This is a Technical Document for an Invitation for Bid (IFB) issued by the City of Austin, Texas, for the procurement of HIV test kits to support the Austin Public Health Program. The City seeks to establish a contract with a qualified vendor to supply annual quantities of one-time use, rapid Human Immunodeficiency Virus (HIV) Type 1 and Type 2 test kits. The solicitation establishes the technical specifications and requirements that proposed test kits must meet to be considered responsive to the bid. Specific details regarding item quantities, response deadlines, bid due dates, site visits, bidder conferences, and contract award timelines should be referenced in the primary IFB document.
The technical specifications document outlines the performance standards, certification requirements, and product characteristics that HIV test kits must satisfy for acceptance. Additional information regarding pricing terms, set-asides, incumbent vendors, funding sources, budget allocations, and other material procurement conditions would be contained within the complete IFB package and related solicitation documents.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB_9100_AAM1023REBID_0600_v1.xlsx | XLSX spreadsheet | |
| IFB_9100_AAM1023REBID_ATT_1_v1.pdf | ||
| IFB_9100_AAM1023REBID_PAC1_v1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bidding Requirements, Contract Forms and Conditions of the Contract
Table of Contents
Rev. Date 06/01/2026 Table of Contents Page 1 of 4
Document Number
Date Title
VOLUME 1 of 3
06/01/2026 Table of Contents
BIDDING REQUIREMENTS, CONTRACT FORMS, & CONDITIONS OF THE CONTRACT
Division 0 - General Requirements
00020 IDIQ 10/01/2024 Invitation for Bids 00100 09/21/2023 Instructions to Bidders 00220 03/30/18 Geotechnical Data 00300U IDIQ 09/01/2021 Unit Price Bid Form 04/03/2020 Total Bid Form 00400 10/10/2022 Statement of Bidder’s Experience 00405 03/30/2018 Certificate of Non-Suspension or Debarment 00410 01/12/2026 Statement of Bidder’s Safety Experience 00440 09/01/2025 Prohibited Activities 00500 IDIQ 08/12/2019 Agreement 00610 02/04/2020 Performance Bond 00620 02/04/2020 Payment Bond 00630 10/22/2019 Non-Discrimination and Non-Retaliation Certificate 00631 03/30/2018 Title VI Assurances Appendix A 00632 03/30/2018 Title VI Assurances Appendix E 00650 06/08/2018 Certificate of Insurance 00670 01/11/2019 Sales Tax Exemption Certificate 00680 03/30/2018 Non-Use of Asbestos Affidavit (Prior to Construction) 00681 03/30/2018 Non-Use of Asbestos Affidavit (After Construction) 00700 10/03/2025 General Conditions 00810 IDIQ 06/01/2026 Supplemental General Conditions 00810A 01/12/2026 Federal Aid Assurances 00820 IDIQ 03/30/2018 Modifications to Bidding Requirements and Contract Forms 00830 10/01/2025 Wage Rates and Payroll Reporting 00830HH 01/12/2026 Wage Rates Highway Heavy 00840 05/30/2025 Construction Training Program Requirements 00900 05/10/2021 Addendum (SAMPLE)
SPECIFICATIONS
Division 1 - General Requirements
01010 08/28/2020 Summary of Work 01050 10/19/2015 Grades Lines & Levels 01095 07/21/2003 Reference Standards and Definitions 01200 05/06/2022 Project Meetings 01300 05/06/2022 Submittals 01353 04/29/2020 Construction Equipment Emissions Reduction Plan 01380 04/14/2023 Construction Photography & Videos 01500 05/09/2025 Temporary Facilities 01505 08/12/2019 Construction and Demolition Waste Management 01550 08/09/2012 Public Safety and Convenience 01900 03/12/2012 Prohibition of Asbestos Containing Materials 01900a 06/05/2006 Statement of Non-Inclusion of Asbestos Containing Material (E/A
Prior to Design)
Rev. Date 06/01/2026 Table of Contents Page 2 of 4
01900b 06/05/2006 Statement of Non-Inclusion of Asbestos Containing Material (E/A After Design)
VOLUME 2 of 3
City Standard Technical Specifications
101S 03/25/2021 Preparing Right of Way 104S 09/26/2012 Removing Portland Cement Concrete 201S 06/17/2021 Subgrade Preparation 210S 02/24/2010 Flexible Base 230S 08/20/2007 Rolling (Flat Wheel) 232S 08/20/2007 Rolling (Pneumatic Tire) 234S 08/20/2007 Rolling (Tamping) 236S 08/20/2007 Proof Rolling 301S 08/20/2007 Asphalts, Oils, and Emulsions 306S 02/24/2010 Prime Coat 307S 02/24/2010 Tack Coat 315S 09/26/2012 Milling Asphaltic Concrete Pavement and Non-P.C. Concrete Base 340 03/20/2024 Hot Mix Asphaltic Concrete Pavement 360S 09/26/2012 Concrete Pavement 402 09/13/2022 Controlled Low Strength Material 403 04/14/2025 Concrete for Structures 406S 09/26/2012 Reinforcing Steel 408S 11/13/2007 Concrete Joint Materials 409S 11/13/2007 Membrane Curing 410S 09/14/2021 Concrete Structures 411S 11/13/2007 Surface Finishes for Concrete 430S 11/15/2011 P.C. Concrete Curb and Gutter 432S 01/04/2010 P.C. Concrete Sidewalk 433S 12/09/2008 P.C. Concrete Driveways 503 11/07/2022 Frames, Grates, Rings, and Covers 504S 02/24/2010 Adjusting Structures 505S 02/24/2010 Concrete Encasement and Encasement Pipe 506 02/22/2021 Manholes 509S 09/26/2012 Excavation Safety Systems 510 06/02/2025 Pipe 511 03/10/2025 Water Valves 513 06/02/2025 Polyethylene (HDPE) Pipe and Fittings C906, 4-Inch & Larger 601S 11/14/2016 Salvaging and Placing Topsoil 602S 06/16/2008 Sodding for Erosion Control 604S 06/17/2021 Seeding for Erosion Control 605S 06/21/2007 Soil Retention Blanket 610 04/14/2025 Preservation of Trees and Other Vegetation 620S 01/04/2016 Filter Fabric 628S 12/31/2013 Sediment Containment Dikes 641S 03/25/2021 Stabilized Construction Entrance 642S 09/01/2011 Silt Fence 700S 09/26/2012 Mobilization 703 09/22/1988 Fencing for Excavation 803S 11/15/2011 Barricades, Signs and Traffic Handling
