IDOT 64L94-045.pdf

PDF 9 MB Posted

Attached to
Reconstruction on IL 81 from 0. 2 miles West of Union St to 0. 3 miles West of IL 78 in Kewanee - Henry County
Solicitation number
64L94
Issued by
Henry County, Illinois

About this file

Project Overview and Bidding Information

This is a Notice to Bidders and Special Provisions document issued by the Illinois Department of Transportation (IDOT) for Contract No. 64L94, a road reconstruction project in Henry County. The project involves the complete removal and replacement of Illinois Route 81 (IL 81/W. 6th Street) spanning 0.91 miles from 0.2 miles west of Union Street to 0.3 miles west of IL 78 in Kewanee. The scope of work includes pavement reconstruction, multi-use path installation, sidewalk and curb-and-gutter work, storm sewer installation, utility adjustments, driveway reconstruction, embankment work, guardrail installation, tree removal, striping, and ADA improvements. Additional work includes temporary traffic signal installation and pavement reconstruction and widening at IL 78 and County Highway 28 (Sale Barn Rd) to facilitate a proposed detour route. Electronic bids must be submitted to the iCX-Integrated Contractors Exchange system prior to 12:00 p.m. on June 12, 2026, when bids will be publicly opened. The contract specifies an interim completion date of November 26, 2026, for potential 2026 work items, with final project completion by 11:59 p.m. on November 24, 2027, plus 15 additional working days allowed for cleanup and punch list items.

Funding, Requirements, and Special Conditions

The project is funded through Federal-aid sources (FAP Route 611, Project STP-9NIE(950)), requiring compliance with both State and Federal law regarding bidder certifications, subletting restrictions, equal employment opportunity provisions, and prevailing wage requirements. The contract will be awarded to the lowest responsive and responsible bidder, with the Department reserving the right to determine responsibility, reject any or all proposals, and re-advertise if necessary. Special provisions address numerous construction requirements including traffic control and road closure procedures with mandatory detour signage, maintenance of local traffic with staged sidewalk work, temporary traffic signal installation and timing by approved consultants, removal and disposal of regulated substances at multiple ISGS sites with documented contamination, and critical path scheduling using CPM methodology with monthly updates. The project requires establishment of a Pedestrian Access Route with directional signage and assignment of onsite personnel to assist disabled pedestrians. Additional requirements include compliance with storm sewer specifications (including water main quality pipe and rubber gasket joints), geotechnical reinforcement, form liner textured surface treatments for retaining structures, and comprehensive work zone traffic control measures subject to monetary deductions ($1,000 per incident) for failure to maintain signal operations or respond to emergency repairs within specified timeframes.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting June 12, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 64L94 HENRY County Section 104R Route FAP 611 Project STP-9NIE(950) District 2 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

June 12, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 64L94 HENRY County Section 104R Project STP-9NIE(950) Route FAP 611 District 2 Construction Funds

0.91 miles of reconstruction on IL 81 from 0.2 miles west of Union St to 0.3 miles west of IL 78 in Kewanee. This includes ADA improvements.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

FAP Route 611 (IL 81)

Section 104R Henry County

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

Section 104R

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 X Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 X Station Numbers in Pavements or Overlays

Section 104R i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

TRAFFIC CONTROL PLAN

COMPLETION DATE PLUS WORKING DAYS

INTERIM COMPLETION DATE

GRANULAR BACKFILL FOR STRUCTURES

GUARDRAIL REMOVAL

MOWING

TEMPORARY PAVEMENT

GEOTECHNICAL REINFORCEMENT

POROUS GRANULAR EMBANKMENT, SPECIAL

PCC AUTOMATIC BATCHING EQUIPMENT

PCC QC/QA ELECTRONIC REPORTS SUBMITTAL

CRITICAL PATH SCHEDULE – TYPE B

ROCK FILL

STORM SEWER WATER MAIN REQUIREMENT

CONSTRUCTION REQUIREMENTS

STORM SEWER, RUBBER GASKET

WORK ZONE PAVEMENT MARKING AND REMOVAL

JOINT TRIMMING

AVAILABILITY OF ELECTRONIC FILES

3D MODEL – CONTRACTOR SUPPLIED

AGGREGATE SHOULDERS SPECIAL, TYPE C

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES

SPECIAL WASTE DISPOSAL

SOIL DISPOSAL ANALYSIS

REGULATED SUBSTANCES PRE-CONSTRUCTION PLAN

REGULATED SUBSTANCES FINAL CONSTRUCTION REPORT

TEMPORARY TRAFFIC SIGNAL INSTALLATION

TEMPORARY TRAFFIC SIGNAL TIMING

RETAINING WALL REMOVAL

FENCE REMOVAL

Section 104R ii

REMOVE CONCRETE END SECTION

REMOVE EXISTING PARKING BLOCKS

REMOVE EXISTING SIGN COMPLETE

REMOVE AND RE-ERECT EXISTING SIGN

CONCRETE STEP REMOVAL

FORM LINER TEXTURED SURFACE

STAINING CONCRETE STRUCTURES

ANTI-GRAFFITI COATING

CHAIN LINK FENCE, 6’ (SPECIAL)

SECTION 404 – NWP #14 (NON-REPORTING)

AGGREGATE SUBGRADE IMPROVEMENT (BDE)

