IDOT 62U72-005.pdf

PDF 5 MB Posted

Attached to
Roadway Add Lanes and Reconstruction Project - City of McHenry within McHenry County
Solicitation number
62U72
Issued by
Mchenry County, Illinois

About this file

This is a Notice to Bidders and Special Provisions document issued by the Illinois Department of Transportation (IDOT) for a roadway reconstruction and lane addition project located in McHenry County. The project, identified as Contract No. 62U72 on Illinois Route 31 (FAP Route 336A), spans 8,360 feet (1.58 miles) north of Bull Valley Road extending to Illinois Route 120 within the City of McHenry. The scope of work includes pavement removal, earth excavation and embankment placement, precast box culvert installation, bridge replacement, storm sewer installation, Portland cement concrete (PCC) pavement construction with curb and gutter, sidewalk and shared use path construction, traffic signal and interconnection installations, highway lighting replacement, water main and sanitary sewer relocation, pavement marking, landscaping, and erosion and sediment control. Electronic bids must be submitted to the iCX-Integrated Contractors Exchange system by 12:00 p.m. on June 12, 2026, with public bid opening to follow. The contract specifies an interim completion date of October 31, 2028, for all lanes open to traffic, sidewalks, shared use paths, permanent traffic signals, pavement marking and signing to be installed and operational, with a final completion date of May 31, 2029. Construction cannot commence until April 1, 2027. The project is funded through Federal-aid highway funds under the National Highway Performance Program (NHPP) and Local Roads and Streets (LNA0) funding mechanism.

The contract will be awarded to the lowest responsive and responsible bidder considering conformity with established terms and conditions. The Department reserves the right to reject any or all proposals and to determine responsibility at the time of award. Significant utility relocations are required prior to and during construction, including work by ComEd, Nicor Gas, Comcast, AT&T, and I3 Broadband, with estimated durations ranging from 90 to 300 working days for various utility relocations. The contractor must maintain normal roadway maintenance, excluding snow removal, from project inception and shall coordinate with adjacent Contract 80C85 (IL 31 from Ames Road to Bull Valley Road) through mandatory weekly coordination meetings. The document includes extensive supplemental specifications, recurring special provisions, and special provisions governing materials, methods, labor requirements, traffic control, environmental compliance, and plant care and landscaping work. Restrictions include prohibitions on tree clearing from April 1 through October 31 (except selective clearing) and comprehensive requirements for weed control spraying, including contractor licensing and pesticide application notification under Illinois law.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting June 12, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 62U72 MCHENRY County Section FAP 336 23 RECON NORTH Route FAP 336A Project NHPP-LNA0(132) District 1 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

June 12, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 62U72 MCHENRY County Section FAP 336 23 RECON NORTH Project NHPP-LNA0(132) Route FAP 336A District 1 Construction Funds

(8,360-Ft) Roadway add lanes and reconstruction project consists of pavement removal, earth excavation and placement of embankment, precast box culvert installation, bridge replacement, storm sewer installation, construction of new PCC pavement with combination concrete curb and gutter, sidewalk and shared use path construction, traffic signals and interconnection installations, highway lighting replacement, water main and sanitary sewer relocation, placement of pavement marking, landscaping, erosion and sediment control. This project is in the City of McHenry within McHenry County.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

FAP ROUTE 336A (IL 31)

PROJECT NHPP-ITEP-LNA0(132)

SECTION FAP 336 23 RECON NORTH

MCHENRY COUNTY

CONTRACT NO. 62U72

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

SECTION FAP 336 23 RECON NORTH

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 X Additional State Requirements for Federal-Aid Construction Contracts 2 X Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 Specific EEO Responsibilities Nonfederal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 X Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 X Station Numbers in Pavements or Overlays

SECTION FAP 336 23 RECON NORTH

i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

MAINTENANCE OF ROADWAYS (D1)

PUBLIC CONVENIENCE AND SAFETY (D1)

PROSECUTION OF WORK

COMPLETION DATE PLUS WORKING DAYS (D1)

RESTRICTION ON WORKING DAYS AFTER A COMPLETION DATE

CONTRACTOR COOPERATION

TREE REMOVAL RESTRICTIONS

STATUS OF UTILITIES (D1)

