IDOT 66C06-057.pdf

PDF 1 MB Posted

Attached to
Milling and Resurfacing Project - Route FAS 297 FAU 392 FAU 5951 - Grundy County
Solicitation number
66C06
Issued by
Grundy County, Illinois

About this file

This is a Notice to Bidders and Special Provisions document issued by the Illinois Department of Transportation (IDOT) for Contract No. 66C06, a milling and resurfacing project located in Grundy County on US Route 6 from IL 47 to 0.7 miles west of NiGas Road in Channahon. The project encompasses approximately 6.81 miles of roadway and includes milling and resurfacing with a 3 3/4-inch designed overlay, Class D patching, pipe culvert end section replacements and cleaning, detector loop replacement, pavement marking, and raised reflective pavement markers. Electronic bids must be submitted through the iCX-Integrated Contractors Exchange system prior to 12:00 p.m. on June 12, 2026, at which time bids will be publicly opened. The contract will be awarded to the lowest responsive and responsible bidder, with the Department reserving the right to reject any or all proposals, determine responsibility at the time of award, and re-advertise the project if necessary.

The project is funded through Federal-aid construction funds under Project STP-PIHG(245) and is classified as District 3 work. Nighttime work restrictions apply to US 6 from Mission Parkway to IL 47, requiring all work to be performed between 7:00 p.m. and 7:00 a.m., with all lanes remaining open to traffic during daytime hours and legal holidays. Multiple utilities are present throughout the project area, including pipelines, electric, water, gas, and fiber facilities, though no significant conflicts are anticipated given the design overlay nature of the work. The contract includes provisions for bituminous materials cost adjustments, quality control requirements for concrete and asphalt mixtures, traffic control measures including automated flagger assistance devices, and environmental monitoring for regulated substances at nine identified sites. Specialized provisions address drainage mitigation during milling operations, pavement marking applications, linear delineator panel installation and performance inspection requirements extending 180 days post-installation, and loop detector testing for traffic signal equipment.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting June 12, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 66C06 GRUNDY County Section (G)RS-6&(F)RS-3 Route FAS 297 FAU 392 FAU 5951 Project STP-PIHG(245) District 3 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

June 12, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 66C06 GRUNDY County Section (G)RS-6&(F)RS-3 Project STP-PIHG(245) Route FAS 297 FAU 392 FAU 5951 District 3 Construction Funds

Milling and resurfacing 3 3/4 inches (designed overlay), class D patching, pipe culvert end section_replacements and cleaning, detector loop replacement, pavement marking, and raised reflective pavement markers on US 6 beginning at IL 47 in Morris, and ends 0.7 miles west of Nigas Road._Approximately 6.81 miles gross length.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

Routes FAU 5951, FAS 297 & FAU 392 (US 6)

Section (G)RS-6 & (F)RS-3 Grundy County

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

Section (G)RS-6 & (F)RS-3

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 X Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 X Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 X Station Numbers in Pavements or Overlays

Section (G)RS-6 & (F)RS-3 i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

STATUS OF UTILITIES TO BE ADJUSTED:

FURNISHED EXCAVATION (SPECIAL)

AGGREGATE SURFACE COURSE, TYPE B

VIBRATORY ROLLER RESTRICTION

DRAINAGE MITIGATION ON MILLING AND RESURFACING PROJECTS

SURFACE COURSE PAVING SEQUENCE

CROSSING STRUCTURES WITH MATERIAL TRANSFER DEVICE

TACK COAT

FURNISH PERMANENT SURVEY MARKERS

LINEAR DELINEATOR PANELS, 6 INCH

LINEAR DELINEATOR PANELS, 4 INCH

MODIFIED URETHANE PAVEMENT MARKING – TWO APPLICATIONS

TEMPORARY INFORMATION SIGNING

NIGHTTIME WORK AND KEEPING ROADS OPEN TO TRAFFIC

TRAFFIC SIGNAL BACKPLATE, LOUVERED, FORMED PLASTIC, SPECIAL

LOOP DETECTOR TESTING

REMOVE AND RELAY PIPE CULVERTS (SPECIAL)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

CLEAN EXISTING END SECTIONS

CLEANING EXISTING INLETS

CONCRETE CURB REPAIR

EXISTING FIELD TILE REMOVAL

REMOVE AND RELAY END SECTIONS

AUTOMATED FLAGGER ASSISTANCE DEVICES (BDE)

BITUMINOUS MATERIALS COST ADJUSTMENTS (BDE)

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

COMPENSABLE DELAY COSTS (BDE)

EROSION CONTROL BLANKET (BDE)

FUEL COST ADJUSTMENT (BDE)

Section (G)RS-6 & (F)RS-3 ii

HOT-MIX ASPHALT (BDE)

HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)

PAVEMENT MARKING (BDE)

PAVEMENT PATCHING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

PREFORMED PLASTIC PAVEMENT MARKING (BDE)

RAISED REFLECTIVE PAVEMENT MARKERS (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SEEDING (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURFACE TESTING OF PAVEMENTS – IRI (BDE)

SURVEYING SERVICES (BDE)

TRAFFIC SIGNAL BACKPLATE (BDE)

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION ...80

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

WORKING DAYS (BDE)

PROJECT LABOR AGREEMENT

Section (G)RS-6 & (F)RS-3

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1, 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of Routes FAU 5951, FAS 297 & FAU 392 (US 6), Project STP-PIHG(245), Section (G)RS-6 & (F)RS-3, Grundy County, Contract No. 66C06 and in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.