BITUMINOUS MATERIALS COST ADJUSTMENTS (BDE)

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

COMPENSABLE DELAY COSTS (BDE)

EROSION CONTROL BLANKET (BDE)

FUEL COST ADJUSTMENT (BDE)

GUARDRAIL (BDE)

HOT-MIX ASPHALT (BDE)

HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)

PAVEMENT MARKING (BDE)

PAVEMENT PATCHING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SEEDING (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

STEEL COST ADJUSTMENT (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURFACE TESTING OF PAVEMENTS – IRI (BDE)

Section 104R iii

SURVEYING SERVICES (BDE)

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION ...99

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

WOOD SIGN SUPPORT (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

PROJECT LABOR AGREEMENT

SWPPP

Section 104R

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the “Standard Specifications for Road and Bridge Construction, adopted January 1, 2022”, the latest edition of the “Manual on Uniform Traffic Control Devices for Streets and Highways”, and the “Manual of Test Procedures for Materials” in effect on the date of invitation for bids, and the “Supplemental Specifications and Recurring Special Provisions” indicated on the Check Sheet included herein, which apply to and govern the construction of FAP Route 611 (IL 81), Project STP-9NIE(950), Section 104R, Henry County, Contract No. 64L94 and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.

LOCATION OF PROJECT

The project is located along IL 81 (W. 6TH Street) and begins approximately 0.1 miles west of Union Street and ends 0.3 miles west of IL 78.

DESCRIPTION OF PROJECT

This project involves the complete removal and replacement of IL 81, including pavement reconstruction, multi-use path, sidewalk, curb and gutter, storm sewer, utility adjustments, driveways, embankment, guardrail, tree removal and striping. It also includes the installation of temporary traffic signals, pavement reconstruction and widening at IL 78 and County Highway 28 (Sale Barn Rd), for a proposed detour route.

TRAFFIC CONTROL PLAN

Effective: January 14, 1999 Revised: January 13, 2017

Standards:

701001 701006 701011 701101 701201 701301

701311 701326 701336 701501 701801 701901

Details:

District 2 Standard 40.1 – Traffic Control for Road Closure

Section 104R

General:

Where construction activities involve sidewalks on both sides of the street, the work shall be staged so that both sidewalks are not out of service at the same time.

Signs:

“BUMP” (W8-1(O)48) signs shall be installed as directed by the Engineer.

“When covering existing Department signs, no tape shall be used on the reflective portion of the sign. Contact the District sign shop for covering techniques.

Any plates or direct applied sheeting used to alter signs shall have the same sheeting as the base sign.

No more than one kind of alteration shall be used to alter a sign.

Any post stubs without a sign in place and visible shall have a reflector placed on each post.

Devices

A minimum of 3 drums spaced at 4 feet shall be placed at each return when the sideroad is open.

Flaggers:

Flaggers shall comply with all requirements and signaling methods contained in the Department’s “Traffic Control Field Manual” current at the time of letting. The flagger equipment listed for flaggers employed by the Illinois Department of Transportation shall apply to all flaggers.

When the mainline flagger is within 200 feet of an intersection, the sideroad flagger shall be required.

When the road is closed to through traffic and it is necessary to provide access for local traffic, all flaggers as shown on the applicable standards will be required. No reduction in the number of flaggers shall be allowed.

Pavement Markings:

All temporary pavement markings that will be operational during the winter months (December through March) shall be paint.

Highway Standards Application:

Traffic Control for Road Closure: This work shall be done according to the Road Closure Standard and Section 701 of the Standard Specifications and District Standard 40.1 – Traffic Control for Road Closure.

“ROAD CLOSED AHEAD” (W20-3(O)-48) with “_____ MILES” (W16-3A(O)-3612) plate mounted below the sign shall be required at the following locations with the distance noted.

Section 104R

The contractor shall erect these signs at IL 78 (1/4 MILES), E 2480th St (3/4 MILES), E 2350th St (2 MILES), and County Highway 28 (4.5 MILES).

“ROAD CLOSED AHEAD” (W20-3(O)-48) with flasher and the appropriate arrow plate (W1- 6(O)-36x18 or W1-7(O)-36x18) shall be required on all side roads within the limits of the mainline “ROAD CLOSED AHEAD” signs.

The Contractor shall notify the Department via email at DOT.D2.TrafficNotice@illinois.gov.

This request shall be submitted a minimum of three weeks (21 days) and no earlier than four weeks (28 days) prior to the anticipated closure date to allow the State adequate time to re-route oversized loads.

Signing and devices required to close the road, according to the Traffic Control for Road Closure detail and contained herein, shall be the responsibility of the Contractor. Detour signing required to detour traffic to alternate routes shall be the responsibility of the Contractor.

The day the detour signing begins, the detour will be in effect when the Contractor has notified the Resident Engineer or personnel on the project. No detour shall be erected on Friday, Saturday or Sunday. The road shall not be closed until the detour signing is completely installed, verified, and ready to accept traffic.

The “ROAD CLOSED” sign on the Type III barricades shall be unobstructed and visible to traffic at all times. No equipment, debris, or other materials shall be stored within 20 feet of the first set of Type III barricades, unless approved by the Engineer.