EMBANKMENT I (D1)

BIOSWALE

FAILURE TO COMPLETE PLANT CARE AND ESTABLISHMENT WORK ON TIME

GENERAL REQUIREMENTS FOR WEED CONTROL SPRAYING

PLANTING PERENNIAL PLANTS, ORNAMENTAL TYPE

PLANTING PERENNIAL PLANTS, ORNAMENTAL TYPE

PLANTING PERENNIAL PLANTS, WETLAND EMERGENT

PLANTING WOODY PLANTS

SEEDING, CLASS 4 (MODIFIED)

SEEDING, CLASS 4B (MODIFIED)

SEEDING, CLASS 5 (MODIFIED)

SUPPLEMENTAL WATERING

WEED CONTROL, NATIVE LANDSCAPE ENHANCEMENT

PRUNING FOR SAFETY AND EQUIPMENT CLEARANCE

MOWING CYCLES

TEMPORARY PAVEMENT (D1)

AGGREGATE SURFACE COURSE FOR TEMPORARY ACCESS (D1)

HOT-MIX ASPHALT BINDER AND SURFACE COURSE (D1)

FRICTION AGGREGATE (D1)

MINERALIZED CARBON DIOXIDE CONCRETE (D-1)

HOT-MIX ASPHALT – MIXTURE DESIGN VERIFICATION AND PRODUCTION (D1)

FLY ASH RESTRICTION

SLIPFORM PAVING (D1)

PORTLAND CEMENT CONCRETE SIDEWALK, (SPECIAL) WITH RETAINING WALL

CONTROLLED STIFFNESS COLUMNS GROUND IMPROVEMENT

SECTION FAP 336 23 RECON NORTH

ii

BIAXIAL GEOGRID

DRAINAGE SCUPPERS, DS-12

CONNECTION TO EXISTING SEWER

ADJUSTMENTS AND RECONSTRUCTIONS (D1)

REMOVE EXISTING FLARED END SECTION

BOX CULVERT REMOVAL

MANHOLES, TYPE A, WITH 2 TYPE 1 FRAME, CLOSED LID, RESTRICTOR PLATE

STORM SEWER ADJACENT TO OR CROSSING WATER MAIN (D1)

CONNECTION OF PROPOSED STORM SEWER TO PROPOSED BOX CULVERT

ROCKFILL

PRECAST CONCRETE JUNCTION CHAMBER

FENCE REMOVAL

STUMP REMOVAL

REMOVE SIGN (SPECIAL)

RELOCATE EXISTING MAILBOX

COFFERDAM (TYPE 1) (IN-STREAM/WETLAND WORK) (D1)

REMOVE EXISTING WATERMAIN (MCHENRY)

SANITARY SEWER TELEVISION INSPECTION, VIDEOTAPING AND RECORDING (MCHENRY)

SANITARY SEWER, DUCTILE IRON 8” & 10”(MCHENRY)

CURED-IN-PLACE PIPE LINER, 8" (MCHENRY)

ABANDON AND FILL EXISTING SANITARY SEWER (MCHENRY)

CONNECTION TO EXISTING MANHOLE (MCHENRY)

DROP SANITARY MANHOLES, WITH TYPE 1 FRAME, CLOSED LID (MCHENRY)

SANITARY MANHOLES TO BE REMOVED (MCHENRY)

SANITARY SEWER (MCHENRY)

SANITARY SEWER REMOVAL (MCHENRY)

SANITARY SEWER, DUCTILE IRON (MCHENRY)

DUCTILE IRON WATER MAIN (MCHENRY)

WATER VALVES (MCHENRY)

FIRE HYDRANTS TO BE REMOVED (MCHENRY)

FIRE HYDRANT WITH AUXILIARY VALVE, VALVE BOX AND TEE (MCHENRY)

WATER MAIN (MCHENRY)

ABANDON EXISTING WATER MAIN, FILL WITH CLSM (CITY OF MCHENRY)

NON-PRESSURE CONNECTION TO EXISTING WATER MAIN (MCHENRY)

VALVE VAULTS TO BE REMOVED (MCHENRY)

STEEL CASINGS 20" (MCHENRY)

