This is an Invitation for Bids (IFB-0643-LUPZ-RE-BID) issued by the Gila River Indian Community's Department of Land Use Planning and Zoning Flood Control Engineering for construction maintenance services to install flow control devices on five existing 24-inch culverts with headwalls in District 6, located in the Laveen area east of 51st Avenue on tribal property. The project involves furnishing all labor, materials, equipment, and supervision necessary to install devices designed to obstruct, regulate, and control drainage flow through existing culvert systems. Devices for two culverts must provide complete flow blockage, while devices for the remaining three culverts must allow a minimum 4-inch clearance at the bottom of the culvert invert for controlled bleed-off. Contractor-submitted devices must be designed and installed to allow future removal without causing damage to culvert structures or surrounding infrastructure. The IFB was issued on July 14, 2026, with a bid submission deadline of Thursday, July 30, 2026, at 2:00 p.m. via the Bonfire e-procurement portal. The deadline for submitting questions is Monday, July 20, 2026, at 2:00 p.m., with responses due Friday, July 24, 2026, at 2:00 p.m. Bid opening is scheduled for Thursday, July 30, 2026, at 3:00 p.m., with bid review and selection on Monday, August 3, 2026, and approximate vendor notification on Monday, August 10, 2026. The estimated project work duration is 30 calendar days following issuance of the Notice to Proceed.
The IFB represents an all-inclusive 100 percent cost based on scope, size, quality, and nature of the project, with the contractor assuming full responsibility for site evaluation, layout, and work scheduling. Gila River Indian Community is exempt from all material, sales, and construction services taxes, and taxes shall not be included in bid amounts. A bid bond of five percent of the bid amount must accompany each submission, with the original bid security delivered within three business days of bid closing to the Procurement Department. Contractors must hold an active Arizona Registrar of Contractors license and license bond. Monthly compensation is based on actual work completion with invoices submitted according to a Schedule of Values, and the Community will retain ten percent retainage until final payment upon substantial completion. Contractors must provide comprehensive insurance including $1 million in general liability per occurrence and $2 million general aggregate, $1 million automobile liability, $2 million excess liability, pollution liability if applicable, and workers' compensation per Arizona law. Performance and payment bonds equal to 100 percent of the contract price are required prior to commencement of work. Tribal Employment Rights Ordinance (TERO) compliance applies, and a Tribal Business License must be obtained prior to commencing work. Native American preference provisions allow qualified Indian-Owned economic enterprises to receive awards if their bids are within specified percentages of the lowest responsive bid, depending on contract value thresholds.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB-0643-LUPZ-FOR BONFIRE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GILA RIVER INDIAN COMMUNITY
INVITATION FOR BIDS
IFB-0643-LUPZ-RE-BID
DISTRICT 6 CULVERT MODIFICATION PROJECT
Request for Construction Maintenance Services
Issue Date: July 14, 2026
Responses Due: Thursday July 30, 2026 @ 2:00 pm
Gila River Indian Community
D6 CULVERT MODIFICATION PROJECT-Construction Maintenance Services
IFB-0643-LUPZ
Table of Contents
SECTION I: ADMINISTRATIVE INFORMATION AND BID INSTRUCTIONS
SECTION II: OVERVIEW
SECTION III: INSTRUCTIONS FOR SUBMITTING A BID
SECTION IV: CONTRACT DOCUMENTS
SECTION V: OTHER REQUIREMENTS
EXHIBIT A - SOLICITATION/ OFFER/ FEE BID FORM / BIDDER’S CERTIFICATION
EXHIBIT B - SCOPE OF WORK
A. Purpose
B. Introduction
C. Definitions
D. Location
E. Project Description
F. Project Team
G. Timeline
H. Scope of Work
I. Deliverables
J. Quality Assurance
K. Safety Requirements
L. Optional Considerations (if applicable)
M. Attachments:
EXHIBIT C - BID BOND
EXHIBIT D - STATEMENT OF BIDDERS QUALIFICATIONS
EXHIBIT E -PREVIOUS PARTICIPATION CERTIFICATION
EXHIBIT F - AUTHORIZATION TO RELEASE INFORMATION
EXHIBIT G - CERTIFICATION REGARDING DEBARMENT, SUSPENSION,
INELIGIBILITY AND VOLUNTARY EXCLUSION
EXHIBIT H - INDIAN ENTERPRISE QUALIFICATION STATEMENT
EXHIBIT I - NON-COLLUSIVE AFFIDAVIT
SECTION I: ADMINISTRATIVE INFORMATION AND BID
INSTRUCTIONS
SOLICITATION TYPE: Invitation for Bid (IFB)
IFB NUMBER: IFB-0643-LUPZ-RE-BID
DESCRIPTION: DISTRICT 6 Culvert Modification Project-
Construction Maintenance Services
IFB SUBMISSION: Upload electronic bids and documents at https://gilariver.bonfirehub.com/portal/?tab=openOp purtunities
DIRECT INQUIRIES IN WRITING TO: Via Bonfire Hub at:
https://gilariver.bonfirehub.com/portal/?tab=openOp purtunities
BIDDING TIMELINE
ISSUE DATE: July 14, 2026, DEADLINE FOR QUESTIONS: Monday, July 20 @ 2:00pm
DEADLINE FOR RESPONSES: Friday, July 24 @ 2:00pm
BID SUBMISSION DEADLINE: Thursday, July 30 @ 2:00 pm
BID-OPENING DATE: Thursday, July 30 @ 3:00pm
BID REVIEW AND SELECTION: Monday August 3rd. 2026
APPROX. NOTIFICATION TO VENDORS: Monday August 10, 2026
The responsibility for submitting a response to this IFB to the Contracts Management Department on or before the stated time and date will be solely the responsibility of the respondent. All responses are subject to the conditions, instructions and the specifications attached hereto.