The Contractor shall not drive around the outside of the Type III barricades but shall relocate the barricades temporarily for access. When it is necessary for the barricades to be moved for access, the Contractor shall move the devices into the left lane and/or left shoulder area behind barricades that are to remain in place. At no time shall the barricades be turned parallel to traffic flow for access purposes.

If a path becomes evident around the outside of the barricades, the Contractor shall be required to place additional Type III barricades to prevent driving around the existing barricades. Additional barricades shall be included in the cost of applicable Traffic Control Standards.

This work shall be paid for at the contract lump sum price for TRAFFIC CONTROL AND

PROTECTION, (SPECIAL).

Road Closure – Closures within Closures: The road closure shall be completed using Type III barricades in compliance with Standards 701901 and signing according to Traffic Control for Road Closure detail. Two flashers shall be installed above each Type III barricade. The "ROAD CLOSED" (R11-2) or “ROAD CLOSED TO THRU TRAFFIC” (R11-4) signs shall be placed as shown in Standard 701901. Flashers shall be installed above all warning signs involving a nighttime road closure. If a portion of the road is completely closed between a side road and any entrances, the roadway will be kept open to local access in the other direction between that closure and the next road.

The Contractor shall be required to notify the Bureau of Project Implementation and affected residents prior to a complete closure.

Section 104R

All costs involved in conforming with this provision shall be considered a part of TRAFFIC

CONTROL AND PROTECTION, (SPECIAL).

Other Devices:

TEMPORARY SIGNALS: The Contractor will be required to have someone available at all times to receive phone calls during non-work hours and who is able to reach the job site within one hour of being called. This person will be able to repair the temporary signals or will be able to have flaggers on site within another hour to flag traffic until the signals are again in operation.

Failure to have a person on site within an hour after the initial call out will result in the Contractor being charged a monetary deduction by the Department of One Thousand Dollars ($1,000).

Failure to have traffic restored either with repaired signals or with flaggers within two hours after the initial call out will result in the Contractor being charged monetary deduction by the Department of One Thousand Dollars ($1,000) per hour until traffic is restored. The Contractor may use a traffic control subcontractor for the first call; however, this does not relieve the prime Contractor from having a person on call.

Traffic Signal Work: No traffic signal work shall begin until all of the traffic signal hardware is on the job site. The existing traffic signal system shall remain in operation during the modernization work. The work shall be scheduled so that a minimum of two signal indications for each phase remains in operation. No signal indication shall be absent for more than seven calendar days.

The Contractor will be allowed to shut down the existing signal system not to exceed 8 hours to replace the existing controller and cabinet. During this shutdown, the intersection will operate as a 4-way "Stop".

The Contractor shall notify the Henry County Highway Department, the corresponding Township Commissioner, city municipality, emergency response agencies (i.e.: fire, ambulance, police), school bus companies and the Department of Transportation (Bureau of Project Implementation) regarding any changes in traffic control.

The Contractor shall notify the Henry County Highway Department, corresponding Township Commissioner and/or city municipality for any sideroad closure or opening.

The Contractor shall submit a maintenance of local traffic plan to the Engineer at the preconstruction meeting telling how local access will be maintained at each access location. It will show which locations will be completely closed, and which locations will be constructed utilizing Traffic Control Standard 701201 and/or barricades. This traffic plan will need to be approved by the Engineer before the roadway is closed to traffic.

Maintenance of Traffic:

The Contractor shall notify the Henry County Highway Department, the corresponding township commissioner, city municipality, emergency response agencies (i.e.: fire, ambulance, police), school bus companies and the Department of transportation (Bureau of Project Implementation) regarding any changes in traffic control.

The Contractor shall notify the Henry County Highway Department, corresponding Township Commissioner and/or city municipality for any sideroad closure or opening.

Section 104R

The Contractor shall submit a maintenance of local traffic plan to the Engineer at the preconstruction meeting telling how local access will be maintained at each access location.

This plan traffic plan will need to be approved by the Engineer before the roadway is closed to traffic.

The Contractor shall be responsible for providing a weekly article and map to the news media (Star Courier, Kewanee Voice, Quad City Times and the Regional News Media WKEI 102.1 – 1450) describing work being performed and stages closed to traffic.

The main line shall be closed for reconstruction using the detour from Sale Barn Rd/County Highway 28 to IL 78 (N. Main Street).

Two (2) changeable message signs shall be placed on this project two (2) weeks prior to the start of work informing the public of lane closures. Location of the message signs will be determined by the Resident Engineer.

A Pedestrian Access Route (PAR) was created and is included in the Maintenance of Traffic Plans. There is existing sidewalk along the south side of IL 81. No sidewalk from the side streets on the north side of IL 81 connect to the south side sidewalk through ADA ramps or striped crosswalks. Therefore, the PAR will consist of erecting Sidewalk Closed signs along the existing sidewalk and additional signage to direct pedestrians south along the W 4th Street and W 5th Street.

The Contractor shall assign an onsite employee to assist in providing reasonable access to pedestrians with disabilities during construction activities when access is not maintained for everyone.

COMPLETION DATE PLUS WORKING DAYS

Effective: December 29, 2006 Revised: April 22, 2019

Revise Article 108.05(b) of the Standard Specifications to read:

“(b) completion Date Plus working Days. When a completion date plus working days is specified, the Contractor shall complete all contract items to safely open all roadways to traffic by 11:59 p.m. on or prior to November 24, 2027, except as specified herein.