ENGINEER’S FIELD OFFICE TYPE A (SPECIAL) (D1)

SECTION FAP 336 23 RECON NORTH

iii

TRAFFIC CONTROL AT AT-GRADE RR CROSSINGS

TRAFFIC CONTROL AND PROTECTION (ARTERIALS) (D1)

TRAFFIC CONTROL PLAN (D1)

KEEPING ARTERIAL ROADWAYS OPEN TO TRAFFIC (LANE CLOSURES ONLY)

TEMPORARY INFORMATION SIGNING

RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REMOVAL

RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REPLACEMENT

MAST ARM SIGN PANELS

TRAFFIC SIGNAL GENERAL REQUIREMENTS

OPTIMIZE TRAFFIC SIGNAL SYSTEM

RE-OPTIMIZE TRAFFIC SIGNAL SYSTEM

SERVICE INSTALLATION (TRAFFIC SIGNALS)

ELECTRIC METER

COILABLE NON-METALLIC CONDUIT

UNDERGROUND RACEWAYS

ROD AND CLEAN EXISTING CONDUIT

HANDHOLES

FIBER OPTIC TRACER CABLE

FULL-ACTUATED CONTROLLER IN EXISTING CABINET

FULL-ACTUATED CONTROLLER AND CABINET

UNINTERRUPTABLE POWER SUPPLY, SPECIAL

FIBER OPTIC CABLE

SPLICE FIBER IN CABINET

TERMINATE FIBER IN CABINET

FIBER OPTIC INTERCONNECT CENTER, 24 PORT OR 48 PORT

ELECTRIC CABLE

EMERGENCY VEHICLE PRIORITY SYSTEM LINE SENSOR CABLE, NO. 20 3/C

TRAFFIC SIGNAL POST

PEDESTRIAN SIGNAL POST

MAST ARM ASSEMBLY AND POLE

CAMERA MOUNTING ASSEMBLY

CONCRETE FOUNDATIONS

LED SIGNAL HEAD AND OPTICALLY PROGRAMMED LED SIGNAL HEAD

LED SIGNAL FACE, LENS COVER

LED PEDESTRIAN SIGNAL HEAD

TRAFFIC SIGNAL BACKPLATE

DETECTOR LOOP

SECTION FAP 336 23 RECON NORTH

iv

VIDEO VEHICLE DETECTION SYSTEM

EMERGENCY VEHICLE PRIORITY SYSTEM

OUTDOOR RATED NETWORK CABLE

ACCESSIBLE PEDESTRIAN SIGNALS

TEMPORARY TRAFFIC SIGNAL INSTALLATION

TEMPORARY TRAFFIC SIGNAL TIMING

CELLULAR MODEM

NETWORK SWITCH

POE EXTENDER

TACTICS LICENSE EXPANSION

REMOTE CONTROLLED VIDEO SYSTEM

RELOCATE NETWORK SWITCH

MODIFY EXISTING CONTROLLER CABINET

REMOVE EXISTING TRAFFIC SIGNAL EQUIPMENT

ELECTRIC SERVICE INSTALLATION AND UTILITY CONNECTION

GENERAL ELECTRICAL REQUIREMENTS (CITY OF MCHENRY)

LIGHTING UNIT COMPLETE, SPECIAL

MAINTENANCE OF LIGHTING SYSTEMS

LUMINAIRE SAFETY CABLE ASSEMBLY

LUMINAIRE SHIELD

RELOCATE EXISTING LIGHTING UNIT

ROADWAY LUMINAIRE, LED

TEMPORARY LUMINAIRE, LED, ROADWAY

UNDERGROUND RACEWAYS

UNIT DUCT

WIRE AND CABLE

PREFORMED PAVEMENT JOINT SEAL

BAR SPLICERS, HEADED REINFORCEMENT

AGGREGATE SUBGRADE IMPROVEMENT (BDE)

BITUMINOUS MATERIALS COST ADJUSTMENTS (BDE)

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

COMPENSABLE DELAY COSTS (BDE)

CONSTRUCTION AIR QUALITY – DIESEL RETROFIT (BDE)

EROSION CONTROL BLANKET (BDE)