Special Provisions to City Standard Technical Specifications
SP402 06/22/2023 Controlled Low Strength Material SP505S 10/16/2017 Concrete Encasement and Encasement Pipe SP506 06/26/2026 Manholes
Rev. Date 06/01/2026 Table of Contents Page 3 of 4
SP509S 10/16/2017 Excavation Safety Systems SP510 06/26/2026 Pipe SP511 06/26/2026 Water Valves SP513 06/26/2026 Polyethylene (HDPE) Pipe and Fittings C906, 4-Inch & Larger SP700S 01/10/2020 Mobilization SP803S 06/26/2026 Barricades, Signs and Traffic Handling
Special Specifications
SS520 06/21/2026 Large Diameter Water Main Manned Entry SS597 06/10/2026 Water Main Replacement by Pipe Bursting SS02225 06/21/2026 Excavation and Backfill SS02614 06/21/2026 Temporary Waterline Stops SS02667 05/18/2026 Emergency Waterline Repairs
City Standard Technical Details
340S-1 09/29/1999 HMAC Transverse Construction Joint 430S-1 09/29/1999 Curb and Gutter Section 430S-2 01/04/2010 Reinforced Curb and Gutter Section 430S-3 09/29/1999 Curb Expansion Joint and Dowel Detail 430S-4 09/29/1999 Concrete Backfill Under Curb and Gutter 430S-5 04/05/1999 Reinforcing Bar Detail at Existing Curb and Gutter 432S-1 10/29/2025 Sidewalk 432S-2A 10/29/2025 Detectable Warning Paver (City Property/ Easements) 432S-3 10/29/2025 Type I Curb Ramps – Full Intersection 432S-3A 10/29/2025 Type I Curb Ramps – “T” Intersection 432S-3B 10/29/2025 Type IA/IB Curb Ramps – Full Intersection 432S-3C 03/13/2006 Type IA/IB Curb Ramps – “T” Intersection 432S-3D 03/13/2006 Combined Curb Ramps – Full Intersection 432S-3E 03/13/2006 Combined Curb Ramps – “T” Intersection 432S-3F 03/13/2006 Combined Sidewalk Curb Ramps with Pavers 432S-3G 06/21/2007 Combined Sidewalk Curb Ramp with Pavers within Limited ROW
Only 432S-3H 08/20/2007 Type I Ramps within PC/PT of Curb and Gutter 432S-5 09/14/2005 Type I Sidewalk Curb Ramp 432S-5A 06/16/2008 Type IA Sidewalk Curb Ramp with Left Flare 432S-5B 09/14/2005 Type IB Sidewalk Curb Ramp 433S-1 04/14/2025 Type I Driveway (1 & 2 Family Residential Use Only) 433S-1A 04/14/2025 Flared Type I Driveway (1 & 2 Family Residential Use Only) 433S-2 02/24/2010 Type II Driveway 503S-4S 02/14/2002 Storm Drain Manhole Ring and 813 mm (32”) Cover 505S-1 08/18/2000 Concrete Encasement 506S-4 08/31/2011 Minor Manhole Adjustment and New Manhole Construction 510S-3 08/19/2002 Typical Trench with Paved Surface 510S-5 03/13/2006 Typical Trench with Unfinished Surface 510-6 02/11/1986 Concrete Thrust Blocking 511-AW-01 05/18/2016 Typical Gate Valve 4”-16” 511-AW-02 11/06/2023 Fire Hydrant 511-AW-03 05/18/2016 Drain Valve 511-AW-04A 09/11/2024 Combination Air Valve (CAV) Assemblies For Potable and Reclaimed Service (2", 4", & 6" only) 511-AW-05 05/18/2016 Automatic Flush Valve 513-AW-01 06/02/2025 HDPE MJ Adapter Connection 520-AW-01A 11/07/2018 Water/Wastewater Service on a Common Lot Line 520-AW-01B 06/02/2025 Water Service & Meter Installation – 1” & Smaller Meters 610S-1 11/15/1999 Tree Protection Fence Locations
Rev. Date 06/01/2026 Table of Contents Page 4 of 4
610S-4 11/15/1999 Tree Protection Fence Modified Type A – Chain Link 628S 03/27/2000 Triangular Sediment Filter Dike 639S-1 08/24/2010 Rock Berm 641S-1 05/23/2000 Stabilized Construction Entrance 642S-1 09/01/2011 Silt Fence 804S-1 01/04/2011 Arterial One Lane Closure 804S-1A 11/13/2007 Residential Road Narrows for Centerline Work 804S-1B 01/02/2025 Merging Bicyclist & Bicyclists Bypass 804S-2 03/13/2006 Collector/Residential Street Flagging Operations 804S-3 03/13/2006 Temporary Traffic Control Pavement Markings 804S-4 04/03/2009 Safety Fence 804S-5 01/04/2010 Channeling Devices 804S-6A 02/21/2001 Low Profile Concrete Barrier Type I (Portable and Precast) 804S-6B 02/21/2001 Low Profile Concrete Barrier Type II (Portable and Precast) 829S-1A 09/26/2012 Bicycle Lane Markings 829S-1B 11/13/2007 Bicycle Lane Markings and Signing at Intersections 1100S-1 01/04/2010 Casting Adjustment 1100S-2 01/04/2011 Flexible Base w/Asphalt Surface Trench Repair – Existing
Pavement 1100S-3 09/14/2005 Asphalt Overlay of Reinforced & Nonreinforced PC Pvt-Trench Repair 1100S-4 12/09/2008 Temporary Trench Repair – Asphalt Surface 1100S-5 09/14/2005 Full Depth Asphaltic Concrete Pavement Trench Repair 1100S-7 09/14/2005 Street Repair Requirements Within Intersections 1100S-8A 02/24/2010 Traffic Lane Replacement for Outer Lane Excavations 1100S-8B 02/24/2010 Traffic Lane Replacement for Interior Lane Excavations
VOLUME 3 of 3
08/2019 MBE/WBE Procurement Program Package
END
ITEM NO. 101S PREPARING RIGHT-OF-WAY 3-25-2021
Austin, Texas, Standard Specifications Manual Created: 2022-10-28 11:15:22 [EST]
(Supp. No. 8-2022)
ITEM NO. 101S PREPARING RIGHT-OF-WAY 3-25-2021
101S.1 Description
This item shall govern the preparation of the right-of-way for construction operations by removal and disposal of all obstructions from the right-of-way and from designated easements, where removal of such obstructions is not otherwise indicated as a separate pay item.