The Contractor will be allowed 15 working days after the completion date for opening the roadway to traffic to complete clean-up work and punch list items. Miscellaneous items may be completed withing the working days allowed for clean-up work and punch list items if approved by the Engineer. Temporary lane closures for this work may be allowed at the discretion of the Engineer.”

Section 104R

INTERIM COMPLETION DATE

This work shall consist of the completion of all outstanding items on or prior to 11:59 p.m. on November 26, 2026. Work to be completed by this time includes all potential 2026 work item improvements.

POTENTIAL 2026 WORK ITEMS

The following anticipated work items shall be completed in 2026, using the Standard Highway Drawings.

• Installation of Perimeter Erosion Barrier

• Tree removal and clearing

• Establish Pedestrian Access Route

• Removal of existing pavement, curb and other items that conflict with the proposed 2026 work items.

• IL 81 roadway improvements (N. Washington Street to Beginning of Project)

• Box culvert removal Station 1305+25

• Installation of proposed storm sewer, from beginning of project to N. Washington St o Not fully connected

• Installation of proposed storm sewer laterals across IL 81

• Installation of proposed storm sewer, station 1318+24.9 to 1324+80.00 LT o Including Outlet Structures

• Retaining wall and parking lot improvements near Pampered Pets

• Retaining wall, curb, parking lot improvements on the east side of N. Adams St.

• Installation of the Soldier Pile wall, north side of IL 81

• Guardrail Installation, station 1307+75 to 1309+95, provided no major profile improvements

• Various retaining walls along IL 81

• Multi-use path along the north side of IL 81 (roughed in at a minimum)

• PCC driveway pavement along IL 81 from beginning station to N. Washington St.

• PCC driveway pavement, south side of IL 81, station 1340+00 to the ending station

• Roadway improvements to the side streets listed below:

o N. Union St o Jackson St o N. Adams St o Lincoln St o N. Washington St o Rice St (N) o Rice St (S) o Ross St o N. Grove o N. Cottage

Section 104R

• Improvements at Pleasure Drive

• ADA ramp and sidewalk improvements at IL 81 and N. Lexington Ave

• Widening at IL 81 and Highway 28

• Potential fill cone near the park property, depending on material sourced from other project locations

• Temporary pavement markings

• Seed or sodding of restored areas

POTENTIAL 2027 WORK ITEMS

The following anticipated work items shall be completed in 2027, with IL 81 closed to through traffic, while using a detour route.

• Establish detour route

• Installation of Temporary Signals at IL 78 and Sale Barn Rd.

• Removal of existing pavement, curb and other items that conflict with the proposed 2027 work items.

• Installation of the remainder of storm sewer and box culverts.

o Connect to storm sewer constructed in 2026

• IL 81 roadway improvements N. Washington St to the end of the project.

• Roadway improvements to the side streets listed below:

o N. West St. (S) o N. West St (N) o Perkins St

• Final landscaping elements

• Permanent pavement marking

• Final utility adjustments

GRANULAR BACKFILL FOR STRUCTURES

Effective: April 19, 2012 Revised: July 16, 2024

Revise the third sentence of the first paragraph of Article 586.03 of the Specifications to read:

“The backfill volume shall be placed in Department acceptable lift thickness for the full width to be backfilled and shall be compacted to not less than 95 percent of the standard laboratory density.”

Delete the fourth sentence of the first paragraph of Article 586.03 of the Specifications.

GUARDRAIL REMOVAL

Effective: August 20, 1990 Revised: April 10, 2014

This work shall be done according to Section 632 of the Standard Specifications except that all removed guardrail will become the property of the Contractor.

Section 104R

This work will be paid for at the contract unit price per Foot for GUARDRAIL REMOVAL, measured from center-to-center of end posts.

MOWING

Effective: January 1, 2002 Revised: April 12, 2016

This work consists of mowing all Seeding Class 2A and Class 4 at the completion of the project or before winter shut down. The vegetation must be at least 6” long before mowing.

The vegetation shall be mowed to obtain a height of not more than 3 inches. All debris must be cleared from the right-of-way immediately after the mowing.

This work will be paid for at the contract unit price per Acre for MOWING.

HOT-MIX ASPHALT SURFACE COURSE, MIX C, N50, SPECIAL

Effective: October 17, 2007 Revised December 29, 2015

Description: This work shall consist of designing, producing and constructing a HMA Surface Course on a prepared base, according to Sections 406, 1030 and 1102 of the Standard Specifications, except as follows.

Materials: Surface Mixture 9.5 Mix C, N50 shall be placed on frontage roads, detours, Good Neighbor Policy roads, city streets, and county or township roads. All others shall match the Mixture and N number of the adjacent mainline.

Required Field Tests: Density Acceptance at 95% - 102% of growth curve at the frequency indicated in Article 1030.05(d)(3).

This work will be paid for at the contract unit price per Ton for HOT-MIX ASPHALT SURFACE

COURSE, MIX C, N50, SPECIAL.

