This is a construction drawings document for an Invitation for Bid (IFB) issued by Colorado Parks and Wildlife for boat ramp resurfacing work at Navajo State Park in Colorado. The project, identified as IFB 2027*014 with Project I.D. No. C25NJ1, involves Phase 3 resurfacing of the boat ramp facility. A pre-bid conference is scheduled for August 20, 2026, at 11:00 a.m., with bid opening set for September 3, 2026, at 2:00 p.m. The project location is Navajo State Park, situated approximately 18 miles from J-L, Colorado, near the New Mexico border. The construction drawings package includes a cover sheet, site map with work summary, plan and profile views, and detailed specifications organized across multiple sheets. Project contacts include the Capital Development Section at 303-291-7391, Park Manager Jonathan Meats at 970-883-2208, Project Manager Tony Marusiak at 970-637-1568, and Design Manager Joe Decrescentis at 303-291-7392.

The document emphasizes Colorado Parks and Wildlife's commitment to providing equitable access and accessibility assistance for project construction layouts and details, with an accessibility specialist available through accessdn@state.co.us or 303-297-1192 to respond within two business days. Contractors are required to contact the Utility Notification Center of Colorado (UNCC) or Common Ground Alliance (CGA) by calling 811 at least two business days before excavation to obtain buried utility information. No pricing terms, set-asides, funding amounts, or contract duration information is specified in this construction drawings document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Navajo SP - Boat Ramp Resurfacing Phase 3

CONSTRUCTION DRAWINGS

PROJECT I.D. NO. C25NJ1

IFB1: 2027*014

PRE-BID CONFERENCE: August 20, 2026, at 11:00 a.m.

BID OPENING: September 3, 2026, at 2:00 p.m.

Navajo State Park

Legend .. J-L, Colorado

• Cities/Towns

@ State Parks c:J Park Boundary

- USFS

------- State Line

Sheet List Table

New Mexico

PROJECT VICINITY MAP

Sheet Number Sheet Title

Cover Sheet

2 Site Map & Work Summary

3 Plan and Profile

4 Details est from hen tum r 18 miles County

DAY USE AREAS

Allison

-Tolgn,clo

SAMBRITOWETLAND .,

COLORADO

New Mexico

PROJECT

LOCATION

COLORADO

PARKS AND WILDLIFE

NAVAJO STATE PARK

LEGEND

GI Park Headquarters

El Amphitheatre g Campground

� Day Use Parking m Picnic Area a, Boat Ramp

!! Boat Mooring

61 Cabins

� Dump Station

- Unpaved Road

I 000 feet

Scale

PROJECT LOCATION MAP

PARKS & WILDLIFE PROJECT CONTACTS

CAPITAL DEVELOPMENT SECTION 303-291-7391

PARK MANAGER - JONATHAN MEATS 970-883-2208

PROJECT MANAGER - TONY MARUSIAK 970-637-1568

DESIGN MANAGER - JOE DECRESCENTIS 303-291-7392

THE STAlE OF COLORADO IS COMMITTED 10 PROVIDING EQUITABLE ACCESS TO OUR SERVICES

TO ALL PLEASE CONTACT OUR COLORADO P.MKS AND WILDLIFE ACCESSIBILITY SPECIAUST

(ACCESSDNROSTATE.CO.US OR 303-297-1192) FOR PERSONALIZED ACCESSIBILITY ASSISTANCE WITH PROJECT CONSTRUCTION LAYOUlS AND DETAILS BELOW. WE WIU. CONTACT YOU DIRECTlY WITHIN 1V«> BUSINESS DAYS. VISIT OUR ACCESSIBIUTY WEBPliGE FOR MORE INFORMATKJN AND

SERVICES, INCWDING AIRA. OUR FREE SERVICE FOR BLIND AND LOW-VISION USERS.

FOR BURIED UTILITY INFORMATION

CALL 811

TWO BUSINESS DAYS

BEFORE YOU DIG

UTILITY NOTIFICATION CENTER

OF COLORADO (UNCC) OR

COMMON GROUND ALLIANCE (CGA)

_J z o_ en n w o_ u 0:::

w

0:::

o_ L 0:::

m f w w

::r::

0:::

w u

AutoCAD SHX Text #5S @ 24" O.C. B.W.

AutoCAD SHX Text

BOAT RAMP - SECTION A-A - TYP. BOTH SIDES NTS

AutoCAD SHX Text

EX. 8" CONC. RAMP

AutoCAD SHX Text

NEW 6" CONC. OVERLAY

AutoCAD SHX Text #5's @ 24" O.C. B.W.

