Bid Verification - 1244555B0001.pdf

PDF 191 KB Posted

Attached to
Bisley Road Landslide Repair on El Yunque National Forest - Solicitation
Solicitation number
1244522B0001
Issued by

About this file

This document contains bid verification information for repair work on Bisley Road Landslide on El Yunque National Forest in Puerto Rico. The project involves mobilization, surveying, erosion control, clearing and grubbing, structure removal, excavation and embankment work, linear grading, riprap installation, aggregate placement, culvert installation, gate installation, and traffic control. Four contractors provided bids for the work ranging from $521,401.79 to $992,374.41. Additionally, the related federal contract opportunity posting provides details on Solicitation Number 1244522B0001 for the Bisley Road Landslide Repair project, including the work location and coordinates, submission deadlines and evaluation criteria, and involvement of the USDA Forest Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Line # Item # Description of Work to Date (Equipment, Labor, and Materials) Quantity Unit IGE Obractec Unit Price

Obratec Total

Novel Unit Price

Novel Total

Advantix Eng Unit Price

Advantix Eng Total

JPI Construction Unit Price

JPI Construction Total

1 151.01 MOBILIZATION 1.00 LS 80,000.00$ 52,135.59$ 52,135.59$ 55,000.00$ 55,000.00$ 58,660.00$ 58,660.00$ 115,417.75$ 115,417.75$

2 152.01

CONSTRUCTION SURVEY AND STAKING METHOD 1

TOLERANCE A

1.00 LS 30,000.00$ 10,055.00$ 10,055.00$ 10,000.00$ 10,000.00$ 32,633.00$ 32,633.00$ 24,058.69$ 24,058.69$

3 157.01

TEMPORARY EROSION CONTROL PLAN AND IMPLEMENTATION

INCLUDES 250 SY. AEC PREMIER COCONUT MAT, 150 FT. X 9 IN.

STRAW WATTLES, AND STRAW BALES AT CULVERTS

1.00 EA 15,000.00$ 12,377.00$ 12,377.00$ 30,000.00$ 30,000.00$ 26,331.00$ 26,331.00$ 14,027.82$ 14,027.82$

4 201.01

CLEARING AND GRUBBING- HEAVY DISPOSE BY SCATTERING.

INCLUDES VEGETATION AND BAMBOO

1.10 AC 60,005.00$ 32,524.00$ 35,776.40$ 20,000.00$ 22,000.00$ 24,157.00$ 26,572.70$ 53,483.20$ 58,831.52$

5 201.04

CLEARING OF ROAD(OPTIONAL ITEM)- HEAVY DISPOSE BY

SCATTERING EXISTING VEGETATION AND BAMBOO WITHIN

THE ROAD, BETWEEN RESEARCH STATION #3 AND Q5.

0.30 AC 16,365.00$ 35,777.00$ 10,733.10$ 20,000.00$ 6,000.00$ 32,157.00$ 9,647.10$ 53,483.20$ 16,044.96$

6 203.01

REMOVAL OF STRUCTURES AND OBSTRUCTIONS

INCLUDES EXISTING WOOD AND PLASTIC DRAINAGE

FEATURES, WOOD SIGNS, 40 FT. CONCRETE PIPE (AT SLIDE),

EXISTING GATE AND ALL GATE POSTS

10.00 CY 10,000.00$ 502.10$ 5,021.00$ 1,000.00$ 10,000.00$ 1,384.00$ 13,840.00$ 3,554.33$ 35,543.30$

7 204.01

EXCAVATION AND EMBANKMENT-SLIDE REPAIR. INCLUDES

MATERIAL EXCAVATION REMOVAL AND WASTE DISPOSAL

900.00 CY 49,500.00$ 102.10$ 91,890.00$ 50.00$ 45,000.00$ 55.22$ 49,698.00$ 115.00$ 103,500.00$

8 212.01

LINEAR GRADING-RESHAPE 2% INSLOPE/OUTSLOPE,

INCLUDES DITCH REHAB, CLEANING OUT 10 EXISTING

CONCRETE DRAIN PIPES, INCLUDING INLET AND OUTLET,

REHABILITATE 3 EXISTING LIVE-STREAM CULVERTS

1.15 MILE 100,000.00$ 10,578.00$ 12,164.70$ 35,000.00$ 40,250.00$ 30,112.00$ 34,628.80$ 97,322.63$ 111,921.02$

9 212.01

LINEAR GRADING-CONSTRUCT 15 ROLLING DIPS, INCLUDES

GEOTEXTILE CLASS (1) TYPE (A) (Mirafi 180N OR EQUIVALENT)

PLACEMENT AND 1 CY. OF CLASS 3 (8"-27") RIP RAP PER DIP

15.00 MILE 45,000.00$ 5,923.00$ 88,845.00$ 7,000.00$ 105,000.00$ 10,179.00$ 152,685.00$ 2,757.77$ 41,366.55$

10 251.01

RIPRAP CLASS 3 (8"-27"): MACHINE PLACED COMMERCIAL

SOURCE-SLIDE FACE REPAIR INLUDES GEOTEXTILE CLASS (1)

TYPE (A) (Mirafi 180N OR EQUIVALENT) PLACEMENT

250.00 CY 160,000.00$ 139.90$ 34,975.00$ 200.00$ 50,000.00$ 105.90$ 26,475.00$ 513.01$ 128,252.50$

11 301.01

CRUSHED AGGREGATE (6 IN. DEPTH) : TABLE 703-2 (3 IN.

MINUS), GRADATION (A) COMPACTION METHOD 204.11 (a) (1)

FURNISH, PLACE, AND HAUL

1350.00 CY 135,000.00$ 88.58$ 119,583.00$ 80.00$ 108,000.00$ 89.10$ 120,285.00$ 173.81$ 234,643.50$

12 602.01

CULVERT AND DRAINS - 36" ID-HDPE CORRUGATED SMOOTH

INSIDE PIPE N-12 WTIB DUAL WALL , INCLUDES GEOTEXTILE

CLASS (1) TYPE (A) (Mirafi 180N OR EQUIVALENT) AND CLASS 3

(8"-27") RIP RAP, 15 CY. INLET-5 CY. OUTLET

60.00 LF 18,000.00$ 411.70$ 24,702.00$ 800.00$ 48,000.00$ 96.30$ 5,778.00$ 1,242.50$ 74,550.00$

13 619.02 GATE, METAL, 20 FT. WIDE INCLUDES SIGNS 1.00 EA 10,000.00$ 12,375.00$ 12,375.00$ 20,000.00$ 20,000.00$ 5,600.00$ 5,600.00$ 15,059.67$ 15,059.67$

14 635.01 TRAFFIC CONTROL PLAN AND IMPLEMENTATION 1.00 EA 5,000.00$ 10,769.00$ 10,769.00$ 5,750.00$ 5,750.00$ 10,449.00$ 10,449.00$ 19,157.13$ 19,157.13$

BID ADDITIVE - TOTAL CONSTRUCTION AMOUNT GRAND TOTAL 733,870.00$ 521,401.79$ 555,000.00$ 573,282.60$ 992,374.41$