TEMPORARY PAVEMENT

Effective: October 17, 2007 Revised: March 26, 2025

This work shall consist of placing a Hot-Mix Asphalt Surface Course or Portland Cement Concrete Base Course and aggregate base to serve as a temporary widening or a runaround at the locations shown on the plans. The choice of material to be used for this item is left to the Contractor to choose from the following options:

HOT-MIX ASPHALT OPTION

This work shall consist of placing and compacting 8 inches of Sub-base Granular Material, Type B and constructing 10 inches of Hot-Mix Asphalt Surface Course at the location shown on the plans. If the thickness is 3 inches or more, it should be placed in multiple lifts.

Description: This work shall consist of designing, producing and constructing an HMA Surface Course on a prepared base, according to Sections 311, 406, 1030 and 1102 of the Standard Specifications, except as follows.

Section 104R

Materials: Surface Mixture 9.5, Mix D, N50, Binder Mixture 19.0, N50 shall be used.

All work including earth excavation and materials required to complete the work listed above shall be included in the contract unit cost per Square Yard for TEMPORARY PAVEMENT.

PORTLAND CEMENT CONCRETE OPTION

This work shall consist of placing and compacting 4 inches of Subbase Granular Material, Type B and constructing a 9-inch-thick Portland Cement Concrete Base Course to serve as a temporary runaround at the location shown on the plans. The minimum width shall be 3 feet.

This work shall be completed according to Sections 311 and 353 of the Standard Specifications.

Welded wire reinforcement shall not be utilized in the base course.

The Contractor shall saw longitudinal joints in base courses wider than 16 feet, according to Standard 420001, except that uncoated steel tie bars may be used instead of epoxy coated tie bars. These joints shall not be sealed.

The Contractor shall saw transverse joints in the base course at 20’ centers according to the detail for Sawed Construction Joints in Standard 420001, except that dowel bars are not required. These joints shall not be sealed.

All work as listed above, including earth excavation, tie bars, sawed joints, and all other required materials shall be included in the contract unit price per Square Yard for

TEMPORARY PAVEMENT.

GEOTECHNICAL REINFORCEMENT

Effective: June 17, 2022 Revised: April 10, 2014

This work consists of furnishing and installing an integrally-formed polypropylene geotechnical grid reinforcement material. The geogrid shall have an aperture, rib and junction cross section sufficient to permit significant mechanical interlock with the material being reinforced. There shall be a high continuity of tensile strength through all ribs and junctions of the grid material to reinforce the subbase or subgrade as shown on the plans and specifications.

MATERIAL

CHARACTERISTICS

TEST METHOD DATA

polymer type polypropylene ultra violet stability ASTM D 4355 50%

DIMENSIONAL

CHARACTERISTICS

TEST METHOD UNIT DATA

open area CW 02215 % 75 (max.)

unit weight ASTM D 5261 oz/yd2 5.0 (min.)

Section 104R

TECHNICAL

CHARACTERISTICS

TEST METHOD UNIT DATA

junction efficiency GRI-GG2 % 90 (min.)

The supplier should provide certification that their product meets the above requirements.

The geotechnical reinforcement shall be placed as described herein or as shown on the cross sections.

Geogrid shall be delivered to the jobsite in such a manner as to facilitate handling and incorporation into the work without damage. Material shall be stored in such a manner as to prevent exposure to direct sunlight and damage by other construction activities.

Prior to the installation of the geogrid, the application surface shall be cleared of debris, sharp objects and trees. Tree stumps shall be cut to the level of the ground surface. If the stumps cannot be cut to the ground level, they shall be completely removed. In the case of subgrades, all wheel tracks or ruts in excess of 3 inches in depth shall be graded smooth or otherwise filled with soil to provide a reasonably smooth surface.

The geotechnical reinforcement shall be placed with the “roll length” parallel to the pavement.

Fabric of insufficient width or length to fully cover the specified area shall be lapped a minimum of 24 inches. The geogrid should be secured in place.

POROUS GRANULAR EMBANKMENT, SPECIAL

Effective: June 8, 1994 Revised: April 12, 2016

This work shall consist of furnishing, transporting, and placing porous granular material according to Section 207 of the Standard Specifications, except as follows: The material shall be CA 7. The coarse aggregate shall be according to Section 1004 of the Standard Specifications.

The top 6” of porous granular material placed under precast concrete box culverts shall be done according to Article 540.06 of the Standard Specifications, except CA7 shall be used.

The cost of the top 6” of porous granular material under precast concrete box culverts will be included in the cost of the box culvert.

The porous granular material placed under precast concrete box culverts below the top 6” will be paid for as POROUS GRANULAR EMBANKMENT, SPECIAL.

This work will be paid for at the contract unit price per Ton for POROUS GRANULAR

EMBANKMENT, SPECIAL.

PCC AUTOMATIC BATCHING EQUIPMENT

Effective: January 1, 2015 Revised: January 31, 2023

Portland cement concrete provided shall be produced from batch plants that conform to the requirements of Article 1103.03 (a) and (b) of the Standard Specifications for Road and Bridge Construction. Semi-automatic batching will not be allowed.

Section 104R

Plants shall have computerized batching interfaced with a printer. IDOT Producer Number, IDOT Design Number, Concrete Material Code, batch weights, aggregate mixtures, water added, amount of each admixture or additive, and percent variance from design shall be printed for each batch. Tickets shall state the actual water-cement ratio as batched, and the amount of water that can be added to the batch without exceeding the maximum water-cement ratio. Truck delivery tickets are still required as per Article 1020.11(a)(7) of the Standard Specifications.

PCC QC/QA ELECTRONIC REPORTS SUBMITTAL

Effective: January 1, 2015 Revised: January 31, 2023

The Contractor’s QC personnel shall be responsible for electronically submitting the following reports to the Department: PRO and IND data for BMPR MI654 “Concrete Air, Slump, and Quantity,”; PRO data for BMPR MI655 “P.C. Concrete Strength,” and PRO data for BMPR MI504 “Aggregate Gradation” reports to the Department. The format for the electronic submittals shall be the QMP package reporting program, which will be provided by the Department. Microsoft Excel 2007 or newer and Microsoft Outlook is required for this program which shall be provided by the Contractor.

CRITICAL PATH SCHEDULE – TYPE B

Description

This work shall consist of preparing, revising, and updating a detailed progress schedule based upon the Critical Path Method (CPM). This work shall also consist of performing time impact analysis of the progress schedule based upon the various revisions and updates as they occur.

General

Revise the first and second paragraphs of Article 108.02 of the Standard Specifications to read:

“After the award of the contract and prior to starting of work, the Contractor shall submit to the Engineer a satisfactory progress schedule, which shall show the proposed sequence of work, including traffic control and staging, and how the Contractor proposes to complete the various items of work within the number of working days setup in the contract or on or before the completion date specified in the contract. Additionally, the Contractor shall submit an updated progress schedule on the first Monday of each month and as deemed necessary by the Engineer. The progress schedule shall be the intended work schedule and shall be used to plan, organize, and execute the work; record and report actual performance and progress, and forecast remaining work.

The progress schedule shall be used as a basis for establishing the controlling item of the construction operations and for checking the progress of all work under the contract. The controlling item shall be defined as the item which must be completed either partially or completely to permit continuation of progress. It shall be the responsibility of the Contractor to show the intended rate of production for each controlling item listed on the schedule during the period such item is controlling.”

Section 104R

Revise the fifth paragraph of Article 108.02 of the Standard Specifications to read:

“No payment under this contract will be made until a progress schedule has been submitted for approval. Payment may be withheld until a satisfactory schedule has been submitted and approved. If the Contractor deviates from the current approved progress schedule by not following the logical sequence of the critical path, payment will be withheld until a revised progress schedule is submitted and approved by the Engineer. Payment may be withheld if scheduled updated progress schedules are not submitted as required.”

Revise the first paragraph of Article 108.03 of the Standard Specifications to read:

“Time is of the essence in this contract. The Contractor shall begin the work to be performed under the contract not later than ten days after the execution of the contract by the Department, unless otherwise provided in the contract. The work shall be prosecuted in such a manner and with such a supply of materials, equipment and labor as is considered necessary to ensure its completion according to the time specified in the contract.

Requirements

The progress schedule shall be developed using project management software approved by the Engineer. The progress schedule submitted shall be a Gantt chart with a tabular data report for each activity and accompanied by a narrative report.

A. Format

The electronic schedule format shall contain the following on each page printed:

• Project Name

• Project Title: Contract number

• Company Name: Contractor’s name

• Type and edition of software

• Submittal date

• Number/Version: Original or update number

• Planning Unit: Calendar Days or Working Days

• Start Date of contract work

• Milestone Completion Date(s) as specified in contract documents

• Page number

B. Target Schedule Development

• The Contractor shall take account in the schedule for any critical closure periods and limitations of operations specified in Article 107.09 of the Standard Specifications or the contract documents

C. Schedule Updates

1. All updates shall be plotted against the Target Schedule. The Contractor shall not make any changes to the original duration, activity relationships or constraints, and shall not add or delete activities, or alter the Target Schedule’s logic when updating the schedule.

Section 104R

2. The updated information will include the original schedule detail and the following additional information:

• Actual start dates

• Actual finish dates

• Activity percent completion

• Remaining duration of activities in progress

• Identified or highlighted critical activities

3. The Engineer shall withhold progress payments if the Contractor does not submit scheduled updates as required.

4. Upon receipt of the updated CPM progress schedule, the Engineer will review the schedule for conformance with the Contract Documents and degree of detail. The Engineer, within 14 calendar days after receipt of the updated CPM progress schedule and supporting documents, will approve or reject it with written comments. If the updated CPM progress schedule is rejected, the Contractor must submit a revised updated CPM progress schedule within seven calendar days after the date of rejection.

5. The updated progress schedule must accurately represent the Project’s current status.

D. Schedule Revisions

Revisions to the Target Schedule may be initiated by a proposal by the Contractor or by direction from the Engineer.

1. Contractor Changes to the Target Schedule.

The Contractor shall comply with the following requirements regarding proposed changes to the Target Schedule:

• If the Contractor proposes to make any changes in the Target Schedule, the Contractor shall notify the Engineer in writing, stating the reasons for the change, identifying each changed activity (including duration and interrelationships between activities) and providing a submittal including compact discs and printed copies of the proposed revised schedule. Every effort must be made by the Contractor to retain the original Activity ID numbers.

• The Engineer has the authority to approve or reject the proposed change(s) in the Target Schedule and shall do so in writing within 14 calendar days after receipt of the Contractor’s submittal. If the Engineer approves the change in the Target Schedule, all future monthly updates will be plotted against the new Target Schedule.

• If the Engineer approves a portion of the change to the Target Schedule, the

Contractor shall submit a revised schedule incorporating such change(s) within seven calendar days after the partial approval along with a written description of the change(s) to the schedule.

Section 104R

2. Engineer Changes to the Target Schedule The Engineer may direct the Contractor to revise the approved baseline CPM progress schedule. Reasons for such direction may include, are limited to the following: (1) changes in the work, (2) re-phasing of the Project or any phase, (3) a change in the duration of the Project or phase, and (4) acceleration of the Project or phase.

• The Engineer will direct the Contractor to provide a revised CPM schedule in writing.

• The Contractor shall submit the revised CPM progress schedule within ten calendar days of receipt of the Engineer’s written direction.

• The Engineer has the authority, in its sole discretion, to approve or reject the revised CPM progress schedule and will do so in writing within fourteen calendar days after receipt of the Contractor’s submittal If the Engineer approves the revised CPM progress schedule, such schedule will be designated the new “Target Schedule”.

• If the Engineer approves a portion of the change to the Target Schedule, the

Contractor shall submit a revised schedule incorporating such change(s) within seven calendar days after the partial approval along with a written description of the change(s) to the schedule.

E. Schedule Presentation (Gantt Chart)

• The following shall be included for each activity in the graphic part of the schedule in the Gantt chart format:

• Activity identification numbers

• Description of the work activity o Maximum 45 characters o Usage of percentage numbers shall not be permitted in the description o Multiple activities with the same description shall include a location as part of the description

• Duration of the work activity in whole days o Must be contiguous and not interruptible o Include production rates

• Sequence and interdependence of work activities o Sequence shall not violate the schedule logic

• Critical path to milestone and contract completion o Only one (1) controlling item shall be designated at any point in time on the schedule

• Work activities shall be broken down such that each activity encompasses a single operation or tightly-integrated operations in a single, contiguous and

Section 104R continuous area of the project. Each activity shall have a duration of not more than 20 working days, except for non-work type activities (such as mobilization), unless otherwise approved by the Engineer.

• Include the following dates:

i. Start/End for each stage of construction

ii. Milestones identified in the contract

iii. Document Submittals

1. Shop drawings, etc.

iv. Work activities

v. Equipment, Access, Installation

• Calculate total float as finish float. Calculate the schedule using retained logic.

Do not sequester float by calendar manipulations or extended duration. Float is not for the exclusive use or benefit of either the Department or the Contractor.

• Include a legend defining all abbreviations, terms, and symbols used

Review and Approval Process

The Contractor shall electronically submit the progress schedule to the Engineer for review in both its original file format and in pdf format.

The Engineer will notify the Contractor in writing, within 14 calendar days after receiving any progress schedule submittal or resubmittal, if the schedule is approved or if any corrections or revisions are required. If corrections or revisions are required to the progress schedule, the Contractor shall submit the revised progress schedule to the Engineer within 7 calendar days after receiving the Engineer’s request for corrections or revisions.

Submittals that are required to be revised and resubmitted shall have the revisions clouded or annotated to designate revisions.

Acceptance or approval of any progress schedule by the Engineer shall not be construed to imply approval of any particular method of construction, sequence of construction, any implied or stated rate of production. Acceptance will not act as a waiver of the obligation of the Contractor to complete the work in accordance with the contract proposal, plans and specifications, modify any rights or obligations of the Department as set forth in the contract, nor imply any obligation of a third party. Acceptance shall not be construed to modify or amend the contract or the time limit(s) therein. Acceptance shall not relieve the Contractor of responsibility for the accuracy of any of the information included on the schedule. Failure of the Contractor to include in the schedule any element of work required for the performance of the contract, any sequence of work required by the contract, or any known or anticipated condition affecting the work shall not excuse the Contractor from completing all work required within the time limit(s) specified in the contract notwithstanding acceptance of the schedule by the Engineer.

Basis of Payment This work will not be paid for separately but shall be included in the cost for MOBILIZATION.

Section 104R

ROCK FILL

Effective: May 1, 1995 Revised: August 29, 2013 This work shall consist of placing CS02 at locations shown in the plans, except for the bedding material provided (in Article 540.06) for box culverts or (in Article 542.04(c)) pipe culverts. The granular bedding layer is included in the unit price for Precast Concrete Box Culverts and Pipe Culverts. The 6 inch bedding layer under Cast-in-Place Culverts shall be gradation CA07, and shall be paid for as ROCK FILL.

The CS02 shall consist of crushed gravel, crushed stone, or crushed concrete of sound durable particles, reasonably free of deleterious materials meeting the following gradation:

Grad No. Sieve Size and Percent Passing 6” 4” 2”

CS02 100 80±10 25±15

This work shall be paid for at the contract unit price per Ton for ROCK FILL.

STORM SEWER WATER MAIN REQUIREMENT

Effective: June 12, 1997 Description: This work shall consist of furnishing and installing water main quality pipe at the locations shown on the plans.

Materials:

a) Ductile iron water main Class 52

Joints for Ductile Iron pipe shall be:

1. Mechanical Joints - AWWA C111 and C600

2. Push-On-Joints - AWWA C111 and C600

b) Polyvinyl Chloride (PVC) Class 12454B (PVC 1120) or Class 12454C (PVC 1220).

Schedule 40 is required for 8" diameter and schedule 80 for larger sizes.

CONSTRUCTION REQUIREMENTS

The storm sewer water main shall be installed according to the applicable portions of Section 550 and 561 of the Standard Specifications and the Standard Specifications for Water and Sewer Main Construction. In case of conflict between the Standard Specifications, the Standard Specifications for Water and Sewer Main Construction in Illinois shall take precedence and shall govern.

No testing or disinfections of the newly laid storm sewer water main will be required. A water-tight connection is required between the storm sewer water main and the storm sewer.

Method of Measurement: Storm sewer water main of the various diameters will be measured for payment in feet, measured in place.

Section 104R

Basis of Payment: This work will be paid for at the contract unit price per Foot for STORM SEWER WATER MAIN REQUIREMENT, of the diameter specified.

STORM SEWER, RUBBER GASKET

Effective: April 5, 2005

This item is included to satisfy the EPA requirements for horizontal and vertical separation of storm sewer and water mains or water service lines outlined in Section 41 of the Standard Specifications for Water and Sewer Main Construction in Illinois.

Storm Sewer, Rubber Gasket is to be used at locations where the water main or water service line crosses below the storm sewer, regardless of vertical separation, or where the bottom of the water main or water service line is less than 18” above the top of the storm sewer.

This work shall consist of constructing storm sewers of the required inside diameter with the necessary fittings in accordance with Section 550 of the Standard Specifications and the following additions or exceptions.

At locations shown on the plans, the contractor shall furnish and install a reinforced concrete pipe of the size, class and type indicated with rubber gasket joints which conforms to ASTM Specification C-361.

The joint shall be approved by the Illinois Environmental Protection Agency for storm sewer lines crossing above water mains.

This work will be measured and paid for at the contract unit price per Foot for STORM SEWER, RUBBER GASKET of the type and size indicated.

WORK ZONE PAVEMENT MARKING AND REMOVAL

Effective: December 29, 2008 Revised: October 5, 2021

This work shall consist of installing and removing temporary pavement marking according to Section 703 and 783 of the Standard Specifications and the following:

All temporary paint on the final wearing surface shall be removed according to Article 1101.12 Water Blaster with Vacuum Recovery and the applicable portions of Section 783 of the Standard Specifications and as described herein.

Add the following paragraph to Article 1101.12 of the Standard Specifications.

“For the high pressure water spray, the pressure at the nozzle shall be approximately 25,000 psi with maximum flow rate of 15 gal/min. The nozzle shall be in close proximity to the pavement surface.”

Section 104R

REMOVAL OF EXISTING STRUCTURES

Effective: July 28, 2014

This work shall be done in accordance with Section 501 of the Standard Specifications. The work shall consist of removing and disposing of existing box culverts, any miscellaneous materials and other items as specified. Removal of existing drop boxes, end sections, headwalls, Spillways, and Weirs along the ditches shall be included in the cost of Removal of Existing Structure for that location.

No. Station Description 1 1305+25.0 LT\RT 2’x2’ single cell concrete box culvert under IL 81.

Barrel section is approximately 51 feet in length.

Downstream side contains a concrete headwall.

Upstream side contains a manhole structure.

2 1307+10.0 LT\RT 2’x2’ single cell concrete box culvert under IL 81.

Barrel section is approximately 50 feet in length.

Downstream side contains a concrete headwall.

Upstream side contains a manhole structure and a 24” concrete pipe tee, along with a 10” PVC storm sewer pipe leading northwest from the upstream manhole.

3 1324+98.0 LT\RT 3’ x 3’ single cell concrete box culvert (S.N 037-C033) under IL 81. Barrel section is approximately 39 feet in length. Downstream side contains a concrete headwall. Upstream side contains a manhole structure.

4 1332+41.0 LT\RT 3’ x 3’ single cell concrete box culvert under IL 81.

Barrel section is approximately 54 feet in length.

Downstream side contains a roadside inlet structure, connected to a 12” storm sewer, which connects into another downstream manhole structure. Upstream side contains an inlet structure.

5 1339+56.0 LT\RT 4’x4’ single cell culvert under IL 81. Barrel section is approximately 68 feet in length consisting of an RCP, bricks, and concrete. Downstream and upstream sides contain a manhole structure. An upstream roadside inlet and an existing 8” storm sewer pipe connects to the culvert.

This work shall be paid for at the contract unit price per Each for REMOVAL OF EXISTING STRUCTURES of the number specified and shall include any upstream or downstream structure and/or storm sewer attached to the box culvert.

Section 104R

JOINT TRIMMING

Effective: March 6, 2023

The following is the sequence for milling and paving:

1. If specified in the contract, mill both lanes and shoulders for the entire project.

2. Place the HMA binder on both driving lanes and shoulders for the entire project.

3. On the first lane to be paved, place the tack coat and new HMA surface course 6 in. wider than the joint to be trimmed.

4. After surfacing the first driving lane and prior to cleaning and start of surfacing on the following lane or shoulder, mill off the extra 6 in. of new HMA surface to the joint location, per the typical sections. The milling equipment must be capable of producing a straight line. The depth of the milling must be controlled so as not to gouge the underlying binder lift.