This IFB’s intent is to represent an all-inclusive 100% cost based on scope, size, quality and nature of the proposed Project. It is the responsibility of the Contractor to evaluate the Project based on a thorough review of all available documents provided by disciplines involved with the development and description of the Project.
Neither the Department of Land Use Planning and Zoning (LUPZ) nor Contracts Management
Department will be responsible for distributing to Contractor’s any hard or electronic copies of plans or specifications. It is up to the Contractor to print them.
Terminology: Bids/Proposal/Solicitation may be used interchangeably. Bidder/Proposer/Vendor/ https://gilariver.bonfirehub.com/portal/?tab=openOppurtunities https://gilariver.bonfirehub.com/portal/?tab=openOppurtunities
Contractor may be used interchangeably. Addendum/Amendment may be used interchangeably.
Bonfire/E-Procurement Platform may be used interchangeably.
INSTRUCTIONS TO BIDDERS FOR ADDENDUMS
Addendums to this Invitation for Bid (IFB)
1. If an addendum is issued, for this solicitation, all terms and conditions that are not modified remain unchanged.
Bidders shall acknowledge receipt of any addendums to this by identifying the addendum number and date on the bid form. Bids failing to acknowledge the bidder’s receipt of any addendum will result in the rejection of the bid if the addendum(s) contained information substantively changing the requirements. Addendums will be posted to the Bonfire website.
ADDITIONAL INSTRUCTIONS REGARDING IFB
Bid packets must be received by the date and time specified via the Bonfire website. If required, when mailing a bid security, please ensure bid security will arrive within 3 business days of the closing of the bid. It is highly recommended that the Original Bid Security be hand delivered to 1632
S. Nelson Dr., Chandler, AZ 85226 during regular business hours. If Bid Security must be mailed, it is encouraged that Sender utilize FedEx/UPS with Tracking to ensure receipt within the given time frame. It will not be the Community’s responsibility if the original documents are not delivered on time.
Read all bid documents thoroughly and carefully. If questions arise it is our advice, that representatives from your company email questions in Bonfire.
All questions regarding the bid, scope of work, specifications, exhibits and the submission of bids should be submitted via the Bonfire Platform. Responses will be provided in an addendum and will be posted on the Bonfire platform.
In order for a bid to be considered, all forms listed must be submitted. See following Section III, Instructions for Submitting a Bid.
SECTION II: OVERVIEW
A. Purpose
The purpose of this Invitation for bids is to provide Contractors with the information required to submit a bid to the Community This IFB’s intent is to represent an all-inclusive 100% cost based on scope, size, quality and nature of the proposed Project. It is the responsibility of the Contractor to evaluate the Project based on a thorough review of all available documents provided by disciplines involved with the development and description of the Project.
B. Solicitation Cost Preparations
GRIC assumes no obligation to pay any costs incurred in the preparation and submission of bids in the response to this IFB or to enter into a contract with any of the bidders.
C. Questions
Read all bid documents thoroughly and carefully. If questions arise, submit them to the
Community no later than the date and time specified in the Bidding Timeline via the e-
Procurement platform. Should there be any doubt as to meaning or intent of any IFB statement or provision, the vendor should submit their inquiries in writing as prescribed. Official answers to questions will be answered in the form of an Addendum.
It is the vendor’s responsibility to retrieve all addendums, and also acknowledge that they have been reviewed in the bid document.
D. Propriety Information:
Clearly state any restrictions on the use of the data contained within this bid in the bid itself.
E. Delivery of Bid to Community
Bids will only be received by the Community’s e-Procurement portal, Bonfire. Bids must be uploaded electronically and shall include all required documents. The link is provided herein: https://gilariver.bonfirehub.com/portal/?tab=openOppurtunities.
Original Bid Security must be delivered to the Community within three (3) Business
Days of the Bid due date.
F. Acceptance and Rejection
The Community reserves the following rights:
• To reject any or all submittals, or any portion thereof;
• To reissue the Invitation for Bid;
• To request additional information from any or all respondents;
• To extend the date for submission of responses through an Addendum;
• To supplement, amend, or modify the IFB and cancel this request with or without the substation of another IFB;
• To disqualify any Bidder who fails to provide information or documents requested herein or who provides inaccurate or misleading information or data;
• To disqualify any Bidder based on any real or apparent conflict of interest;
• To waive any minor defects in the submittal if this is to the advantage of the
Community; and
• To accept the bid that is in the best interest of the Community
The Community’s decision to waive any irregularities or minor defects in a bid shall in no way modify the Vendor’s obligations if awarded a Contract.
Responses that contain false or misleading statements or provide references that do not support an attribute or condition claimed by the vendor may be rejected.
SECTION III: INSTRUCTIONS FOR SUBMITTING A BID
A. Bid must be received by the date and time specified. The e-Procurement portal clock is the official clock for the determination of all deadline dates and times. Without exception, bids will not be accepted after the submission deadline regardless of any technical difficulties such as poor internet connections.
B. Contractors are solely responsible to ensure timely submission of their bid to the
Community via the eProcurement Portal as given in this solicitation. Proposals must be uploaded, submitted, and finalized prior to the closing date and time listed in this document. It is strongly recommended that Contractors give themselves sufficient time and at least one (1) day before the closing date to begin the uploading process and to finalize their submissions.
C. The Community assumes no responsibility for failure of any computer or other equipment to deliver all or a portion of the bid at the time and in the manner required by the solicitation. Neither Bonfire nor the Community warrant that access to and use of the Bonfire website will be free from interruptions or free from errors, nor shall
Bonfire or the Community be responsible for any inadvertent disclosure of proposal repository information or any unauthorized access to proposal repository information by third persons.
