About this file

This is a Measurement and Payment specification document (Section 01 20 00) for the Sweetwater Creek Wastewater Treatment Plant (WWTP) Aeration Basin Upgrades project, issued as Addendum 2 on September 18, 2023. The project involves concrete rehabilitation work on Aeration Basins No. 1 and No. 2, and Secondary Clarifiers No. 1 and No. 2, including repairs to floors, walls, beams, and top slabs. The contract includes both lump sum work items and unit price items. Unit price items encompass various concrete repair methods, including crack repairs using cementitious surface seals, epoxy injection, and waterproof injection grout; concrete spall repairs; construction joint repairs; formed spall repairs; cement-based textured coatings; and expansion joint repairs. The Engineer and Contractor must jointly inspect and evaluate the basin and clarifier concrete elements to determine the extent of rehabilitation work before repair material application begins. Measurement of volumetric repairs follows cross-sections taken every one foot along the length of affected areas, with concrete repair thickness measured at six-inch vertical increments.

Compensation for all services, materials, and equipment is included within the stipulated lump sum and unit price bid items, with no separate payment for temporary works, bonds, insurance, or other contract requirements. The contract includes a Material Testing Allowance to reimburse the Contractor at cost for third-party testing agencies and certified coatings inspectors complying with Association for Materials Protection and Performance (AMPP) standards; retesting due to failed initial tests is at the Contractor's expense. An Unforeseen Conditions Allowance provides funds for additional work authorized by the Owner through written Work Change Directives (WCDs), which must be fully executed before work commences. The Engineer's estimated quantities for unit price items are approximate only and are provided for bid comparison purposes; the Owner reserves the right to increase, decrease, or eliminate quantities as deemed necessary, with no adjustment to unit bid prices resulting from quantity changes.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

09-18-2023 01 20 00 - 1 SWEETWATER CREEK WWTP

MEASUREMENT AND PAYMENT AERATION BASIN UPGRADES

SECTION 01 20 00

MEASUREMENT AND PAYMENT

PART 1 – GENERAL

1.01 SUMMARY

A. Section lncludes:

1. Items listed in this Section refer to and are the same pay items listed in the Bid

Form and constitute all pay items for completing the Work.

2. Compensation for all services, items, materials, and equipment shall be include in prices stipulated for lump sum and unit price pay items listed in this Section and included in the Contract.

3. No direct or separate payment will be made for providing miscellaneous temporary or accessory works, bonds, insurance, or other requirements of the General

Conditions, Supplementary Conditions, General Requirements, and other requirements of the Contract Documents.

4. Each lump sum and unit bid price shall include an amount considered by

Contractor to be adequate to cover Contractor’s overhead and profit for each separately identified item.

B. Related Sections:

1. Payments to Contractor: Refer to General Conditions, Supplementary Conditions, and Agreement.

2. Changes to Contract Price: Refer to General Conditions, Supplementary

Conditions, and Section 01 26 00 − Contract Modification Procedures.

3. Schedule of Values: Refer to General Conditions, Supplementary Conditions, and

Section 01 29 73 − Schedule of Values.

1.02 ENGINEER’S ESTIMATE OF QUANTITIES

A. ENGINEER’S and OWNER’s estimated quantities for unit price pay items, as listed in the Bid Form, are approximate only and are included solely for the purpose of comparison of Bids. Owner does not expressly or by implication agree that the nature of the materials encountered below the surface of the ground or the actual quantities of material encountered or required will correspond therewith and reserves the right to increase or decrease any quantity or to eliminate any quantity as Owner may deem necessary. Contractor will not be entitled to any adjustment in a unit bid price as a result of any change in an estimated quantity and agrees to accept the aforesaid unit bid prices

09-18-2023 01 20 00 - 2 SWEETWATER CREEK WWTP

as complete and total compensation for any additions caused by changes or alterations in the Work ordered by Owner.

1.03 ADMINISTRATIVE REQUIREMENTS

A. Contractor shall include all additional Work items, services, goods, resources, and manpower necessary for installation of the Work to provide a completely functional system in accordance with the Contract Documents. Contractor shall include these costs associated with providing a completely functional system within the listed items on the

Bid Form and as specified herein.