Such obstructions shall be considered to include, but not be limited to, remains of houses not completely removed by others, foundations, floor slabs, concrete, brick, lumber, plaster, cisterns, water wells, septic tanks and drain fields, basements; abandoned utility pipes, conduits, underground service station tanks, fences, retaining walls, outhouses, shacks and all other debris.
This item shall also include, but not be limited to, the removal of trees, stumps, roots, bushes, shrubs, curb and gutter, driveways, paved parking areas, miscellaneous stone, brick, sidewalks, drainage structures, manholes, inlets, abandoned railroad tracks, scrap iron, and all rubbish and debris whether above or below ground. Care should be taken to identify and protect existing infrastructure.
This specification is applicable for projects or work involving either inch-pound or SI units. Within the text the inch-pound units are given preference followed by SI units shown within parentheses.
101S.2 Submittals
The submittal requirements of this specification item may include:
A. A permit when utility adjustments are made in the right-of-way, and
B. A plan for removal and deposition of all non-salvageable materials and debris.
101S.3 Construction Methods
Prior to commencement of this work, all required erosion controls and tree protection measures indicated on the Drawings shall be in place. The existing utilities shall be located and protected as specified in the Standard Contract Documents, Section 00700, "General Conditions" and/or as specified on the Drawings. A permit shall be required when utility adjustments are to be made in preparation for construction in the right-of-way, as specified in Section
5.2.0 of the City of Austin Utilities Criteria Manual.
Areas within the construction limits shall be cleared of all obstructions, abandoned structures, and other items as defined above. All vegetation, except trees or shrubs indicated for preservation, shall also be removed. Trees and shrubs, which are scheduled for preservation, shall be carefully trimmed as directed and shall be protected from scarring, barking or other injuries during construction operations in accordance with Item No. 610S, " Preservation of Trees and Other Vegetation". All exposed cuts over 2 inches (50 millimeters) in diameter, exposed ends of pruned limbs or scarred bark shall be treated with an approved asphalt material within 24 hours of the pruning or injury.
Construction equipment shall not be operated nor construction materials stockpiled under the canopies of trees, unless otherwise indicated on the Drawings and/or specified in the Contract Documents. Excavation or embankment materials shall not be placed within the drip line of trees until tree wells are constructed.
Culverts, storm sewers, manholes and inlets shall be removed in proper sequence for maintenance of traffic and drainage.
Created: 2022-10-28 11:15:22 [EST]
Unless otherwise indicated on the Drawings and/or Contract Documents, all underground obstructions, stumps and roots shall be removed to the following depths:
1. In areas to receive 6 inches (150 mm) or more embankment, a minimum of 12 inches (300 mm) below natural ground.
2. In areas to receive less than 6 inches (150 mm) of embankment, a minimum of 18 inches (450 mm) below the lower elevation of embankment, structure or excavation.
3. In areas to be excavated a minimum of 18 inches (450 mm) below the lower elevation of the embankment, structure or excavation.
4. In all other areas, a minimum of 12 inches (300 mm) below natural ground.
Holes remaining after removal of all obstructions, objectionable material, trees, stumps, etc. shall be backfilled with select embankment material and compacted by approved methods.
When a utility in service conflicts with the construction, it shall be modified as specified in the Standard Contract Documents, Section 00700, "General Conditions" and/or as specified on the Drawings.
Where an abandoned underground piped utility is found, it shall be cut and plugged with 6 inches (150 mm) of concrete (in accordance with Specification Item 403, "Concrete for Structures") brick and mortar (in accordance with Specification Item 506S, "Manholes") or a precast stopper grouted in place.
Material to be removed will be designated as salvageable or non-salvageable by the Engineer or designated representative prior to removal from the construction site by the Contractor. All material, which is located within the public right-of-way and is declared by the Engineer as salvageable, will remain the property of the City of Austin and will be stored at the site or loaded on city trucks as directed by the Engineer. All non-salvageable materials and debris shall become the property of the Contractor and shall be removed from the site and deposited at a permitted disposal site.
101S.4 Measurement
The preparation of right-of-way for new construction, when included in the contract as a pay item, will be measured by the acre (hectare: 1 hectare equals 2.471 acres), 100 foot (100 feet equals 30.5 meters) stations or lump sum, regardless of the width of the right-of-way.
Measurement for payment will be made only on areas indicated and classified as "Preparing Right-of-Way."
Source: Rule No. R161-21.01 , 3-25-2021.
101S.5 Payment
The work and material presented herein will not be paid for directly, but shall be included in the unit price bid for the item of construction in which this item is used unless specified as a separate pay item in the contract bid form.
When included for payment, it shall be paid for at the contract bid price for "Preparing Right-of-Way." This price shall include full compensation for work herein specified, including the furnishing of all materials, equipment, tools, labor and incidentals necessary to complete the work.
When payment is made under the Lump Sum pay item the total payment of this item shall not exceed 5% of the original contract amount until final payment. Any remainder will be paid as part of final payment.
Payment, when included as a contract pay item, will be made under one of the following:
Pay Item No. 101S-A: Preparing Right-of-Way - Per Acre.
Pay Item No. 101S-B: Preparing Right-of-Way - Per 100 foot Station.
Pay Item No. 101S-C: Preparing Right-of-Way - Per Lump Sum.
Source: Rule No. R161-21.01 , 3-25-2021.