LOCATION OF PROJECT

This project is located in Grundy County at US Route 6 in Morris, from IL 47 to 0.7 mile west of NiGas Road in Channahon.

DESCRIPTION OF PROJECT

This project is located on FAU 5951, FAS 297 & FAU 392 (US 6) beginning at IL 47 to 0.7 mile west of NiGas Road in Channahon. The work consists of milling and resurfacing 3 3/4" (designed overlay). Additional work shall include Class D patching, pavement marking, pipe culvert end section replacements and cleaning and loop replacement.

Section (G)RS-6 & (F)RS-3

STATUS OF UTILITIES TO BE ADJUSTED:

(Effective January 1, 2007; Revised January 24, 2011)

Name & Address of Utility

Type

Location

Estimated Date Relocation Complete

APL - Alliance Pipeline Owned by Enbridge (Pembina)

Pipeline Alliance Pipeline is located in Saratoga Township. If they cross US 6, there may be rolling restrictions when compacting the asphalt.

Project is a design overlay. No conflicts are anticipated.

AT&T Distribution

Distribution AT&T may have facilities throughout the project area.

Project is a design overlay. No conflicts are anticipated.

AT&T (Transmission) Transmission AT&T transmission may have facilities in Aux Sable Township.

anticipated.

Comcast 688 Industrial Drive Elmhurst, Illinois 60126

Cable Comcast may have the project area.

Project is a design overlay. No conflicts are anticipated.

ComEd Three Lincoln Centre Suite 600 Oakbrook Terrace, IL 60181

Electric ComEd appears to have electric facilities throughout the project area.

Project is a design overlay. No conflicts are anticipated.

Enterprise Products 6005 East Rte. 6 Morris, IL 60450

10” Pipeline Enterprise Products pipeline crosses US 6 approximately 0.7 mile east of Gun Club Road (or approx.

176’ west of the Electric substation entrance).

There may be rolling restrictions when compacting the asphalt.

Section (G)RS-6 & (F)RS-3

Grundy County Highway Morris, IL

Public works No response from the County at this time.

Project is a design overlay. No conflicts are anticipated.

IL American Water 1000 International Parkway Woodridge, IL 60517

Water IL American Water may have facilities in Morris and Saratoga Township.

anticipated.

Midwest Fiber Networks 6700 N. Flint Road Glendale, WI 53209

Fiber Midwest Fiber Networks may have facilities in the Morris portion of the project area.

Project is a design overlay. No conflicts are anticipated.

Morris, City of 700 N Division St Morris, IL 60450

Public works The City of Morris may have water and sewer throughout most of the project.

Project is a design overlay. No conflicts are anticipated.

Nicor 1844 Ferry Rd.

Naperville, IL 60563

Nicor Ref: SC26153

Gas Nicor may have the project area.

Early research shows a 4” gas line on the north side US 6 and a 2” gas line crosses Route 6 on the west of Ashley Road.

anticipated.

Oneok Illinois

Pipeline Oneok crosses US 6 approximately 0.7 mile east of Gun Club Road (or approx.

176’ west of the Electric substation entrance). There may be rolling restrictions when compacting the asphalt.

There may also be another Oneok pipeline in the project area.

Section (G)RS-6 & (F)RS-3

Vistra Kendell Energy 1401 County Line Rd Minooka, IL 60447

Gas/electric Vistra appears on a JULIE Design Ticket in Aux Sable Township. However, they are east of the project limits.

No conflicts.

The above represents the best information of the Department and is only included for the convenience of the bidder. The applicable provisions of Section 102 and Articles 105.07, 107.20, 107.37, 107.38, 107.39, 107.40, and 108.02 of the Standard Specifications for Road and Bridge Construction shall apply.

Above utility relocation information reflected as of March 12, 2026.

FURNISHED EXCAVATION (SPECIAL)

(Effective July 1, 1990; Revised October 11, 2024)

This work shall consist of excavating, hauling, and placing suitable materials obtained from locations approved by the Engineer from outside the limits of the right of way.

The final surface of all embankment areas shall be seeded. The top 4 in. of the seeded areas shall be vegetation sustaining soil subject to the approval of the Engineer. The cost of shaping the slopes and providing vegetation sustaining soil will not be paid for separately but shall be included in the cost of FURNISHED EXCAVATION (SPECIAL).

Method of Measurement. Furnished excavation will be measured per cubic yard and shall be measured by truck volume methods at the point of unloading. The Engineer and the Contractor shall agree upon the volume of each truck before hauling begins.

Basis of Payment. This work will be paid for at the contract unit price per cubic yard for

FURNISHED EXCAVATION (SPECIAL).

AGGREGATE SURFACE COURSE, TYPE B

(Effective January 1, 2007)

Add the following to Article 402.07 of the Standard Specifications:

The top layer shall be given a final rolling with a roller meeting the requirements of Article 1101.01.

