IDOT NEVI program - Vendor Q and A Addendum 1.docx

DOCX document 15 KB Posted

Attached to
Electric Vehicle Infrastructure - RFI
Solicitation number
23-494DOT-FINAD-B-35462
Issued by
Illinois

About this file

This document is an Addendum to an Illinois Department of Transportation (IDOT) Request for Information (RFI) for the National Electric Vehicle Infrastructure (NEVI) program. The RFI seeks to gather information from vendors, but does not constitute a solicitation or any obligation. IDOT anticipates construction to start no sooner than spring/summer 2024, with a grant program or formal procurement to be released at the end of 2023 or early 2024. This timeline is tentative.

The RFI does not currently identify any vendors under agreement for the NEVI program. Pricing information is not requested as part of this RFI. The State of Illinois is the sole jurisdiction involved in this RFI, and there are no set-asides, incumbents, or specific funding sources identified in the document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Illinois Department of Transportation Request For Information (RFI) Vendor Questions and Answers – Addendum #1

B-35462 / 23-OPP-R-164329

1. Are there any systems currently in place by other vendors?

Response: There are no vendors identified or under any kind of agreement for the NEVI program.

2. Is there a timeline for this project?

Response: IDOT anticipates construction to start no sooner than spring/summer 2024 with the release of a grant program or formal procurement end of 2023 or early 2024. This timeline is tentative.

File details come from the government source that posted it. Updated .