End
SPECIFIC CROSS REFERENCE MATERIALS
Specification 101S, "PREPARING RIGHT-OF-WAY"
City of Austin Standard Contract Documents
Designation Description
00700 General Conditions
City of Austin Utilities Criteria Manual
Section 5.2.0 Permit for Excavation in the Public Right-of-Way
City of Austin Standard Specifications
Item No. 110S Street Excavation
Item No. 111S Excavation
Item No. 120S Channel Excavation
Item No. 132S Embankment
Item No. 403 Concrete for Structures
Item No. 506S Manholes
Item No. 610S Preservation of Trees and Other Vegetation
RELATED CROSS REFERENCE MATERIALS
Specification 101S, "PREPARING RIGHT-OF-WAY"
City of Austin Standard Contract Documents
Designation Description
01500 Temporary Facilities
01550 Public Safety and Convenience
The Code of the City of Austin, Code of Ordinances, Volume 2
Article 14-11-181 Permit Required
Article 14-11-189 Conditions for Permit Issuance
Article 14-11-190 Permit Term
Item No. 102S Clearing and Grubbing
Item No. 104S Removing Portland Cement Concrete
Item No. 201S Subgrade Preparation
Item No. 203 Lime Treatment for Materials In Place
Item No. 204S Portland Cement Treatment for Materials In Place
Item No. 230S Rolling (Flat Wheel)
Item No. 232S Rolling (Pneumatic Tire)
Item No. 234S Rolling (Tamping)
Item No. 236S Rolling (Proof)
Item No. 602S Sodding for Erosion Control
Item No. 604S Seeding for Erosion Control
Item No. 622S Diversion Dike
Item No. 628S Sediment Containment Dikes
Item No. 642S Silt Fence
City of Austin Standard Details
610S-1 Tree Protection Fence Locations
610S-2 Tree Protection Fence, Type B Chainlink
610S-3 Tree Protection Fence, Type B Wood
610S-4 Tree Protection Fence, Modified Type A
610S-5 Tree Protection Fence, Modified Type B
621S-1 Diversion
622S-1 Diversion Dike
624S-1 Earth Outlet Sediment Trap
625S-1 Grade Stabilization Structure
627S-1 Grass Lined Swale
627S-2 Grass Lined Swale With Stone Center
628S Triangular Sediment Filter Dike
628S-1 Hay Bale Dike
629S-1 Brush Berm
630S-1 Interceptor Dike
631S-1 Interceptor Swale
632S-1 Storm Inlet Sediment Trap
633S-1 Landgrading
634S-1 Level Spreader
635S-1 Perimeter Dike
636S-1 Perimeter Swale
637S-1 Pipe Slope Drain (Flexible)
637S-2 Pipe Slope Drain (Flexible)
638S-1 Pipe Outlet Sediment Trap
639S-1 Rock Berm
641S-1 Stabilized Construction Entrance
642S-1 Silt Fence
643S-1 Stone Outlet Structure
644S-1 Stone Outlet Sediment Trap
Texas Department of Transportation: Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges
Designation Description
Item No. 100 Preparing Right-of-Way
Item No. 110 Excavation
Item No. 112 Subgrade Widening
Item No. 132 Embankment
Item No. 150 Blading
Item No. 158 Specialized Excavation Work
Item No. 160 Furnishing and Placing Topsoil
Item No. 164 Seeding for Erosion Control
Texas Department of Transportation: Standard Specifications for Construction and Maintenance of Highways, Designation Description
Item No. 204 Sprinkling
Item No. 210 Rolling (Flat Wheel)
Item No. 211 Rolling (Tamping)
Item No. 213 Rolling (Pneumatic Tire)
Item No. 260 Lime Treatment for Materials Used as Subgrade (Road Mixed)
Item No. 265 Lime-Fly Ash (LFA) Treatment for Materials Used as Subgrade
Texas Department of Transportation: Manual of Testing Procedures
Tex-103-E Determination of Moisture Content of Soil Materials
Tex-104-E Determination of Liquid Limit of Soils
Tex-105-E Determination of Plastic Limit of Soils
Tex-106-E Method of Calculating the Plasticity Index of Soils
Tex-114-E Laboratory Compaction Characteristics and Moisture-Density Relationship of Subgrade & Embankment Soil
Tex-115-E Field Method for Determination of In-Place Density of Soils and Base Materials
ITEM NO. 104S REMOVING PORTLAND CEMENT CONCRETE 9-26-12
Austin, Texas, Standard Specifications Manual Created: 2022-10-28 11:15:23 [EST]
ITEM NO. 104S REMOVING PORTLAND CEMENT CONCRETE 9-26-12
104S.1 Description
This item shall govern the demolition, removal and satisfactory disposal of existing Portland cement concrete, as classified, at locations indicated on the Drawings or as directed by the Engineer or designated representative.
This specification is applicable for projects or work involving either inch-pound or SI units. Within the text inch-pound units are given preference followed by SI units shown within parentheses.
104S.2 Submittals
The submittal requirements of this specification item may include:
A. A permit when utility adjustments are made in the right-of-way, and
B. A plan for removal and deposition of all 'broken up' existing Portland cement (p.c.) concrete materials and debris.
104S.3 Classification
Existing Portland cement concrete, when removed under this section, will be classified as follows:
1. Concrete Curb will include curb, curb and gutter and combinations thereof,
2. Concrete Slabs will include, but not be limited to, house slabs, patio slabs, porch slabs, concrete riprap and concrete pavement,
3. Sidewalks and Driveways will include concrete sidewalks and driveways,
4. Concrete Walls will include all walls, regardless of height, and wall footings,
5. Concrete Steps will include all steps and combinations of walls and steps,
6. Abandoned Foundations will include abandoned utility foundations,
7. Miscellaneous Concrete shall include all other concrete items, which are not identified in items 1 through 6 above.
104S.4 Materials
Mortar shall conform to mortar specified in Standard Specification Item No. 403, "Concrete for Structures".
104S.5 Construction Methods
Prior to commencement of this work, all required erosion control and tree protection measures shall be in place.
The existing utilities shall be located and protected as specified in the Standard Contract Documents, Section 00700, "General Conditions". A permit shall be required when utility adjustments are to be made in preparation for highway construction, as specified in Section 5.2.0 of the City of Austin Utilities Criteria Manual.
The existing Portland cement concrete shall be broken up, removed in accordance with Item No. 101S, "Preparing Right-of-way" and disposed of by the Contractor and deposited at a permitted disposal site.
Created: 2022-10-28 11:15:23 [EST]
When it is specified that only a portion of the existing Portland cement (p.c.) concrete is to be removed and that the remaining p.c. concrete will continue to serve its purpose, special care shall be exercised to avoid damage to that portion which will remain in place. Unless otherwise established by the Engineer or designated representative, existing p.c. concrete shall be cut to the neat lines, that are indicated on the Drawings, by sawing with an appropriate type circular type circular concrete saw to a minimum depth of ½ inch (12.5 mm). Any reinforcing steel encountered shall be cut off 1 inch (25 mm) inside of p.c. concrete sawed line. Any existing p.c. concrete, which is damaged or destroyed beyond the neat lines so established, shall be replaced at the Contractor's expense.