VIBRATORY ROLLER RESTRICTION

(Effective: November 26, 2013)

The use of vibratory rollers in dynamic mode shall not be allowed on bridge decks and in urban areas that may include aging infrastructure under the roadway. These locations will be determined in the field by the Engineer.

The restriction of dynamic vibratory rollers in these areas shall not waive density requirements.

Section (G)RS-6 & (F)RS-3

DRAINAGE MITIGATION ON MILLING AND RESURFACING PROJECTS

(Effective January 1, 2022)

Milling operations on this project have the potential to cause water encroachment on the travel lanes during and after a rainfall event. The Contractor shall schedule the milling and resurfacing operations to minimize the potential for the encroachment. The Contractor shall be responsible for mitigating any encroachments as directed by the Engineer. Mitigation may include, but not be limited to, constructing lateral ditches through shoulders and modifying then repairing curb inlets to provide drainage.

The work associated with drainage mitigation will be included in the cost of the Hot-Mix Asphalt Surface Removal pay item.

SURFACE COURSE PAVING SEQUENCE

(Effective July 1, 1990; Revised January 1, 2007) The HMA surface course shall be placed in a sequence that will minimize the time the centerline edge is exposed to traffic. When at the end of a day's operations the exposed centerline edge is greater than 1000 ft., the contractor will be required to pave in the adjacent lane on the following workday.

CROSSING STRUCTURES WITH MATERIAL TRANSFER DEVICE

(Effective May 23, 2001; Revised January 1, 2025)

The Bureau of Bridges and Structures has analyzed the existing structures within the specified construction zone. Based on this analysis, an emptied Material Transfer Device with the identified maximum gross weight restrictions shown for each structure, will be allowed to cross the following structures:

032-0025 (40 tons) 032-0075 (40 tons) 032-2531 (40 tons) 032-2551 (40 tons)

If the same Material Transfer Device is used throughout the entire project, it shall be limited to an empty gross weight based on the smallest weight identified in the list above.

TACK COAT

(Effective December 10, 2025)

Replace the application rate table in Article 406.05 (c)(1) of the Standard Specifications with the following:

Type of Surface to be Tacked Residual Asphalt Rate lb./sq ft Concrete, Existing HMA, and Milled HMA .05 New HMA and Brick .05

Section (G)RS-6 & (F)RS-3

FURNISH PERMANENT SURVEY MARKERS

(Effective May 28, 2025)

Description. Survey markers shall be in general accordance with Highway Standard 667101;

except they shall be bronze instead of aluminum and shall have a diameter of 3.5 inches. They shall be stamped “SECTION CORNER” as a circular row of text inside the words “ILLINOIS DEPARTMENT OF TRANSPORTATION” and shall have a “+” stamped in the center instead of a dimpled triangle.

The Engineer will supply a Professional Land Surveyor and equipment for installation of the survey markers. The Contractor shall supply traffic control for installation of the survey markers by the Engineer.

Basis of Payment. This work will be paid for at the contract unit price per each for FURNISH

PERMANENT SURVEY MARKERS.

LINEAR DELINEATOR PANELS, 6 INCH

(Effective April 28, 2017)

Description. Linear delineator panels shall be placed on each parapet wall 6 inches down from the top. Panels shall also be placed on structures containing bridge rail as directed by the Engineer. These panels shall be either white or yellow, matching the color of the adjacent pavement marking edge line. They should be spaced at a minimum of 80 foot centers horizontally, with the first and last panel located within 20 feet of the parapet wall ends. Structures that contain existing linear delineator panels shall have any damaged or missing panels removed and replaced as directed by the Engineer.

When attaching linear delineator panels to concrete, the panels shall be secured using an anchor bolt method approved by the Engineer that will anchor the entire panel securely but also facilitate removal of the panel by maintenance operations if damaged or weathered in the future. The Contractor shall also sufficiently cover the back side of the linear delineator panel, to the satisfaction of the Engineer, with an adhesive caulking system to aid in the permanent adhesion and alignment of the panels prior to drilling through the pre-drilled linear delineation system holes.

When securing the linear delineator panels to metal bridge rail or any other metal surfaces, the Contractor may use a linear delineation system panel and bracket mounting method approved by the Engineer. The Contractor may also use an adhesive caulking method to sufficiently cover the back side of the linear delineator panel to the satisfaction of the Engineer. The Contractor shall be responsible for testing the durability and strength of the method used to ensure permanent adhesion of the linear delineator panel to the bridge rail. Drilling into metal bridge rail or other metal surfaces to secure the linear delineator panels will not be permitted.

When removing and replacing missing or damaged linear delineator panels, the existing linear delineator panels and any adhesive used to secure the existing linear delineator panels shall be removed to the satisfaction of the Engineer. All cost and labor associated with the removal and cleanup of the existing linear delineator panels shall be included in the unit price of the pay item

LINEAR DELINEATOR PANELS, 6 INCH.