FUEL COST ADJUSTMENT (BDE)

GUARDRAIL (BDE)

HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)

SECTION FAP 336 23 RECON NORTH

v

INLET FILTERS

LONGITUDINAL TINING (BDE)

PAVEMENT MARKING (BDE)

PAVEMENT PATCHING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

PREFORMED PLASTIC PAVEMENT MARKING (BDE)

RAISED REFLECTIVE PAVEMENT MARKERS (BDE)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SEEDING (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (BDE)

STEEL COST ADJUSTMENT (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – FEDERAL AID CONTRACT (BDE)

SURFACE TESTING OF PAVEMENTS – IRI (BDE)

SURVEYING SERVICES (BDE)

TEMPORARY CONCRETE BARRIER (BDE)

TRAINING SPECIAL PROVISIONS (BDE)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

PROJECT LABOR AGREEMENT

STORM WATER POLLUTION PREVENTION PLAN (SWPPP)

IEPA WATER MAIN PERMIT (MCHENRY)

IEPA SANITARY SEWER PERMIT (MCHENRY)

SECTION FAP 336 23 RECON NORTH

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1, 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the “Manual of Test Procedures of Materials” in effect on the date of invitation of bids, and the "Supplemental Specifications and Recurring Special Provisions" indicated on the Check Sheet included herein which apply to and govern the construction of FAP Route 336A (IL 31), Project NHPP-ITEP-LNA0(132), Section FAP 336 23 Recon North, McHenry County, Contract No. 62U72, and in case of conflict with any parts, or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.

FAP Route 336A (IL 31) Project NHPP-ITEP-LNA0(132)

Section FAP 336 23 Recon North McHenry County

Contract No. 62U72

LOCATION OF PROJECT

This project begins on the centerline of IL 31 north of Bull Valley Road and extends in a northerly direction to IL 120 in the City of McHenry within McHenry County. This project has a gross and net length of 8,360 feet (1.58 miles).

DESCRIPTION OF PROJECT

This project consists of adding lanes and a reconstruction, and the work to be completed under this contract consists of pavement removal, earth excavation and placement of embankment, precast box culvert installation, bridge replacement, storm sewer installation, construction of new PCC pavement with combination concrete curb and gutter, sidewalk and shared use path construction, traffic signals and interconnection installations, highway lighting replacement, water main and sanitary sewer relocation, placement of pavement marking, landscaping, erosion and sediment control, and any incidental and collateral work necessary to complete the project as shown on the plans and described herein.

SECTION FAP 336 23 RECON NORTH

MAINTENANCE OF ROADWAYS (D1)

Effective: September 30, 1985 Revised: November 1, 1996

Beginning on the date that work begins on this project, the Contractor shall assume responsibility for normal maintenance of all existing roadways within the limits of the improvement. This normal maintenance shall include all repair work deemed necessary by the Engineer but shall not include snow removal operations. Traffic control and protection for maintenance of roadways will be provided by the Contractor as required by the Engineer.

If items of work have not been provided in the contract, or otherwise specified for payment, such items including the accompanying traffic control and protection required by the Engineer will be paid for in accordance with Article 109.04 of the Standard Specifications.

PUBLIC CONVENIENCE AND SAFETY (D1)

Effective: May 1, 2012 Revised: July 15, 2012

Add the following to the end of the fourth paragraph of Article 107.09:

“If the holiday is on a Saturday or Sunday, and is legally observed on a Friday or Monday, the length of holiday period for Monday or Friday shall apply.”

Add the following sentence after the Holiday Period table in the fourth paragraph of Article 107.09:

“The length of holiday period for Thanksgiving shall be from 5:00 AM the Wednesday prior to 11:59 PM the Sunday after”

Delete the fifth paragraph of Article 107.09 of the Standard Specifications:

“On weekends, excluding holidays, roadways with average daily traffic of 25,000 or greater, all lanes shall be open to traffic from 3:00 P.M. Friday to midnight Sunday except where structure construction or major rehabilitation makes it impractical.”

PROSECUTION OF WORK

Add the following to Article 108.03 of the Standard Specifications as follows:

“The Contractor will not be allowed to proceed with any construction operations until April 1, 2027. The Engineer’s written approval shall be obtained by the Contractor before proceeding with any work on this project.”