Remaining p.c. concrete shall be mortared to protect the reinforcing steel and provide a neat clean appearance.
When reinforcement is encountered during the removal of portions of existing structures to be modified, a minimum of 1 foot (300 mm) of steel length shall be cleaned of all old p.c. concrete and left in place to tie into the new construction where applicable. All unsuitable material shall be removed and replaced with approved material.
All foundations, walls or other objectionable material shall be removed to a minimum depth of 18 inches (450 mm) below all structures and 12 inches (300 mm) below areas to be vegetated.
104S.6 Measurement
When included in the contract as a separate pay item, the removal of p.c. concrete curb and p.c. concrete wall as prescribed above will be measured by the lineal foot (meter: 1 meter is equal to 3.281 feet) in its original position regardless of the dimensions or size. The removal of p.c. concrete slabs, p.c concrete sidewalks and driveways, as prescribed above, will be measured by the square foot (square meter: 1 square meter is equal to 10.764 square feet) in original position, regardless of the thickness and existence of reinforcing steel. Portland cement concrete steps removed will be measured per lineal foot (meter: 1 meter is equal to 3.281 feet) of each individual step tread including the bottom step. The removal of p.c. concrete foundations will be measured per each individual foundation. The removal of miscellaneous concrete will be measured per lump sum.
104S.7 Payment
The work and materials presented herein will generally not be paid for directly, but shall be included in the unit price bid for the item of construction in which this item is used. When specified in the contract bid form as a separate pay item, the item will be paid for at the contract unit bid price(s) for "Remove P.C. Concrete Curb", "Remove P.C. Concrete Slab", "Remove P.C. Concrete Sidewalks and Driveways", "Remove P.C. Concrete Walls", "Remove P.C. Concrete Steps", "Remove P.C. Concrete Foundations" and "Remove Miscellaneous P.C. Concrete".
The bid prices shall include full compensation for all Work herein specified, including the disposal of all material not required in the Work, the furnishing of all materials, equipment, tools, labor and incidentals necessary to complete the Work.
Payment will be made under one of the following:
Pay Item No. 104S-A: Remove P.C. Concrete Curb Per Lineal foot.
Pay Item No. 104S-B: Remove P.C. Concrete Slab Per Square foot.
Pay Item No. 104S-C: Remove P.C. Concrete Sidewalks and Driveways
Per Square foot
Pay Item No. 104S-D: Remove P.C. Concrete Wall Per Lineal foot.
Pay Item No. 104S-E: Remove P.C. Concrete Steps Per Lineal foot.
Pay Item No. 104S-F: Remove P.C. Concrete Foundations
Per Each.
Pay Item No. 104S-G: Remove Miscellaneous P.C.
Concrete
Per Lump Sum.
SPECIFIC CROSS REFERENCE MATERIALS
Specification Item 104S, "REMOVING CONCRETE"
City of Austin Standard Contract Documents
00700 General Conditions
City of Austin Utilities Criteria Manual
Section 5.2.0 Permit for Excavation in the Public Right-of-Way
Item No. 101S Preparing Right-of-way
Item No. 110S Street Excavation
Item No. 111S Excavation
Item No. 120S Channel Excavation
Item No. 132S Embankment
Item No. 403 Concrete for Structures
Item No. 610S Preservation of Trees and Other Vegetation
Specification Item 104S, "REMOVING CONCRETE"
City of Austin Standard Contract Documents
01500 Temporary Facilities
01550 Public Safety and Convenience
The Code of the City of Austin, Code of Ordinances, Volume 1
Article 15-12-166 Permit Required
Article 15-12-173 Conditions for Permit Issuance
Article 15-12-174 Permit Term
Item No. 201S Subgrade Preparation
Item No. 602S Sodding for Erosion Control
Item No. 604S Seeding for Erosion Control
Item No. 622S Diversion Dike
Item No. 628S Sediment Containment Dikes
Item No. 642S Silt Fence
610S-1 Tree Protection Fence Locations
610S-2 Tree Protection Fence, Type B Chainlink
610S-3 Tree Protection Fence, Type B Wood
610S-4 Tree Protection Fence, Modified Type A
610S-5 Tree Protection Fence, Modified Type B
621S-1 Diversion
622S-1 Diversion Dike
624S-1 Earth Outlet Sediment Trap
625S-1 Grade Stabilization Structure
627S-1 Grass Lined Swale
627S-2 Grass Lined Swale With Stone Center
628S Triangular Sediment Filter Dike
628S-1 Hay Bale Dike
629S-1 Brush Berm
630S-1 Interceptor Dike
631S-1 Interceptor Swale
632S-1 Storm Inlet Sediment Trap
633S-1 Landgrading
634S-1 Level Spreader
635S-1 Perimeter Dike
636S-1 Perimeter Swale
637S-1 Pipe Slope Drain (Flexible)
637S-2 Pipe Slope Drain (Flexible)
638S-1 Pipe Outlet Sediment Trap
639S-1 Rock Berm
641S-1 Stabilized Construction Entrance
642S-1 Silt Fence
643S-1 Stone Outlet Structure
644S-1 Stone Outlet Sediment Trap
Texas Department of Transportation: Standard Specifications for Construction and Maintenance of Highways, Designation Description
Item No. 100 Preparing Right-of-way
Item No. 104 Removing Concrete
Item No. 110 Excavation
Item No. 112 Subgrade Widening
Item No. 132 Embankment
Item No. 158 Specialized Excavation Work
Item No. 420 Concrete Structures
ITEM NO. 201S SUBGRADE PREPARATION 6-17-2021
Austin, Texas, Standard Specifications Manual Created: 2022-10-28 11:15:24 [EST]
ITEM NO. 201S SUBGRADE PREPARATION 6-17-2021
201S.1 Description
This item shall govern scarifying; blading and rolling the subgrade to obtain a uniform texture and provide as nearly as practicable a uniform density for the top 6 inches (150 mm) of the subgrade.
This specification is applicable for projects or work involving either inch-pound or SI units. Within the text and accompanying tables, the inch-pound units are given preference followed by SI units shown within parentheses.