Section (G)RS-6 & (F)RS-3

Each panel shall not be less than 34 inches in length and 6.00 inches in width. The panels shall be constructed of cube-corner retroreflective material in standard highway colors permanently bonded to an aluminum substrate. The lateral edges of each panel shall be hemmed. The panel assembly shall have a repeating raised lateral ridge every 2.25 inches. Each ridge shall be 0.34 inches high with a 45° profile and a 0.28 inch radius top.

Daytime color requirements shall be determined from measurement of the retroreflective sheeting applied to aluminum test panels. Daytime color shall be measured instrumentally using a spectrophotometer employing annular 45/0 (or equivalent 0/45) illuminating and viewing geometry. Measurements shall be made in accordance with ASTM E1164 for ordinary colors or ASTM E2153 for fluorescent colors. Chromaticity coordinates shall be calculated for CIE Illuminant D65 and the CIE 1931 (2o) Standard Colorimetric Observer in accordance with ASTM E308 for ordinary colors or ASTM E2152 for fluorescent colors.

Chromaticity Limits for White x y x y X y x y Limit Y (%) Min Max

White 0.303 0.287 0.368 0.353 0.340 0.380 0.274 0.316 40 - Chromaticity Limits for Fluorescent Yellow

Total

Luminance x Y x Y X y x y Factor YT (%) Min

Fluor.

Yellow 0.521 0.424 0.557 0.442 0.479 0.520 0.454 0.491 40

Inspection of Linear Delineator Panels. The linear delineator panels installed under this contract will be inspected following installation, but no later than December 30th. In addition, they will be inspected following a winter performance period that extends 180 days from December 30th.

Within 15 calendar days after the end of the winter performance period, a final performance inspection will be made. If this inspection discloses any work which is not visibly intact and serviceable, the Contractor shall, within 30 calendar days, completely repair or replace such work to the satisfaction of the Engineer.

Measured in its entirety, the work shall be 97 percent intact.

Upon completion of the final performance inspection, or after satisfactory completion of any necessary corrections, the Engineer shall notify the Contractor in writing of the date of such final performance inspection and release him/her from further performance responsibility.

This delay in performance inspection and performance acceptance of the linear delineator panels shall not delay acceptance of the entire project and final payment due if the contractor requires and receives from the subcontractor a third party “performance” bond naming the Department as obligee in the full amount of all linear delineator panels listed in the contract, multiplied by the

Section (G)RS-6 & (F)RS-3 contract unit price. The bond shall be executed prior to acceptance and final payment of the non-linear delineator panel items and shall be in full force and effect until final performance inspection and performance acceptance of the linear delineator panels. Execution of the third party bond shall be the option of the Contractor.

Basis of Payment. This work, including all materials, equipment, and labor necessary to complete the work as described will be paid for at the contract unit price per each for LINEAR DELINEATOR

PANELS, 6 INCH.

LINEAR DELINEATOR PANELS, 4 INCH

(Effective January 1, 2022)

Description. This work shall consist of furnishing and installing linear delineators on steel plate beam guardrail at locations shown on plan details.

CONSTRUCTION REQUIREMENTS

General. Linear delineator panels shall be attached to steel plate beam guardrail as shown on plan details and as directed by the Engineer. These panels shall be either white or yellow, matching the color of the adjacent pavement marking edge line. They should be spaced at a minimum of 80-foot centers horizontally, with a minimum of two linear delineator per guardrail run.

Linear delineators shall not be place on guardrail terminal sections. Linear delineator spacing through horizontal curves where the normal speed limit is reduced, the spacing of the linear delineators shall be reduced to 40-foot centers. Existing steel plate beam guardrail that contain existing linear delineator panels shall have any damaged or missing panels removed and replaced as directed by the Engineer.

When securing the linear delineator panels to steel plate beam guardrail, the Contractor may use a linear delineation system panel and bracket mounting method approved by the Engineer. Linear delineation system panel and bracket including installation methods shall be according to the manufacture’s recommendations.

The Contractor shall be responsible for testing the durability and strength of the method used to ensure permanent adhesion of the linear delineator panel to the bridge rail. Drilling into metal bridge rail or other metal surfaces to secure the linear delineator panels will not be permitted.

When removing and replacing missing or damaged linear delineator panels, the existing linear delineator panels and any adhesive or bracket when used to secure the existing linear delineator panels shall be removed to the satisfaction of the Engineer. All cost and labor associated with the removal and cleanup of the existing linear delineator panels shall not be paid for separately but shall be included in the cost of this work.

Each panel shall not be less than 34 inches in length and 4.00 inches in width. The panels shall be constructed of cube-corner retroreflective material in standard highway colors permanently bonded to an aluminum substrate. The lateral edges of each panel shall be hemmed. The panel assembly shall have a repeating raised lateral ridge every 2.25 inches. Each ridge shall be 0.34 inches high with a 45° profile and a 0.28-inch radius top.

Daytime color requirements shall be determined from measurement of the retroreflective sheeting applied to aluminum test panels. Daytime color shall be measured instrumentally using a

Section (G)RS-6 & (F)RS-3 spectrophotometer employing annular 45/0 (or equivalent 0/45) illuminating and viewing geometry. Measurements shall be made in accordance with ASTM E1164 for ordinary colors or ASTM E2153 for fluorescent colors. Chromaticity coordinates shall be calculated for CIE Illuminant D65 and the CIE 1931 (2o) Standard Colorimetric Observer in accordance with ASTM E308 for ordinary colors or ASTM E2152 for fluorescent colors.