AutoCAD SHX Text

SURFACE FINISH - DETAIL 1 NTS

AutoCAD SHX Text 14" WIDE x 2" DEEP CONTROL CRACK JOINT. SEAL WITH SIKAFLEX 1a CAULK & BACKER ROD. MAX. SPACING 20'

AutoCAD SHX Text

NOTE: MATCH ANGLE AND DEPTH OF PREVOUS RAMP OVERLAY CONSTRUCTION

AutoCAD SHX Text 2"

AutoCAD SHX Text 3"

AutoCAD SHX Text 90°

AutoCAD SHX Text

BOAT RAMP TRANSITION - SECTION B-B STA 9+20 NTS

AutoCAD SHX Text

BOAT RAMP END - SECTION C-C STA TBD NTS

AutoCAD SHX Text

#5 DOWELS @ 12" 18" LONG

AutoCAD SHX Text

NEW RAMP TRANSITION 5'-0"

AutoCAD SHX Text #5's @12" O.C. B.W. BOTH FACES

AutoCAD SHX Text

#5 DOWELS @ 12" 18" LONG

AutoCAD SHX Text

EXISTING

AutoCAD SHX Text

NEW RAMP TRANSITION TO EXISTING ±10'-0"

AutoCAD SHX Text

#5 DOWELS ±14" LONG @ 12" SPACING

AutoCAD SHX Text 18"

AutoCAD SHX Text

STA. 9+20

AutoCAD SHX Text 18"

AutoCAD SHX Text 6"

AutoCAD SHX Text

STA. TBD

AutoCAD SHX Text

UNDISTURBED NATIVE SOIL

AutoCAD SHX Text

UNDISTURBED NATIVE SOIL

AutoCAD SHX Text

DRAINAGE GROOVE - DETAIL 3 NTS

AutoCAD SHX Text

SURFACE GROOVE TREATMENT (TYP.) SLANT 2' IN 10'

AutoCAD SHX Text

NOTE: MATCH WIDTH AND LOCATION OF GROOVES OF 2014 RAMP OVERLAY CONSTRUCTION.

AutoCAD SHX Text #5s @24" O.C. B.W.

AutoCAD SHX Text 6"

AutoCAD SHX Text

#5 DOWELS @ 12" 18" LONG

AutoCAD SHX Text 8"

AutoCAD SHX Text

GROOVES (TYP.)

AutoCAD SHX Text 6"

AutoCAD SHX Text 1"

AutoCAD SHX Text

FLOW

AutoCAD SHX Text

RAMP CONSTRUCTION JOINT- DETAIL 5 NTS

AutoCAD SHX Text

DRAINAGE CHANNEL - DETAIL 4 NTS

AutoCAD SHX Text

NEW 6" OVERLAY

AutoCAD SHX Text

GROOVE TEXTURING ON SURFACE

AutoCAD SHX Text 2x4 KEY

AutoCAD SHX Text

CONSTRUCTION JOINT @ , AND GRADE BREAKS AS DIRECTED BY PROJECT MANAGER

AutoCAD SHX Text

DATE

AutoCAD SHX Text

BY

AutoCAD SHX Text

DESIGNER:

AutoCAD SHX Text

DRAFTER:

AutoCAD SHX Text

CHECKED BY:

AutoCAD SHX Text

APPROVED:

AutoCAD SHX Text

APPROVED:

AutoCAD SHX Text

CHIEF ENGR.:

AutoCAD SHX Text

REVISIONS:

AutoCAD SHX Text

DATE

AutoCAD SHX Text

PROJECT NO.

AutoCAD SHX Text

SHEET NO.

AutoCAD SHX Text

NAVAJO SP

AutoCAD SHX Text

FINAL

AutoCAD SHX Text

BOAT RAMP RESURFACING PHASE 3

AutoCAD SHX Text

NB

AutoCAD SHX Text 08/26

AutoCAD SHX Text

JTN

AutoCAD SHX Text 08/26

AutoCAD SHX Text

C25NJ1

AutoCAD SHX Text

DETAILS

AutoCAD SHX Text

AutoCAD SHX Text

OF 4

AutoCAD SHX Text 4'-0"

AutoCAD SHX Text 5'-0"

AutoCAD SHX Text

10'-0" WALKWAY

AutoCAD SHX Text

EXISTING CONCRETE RAMP

AutoCAD SHX Text 60'-0"

AutoCAD SHX Text GROOVED SURFACE FOR DRAINAGE 10ft FROM EACH EDGE

AutoCAD SHX Text

NOTE: NO UTILITY CHASE OR RAISED CURB ON EITHER SIDE FOR NEW WORK

AutoCAD SHX Text 08/26

2027 Navajo SP - Boat Ramp Resuracing Drawing Cover.pdf
2025 Navajo SP - Boat Ramp Resurfacing Phase 3-1 Cover Sheet.pdf
Sheets and Views
1 Cover Sheet
2025 Navajo SP - Boat Ramp Resurfacing Phase 3-2 Site Map & Work Summary.pdf
Sheets and Views
2 Site Map & Work Summary
2025 Navajo SP - Boat Ramp Resurfacing Phase 3-3 Plan and Profile.pdf
Sheets and Views
3 Plan and Profile
2025 Navajo SP - Boat Ramp Resurfacing Phase 3-4 Details.pdf
Sheets and Views
4 Details
2025 Navajo SP - Boat Ramp Resurfacing Phase 3-2 Site Map & Work Summary.pdf
Sheets and Views
2 Site Map & Work Summary

File details come from the government source that posted it. Updated .