D. In the case of disruption of electronic communications or loss of services by Bonfire within two (2) hours prior to the deadline for submissions, the Community will delay the deadline to ensure the ability of potential Contractors to submit proposals. If this occurs, instructions will be communicated to known Plan Holders.
E. Failure of a Contractor to provide information required in this IFB will result in disqualification of the Bid. The bidder who has submitted a Bid that is most cost effective, responsible, and responsive to the Community’s needs and in the best interest of the Community will be recommended for award of the contract.
F. Submission Modifications: Contractors will have the ability to modify their submission up to the submission deadline listed for this IFB directly through Bonfire. Any bid may be withdrawn prior to the scheduled date and time set for the bid opening by clicking un-submit within Bonfire by the proposer or their authorized agent. No bid may be withdrawn after the date and time set for the bid opening.
G. Submittal Format: the following documents must be uploaded as prescribed in Bonfire:
1. Exhibit A, Solicitation / Offer/ Fee Bid Form/ Bidder’s Certification: Each prospective bidder must submit this form and provide a detailed schedule of values in whole dollars for all of the work.
2. Exhibit B, Scope of Work, for D6 Culvert Modification Project
3. Exhibit C, Bid Bond (PDF of Bid Security uploaded to Bonfire, with Original delivered to the Procurement Office within 3 days of Bid closing).
4. Exhibit D, Statement of Bidders Qualifications (please submit Financial
Statements separately in the Bonfire Portal).
5. Exhibit E, Previous Participation Certification.
6. Exhibit F, Authorization to Release Information.
7. Exhibit G, Certification Regarding Debarment, Suspension, Ineligibility, and
Voluntary Exclusion.
8. Exhibit H, Indian Enterprise Qualification Statement, if applicable.
9. Exhibit I, Non-Collusive Affidavit.
10. Licenses and Certifications.
11. W9.
12. Insurance Certificate(s). If award is made, Contractor shall provide an updated certificate which shall meet all requirements listed in this IFB including the
Community being named as an additional insured.
13. Financial Statements.
H. Native American Preference
Native American Preference Form. Each Contractor seeking to qualify for Native
American Preference shall submit proof of Native American ownership with their bids as stated in Exhibit H. The requirements of this section are subject to the Indian-
Owned economic enterprise or organization meeting the requirements and qualifications as indicated in the Invitation for Bid documents. Upon meeting the requirements and qualifications, the award shall be made to the qualified Indian-
Owned economic enterprise or organization if they are the overall lowest responsive bidder. If the lowest responsive bid of the qualified Indian-Owned economic enterprises or organizations is not the overall lowest responsive bid, however if such bid is no more than “X” higher than the overall lowest responsive bid price, the award shall be made to this qualified Indian-Owned economic enterprise or organization.
The factor “X” is determined as follows:
When the lowest responsive, responsible bid is: X = lesser of:
Less than $100,000 10% of that bid, or $9,000
At least $100,000, but less than $200,000 9% of that bid, or $16,000
At least $200,000, but less than $300,000 8% of that bid, or $21,000
At least $300,000, but less than $400,000 7% of that bid, or $24,000
At least $400,000, but less than $500,000 6% of that bid, or $15,000
At least $500,000, but less than $1,000,000 5% of that bid, or $40,000
At least $1,000,000, but less than $2,000,000 4% of that bid, or $60,000
At least $2,000,000, but less than $4,000,000 3% of that bid, or $80,000
I. Additional Information on Required Documents
1. Contractor’s Qualification Statement. The Contractor shall submit a Contractor’s
Qualification Statement (Exhibit D). Attach any additional information not covered within the Contractor’s Qualification Statement, but requested of the
Contractor under this Section directly to the Contractor’s Qualification
Statement unless documents are to be uploaded separately in Bonfire.
2. Financial Statements (Audited preferred): Do not attach the Financial Statements to the Contractor’s Qualification Statement. Instead, provide this as a separate file uploaded in Bonfire in the designated category.
3. Bid Security. Exhibit C - A Bid security of five percent (5%) of the bid amount must accompany each Bid. The Bid security must be in the form of a certified or bank check made payable to the Community, or a bid bond issued by a solvent surety licensed to do business in the state in which the project is located and from a Treasury Listed type “A” Company. A PDF of the Bid Security must be submitted via the Bonfire platform and original must be delivered to the
Community at 1632 S. Nelson Dr., Chandler, AZ 85226 during regular business hours, no more than three (3) business days after bid opening. It is strongly recommended that if mailing the bid security, Bidder utilize FedEx or UPS with document tracking/delivery notification. The Bid security of the successful
Contractor will be retained until the Contractor has executed the Construction
Agreement, furnished the required contract security and certificates of insurance, and met the other conditions regarding award of the contract, whereupon the Bid security will be returned. The Community may annul the award, and Bid security of the prospective Contractor will be forfeited if the successful
Contractor fails to deliver the Construction Agreement and furnish the required contract security, performance and payment bond and certificates of insurance upon execution of the contract. The Bid security of other prospective Contractors whom the Community believes to have a reasonable chance of receiving the award may be retained by the Community until the 60th day after the end of the Project Team’s Bid review, whereupon Bid security furnished by such prospective Contractors will be returned. Bid security with
Bids that are not competitive will be returned, upon request, within seven (7) days after the end of the Project Team’s Bid review.
4. Licenses and Qualifications. Each Bid must contain evidence of the prospective
Contractor’s qualification to do business in Arizona, i.e. a contractor’s license.
Prospective bidders shall be currently and actively licensed with the State of
Arizona, Registrar of Contractors on or before the date and time bids are due. In addition, each prospective Contractor must provide proof of an active license bond in its name, obtained pursuant to Arizona Revised Statutes Section 32-
1152.