201S.2 Submittals
The submittal requirements of this specification item may include:
A. A plan identifying classification and characteristics (P.I., optimum moisture-density, etc.) of insitu subgrade soils, as well as the source, classification and characteristics of any proposed borrow material, B. Type and size of equipment proposed to produce the required compaction, and
C. Compaction (moisture-density, etc) test results for in-situ subgrade soils and/or borrow materials.
201S.3 Construction Methods
Prior to initiation of subgrade preparation activities, all operations involving Standard Specification Item No. 101S," Preparing Right-of-Way" and/or Standard Specification Item No. 102S, "Clearing and Grubbing" shall be completed.
The surface of the subgrade shall be scarified and shaped in conformity with the typical sections and the lines and grades indicated on the Drawings; by the removal of existing material or addition of approved material as established by the Engineer or designated representative. Any deviation in the subgrade cross section which exceeds ½ inch in a length of 10 feet (12 mm in a length of 3 meters), measured longitudinally, shall be corrected by loosening, adding or removing material, and then reshaping and compacting by sprinkling and rolling.
All unsuitable material shall be removed and replaced with approved material. All foundations, walls or other objectionable material shall be removed in accordance with Standard Specification Item No. 104S, "Removing Portland Cement Concrete" to a minimum depth of 18 inches (450 mm) under all structures and 12 inches (300
mm) under areas to be vegetated. All holes, ruts and depressions shall be filled with approved material and compacted by approved methods.
The subgrade shall be prepared sufficiently in advance to insure satisfactory prosecution of the Work. The Contractor will be required to set blue tops for the subgrade on the centerline, at the quarter points and along the curb lines or edge of pavement at maximum intervals of 50 feet (15 meters). The subgrade shall be tested by proof rolling in conformity with Standard Specification Item No. 236S, "Proof Rolling" prior to placement of the first course of base material. Any unstable or spongy subgrade areas identified by proof rolling shall be corrected either by additional re-working, drying and compaction, or by removal and replacement of unsuitable materials. When specifically directed by the Engineer or designated representative, the Contractor shall re-work the subgrade* as follows:
A. Remove the unstable subgrade to the full depth of the unstable insitu material or to a minimum depth of 6 inches (150 mm), whichever is greater;
B. Spread the material over a sufficient area to allow reworking of the excavated material;
Created: 2022-10-28 11:15:24 [EST]
C. Disc, scarify or otherwise breakup the excavated material and allow to dry (Note: If approved by the Engineer or designated representative, the addition of lime or other additive may be used to aid in the drying process or to stabilize the unstable material);
D. Fill the excavated area with the re-worked material and compact to specified densities; and
E. Proof roll the re-worked area.
* The Rework process will not be allowed for unstable organic subgrade soils. These type soils will be permanently removed and replaced with materials approved by the Engineer or designated representative.
All suitable material removed in accordance with Standard Specification Item No, 111S, "Excavation", may be utilized in the subgrade with the approval of the Engineer or designated representative. All other material required for completion of the Subgrade, including those defined in accordance with Specification Item No. 130S, "Borrow", shall also be subject to approval by the Engineer or designated representative.
It is the intent of this specification to provide the required density and moisture control for the subgrade based on the plasticity characteristics of the approved materials. The subgrade materials shall be sprinkled as required and compacted to the extent necessary to provide the density specified below, unless otherwise indicated on the Drawings. The Plasticity Index (P.I.) will be established in accordance with TxDOT Test Methods Tex-104-E, Tex- 105-E and Tex-106-E. The density determination will be made in accordance with TxDOT Test Method Tex-114-E and field density measurements will be made in accordance with TxDOT Test Method Tex-115-E.
Description Density, Percent Moisture
Non-swelling Soils (P.I. less than 20) Not less than 95
Swelling Soils (P.I. between 20 and 35) Not less than 95 nor more than 102
Not less than optimum
Swelling Soils (P.I. greater than 35) Not less than 95 nor more than 100
Not less than optimum
Subgrade materials on which planting or turf will be established shall be compacted to a minimum of 85 percent of the density as determined in accordance with TxDOT Test Method Tex-114-E. Field tests for density in accordance with TxDOT Test Method Tex-115-E will be made as soon as possible after compaction operations are completed. If the material fails to meet the density specified, it shall be reworked as necessary to obtain the density required.
Prior to placement of any base materials, the in-place density and moisture content of the top 6 inches (150 mm) of compacted subgrade shall be checked. If the tests indicate that the relative density and moisture do not meet the limits specified in the table above, the subgrade shall be reworked as necessary to obtain the specified compaction and moisture content. All initial testing will be paid for by the City of Austin. All retesting shall be paid for by the Contractor.
201S.4 Measurement
All acceptable subgrade preparation when included in the contract as a separate pay item, will be measured by the square yard (square meter: 1 square meter equals 1.196 Square yards). The measured area includes the entire width of the roadway for the entire length as indicated on the Drawings.
201S.5 Payment
The work and materials presented herein will generally not be paid for directly, but shall be included in the unit price bid for the item of construction in which this item is used when specified as a separate pay item in the contract bid form, subgrade preparation shall be measured as specified above and paid for at the contract unit bid price for "Subgrade Preparation". The bid price shall include full compensation for all work herein specified, including the furnishing of all materials, equipment, tools and labor and incidentals necessary to complete the work.
Payment, when included as a contract pay item, will be made under:
Pay Item No. 201S: Subgrade Preparation Per Square Yard.
Specification Item 201S, "SUBGRADE PREPARATION"
City of Austin Standard Specification Items
Designation Description
Item No. 101S Preparing Right-of-Way
Item No. 102S Clearing and Grubbing
Item No. 104S Removing Portland Cement Concrete
Item No. 110S Street Excavation
Item No. 111S Excavation
Item No. 130S Borrow
Item No. 236S Proof Rolling
Tex-103-E Determination of Moisture Content of Soil Materials
Tex-104-E Determination of Liquid Limit of Soils
Tex-105-E Determination of Plastic limit of Soils
Tex-106-E Method of Calculating the Plasticity Index of Soils
Tex-114-E Laboratory Compaction Characteristics & Moisture Density Relationship of Subgrade & Embankment Soil
Tex-115-E Field Method for Determination of In-Place Density of Soils & Base Materials
Specification Item 201S, "SUBGRADE PREPARATION"
City of Austin Standard Specifications
Item No.132S Embankment
Texas Department of Transportation: Standard Specifications for Construction and Maintenance of Highways, Designation Description
Item No. 100 Preparing Right-of-Way
Item No. 110 Excavation
Item No. 112 Subgrade Widening
Item No. 132 Embankment
Item No. 150 Blading
Item No. 158 Specialized Excavation Work
Item No. 204 Sprinkling
Item No. 210 Rolling (Flat Wheel)
Item No. 211 Rolling (Tamping)
Item No. 213 Rolling (Pneumatic Tire)
Tex-103-E Determination of Moisture Content of Soil Materials
ITEM NO. 210S FLEXIBLE BASE 2-24-10
Austin, Texas, Standard Specifications Manual Created: 2022-10-28 11:15:25 [EST]
ITEM NO. 210S FLEXIBLE BASE 2-24-10
210S.1 Description
This item governs furnishing and placing a crushed stone base course for surfacing, pavement, or other base courses. "Flexible Base" shall be constructed on an approved, prepared surface in one or more courses conforming to the typical sections and to the lines and grades, indicated on the Drawings or established by the Engineer or designated representative.