Chromaticity Limits for White x y x y X y x y Limit Y (%) Min Max

White 0.303 0.287 0.368 0.353 0.340 0.380 0.274 0.316 40 -

Chromaticity Limits for Fluorescent Yellow

Total

Luminance x Y x Y X y x y Factor YT (%) Min

Fluor.

Yellow 0.521 0.424 0.557 0.442 0.479 0.520 0.454 0.491 40

Inspection of Linear Delineator Panels. The linear delineator panels installed under this contract will be inspected following installation. In addition, they will be inspected following a winter performance period that extends 180 days from December 30th.

Within 15 calendar days after the end of the winter performance period, a final performance inspection will be made. If this inspection discloses any work which is not visibly intact and serviceable, the Contractor shall, within 30 calendar days, completely repair or replace such work to the satisfaction of the Engineer.

Measured in its entirety, the work shall be 97 percent intact.

Upon completion of the final performance inspection, or after satisfactory completion of any necessary corrections, the Engineer shall notify the Contractor in writing of the date of such final performance inspection and release him/her from further performance responsibility.

This delay in performance inspection and performance acceptance of the linear delineator panels shall not delay acceptance of the entire project and final payment due if the contractor requires and receives from the subcontractor a third party “performance” bond naming the Department as obligee in the full amount of all linear delineator panels listed in the contract, multiplied by the contract unit price. The bond shall be executed prior to acceptance and final payment of the non-linear delineator panel items and shall be in full force and effect until final performance inspection and performance acceptance of the linear delineator panels. Execution of the third-party bond shall be the option of the Contractor.

Basis of Payment. This work, including all materials, equipment, and labor necessary to complete the work as described will be paid for at the contract unit price per each for LINEAR DELINEATOR

PANELS, 4 INCH.

Section (G)RS-6 & (F)RS-3

MODIFIED URETHANE PAVEMENT MARKING – TWO APPLICATIONS

(Effective March 30, 2023)

Description. This work consists of furnishing and applying modified urethane pavement marking according to Section 780 of the Standard Specifications except that the modified urethane shall be applied in two applications.

Materials. Each application shall meet the requirements of Article 780.12 of the Standard Specifications.

CONSTRUCTION REQUIREMENTS

General. The first application shall be allowed to cure for a minimum of 14 days prior to placing the second application over the first. The Contractor shall not place one thick application in lieu of two regular applications.

Basis of Payment. Each application will be measured and paid for.

TEMPORARY INFORMATION SIGNING

(Effective September 24, 2013; Revised July 31, 2020)

Description. This work shall consist of the furnishing, installation, maintenance, and removal of temporary information signs.

Materials. Materials shall be according to the applicable portions of Section 701 of the Standard Specifications and as shown on the plans.

Construction Requirements. The temporary information signs shall be in place at least one week prior to the beginning of construction activities that impact traffic flow and shall remain in place until the completion of the project. If all lanes are open for an extended period of time during the project, the Contractor shall cover the signs until lane closures resume. If the project is shut down for the winter, the signs shall read “Road Work Resumes Spring XXXX.”

Signs shall be installed according to the requirements of Section 701.

Method of Measurement. This work will be measured for payment in square feet in place. The auxiliary sign panel will not be measured for payment.

Basis of Payment. This work will be paid for at the contract unit price per square foot for

TEMPORARY INFORMATION SIGNING.

Section (G)RS-6 & (F)RS-3

NIGHTTIME WORK AND KEEPING ROADS OPEN TO TRAFFIC

All work on US 6 from Mission Parkway to IL 47, shall be performed during nighttime hours defined as 7:00 p.m. – 7:00 a.m.

At all other times, including daytime hours and legal holidays defined in Article 107.09 of the Standard Specifications, all lanes of US 6 shall remain open to traffic.

When a legal holiday restricts lane closures to 11:59 p.m., the beginning of the nighttime hours shall move from 7:00 p.m. to 11:59 p.m. for the effected day.

This work will not be paid for separately but shall be included in the cost of the applicable traffic control items.

TRAFFIC SIGNAL BACKPLATE, LOUVERED, FORMED PLASTIC, SPECIAL

This item consists of furnishing and installing a LOUVERED, FORMED PLASTIC TRAFFIC SIGNAL BACKPLATE as specified herein and all hardware accessories required to install on all proposed signal heads as described in Article 882 and 883.

The vacuum formed ABS plastic backplate shall have a nominal ½ inch deep back flange on all inside and outside edges. The backplate shall be louvered and provide openings (louvers) to all wind to penetrate and reduce wind loading. The louver openings shall cover a minimum of 20 percent of the surface area of the backplate. The entire front and side surface of the backplate including louver shall be manufactured so that it is imprinted with fluorescent yellow sheeting. The sheeting shall be Type AZ sheeting according to Article 1091.03 and applied to the preferred orientation for the maximum angularity according to the manufacture’s recommendation.

Basis of Payment. This item shall be paid for at the contract unit price each for TRAFFIC SIGNAL

BACKPLATE, LOUVERED, FORMED PLASTIC, SPECIAL.

LOOP DETECTOR TESTING

(Effective December 1, 1999; Revised January 1, 2007)

The Contractor is advised of the presence of existing detector loops which shall be retained in the completed signal installation. The condition of each existing loop detector which will be retained shall be documented.

The required loop detector testing shall consist of measuring the following electrical characteristics of each loop within the intersection to determine if the loop meets the indicated criteria:

1. Loop Inductance. Stable frequency (frequency varies by less than +/-3 hertz) and minimum

50 microhenries when driven by amplifier.

For any loop that does not show a stable frequency, the Contractor shall determine if the unstable frequency is due to equipment malfunctions in the cabinet or outside the cabinet.

The Contractor shall notify the Engineer of the source of the unstable frequency. Any problem due to existing equipment problems in the cabinet shall be repaired by city maintenance. Any

Section (G)RS-6 & (F)RS-3 problem caused by the required construction work shall be repaired and paid for separately on this contract.

Any loop that does not exceed 50 microhenries inductance shall be replaced.

2. Loop Resistance to Ground. Minimum 50 megohms.

For any loop circuit with less than 50 megohms resistance to ground or any loop that is being replaced, the Contractor shall break the loop to lead-in splice and measure the resistance to ground of the detector loop alone and each leg of the detector loop lead-in cable. If a single leg of the lead-in cable has a low resistance to ground, the Contractor shall replace the lead-in cable. If the detector loop, separated from the lead-in cable, passes the required tests, the loop shall not be replaced.

3. Loop Circuit Resistance. Maximum 3 ohms for lead-in less than 200 feet. Maximum 5 ohms for lead-in greater than 200 feet.

For any loop circuit with resistance greater than stated above, the splice shall be opened and the loop and each leg of the lead-in cable shall be tested. If the detector loop cable is the cause of the high resistance reading, the detector loop shall be replaced. If the lead-in cable is the cause of the high resistance reading, the lead-in cable shall be replaced.

The Contractor shall furnish a Decatur Electronics Loop Tester, Model DLT-150, or superior, to measure the loop resistance above ground, and quality factor of each loop. This unit shall remain the property of the Contractor.

The measurements shall be recorded for each loop circuit, including lead-in cable, following completion of the work, in the presence of the Engineer. The measurements shall be taken at the controller cabinet.

Any damaged detector loop or lead-in cable shall be replaced.

If an existing detector loop is damaged due to construction operations, the Contractor shall notify the Department at 815-434-8505 to modify the signal program until the detector loop can be replaced. The Contractor shall replace the loop as soon as possible.

Loop detector testing will be performed at each loop detector circuit following completion of work likely to damage the existing loops. The lead-in cable must be disconnected from the detector loop panel in the cabinet to prevent damage to the inductive loop detector. When the Contractor has made all necessary repairs, the Department’s Traffic Signal Section shall be contacted to meet with the Contractor at the intersection to confirm the satisfactory readings.

Method of Measurement. This work will be measured for payment per intersection, regardless of the number of tests required. Any work required to replace any splices broken for testing of the lead-in cable and detector loop shall be included in the cost of this pay item.

Basis of Payment. This work will be paid for at the contract unit price per each intersection as

LOOP DETECTOR TESTING.

Section (G)RS-6 & (F)RS-3

REMOVE AND RELAY PIPE CULVERTS (SPECIAL)

Description. This work shall consist of removing and relaying existing precast reinforced concrete pipe culvert at locations shown on plan details.

Materials. Materials shall be according to the following.

Item Article/Section

(a) Precast Reinforced Concrete Pipe Culvert………………………….…………..1042.03(c)(d)(e)

(b) Mastic Joint Sealer for Pipe………………………………………….…………………………1055

(c) External Sealing Band……………………………………………….………………………….1057

(d) Fine Aggregate……………………………………………………………………………….1003.04

Equipment. Equipment shall be at the approval of the Engineer.

CONSTRUCTION RE QUIREMENTS

General. This work shall be according to applicable portions of Sections 542 of the Standard Specifications and as modified herein.

Excavation. Locations where pipe culvert removal and relaying are designated in the plans, the locations shall be excavated to expose the existing pipe culvert and the excavated material shall be stockpiled to be reincorporated into the new construction. If the Engineer determines that the excavated materials are unsuitable for reuse, the excavated materials shall be disposed of at the direction of the Engineer and replaced with approved material. Furnishing and incorporating new embankment material will be paid for according to Article 109.04 of the Standard Specifications.

Removal. Removal shall consist of the following procedures.

a) Remove existing pipe culvert and store in a location designated by the Engineer so damage does not occur to the pipe(s).

1) In the event the pipe culvert is damaged by the Contractor’s removal operations, the pipe culvert shall be “Replaced” at the Contractor’s expense.

2) If the Engineer determines that the existing pipe culvert is unsuitable for reuse, the pipe culvert shall be replaced at the direction of the Engineer. Cost for furnishing a new pipe culvert shall be paid for according to Article 109.04 of the Standard Specifications.

3) Relaying Pipe Culvert. Relaying existing pipe culvert shall be as follows.

a) Install the pipe culvert on a prepared subbase to match the existing flowline elevation.

1) When necessary, the existing location(s) for the pipe culvert installation shall be excavated a minimum of 4” below the existing flowline elevation. Excavated materials shall be reused and incorporated into the new construction.

2) Prepared subbase shall be a minimum of 4” and compacted to the satisfaction of the Engineer.

Section (G)RS-6 & (F)RS-3

Method of Measurement. This work will be measured for payment as follows.

a) Contract Quantities. The requirements for the use of contract quantities shall conform to Article 202.07(a).

b) Measured Quantities. This work will be measured for payment per foot of pipe culvert removed and relayed.

Necessary excavations and Subbase material when required shall not be paid for separately but shall be included in the cost of the related work.

Basis of Payment. This work will be paid for at the contract unit price per each for REMOVE AND RELAY PIPE CULVERTS, SPECIAL which price shall be payment in full to complete this work.

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

Description. This work shall consist of the removal and disposal of regulated substances according to Section 669 of the Standard Specifications as revised below.

Contract Specific Work Areas. For stationing, the lateral distance is measured from centerline and the farthest distance is the offset distance or construction limit, whichever is less.

The following contract specific work areas shall be monitored by the Environmental Firm for soil contamination and workers protection.

Site 4791-3 – Vacant Land, 100 block of E. US 6, Morris, Grundy County

• Station 3+00 (LT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters: VOCs, SVOCs, and Metals.

Site 4791-5 – Chase Bank, 1925 N. Division Street, Morris, Grundy County

• Station 1+00 to Station 2+75 (RT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters: VOCs, SVOCs, and Metals.

Site 4791-8 – Walmart, 333 E. US 6, Morris, Grundy County

• Station 10+50 to Station 11+50 (RT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters: VOCs, SVOCs, and Metals.

Site 4791-9 – WashCove Car Wash, 366 E. US 6, Morris, Grundy County

• Station 11+00 (LT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(1). Contaminants of concern sampling parameters: VOCs, SVOCs, and Metals.

Site 4791-11 – Aldi, 355 E. US 6, Morris, Grundy County

• Station 22+35 (RT). The Engineer has determined this material meets the criteria of and shall

Section (G)RS-6 & (F)RS-3

Site 4791-14 – Evergreen Plaza, 425 E. US 6, Morris, Grundy County

• Station 37+20 (RT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling

Site 4791-19 – Gene Funk’s Morris Trailer Sales, 802 E. US 6, unincorporated Saratoga Township, Grundy County

• Station 62+68 (LT). The Engineer has determined this material meets the criteria of and shall

Site 4791-41 – Love’s Travel Stop, 8909 Brisbin Road, Morris, Grundy County

• Station 192+65 (RT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters: VOCs, SVOCs, and Metals.

• Station 202+25 (RT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling parameters: VOCs, SVOCs, and Metals.

• Station 202+80 (RT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling

Site 4791-50 – Lyondell Basell Employee Park, 9331 N. Tabler Road, unincorporated Aux Sable Township, Grundy County

• Station 290+00 (LT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling

Site 4791-55 – Lyondell Basell MIO Complex, 8805 N. Tabler Road, unincorporated Aux Sable Township, Grundy County

• Station 281+46 (RT). The Engineer has determined this material meets the criteria of and shall be managed in accordance with Article 669.05(a)(5). Contaminants of concern sampling

Work Zones Three distinct OSHA HAZWOPER work zones (exclusion, decontamination, and support) shall apply to projects adjacent to or within sites with documented leaking underground storage tank (LUST) incidents, or sites under management in accordance with the requirements of the Site Remediation Program (SRP), Resource Conservation and Recovery Act (RCRA), or Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), or as deemed necessary. For this project, the work zones apply for the following ISGS PESA Sites:

None.

Additional information on the contract specific work areas listed above collected during the regulated substances due-diligence process is available through the District’s Environmental Studies Unit (DESU).

Section (G)RS-6 & (F)RS-3

Any waste generated as a special waste or a waste not certified as a non-special waste from this project should be manifested off-site using the IEPA Bureau of Land generator number associated IDOT right-of-way in the affected county. The IEPA generator number for IDOT right-of-way in Grundy County is 0638995002.

CLEAN EXISTING END SECTIONS

This work shall consist of furnishing all labor, material and equipment to remove earth or silt and other debris from the existing end sections of drainage structures at the locations shown in the plans as directed by the Engineer.

The work shall include cleaning the existing end section of debris, sedimentation, trash, or other obstructions that interfere with the effective flow of water through the pipe. Cleaning the existing end section shall be to the satisfaction of the Engineer.

The materials removed shall be disposed of in accordance with the applicable portions of Article

202.03 of the Standard Specifications. When specified in the plans, earthen material or silt from cleaning operations shall remain within project limits.

Cleaning the existing end sections will be measured and paid for at the contract unit price per each for CLEAN EXISTING END SECTION.

CLEANING EXISTING INLETS

Description. This work shall consist of the removal of all debris, including but not limited to fallen trees, and sediment/earth accumulated at the entrance of the culverts or excavation needed to reshape the channel, at locations scheduled in the plans. The contractor shall be responsible for hauling all debris off-site and cleaning the road upon completion prior to opening lanes to traffic.

Special attention shall be given to overhead wires and other utility installations during this project.

Basis of Payment. This work shall be paid at the contract unit price per EACH for CLEANING

EXISTING INLETS.

CONCRETE CURB REPAIR

This work consists of the removal and repair of the existing concrete curb as shown in the plans, in accordance with Sections 440 and 606 of the Standard Specifications for Road and Bridge Construction and as directed by the Engineer.

Existing concrete curb to be repaired under this pay item is broken or otherwise damaged. The replacement curb should match the original configuration / cross section.

This work shall be paid for at the contract unit price per foot for CONCRETE CURB REPAIR, which shall include all removal, disposal, equipment, labor and material required to complete the work.

Section (G)RS-6 & (F)RS-3

EXISTING FIELD TILE REMOVAL

Description. This work consists of the removal and satisfactory disposal of existing field tiles in accordance with the applicable portions of Section 501and 611 of the Standard Specifications and as directed by the Engineer.

The quantities listed in the Schedule of Quantities are for the purpose of obtaining a unit price and may be increased or decreased as deemed necessary by the Engineer. Any and all changes in quantities shall be made at the contract unit price.

Basis of Payment. This work will be paid for at the contract unit price per FOOT for EXISTING FIELD TILE REMOVAL, which price shall include all labor, equipment and materials necessary to complete the work.

REMOVE AND RELAY END SECTIONS

Description. This work shall consist of removing and relaying existing precast reinforced concrete flared end sections at locations shown in the plans.

Materials. Materials shall be according to the following.

(a) Precast Reinforced Concrete End Block…………………………….…………..1042.03(c)(d)(e)

(b) Mastic Joint Sealer for Pipe………………………………………….…………………………1055

(c) External Sealing Band……………………………………………….………………………….1057

(d) Fine Aggregate……………………………………………………………………………….1003.04

Equipment. Equipment shall be at the approval of the Engineer.

CONSTRUCTION RE QUIREMENTS

General. This work shall be according to applicable portions of Section 542.07(b)(1) of the Standard Specifications and as modified herein.

Excavation. Locations where end section removal and relaying are designated in the plans, the locations shall be excavated to expose the existing concrete end sections and the excavated material shall be stockpiled to be reincorporated into the new construction. If the Engineer determines that the excavated materials are unsuitable for reuse, the excavated materials shall be disposed of at the direction of the Engineer and replaced with approved material. Furnishing and incorporating new embankment material will be paid for according to Article 109.04 of the Standard Specifications.

Removal. Removal shall consist of the following procedures.

b) Remove existing precast reinforced concrete flared end section(s) and store in a location designated by the Engineer so damage does not occur to the end section.

4) In the event the precast reinforced concrete flared end section is damaged by the

Contractor’s removal operations, the precast reinforced concrete flared end section shall be “Replaced” at the Contractor’s expense.

Section (G)RS-6 & (F)RS-3

5) If the Engineer determines that the existing precast reinforced concrete flared end section is unsuitable for reuse, the precast reinforced concrete flared end section shall be replaced at the direction of the Engineer. Cost for furnishing a new precast reinforced concrete flared end section shall be paid for according to Article 109.04 of the Standard Specifications.

c) Remove the existing end block (precast toe wall). There will be no salvage to the existing end block.

Relaying End Section. Relaying existing precast reinforced concrete flared end section(s) shall be as follows.

b) Install the new end block (precast toe wall) on a prepared subbase to match the existing flowline elevation of the existing precast reinforced concrete flared end section.

3) When necessary, the existing location(s) for the end block installation shall be excavated a minimum of 4” below the existing flowline elevation of the existing precast reinforced concrete flared end section. Excavated materials shall be reused and incorporated into the new construction.

4) Prepared subbase shall be a minimum of 4” and compacted to the satisfaction of the Engineer.

5) The new end block (precast toe wall) shall be according to the requirements of

Standard 542301. The end block when installed and shall be leveled and plumbed.

The Engineer shall approve of the end block installation prior to relaying the existing precast reinforced concrete flared end section.

c) Relay existing precast reinforced concrete flared end section according to applicable portions of Section 542 of the Standard Specifications to match existing flowline elevation(s).

Method of Measurement. This work will be measured for payment as follows.

c) Contract Quantities. The requirements for the use of contract quantities shall conform to Article 202.07(a).

d) Measured Quantities. This work will be measured for payment per each end section removed and relayed.

Necessary excavations and Subbase material when required shall not be paid for separately but shall be included in the cost of the related work.

Basis of Payment. This work will be paid for at the contract unit price per each for REMOVE AND RELAY END SECTIONS which price shall be payment in full to complete this work.

Section (G)RS-6 & (F)RS-3

AUTOMATED FLAGGER ASSISTANCE DEVICES (BDE)

Effective: January 1, 2008 Revised: April 1, 2023

Description. This work shall consist of furnishing and operating automated flagger assistance devices (AFADs) as part of the work zone traffic control and protection for two-lane highways where…