5. Certification Regarding Debarment, Suspension, Ineligibility and Voluntary
Exclusion. Each bid must contain Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion (Exhibit G). Prospective
Contractors who fail to provide such information in their Bid shall be deemed non-responsible Bidders and shall be disqualified.
6. Insurance Certificates: Contractor shall provide a PDF of their insurance certificate documenting the minimum limits for policies as set forth in this IFB. If award is made to the Contractor, an updated certificate will be requested documenting additional requirements such as the Community being named as an additional insured.
SECTION IV: CONTRACT DOCUMENTS
Form of Contract and Contract Documents
Unless otherwise expressed elsewhere in writing, the Construction Agreement will include, without limitation, the following as part of one integrated agreement:
1. The Agreement;
2. Performance bond;
3. Payment bond;
4. Certificates of Insurance and Endorsements;
5. Fee Bid Form /Schedule of values and Bidder’s Certification;
6. The Invitation for Bids and its Addendums; and
7. The following which may be delivered or issued on or after the Effective
Date of the Agreement and are not attached hereto:
a. Notice to Proceed.
b. Change Orders.
General Scope of Work (See Exhibit B)
SECTION V: OTHER REQUIREMENTS
It is the responsibility of each prospective Contractor, prior to submitting a Bid, to:
1. Examinations: Examine thoroughly the IFB documents and other related data identified in the Bid Documents.
2. Seasonal Rains: Take into consideration and be aware that seasonal rains might considerably affect site conditions. As such, prospective Contractors shall schedule for alternate construction, techniques or any additional equipment needed, as the
Community will not be responsible for the adverse conditions that occur annually in this region.
3. Nature of Work: The Contractor assumes all responsibility for deductions and conclusions as to the difficulties in performing the work, which may be made as to the nature of performing work affected by the geology and other surface and subsurface conditions at the project site.
4. Designated Personnel and Minimum Amount of Work: Only key personnel indicated in the contractor’s bid assigned to the project will be utilized, and all substitutions will be subject to the prior approval of the LUPZ.
5. Community Involvement: The Gila River Indian Community will be intimately involved in the construction process of the project. To understand all the requirements involved, the Contractor will confer, consult, and work closely with the
LUPZ and its representatives during each phase of construction to ensure an exchange and understanding of ideas, and to expedite the work.
6. Gila River Furnished Codes: The Department will maintain and furnish the
Contractor with the applicable Community Ordinances. Applicable codes and standards will be those in effect at time of contract award.
7. Communications: All notices, requests, instructions, approvals, proposals, and claims must be in writing to:
Jorene Tsosie, Contract Specialist
Jorene.Tsosie.PROC@gric.nsn.us
8. Performance and Payment Bonds: Contractor shall furnish performance and payment bonds, each in an amount at least equal to the Contract Price as security for the faithful performance and payment of all of Contractor’s obligations under the Contract
Documents. These bonds shall remain in effect until one year after the date when final payment becomes due or until completion of the warranty period, whichever is later, except as provided otherwise by Laws or Regulations or by the Contract Documents.
Contractor shall also furnish such other bonds as are required by the Contract
Documents. In the case that contractors have entered into a joint venture agreement to qualify for contract, all parties of the said joint venture must be listed on all bonds.
9. Insurance.
The Contractor shall maintain adequate insurance coverage throughout the term of the Agreement, including the warranty period. Insurance coverage shall include, but is not limited to, General Liability Insurance, Workers
Compensation Insurance, and Property Insurance.
Contractor agrees that before beginning any work under the Agreement, and as a condition precedent hereto, the Contractor shall provide the Community with a Certificate of Insurance demonstrating that the insurance required in this section has been purchased and is in effect. The Contractor shall provide documentary proof of insurance showing the following:
▪ Commercial General Liability Insurance- Commercial general liability insurance with minimum limits of $1,000,000 per occurrence and $2,000,000 general aggregate (on a current ISO CGL form or its equivalent, including without limitation, broad form contractual liability, bodily injury, property damage, fire, legal liability, and products and completed operations coverage) under which the
Community and Department shall be named as additional insured. This policy shall be written or endorsed to include the following provisions:
• Waiver of subrogation as set forth herein below.
• No Explosion, Collapse or Underground Exclusions.
• No Subsidence Limitations.
• AM Best Rating of A-8 or better.
• No Claims Made Policy forms acceptable on commercial general liability policy.
• An endorsement providing limited coverage with respect to property under the care, custody and control of Contractor.
• Completed Operations Aggregate of $2,000,000.00.
▪ Excess Liability- in the amount of $2,000,000.
▪ Automobile Liability Insurance- Automobile liability insurance shall cover all owned, non-owned and hired vehicles as applicable to the work under the agreement, with $1,000,000 combined single limits.
▪ Pollution Liability- If Contractor’s work may involve asbestos or lead, mold or other pollutant abatement, Contractor shall provide liability insurance coverage for claims arising out of abatement, removal and storage, transportation, and/or disposal activities. Such insurance shall be written on an occurrence basis with no sunset clause, or on a claim made basis with a minimum 5 year extended reporting period (Tail) with limits of not less than
$2,000,000.
▪ Workers Compensation Insurance as required by Arizona law, including
Employer’s Liability, with limits of:
• For bodily injury by accident, $1,000,000 per accident
• For bodily injury by disease, $1,000,000 per employee and
$1,000,000 policy limit
▪ Performance and Payment Bonds, (A+) for construction in an amount equal to 100% of the contract price, shall be furnished to the Community prior to and as a condition precedent to commencement of work. Said bonds shall be in effect through the warranty period. Such Bonds shall name Contractor as principal and the Community and Department as joint obligees.
▪ Waiver of Subrogation- To the extent permitted by law and without affecting the coverage provided by insurance required to be maintained hereunder, Contractor waives any right to recover against the
Community on account of any and all claims Contractor may have against the Community with respect to any loss or damage insured against under the insurance actually carried to the extent of the proceeds realized had the insurance required hereunder been carried by the
Contractor. Contractor agrees immediately after execution of this
Agreement to give each insurance company, which has issued to it policies of insurance, written notice of the terms of the mutual waivers contained in this paragraph, and if necessary, to have the insurance policies properly endorsed.
Contractor will also provide Gila River Indian Community with a copy of the additional insured endorsement along with any other requested coverage forms demonstrating that the insurance policy complies with the requirements of this Section. The Certificate of Insurance will expressly entitle Gila River Indian Community to thirty (30) calendar days’ notice, by certified mail, before any insurance policy referred to therein is modified or canceled. At least thirty (30) calendar days prior to the expiration of the coverage required in this Agreement, Contractor shall provide certificates evidencing that all coverage required herein has been renewed.
Contractor agrees that its failure to obtain or maintain the insurance required by this Section, or to provide a satisfactory Certificate of Insurance, shall be deemed to be a material breach of this Agreement and shall entitle Gila River
Indian Community to cancel this Agreement and/or recover damages at its election.
It is understood and agreed that the insurance coverage and limits, required above, shall not limit the extent of this Contractor’s responsibilities and liabilities specified within the contract documents or by law.
It is understood and agreed that authorization is hereby granted to Gila River
Indian Community to withhold payments to the Contractor until a properly executed Certificate of Insurance providing insurance as required herein, accompanied by a signed Agreement, is received by Gila River Indian
Community.
Contractor agrees that any contract it enters into with a lower tier contractor for the performance of any aspect of Contractor’s work under this
Agreement shall expressly bind such other contractor to this language and requirements herein, making such obligations applicable to the other contractor to the same extent as the Contractor.
Contractor shall also require its lower tier subcontractor to likewise bind and obligate any additional lower tier with which it contracts for any portion of the work under this Agreement. This purpose of this provision is to require any lower tier contractors, regardless of level, to provide the insurance and indemnity required by this Agreement.
10. Communities Payment Terms: The Contractor shall receive monthly compensation in accordance with the actual work completed and shall invoice in accordance with the
Schedule of Values. To the extent an invoice includes billed amounts for administrative fees, including but not limited to: General Conditions, Bonds, Insurance, Overhead, and Profit, invoiced amounts shall not exceed the percentage of completion of the project in its entirety. Based upon invoices submitted by the Contractor to the
Community and approved by the Project Manager and Community, the Community shall make payments on account of the contract sum to the Contractor. Ten percent
(10%) retainage of the amount in the invoice shall be subtracted from the total amount of the invoice and retained by the Community and released upon the Contractor meeting the final payment requirements.
The Contractor shall receive final payment upon the substantial completion of the project. Substantial completion of the project shall be achieved when the Contractor completes one hundred percent (100%) of the punch list and the Community issues a
Certificate of Substantial Completion. The Community agrees that it will act with due diligence in inspecting the work and assisting in the preparation of punch lists for the
Contractor. The issuance of a Certificate of Substantial Completion shall not relieve the Contractor of its warranty obligations. If the Contractor fails to complete any or all of the Punch List Work in accordance with the Certificate of Substantial
Completion, the Community may, in its sole discretion, complete any or all of the
Punch List Work, and such separate fees shall be withheld from the amounts payable to the Contractor at final completion. If the amounts withheld by the Community are insufficient to compensate for the completion of work, then upon the demand of the
Community, the Contractor shall pay the Community the amount equal to the deficiency.
In the absence of a written Amendment, the Contractor shall not receive any compensation for work not described in the Contract Documents, nor be entitled to any fees not identified in the Schedule of Values. All claims for additional compensation and/or time must be made in writing within twenty-one (21) calendar days of the event(s) giving rise to the claim. Failure to provide such written notice shall result in forfeiture of the claim.
The Department shall review and approve all invoices submitted by the Contractor prior to payment. Such review shall include an inspection of the Project work. Payment shall be approved and authorized for work only to the extent such work conforms to the specifications and/or other similar documents approved by the Department.
Noncompliance with and/or failure to provide timely submittals of contract requirements, and/or nonconformance to the plans and specifications approved by the
Department, will be justification of withholding payments in full or additional portions thereof. Payments will be due thirty (30) calendar days from the Department’s approval of invoices and receipt by the Community’s Finance Department of such invoices.
The Contractor is required to deliver original invoices to the Community’s Finance
Department at the following address with a copy to the Department:
Finance Department/ Accounts Payable
Post Office Box 2160
Sacaton, AZ 85147
11. Tribal Business License, Building Permits: The Contractor and all Subcontractor(s) shall be responsible for obtaining a Tribal Business License with the Office of Internal
Audit prior to commencing work on the Project. Upon request from an authorized
Community representative, Contractor, Subcontractor, and/or sub-subcontractor must present their Gila River Business License to the requesting representative.
12. Tribal Employment Rights Ordinance (TERO): The Contractor shall be responsible for complying with the provisions of the Community’s Tribal Employment Rights
Ordinance, Title 12, and with other applicable Community ordinances. The Contractor must contact the Tribal Employments Rights Office (TERO) to obtain a copy of the
Compliance packet.
13. Tribal Native Plant Ordinance: The Contractor shall be responsible for complying with the provisions of the Community’s Tribal Native Plant Ordinance and with other applicable Community ordinances.
14. Taxes: Gila River Indian Community is exempt from all material, sales and construction services taxes and as such, taxes shall not be included in the bid amount.
15. Project Site Layout: The Contractor shall be responsible for all layouts on the project site(s).
16. Temporary Service Lines: Contractor shall provide all necessary temporary service lines and fittings required, and remove such items upon completion of work. Repair any resulting damage, and leave the permanent utility service in as good condition as they were prior to commencing work.
17. Facilities: Contractor will be responsible for provision of toilet facilities as required.
Facilities shall be enclosed and maintained in sanitary condition.
18. Parking: There will be no parking on adjacent Allotted Land; the contractor shall protect all adjacent property.
19. Site Protection: Contractor shall be responsible, at the contractor’s cost and expense, for the security and protection of the site, under contractor’s control, and of the work until that portion to the site(s) are complete and accepted by LUPZ. The Contractor shall take all necessary measures to provide such security.
20. Damages: The Contractor shall be liable for and shall promptly repair or otherwise remedy all damages to said portion of the site and of the work caused by vandalism.
21. Temporary Access: The Contractor shall provide and maintain a suitable means of temporary access into contract work areas as necessary for vehicles and equipment of all trades requiring such access. The Contractor shall repair any damage to existing pavement or other construction when damaged from operations under the
Construction Agreement.
22. Signage: Other than those that may be required for safety and as specified herein, the
Contractor shall post no signs at the project site.
23. Traffic Control: The Contractor shall be responsible for all traffic control at streets adjacent to the project site as required when vehicles enter and leave the site. The
Contractor shall comply with all Community laws and regulations, including any applicable State or County regulations, for traffic control.
24. Choice of Law: Performance of the terms of the Agreement shall be in accordance with and pursuant to the laws of the Community and any action, special proceeding or other proceeding that may arise from, in connection with or by reason of the
Agreement shall be resolved pursuant to the laws of the Community and in its courts.
Nothing in the agreement, or in any related exhibit, document or undertaking, shall be construed as affecting, modifying or otherwise impairing the sovereign immunity enjoyed by the Community or any of its affiliates or subdivisions.
25. Ownership of Work Product: The Contractor agrees that all documents or other work product generated on behalf of the Community in connection with this Agreement are property of the Community.
26. Confidentiality: The Contractor agrees that neither they nor their agents or representatives shall communicate, whether in writing or verbally, any information concerning work performed in connection with this Agreement except in strict compliance with the terms and conditions of an express authorization by the
Community Governor, the Lieutenant Governor, or the General Counsel of the
Community.
27. Material and Equipment: The Contractor warrants to the Gila River Indian Community c/o LUPZ that all materials and equipment furnished will be new and that all work will be of good quality, free from faults and defects, and in conformance with acceptable standards.
Contractor shall properly and continuously protect the work, materials and equipment against damage by weather, or water and cover work liable to be damaged whenever work is in progress.
The Contractor shall be responsible for the safe and secure storage of materials purchased and delivered in advance of installation and stored within the Community whether stored at the project site or off the project site.
Storage of all materials by the Contractor shall be at its expense. The Gila River Indian
Community assumes no responsibility or liability for the security of Contractor owned property whether on or off the project site.
28. Progress Schedule: As soon as possible, after contract award, the Contractor will meet with the Community’s Project Manager of Record and coordinate the work schedule
(i.e. start date), projected rate of accomplishment, etc.
29. Pre-Construction Conference and Notice to Proceed: Following the award of a construction contract, a pre-construction conference will be held for discussing all design, construction and contract administration and safety related issues.
30. Bid Protest Procedure: In the event a Company wishes to contest a contract awarded under the provision contained within this IFB, the Company shall initiate a written document stating the reason(s) to be the basis of the protest. In addition, the Company shall provide supporting documents. Written protests shall be sent to Tecumseh
Manuel, Procurement Director, Procurement Department, 1632 South Nelson Drive, Chandler, Arizona, 85226.
31. Apply for a receive approved right of entry from LUPZ Ordinance before work is performed.
EXHIBIT A - SOLICITATION/ OFFER/ FEE BID
FORM / BIDDER’S CERTIFICATION
Solicitation Number: IFB-0643-LUPZ Solicitation Type: Invitation for Bid Date Issued: July 14,2026
Issued by: Gila River Indian Community
Contracts
Management
1632 South Nelson
Drive Chandler, AZ
85226
SOLICITATION
One Bid for furnishing the services or supplies in the attached solicitation will be received via Bonfire as specified herein until 2:00PM local (AZ) time on Thursday, July 30,2026. Vendors should allow sufficient time to upload their bid to ensure receipt of the Bid by the time specified. Late Submissions will not be accepted. All offers are subject to all terms and conditions in this solicitation. Vendors should not mail their bids.
For information Contact: via Bonfire
Alternate Contact information
Jorene Tsosie, Contract Specialist
Jorene.Tsosie.PROC@gric.nsn.us
Office Number: 520-796-3969
OFFER
In compliance with the above, the undersigned agrees, if the offer is accepted within 60 calendar days from the date for the receipt of offers specified above, to furnish any and all items at the prices bid.
The Offeror/Bidder acknowledges amendments: through by signing below.
Name and Address of Offeror/Bidder:
Name and Title of Person Authorized to sign Offer/Bid:
Telephone Number:__________________ Email Address: _________________________
Signature: Date:
FEE BID FORM
Date:
TO: Gila River Indian
Community Contracts
Management, 1632 South Nelson
Drive Chandler, AZ
85226
PROJECT: IFB-0643-LUPZ-Re-E-BID IFB for D6 Culvert Modification Project-
Construction Maintenance Services
Bid Submitted by:
(state whether bidder is corporation, partnership, individual, etc.)
1. The undersigned acknowledges having visited the site and having familiarized itself with the local conditions affecting the cost of the work. The undersigned further acknowledges that it has received and has familiarized itself with the following:
Bidding and Contract Documents:
A. The Agreement. (Terms as specified in this IFB)
B. Performance bond.
C. Payment bond.
D. Certificates of Insurance and Endorsements.
E. Fee Bid Form / Detailed Schedule of Values / Bidder’s Certification
F. The Invitation for Bids and its Addendums.
2. In submitting this bid, the undersigned agrees:
To furnish all material, labor, tools, expendable equipment, and all utility and transportation services necessary to perform and complete, in a competent manner, all of the work required in accord with the IFB, addendum(s) and Contract Documents, for the price stated in this
Bid Form, for the consideration hereinafter set forth.
To hold this bid open for 60 calendar days after the receipt of bids, and to accept the provisions of the Instructions to Bidders regarding disposition of bid security.
To execute and deliver a Contract in the prescribed form if awarded on the basis of this bid, and to furnish performance and payment security acceptable to the Owner in accord with the General Conditions within 10 days after the Contract is presented for signature.
To commence work at the time stipulated in a Notice to Proceed or Contract Document and to complete the work within Contract term.
3. The undersigned hereby proposes and agrees to perform the work in accordance with the following Fee Bid Form / Detailed Schedule of Values / Bidder’s Certification.
4. The undersigned hereby proposes and agrees to perform the work as described in this IFB and any addendum(s) for the sum of:
5. The Bid includes the following amounts:
Culvert 1 $
Culvert 2 $
Culvert 3 $
Culvert 4 $
Culvert 5 $
(The above numbers are for purposes of the Owner’s evaluation, only, and do not bind the Owner for such particular payments.)
6. The Bidder proposes to use the following subcontractors, if any:
Mechanical Work:
Electrical Work:
Site Work:
Material Suppliers:
Additional Subcontractors:
7. The undersigned proposes to use the following listed persons (with their positions) in its core crews (if any), subject to the Owner’s approval.
(name) (position)
8. The undersigned has attached the required Bid Bond (PDF) and will deliver the original within
3 days of the bids closing:
In submitting this bid, it is understood that the right to reject any and all bids and to waive irregularities in the bidding has been reserved by the Owner.
The full name and address of all person and parties interested in the foregoing bids as principals are as follows:
Bidder
Address
Phone Fax
If the Contractor is entering into a partnership/joint venture to perform the work, provide the following information for the partnering/joint venture firm:
Bidder
Address
Phone Fax
BIDDER’S CERTIFICATION
The Bidder hereby certifies that the information contained in these certifications and representations is accurate, complete and current:
1. The undersigned, having read and examined the Invitation for Bids, the Contract
Documents, and any Addendum for: IFB-0643-LUPZ having inspected the site and all conditions affecting the work, the Bidder proposes to furnish all materials and perform all labor necessary for the completion of the work indicated in this IFB. The Bidder agrees that if any or all bids are accepted, Bidder will enter into a contract according to the Contract required by the owner for the faithful performance of the labor and materials included in bid or bids accepted.
2. In submitting this bid it is understood that the Gila River Indian Community c/o LUPZ and
Contracts Management reserves the right to reject any and all bids. It is agreed that this bid may not be withdrawn for a period of (60) days subsequent to the opening of bids without the consent of Gila River Indian Community c/o LUPZ.
3. Attached Contractors Qualification Statement.
4. Bidder agrees to comply with all City, State and Federal Statutes relating to Liability
Insurance, Safety and Sanitary Regulations.
5. Bidder will sign on line indicated below, if a partnership the firm name will be signed, followed by the signature of the partner signing, if a corporation name will be signed followed by the signature and the official title of the officer signing name.
6. The Bidder has visited the project site, become familiar with local conditions and become familiar with all parts of this IFB. The Bidder has no outstanding questions with regard to this IFB.
7. The Bidder will enter into and execute the Contract with Gila River Indian Community c/o
LUPZ. If a Contract is awarded on the basis of this bid, and if the Bidder does not execute a Contract for any reason, other than as authorized by law, the Bidder and Bidder’s Surety are liable to Gila River Indian Community as indicated in the Instructions to Bidders.
If the Bidder is a Corporation, partnership or sole proprietorship, an officer, partner or principal of the Bidder, as applicable, shall print or type the legal name of the Bidder on the line provided and sign the Bid Form. If the Bidder is a joint venture, an officer, partner or principal, as applicable, of each member of the joint venture shall print or type the legal name of the applicable member on the line provided and sign the Bid Form. All signatures must be original.
Bidders Name:
Authorized Signature:
Print Name:
Title:
Company Name:
Mailing Address:
Telephone Number:
Email Address:
Facsimile Number:
Where Incorporated:
Federal Identification Number:
Contact Person for Contract Processing:
(Please Print)
Additional Signature for Joint Venture
Bidders Name:
Authorized Signature:
Print Name:
Title:
Company Name:
Mailing Address:
Telephone Number:
Email Address:
Facsimile Number:
Where Incorporated:
Federal Identification Number:
Contact Person for Contract Processing:
(Please Print)
Seal – (If Corporation)
Dated this day of , .
(print name of bidder)
(address of bidder)
(print name of authorized officer) (title)
(signature of authorized officer)
ARIZONA CONTRACTORS LICENSE#:
TYPE OF LICENSE:
Additional Signatures if a Joint Venture:
Signature:
EXHIBIT B - SCOPE OF WORK
DISTRICT 6 CULVERT MODIFICATION PROJECT
Request for Construction Maintenance Services
LUPZ Flood Control Project No. FC 26-010 SFC
Prepared May 13, 2026
A. Purpose
This Scope of Work is meant to provide construction firms with sufficient information to enable them to prepare and submit a proposal, schedule and fee to install culvert flow obstruction devices onto certain culverts described in this request.
B. Introduction
The Gila River Indian Community’s Department of Land Use Planning and Zoning Flood Control
Engineering (“LUPZ”) is soliciting construction firms to provide maintenance services to install flow control devices on existing 24” culverts with headwalls within our drainage system east of
51st Avenue. The Contractor shall furnish all labor, materials, equipment, and supervision necessary to install devices designed to obstruct, regulate, and control drainage flow through existing culvert systems. These devices shall be designed and installed to allow for future removal without causing damage to the culvert structure or surrounding infrastructure and environment.
C. Definitions
From this point forward, the Gila River Indian Community shall mean “Community” and reference to the Community’s lands as “Reservation”. LUPZ shall mean “LUPZ Flood Control Engineering” or “Department”. The construction firm shall mean the “Contractor”. The activity of the District 6
Culvert Modifications Project shall mean “the Project”.
D. Location
The Gila River Indian Community is a federally recognized Indian Tribe with a constitution and sovereign government status. The Project is located in District 6, described as a portion of tribal property and a part of the NW ¼ corner of Section 5, T2S, R2E. See Exhibits 1 and 2 for specific
Project locations and access. See Exhibits 3 and 4 for images of culverts.
The proposed activity will be located in existing tribal drainage easements (“D.E.”) defined under
GR-046-19. These easements are also disturbance boundaries. No cultural or environmental clearance is necessary if all work are maintained within these disturbance limits. Improvements shall not be extended beyond these disturbance boundaries.
E. Project Description
The 2019 Komatke Flood Control Project – Phase 1 installed basins, levees, and channels upstream of the 51st Avenue Subdivision in the Laveen, AZ area to control mountain runoff. After several rounds of storm events, LUPZ has received complaints of nuisance flows entering property from our completed project. Although discharge of these flows were designed and planned for, additional flood mitigation is needed to further protect property. Certain culverts will need to be obstructed fully and partially to meter flow more appropriately. Internal hydraulic analysis showed these modifications will not impact the current design of the system. Access to the culvert systems begins from 51st Avenue and the Ray Road alignment. This Project will:
• Provide temporary or semi-permanent flow control from existing culverts.
• Continue bleed off of basins within acceptable drain time.
• Allow for runoff to spill over into existing spillways, basins, and other culverts.
• Maintain structural integrity of existing culverts and the entire drainage system.
• In the event removal is required, ensure devices can be safely and efficiently removed in the future with reasonable tools.
• To the extent practicable, the devices must be tamper proof.
• All activity shall be maintained within the existing drainage easements.
• Minimize environmental and hydraulic impacts.
F. Project Team
LUPZ Flood Control Engineering is the Department Section who will manage the Project as the agent of GRIC. The selected construction firm will report to and submit draft invoices to Seaver
Fields III, Project Coordinator with the Department for review prior to submittal of final invoicing.
A list of qualified sub-consultant professional disciplines shall be submitted with the proposal and considered as the Contactor’s Team, if the Contractor chooses a team.
G. Timeline
1. Proposal Timeline:
• Refer to GRIC Contracts Mgt. on review for proposals timelines after advertisement.
2. Project Timeline.
• If order of materials are required, no work shall be conducted until orders are ready to be installed. Delays in ordering material shall not take away from contracted work time.
• Payment of materials will only occur after installation of the devices.
• Actual work is estimated to last 30-calendar days after a notice to proceed is issued.
• Apply for and receive approval for right-of-entry from LUPZ Ordinance.
• Contractor shall provide a schedule summarizing the activities.
H. Scope of Work
In general, the Contractor will:
1. Site Assessment and Preparation
• Verify existing culvert system dimensions, materials, and conditions. Access to the culverts are shown on Exhibits 1 and 2.
• Identify flow characteristics and potential impacts of obstruction.
• Clear debris and sediment as necessary to facilitate installation.
• Implement applicable erosion and sediment control measures such as best management practices before, during, and after construction.
• Apply for and gain approvals for right-of-entry from LUPZ Ordinance.
2. Design and Submittals
• Submit shop drawings and product data for proposed devices to LUPZ.
• Devices may include plugs, slide gates, flap gates, or similar systems.
• Demonstrate that all devices and applicable systems are reasonably removable and do not require excessively permanent modification to culvert structures.
• Provide calculations or documentation showing structural adequacy and hydraulic performance. Product information may suffice.
3. Materials
• Use water tight seal and corrosion resistant materials (e.g., stainless steel, aluminum, HDPE, coated steel, etc.).
• All anchoring or fastening systems shall be non-evasive or minimally invasive and designed for removal.
• Gaskets, seals, and fittings shall be durable and replaceable.
4. Installation
• Install devices on upstream end of culverts and in accordance with approved submittals and manufacturer recommendations.
• Devices for culverts 1 and 2 shall provide complete blockage to flow. See attached
Exhibit 3.
• Devices for culverts 3, 4, and 5 must have a minimum 4” (0.33 ft.) clearance between the device and bottom culvert invert. This clearance is necessary for a controlled bleed off of basins. A device that allows adjustable clearance is acceptable. See attached
Exhibit 3.
• Avoid excessive cutting, drilling, or altering culvert system unless explicitly approved.
• Ensure installation allows for proper sealing and intended flow control.
• Provide safe access for installation and future removal.
• All components must be reasonably tamper proof, but shall be removable using standard tools and without specialized demolition.
• No permanent grouting, welding, or embedding that would prevent removal shall be allowed unless specifically approved.
• Contractor shall demonstrate removal procedure upon request.
I. Deliverables
• Installation of semi-permanent water tight, corrosion resistant, tamper proof, but reasonably removable flow control…