This specification is applicable for projects or work involving either inch-pound or SI units. Within the text and accompanying tables, the inch-pound units are given preference followed by SI units shown within parentheses.
210S.2 Submittals
The submittal requirements of this specification item may include:
A. Source, gradation and test results for the crushed limestone material, B. Notification that the crushed limestone stockpile is completed and ready for testing, and
C. Field density test results for in-place compacted flexible base, 210S.3 Material
A. Mineral Aggregate
The material shall be crushed argillaceous limestone meeting the requirements specified herein. The material shall be from sources approved by the City and shall consist of durable crushed stone that has been screened to the required gradation.
Flexible base materials shall be tested according to the following TxDoT standard test methods:
a) Preparation for Soil Constants and Sieve Analysis Tex-101-E
b) Liquid Limit Tex-104-E
c) Plastic Limit Tex-105-E
d) Plasticity Index Tex-106-E
e) Sieve Analysis Tex-110-E
f) Wet Ball Mill Tex-116-E
g) Triaxial Test Tex-117-E, Part II
1. Plasticity Index shall be determined in accordance with Tex-107-E (Linear Shrinkage) when liquid limit is unattainable as defined in Tex-104-E.
2. When a soundness value is required on the drawings, the material shall be tested in accordance with Tex-411-A.
Base material shall be stockpiled after crushing, then tested by the City's designated laboratory and approved by the Engineer or designated representative prior to being hauled to the Project.
The material shall be well graded and shall meet the following requirements:
Sieve Designation Other Requirements % Retained
Created: 2022-10-28 11:15:25 [EST]
US SI
1¾″ 45 mm 0
⅞″ 22.4 mm 10—35
⅜′ 9.5 mm 30—50
#4 4.75 mm 45—65
#40 425 μm 70—85
Maximum Plasticity Index 10
Maximum Wet Ball Mill 42
Maximum Increase in passing #40 (425 μm) sieve from Wet Ball Mill Test 20
Minimum compressive strength when subjected to the triaxial test shall be 35 psi at 0 psi lateral pressure [240 kiloPascal (kPa) at 0 kPa lateral pressure] and 175 psi at 15 psi lateral pressure [1200 kiloPascal (kPa) at 100 kPa lateral pressure].
B. Asphaltic Material
Prime Coat. Prime Coat shall conform to the requirements of Standard Specification Item 306S, "Prime Coat", except for measurement and payment.
210S.4 Stockpiling, Storage and Management
A. Managing Material:
The stockpile shall be constructed on a relatively smooth area that has been cleared of debris, weeds, brush, trees and grass. Stockpiles shall contain between 25,000 and 50,000 cubic yards (19,100 to 38,200 cubic meters). The stockpile shall be constructed using scrapers, bottom dumps or other similar equipment that allows dumping and spreading without rehandling. The stockpile shall be constructed to allow dumping and spreading in one direction only. The height of the stockpile shall not exceed the capabilities of available equipment to make a full cut (bottom to top) on any of the four sides.
A stockpile shall be completed before being tested by the City. The Contractor's supplier shall notify the City when a stockpile has been completed and is ready to be tested. The stockpile shall not be added to after it has been tested.
The Contractor shall provide material only from stockpiles that have been inspected, tested and accepted by the City. A ticket showing the date, source, stockpile number, and net weight (mass) shall be provided to the Inspector with each load of material delivered to the Project.
Material shall be loaded from the stockpile by making successive vertical cuts through its entire depth.
B. Test Sampling:
The Contractor's supplier may choose the method of sample gathering for testing by the City's laboratory as follows:
1. The supplier shall make a full-height cut a sufficient distance into each side of the stockpile to obtain a uniform sample. The four samples (one from each side of the stockpile) shall then be combined and mixed into a single "test" specimen from which the City's laboratory can obtain a sample.
2. As the stockpile is constructed, a perpendicular cut will be made across the spreading direction at every two feet to four feet (0.6 to 1.2 meters) of height and the sample used to start a "mini" stockpile.
The process shall be repeated in two feet to four feet (0.6 to 1.2 meter) increments of height, until the stockpile and the "mini" stockpile are completed. Samples shall be obtained from the "mini" stockpile in the same manner described in (1) above.
C. Testing and Acceptance:
When initial tests indicate that the material is unacceptable, the City may, if requested by the Contractor's supplier, sample and test the material one more time. The additional sampling and testing shall be paid for by the supplier.
210S.5 Construction Methods
A. Preparation of Subgrade:
Flexible base shall not be placed until the Contractor has verified by proof rolling that the subgrade has been prepared and compacted in conformity with Standard Specification Item 201S, "Subgrade Preparation," to the typical sections, lines and grades indicated on the Drawings. Any deviation shall be corrected and proof rolled prior to placement of the flexible base material.
The Contractor shall not place flexible base until the subgrade has cured to the satisfaction of the Engineer or designated representative, regardless of whether or not the subgrade has been successfully proof rolled. As a minimum, this will be after the surface displays no damp spots and there is no evidence of "sponginess" in the subgrade.
B. First Lift:
Immediately before placing the flexible base material, the subgrade shall be checked for conformity with grade and section. The thickness of each lift of flexible base shall be equal increments of the total base depth. No single lift shall be more than six inches (150 mm) or less than three inches (75 mm) compacted thickness.
The material shall be delivered in approved vehicles. It shall be the responsibility of the Contractor to deliver the required amount of material. If it becomes evident that insufficient material was placed, additional material as necessary shall be delivered and the entire course scarified, mixed and compacted.
Material deposited upon the subgrade shall be spread and shaped the same day unless otherwise approved by the Engineer or designated representative. In the event inclement weather or other unforeseen circumstances render spreading of the material impractical, the material shall be spread as soon as conditions allow.
Additionally, if the material cannot be spread and worked the same day it is deposited, the Contractor shall "close up" the dump piles before leaving the job site. "Closed up" shall be defined as the use of a motor grader to blade all dump piles together, leaving no open space between piles.
The material shall be spread, sprinkled, if required, then thoroughly mixed; bladed, dragged and shaped to conform to the typical sections indicated on the Drawings.
All areas and "nests" of segregated coarse or fine material shall be corrected or removed and replaced with well-graded material.
Each lift shall be sprinkled as required to bring the material to optimum moisture content, then compacted to the extent necessary to provide not less than the percent density specified in Section 210S.5.D, "Density."
In addition to the requirements specified for density, the full depth of flexible base material shall be compacted to the extent necessary to remain firm and stable under construction equipment. After each section of flexible base material is completed, tests, as necessary, will be made by the Engineer or designated representative. As a minimum, three in-place density tests per section per day will be taken. If the material fails to meet the density requirements, it shall be reworked as necessary to meet these requirements. All initial testing will be paid for by the City. All retesting shall be paid for by the Contractor.
Throughout the entire operation, the surface of the material shall be maintained by blading and, upon completion, shall be smooth and shall conform to the typical section indicated on the Drawings and to the established lines and grades.
In that area on which pavement is to be placed, any deviation in excess of 1/4 inch (6.5 mm) in cross section or 1/4 inch in a length of 16 feet (6.5 mm in a length of 5 meters) measured longitudinally shall be corrected by loosening, adding or removing material, and by reshaping and recompacting. All irregularities, depressions or weak spots shall be corrected immediately by scarifying the areas affected, adding suitable material as required, and by reshaping and recompacting. Should the lift, due to any reason or cause, lose the required stability, density and/or finish before the surfacing is complete, it shall be recompacted and refinished at the Contractor's expense.
C. Succeeding Lifts:
Construction methods for succeeding lifts shall be the same as prescribed for the first lift. For that lift of the flexible base upon which the curb and gutter will be constructed, as well as the last flexible base lift (i.e. top of the flexible base), the Contractor shall check the surface of the lift for conformity to the lines and grades by setting "blue tops" at intervals not exceeding 50 feet (15 meters) on the centerline, at quarterpoints, at curb lines or edge of pavement, and at other points that may be indicated on the Drawings.
When the thickness of a particular lift of the flexible base is in question, the Contractor shall check the surface of the lift for conformity to the lines and grades by setting "blue tops" at intervals not exceeding 50 feet (15 meters) on the centerline, at quarter points, at curb lines or edge of pavement, and at other points that may be indicated on the Drawings
D. Density:
The flexible base shall be compacted to not less than 100 percent density as determined by TxDoT Test Method Tex-113-E.
Field density determination shall be made in accordance with TxDoT Test Method Tex-115-E unless otherwise approved by the Engineer or designated representative. Each lift of the flexible base shall also be tested by proof rolling in conformity with Standard Specification Item 236S "Proof Rolling."
E. Priming:
After the flexible base material has been compacted to not less than 100 percent density, and tested by proof rolling, a prime coat will be applied in accordance with Standard Specification Item 306S, "Prime Coat."
F. Curing:
Pavement materials, such as a tack coat or surface course, shall not be placed on the primed surface until the prime coat has been absorbed into the base course. At least 24 hours, or longer if designated by the Engineer or designated representative, shall be allowed when cutback asphalt is used as the prime coat.
210S.6 Measurement
"Flexible Base" will be measured by the cubic yard (cubic meter: 1 cubic meter equals 1.196 cubic yards), complete in place, as indicated in the Contract Documents.
210S.7 Payment
This item will be paid for at the contract unit bid price for "Flexible Base". The unit bid price shall include full compensation for all work specified herein, including the furnishing, hauling, placing and compacting of all materials; for rolling, proof rolling, recompacting and refinishing; for all water required; for retesting as necessary;
for priming; and for all equipment, tools, labor and incidentals necessary to complete the Work.
Prime coat will not be measured nor paid for directly but shall be inculded in the unit price bid for Standard Specification Item 210S, "Flexible Base."
Payment will be made under one of the following:
Pay Item No. 210S-A: Flexible Base Per Cubic Yard.
Specification 210S, "Flexible Base"
City of Austin Standard Specifications
Designation Description
Item No. 201S Subgrade Preparation
Item No. 306S Prime Coat
Texas Department of Transportation: Standard Specifications for Construction and Maintenance of Highways, Designation Description
Tex-101-E Preparation of Soil and Flexible Base Materials for Testing
Tex-104-E Determination of Liquid Limit of Soils
Tex-105-E Determination of Plastic Limit of Soils
Tex-106-E Method of Calculating the Plasticity Index of Soils
Tex-107-A Determination of Bar Linear Shrinkage of Soils
Tex-110-E Determination of Particle Size Analysis of Soils
Tex-113-E Laboratory Compaction Characteristics and Moisture-Density Relationship of Base Materials and Cohesionless Sands
Tex-115-E Field Method for Determination of In-Place Density of Soils and Base Materials
Tex-116-E Ball Mill Method for Determination of the Disintegration of Flexible Base Material
Tex-117-E Triaxial Compression Tests for Disturbed Soils and Base Materials
Tex-411-A Soundness of Aggregate By Use of Sodium Sulfate or Magnesium Sulfate
Specification 210S, "Flexible Base"
City of Austin Standard Details
Designation Description
No. 1000S-2 Flexible Base with Asphalt Surface Trench Repair-Existing Pavement
No. 510S-3 Typical Trench with Paved Surface
No. 1000S Bus Stop Paving
No. 1000S-10 Local Street Sections
No. 1000S-11(1) Residential and City of Austin Neighborhood Collector Street Sections
No. 1000S-11(2) Industrial and Commercial Collector Street Sections
No. 1000S-12(1) Primary Collector Street Sections
No. 1000S-12(2) Primary Arterial Street Sections
No. 1000S-13(1) Minor Arterial Street Sections (4 Lanes)
No. 1000S-13(2) Minor Arterial Street…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .