B.08.02 Att 8_Price Schedule Koknese Nursing Home.docx
DOCX document 35 KB Posted
- Attached to
- Koknese Nursing Home Renovation, Latvia
- Solicitation number
- IEU-24-0007
- Issued by
-
Department of the Army European Command
About this file
This document is a Price Schedule for the Koknese Nursing Home Renovation project in Irsi, Latvia. It includes pricing for base and option items required to complete the design and construction work, as outlined in the attached Plans, Specifications, and Statement of Work. The base item is for the reconfiguration of the nursing home, with option items for replacing the second-floor emergency egress stairs, providing a new elevator, repairing the water supply pipe, and providing exterior paving around the building perimeter. The period of performance and liquidated damages terms are referenced from the solicitation. The government reserves the right to award the options up to 180 calendar days from contract award. Interested offerors must submit a non-price proposal and a price proposal to be considered for contract award. Companies must be SAM-registered to be eligible for this contract.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE SCHEDULE
Koknese Nursing Home Renovation Irši, Latvia 31-Jan-24
PRICE SCHEDULE
Koknese Nursing Home Renovation Irši, Latvia 31-Jan-24
Offerors shall provide pricing for all base and option items.
The following items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Statement of Work (SOW), Solicitation. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, and safety requirements. All work shall be performed in accordance with these documents. Refer to Specification Section 01 22 00 Price and Payment Procedures for additional description of the work associated with each of the items.
Period of Performance: Refer to clause COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10) in the Solicitation for the period of performance for all base and option items.
Liquidated Damages: Refer to clause LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12) in the Solicitation for the liquidated damages for all base and option items.
Option Items: The Government reserves the right to award the options up to 180 calendar days from contact award. See Section 01 22 00 for additional information regarding the award of options.
| Item No. |
| Title |
| Quantity |
| Unit |
| Unit Price |
| Amount |
BASE ITEMS
| 0001 |
| Reconfiguration of Nursing Home |
| 1 |
| Job |
| $ |
| $ |
| Total of Base Item 0001 |
| $ |
OPTION ITEMS
| 0002 |
| Replace second floor emergency egress stairs |
| 1 |
| Job |
| $ |
| $ |
| 0003 |
| Provide new elevator |
| 1 |
| Job |
| $ |
| $ |
| 0004 |
| Repair water supply pipe |
| 1 |
| Job |
| $ |
| $ |
| 0005 |
| Provide exterior paving around building perimeter |
| 1 |
| Job |
| $ |
| $ |
| Total of Option Items 0002 thru 0005 |
| $ |
| Total of all Base and Option Items |
| $ |
EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.
-- END OF PROPOSAL SCHEDULE --
Oct 2020 Date