B. Bid Items:

1. Lump Sum Work: Payment for Lump Sum Work will be full compensation for administration and completion of the Work at Sweetwater Creek WWTP, as shown on the Drawings and specified in the Contract Documents, except Work specifically included under other Bid Items.

2. Material Testing Allowance - Owner will provide funds as specified on the bid sheet to reimburse the Contractor at cost for hiring one or more testing agency(ies) to perform all sampling, field testing, coating inspections, materials testing and laboratory testing as specified herein, or as directed by the Engineer. Concrete coatings shall be inspected by a 3rd party certified Coatings Inspector by the

Association for Materials Protection and Performance (AMPP). Inspector to perform surface preparation and coatings inspections and testing as specified in

Specification 09 96 59.

The testing allowance is to be used for first tests only. Any retesting due to failed first tests shall be at the Contractor’s expense. The Contractor shall clearly mark on its invoices costs associated with testing and coating inspection services identifying the cost to the Contractor of the testing service and coating inspection services. The Contractor agrees to invoice Owner for testing and coating inspection services at its cost with no markup.

3. Unforeseen Conditions Allowance -Allow the amount provided in the Bid for additional Work authorized by the Owner that is outside the original scope of work of this Contract. The Owner will issue a written Work Change Directive (WCD) to incorporate cost or schedule changes into the Contract. The WCD shall be used for increases and decreases in the Contract price, within the amount set forth in the Bid, or to make changes in schedule for performance of the Work. A WCD work shall authorize the Contractor to perform changes in the Work. The

Contractor shall not start on WCD work until the Contractor receives a fully authorized, written WCD form, signed by the appropriate Owner personnel – the

Contractor shall not consider verbal statements as authorization to proceed with the changes. The Contractor should not expect that any WCDs will be issued.

Owner shall have no obligation to pay for WCD work unless the same is performed pursuant to a written WCD form signed before the WCD work is commenced.

09-18-2023 01 20 00 - 3 SWEETWATER CREEK WWTP

3. Unit Price Items Allowance

a. Payment for Bid Items under “Unit Price Items Allowance” will be made according to the unit prices in the Bid Schedule of the Bid Evaluation Sheet, which shall constitute full payment to perform the work described herein.

b. Aeration Basin No. 1 and No. 2 and Secondary Clarifier No. 1 and No. 2 concrete floors, walls, beams, and top slabs rehabilitation shall be as shown on Drawing S-001 and other applicable Drawings and as specified in Section

03 01 30 – Concrete Repairs and other applicable sections of the

Specifications.

c. To determine the extent of the rehabilitation work for the aeration basin and secondary clarifier floors, walls, beams, and top slabs, Engineer and

Contractor shall jointly inspect and evaluate the aeration basin and secondary clarifier floors, walls, beams, and top slabs.

d. Contractor shall not begin the application of repair material until the quantities of repair have been identified, submitted to, and approved by the

Engineer. Repair shall be performed where approved by Engineer after removal of unsound material. Concrete floor, wall, beam, and top slab rehabilitation shall include, but not be limited to, all removal of unsound material, substrate cleaning, rebar cleaning and protection, bond breaker, mortar, grout, epoxy bonding agents, adhesives, sealants, rebar, accessories, etc. as required to rehabilitate the existing concrete floors, walls, beams, and top slabs as directed by the Engineer. For all repair work measured on a volumetric basis (e.g., cubic feet), the volume of repair material required shall be measured by cross-sections taken every 1 foot along the length of the floor or wall or top slab and beams to be repaired.

The thickness of required concrete repair shall be measured at 6-inch vertical increments on each cross-section.

e. Concrete Crack Repair – Surface Seal: Payment will be made according to the unit prices in the Bid Schedule of the Bid Form, which shall constitute full payment to provide Concrete Crack Repair – Cementitious Surface Seal on the concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers. Bid Items shall include, but not be limited to, all materials, equipment, labor, tools, indirect costs, overhead, and profit required to repair cracks in the existing concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers using surface seal crack repair material, meeting all requirements of the Contract Documents.

Measurement will be per linear foot of crack repair performed using joint sealant.

f. Concrete Crack Repair - Epoxy Injection: Payment will be made according to the unit price in the Bid Schedule of the Bid Form, which shall constitute full payment to provide Concrete Crack Repair – Epoxy Injection on the concrete

09-18-2023 01 20 00 - 4 SWEETWATER CREEK WWTP

floors, walls, beams, and top slabs of aeration basins and secondary clarifiers. Bid Items shall include, but not be limited to, all materials, equipment, labor, tools, indirect costs, overhead, and profit required to repair cracks in the existing concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers using epoxy injection material, meeting all requirements of the Contract Documents. Measurement will be per linear foot of crack repair performed using epoxy injection material.

g. Concrete Crack Repair - Waterproof Injection Grout: Payment will be made according to the unit price in the Bid Schedule of the Bid Form, which shall constitute full payment to provide Concrete Crack Repair – Waterproof

Injection Grout on the concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers. Bid Items shall include, but not be limited to, all materials, equipment, labor, tools, indirect costs, overhead, and profit required to repair cracks in the existing concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers using waterproof injection grout, meeting all requirements of the Contract Documents.

Measurement will be per linear foot of crack repair performed using waterproof injection grout.

h. Concrete Surface Spall Repair: Payment will be made according to the unit price in the Bid Schedule of the Bid Form, which shall constitute full payment to provide Concrete Surface Spall Repair on the concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers. Bid Items shall include, but not be limited to, all materials, equipment, labor, tools, indirect costs, overhead, and profit required to repair concrete spalls in the existing concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers using spall repair patching material, meeting all requirements of the Contract Documents. Measurement will be per square foot of concrete spall repair.

i. Concrete Construction Joint Repair: Payment will be made according to the unit price in the Bid Schedule of the Bid Form, which shall constitute full payment to provide Concrete Construction Joint Repair on the concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers. Bid Items shall include, but not be limited to, all materials, equipment, labor, tools, indirect costs, overhead, and profit required to repair concrete spalls in the existing concrete floors, walls, beams, top slabs of aeration basins and secondary clarifiers using spall repair patching material, meeting all requirements of the Contract Documents. Measurement will be per square foot of concrete construction joint repair.

j. Concrete Formed Spall Repair: Payment will be made according to the unit price in the Bid Schedule of the Bid Form, which shall constitute full payment to provide Concrete Formed Spall Repair on the concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers. Bid Items shall include, but not be limited to, all materials, equipment, labor, tools, 09-18-2023 01 20 00 - 5 SWEETWATER CREEK WWTP indirect costs, overhead, and profit required to repair concrete spalls in the existing concrete floors, walls, beams, top slabs of aeration basins and secondary clarifiers using spall repair patching material, meeting all requirements of the Contract Documents. Measurement will be per cubic foot of concrete cavity repair.

k. Cement-Based Textured Coating: Payment will be made according to the unit price in the Bid Schedule of the Bid Form, which shall constitute full payment to provide Cement-Based Textured Coating on the concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers. Bid

Item shall include, but not be limited to, all materials, equipment, labor, tools, indirect costs, overhead, and profit required to provide cement-based textured coating on the existing concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers using cement-based textured coating, meeting all requirements of the Contract Documents. Measurement will be per square foot of cement-based textured coating.

l. Expansion Joint Repair: Payment will be made according to the unit price in the Bid Schedule of the Bid Form, which shall constitute full payment to provide Expansion Joint Repair on the concrete floors, walls, and top slabs of aeration basins and secondary clarifiers. Bid Item shall include, but not be limited to, all materials, equipment, labor, tools, indirect costs, overhead, and profit required to provide expansion joint repair on the existing concrete floors, walls, beams, and top slabs of aeration basins and secondary clarifiers using joint sealant material, meeting all requirements of the

Contract Documents. Measurement will be per linear foot of expansion joint repair.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION