METHOD 204.11 (a) (1)
FURNISH, PLACE, AND HAUL 1,350 AQ-CY
602.0
CULVERT AND DRAINS - 36" ID-HDPE
CORRUGATED SMOOTH INSIDE PIPE N-12
WTIB DUAL WALL , INCLUDES GEOTEXTILE
CLASS (1) TYPE (A) (Mirafi 180N OR
EQUIVALENT) AND CLASS 3 (8"-27") RIP
RAP, 15 CY. INLET-5 CY. OUTLET 60 CQ-LF
619.0
GATE, METAL, 20 FT. WIDE INCLUDES
SIGNS 1 CQ-EACH
635.0
TRAFFIC CONTROL PLAN AND
IMPLEMENTATION 1 CQ-EACH
GRAND TOTAL FOR ALL ITEMS $0.00
B.2 SCHEDULE NOTES
Before preparing the bid, carefully read the Solicitation Provisions. Insert a unit bid price, in figures, for each pay item for which a quantity appears in the schedule of items. Multiply the unit price by the quantity for each pay item and show the Total amount. Total all of the amounts bid for each pay item and show the total bid amount. When the word “LS” (Lump Sum) appears as a unit bid price, insert an amount for each lump sump pay item. Should any mathematical check made by the Government show a mistake in the amount bid, the unit price, and subsequently the corrected extension shall govern.
DO NOT CHANGE/REVISE ANY OF THE QUANTITIES OR UNITS LISTED. A change to the quantities or units will cause the bid to be rejected as nonresponsive.
Contract quantity (CQ). The quantity to be paid is the quantity shown in the bid schedule. This amount will not be adjusted to reflect actual quantitates after contract award. If during the solicitation, there is evidence that a quantity specified as a contract quantity is incorrect, submit calculations, drawings, or other evidence indicating why the quantity is in error and request, in writing, that the quantity be adjusted.
Actual quantity (AQ). The quantity to be paid is the actual quantity used during construction.
This line item is subject to FAR 52.211-18 Variation in Estimated Quantity.
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
Line Item 0001 - Bisley Road Landslide Repair on El Yunque National Forest
For more information, see attachments listed in Section J.
C.2 PROJECT LOCATON
Line Item 0001 - Bisley Road Landslide Repair on El Yunque National Forest
Commonwealth of Puerto Rico, County of Rio Grande, El Yunque National Forest.
The project is located south of the El Portal Visitor Center. From PR-3 in Rio Grande, Puerto Rico follow PR-191 for approx. 3 miles then turn left onto PR-988 for approx. 3 miles, Forest Service Road 915 will be on your right. Project coordinates: Latitude: 18°19' 17.23"N; Longitude: 65°44' 33.49"W.
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
The magnitude of construction for this project is between $500,000 and $1,000,000.
C.4 TECHNICAL SPECIFICATIONS
Technical specifications shall be used and are listed in Section J as an attachment.
SECTION D--PACKAGING AND MARKING
D-1 PACKING AND MARKING
All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.
D-2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
52.211-18 Variation in Estimated Quantity (APR 1984) 52.242-14 Suspension of Work (APR 1984)
52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than __90 days after the notice to proceed_. The time stated for completion shall include final cleanup of the premises.
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
Reserved.
G.2 OTHER REQUIREMENTS
Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within __10__days after the date of contract award. The conference will be held at __TBD____.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
H.2 OTHER REQUIREMENTS
USE OF PREMISES
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.
(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.
ARCHAEOLOGICAL OR HISTORIC SITES
If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.
CONTROL OF EROSION, SEDIMENTATION, AND POLLUTION
(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
(b) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
Federal Acquisition Regulation (FAR) Clauses:
https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:
https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at:
https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm
52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-14 Display of Hotline Poster(s) (NOV 2021) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform
Employees of Whistleblower Rights (JUN 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or
Statements (JAN 2017) 52.204-2 Security Requirements (MAR 2021) Alternate II (APR 1984) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY
2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN
2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-15 Service Contract Reporting Requirements for Indefinite Delivery Contracts (OCT
2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014)
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021)
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JUN 2020)
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
(OCT 2018)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.214-29 Order of Precedence – Sealed Bidding (JAN 1986) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-28 Post Award Small Business Program Representation (SEP 2021) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY
2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
(MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC
2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN 2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction
Contracts (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction
Contracts (AUG 2018)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020)
52.223-20 Aerosols (JUN 2016) 52.223-21 Foams. (JUN 2016) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises
(JUN 2000)
52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT
2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984)
Alternate 1 (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)
Alternate I (APR 1984) 52.242-5 Payments to Small Business Subcontractors (JAN 2017)
52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-2 Subcontracts (JUN 2020) 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN 2022)
(DEVIATION APR 2020)
52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994)
Alternate I (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--
Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
52.219-14 Limitations on Subcontracting (SEP 2021)
(a) This clause does not apply to the unrestricted portion of a partial set- aside.
(b) Applicability. This clause applies only to ---imilarly situated entity, as used in this clause, means a first-tier subcontractor , including an independent contractor , that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract , any small business concern , without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract .
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2)Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3)
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4)Orders issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i)Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii)Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—
(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor 's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract;
(2) Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor 's 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract;
(3) General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor 's 85 percent subcontract amount that cannot be exceeded; or
(4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor 's 75 percent subcontract amount that cannot be exceeded.
(f) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause—
[Contracting Officer check as appropriate.]
□ By the end of the base term of the contract and then by the end of each subsequent option period; or
□ By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g)A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.
52.225-9 Buy American Act-Construction Materials (NOV 2021)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item-
(1) Means any item of supply (including construction material) that is-
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace;
and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work.
The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States;
or
(ii) A construction material manufactured in the United States, if-
(A) The cost of its components mined, produced, or manufactured in the United
States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States.
Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United
States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any
Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy
American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description Unit of Measure Quantity Price (dollars)* Item1:
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______
Item2:
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
52.228-1 Bid Guarantee (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –
(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be __20__ percent of the bid price or $ 3,000,000_, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION APR 2020)
(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -
(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and
(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].
(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.
(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.
(c)A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.
(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For
90 days following final payment.
(d)The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.
52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION APR
2020)
(a)Definitions. As used in this clause -- “Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance Bonds (Standard Form 25, EXCEPT THAT A SEAL IS NOT REQUIRED). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A, EXCEPT THAT A SEAL IS NOT REQUIRED). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection.
(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier’s check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of Treasury Financial Management Service Surety Bond Branch 3700 East West Highway, Room 6F01 Hyattsville, MD 20782 Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
52.228-17 Individual Surety – Pledge of Assets (Bid Guarantee) (FEB 2021)
(a)Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b)The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228-1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c)The Contracting Officer may release the security interest on the individual surety's assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
52.232-40 Providing Accelerated Payments to Small Business Subcontractors (NOV 2021)
(DEVIATION APR 2020)
(a)[(1) In accordance with 31 U.S.C. 3903 and 10 U.S.C. 2307, upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract [in accordance with the accelerated payment date established], to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, [with a goal of 15 days] after receipt of a proper invoice and all other required documentation from the small business subcontractor [if a specific payment date is not established by contract.
(2) The Contractor agrees to make such payments to its small business subcontractors without any further consideration from or fees charged to the subcontractor].
(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.
(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial products or commercial services.
52.236-4 Physical Data (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by See attachments.
(b) Weather conditions __________ [insert a summary of weather records and warnings].
Rio Grande, PR Weather Details
Month Precip
(IN)
Min Temp (F)
Avg. Temp (F)
Max Temp (F)
January 6.42 73.8 78.8 83.8 February 5.56 71.7 76.8 82 March 5.15 73.3 79.1 85 April 6.34 74.3 80.2 86.1 May 11.15 75.8 80.6 85.4
June 8.7 76.5 81.8 87.2 July 8.92 78.2 83.4 88.6 August 9.61 79.2 84 88.8
September 12.38 79.1 84.9 90.7
October 10.85 77.7 84.1 90.6 November 12.85 76.6 82.1 87.6 December 9.18 74.5 79.7 85
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
J.1 ATTACHMENTS
J1 – Statement of Work J2 – Drawings Bisley Road Landslide Repair J3 – Wage Determination, PR20210002 J4 – Forest Service Supplemental
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND
OTHER STATEMENTS OF OFFERORS OR RESPONDENTS
K.1 PROVISIONS
52.204-8 Annual Representations and Certifications (JAN 2022) (DEVIATION JUL 2020)
(a) (1) The North American Industry Classification System (NAICS) code for this acquisition is__________________ [insert NAICS code].
(2) The small business size standard is _____________ [insert size standard].
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees if the acquisition -
(i)Is set aside for small business and has a value above the simplified acquisition threshold;
(ii)Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii)Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b) (1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
(i) ☐ Paragraph (d) applies.
(ii) ☐ Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless–
(A) The acquisition is to be made under…