SECTION FAP 336 23 RECON NORTH

COMPLETION DATE PLUS WORKING DAYS (D1)

Effective: September 30, 1985 Revised: January 1, 2007

Revise Article 108.05 (b) of the Standard Specifications as follows:

"When a final completion date plus working days is specified, the Contractor shall complete all contract items and safely open all roadways to traffic by 11:59 PM on May 31, 2029, except as specified herein.

The Contractor will be allowed to complete all clean-up work and punch list items within ten working days after the completion date for opening the roadway to traffic. Under extenuating circumstances, the Engineer may direct that certain items of work, not affecting the safe opening of the roadway to traffic, may be completed within the working days allowed for clean-up work and punch list items. Temporary lane closures for this work may be allowed at the discretion of the Engineer.

*The interim completion date for all lanes open to traffic, all sidewalks and shared use paths open for use, all permanent traffic signals, pavement marking and signing installed and operational shall be October 31, 2028."

Article 108.09 or the Failure to Complete the Work on Time special provision, if included in this contract, shall apply to both the completion date and the number of working days.

RESTRICTION ON WORKING DAYS AFTER A COMPLETION DATE

Effective: January 21, 2003 Revised: January 1, 2007

All temporary lane closures during the period governed by working days after a completion date will not be permitted during the hours of 6:00 a.m. to 9:00 a.m. and 3:00 p.m. to 6:00 p.m. Monday through Friday.

All lane closure signs shall not be erected any earlier than one-half hour before the starting hours listed above. Also, these signs should be taken down within one-half hour after the closure is removed.

Failure to Open Traffic Lanes to Traffic: Should the Contractor fail to completely open and keep open all the traffic lanes to traffic in accordance with the limitations specified above, the Contractor shall be liable and shall pay to the Department the amount of $250 per lane blocked, not as a penalty but as liquidated and ascertained damages, for each and every 15 minute interval or a portion thereof that a lane is blocked outside the allowable time limitations. The Department may deduct such damages from any monies due to the Contractor. These damages shall apply during the period governed by working days after a completion date and any extensions of that contract time.

SECTION FAP 336 23 RECON NORTH

CONTRACTOR COOPERATION

The Contractor’s attention is directed to the fact that other separate contracts may be under construction during the duration of this contract. Adjacent contracts may consist of, but are not limited to projects near:

• Contract 80C85: IL 31 from Ames Road to Bull Vally Road

The Contractor will be governed by Article 105.08 of the Standard Specifications.

The Contractor will be required to attend a weekly coordination meeting at a time and location to be determined by the Department. The Contractor will coordinate proposed project start dates, maintenance of traffic, and sequence of construction with the Engineer and other contractors to present an effective and timely schedule for successful completion of the project.

The cooperation between work under this contract and Contract 80C85 is essential due to the adjacent limits of construction and shared maintenance of traffic responsibilities along IL 31. All traffic staging configurations and changes to staging along IL 31 shall be coordinated with the contractor performing work under those contracts.

TREE REMOVAL RESTRICTIONS

Trees 3 inches or greater in diameter at breast height shall not be cleared from April 1st through October 31st of any given year. Selective clearing will be allowed during the restriction period.

STATUS OF UTILITIES (D1)

Effective: June 1, 2016 Revised: April 1, 2025

Utility companies and/or municipal owners located within the construction limits of this project have provided the following information regarding their facilities and the proposed improvements.

The tables below contain a description of specific conflicts to be resolved and/or facilities which will require some action on the part of the Contractor to proceed with work. Each table entry includes an identification of the action necessary and, if applicable, the estimated duration required for the resolution.

Utilities To Be Adjusted. Conflicts noted below have been identified by following the suggested staging plan included in the contract. The company has been notified of all conflicts and will be required to obtain the necessary permits to complete their work; in some instances, resolution will be a function of the construction staging. The responsible agency must relocate, or complete new installations as noted below; this work has been deemed necessary to be complete for the Contractor to then work in the stage under which the item has been listed.

SECTION FAP 336 23 RECON NORTH

Pre-Stage

APPROXIMATE

LOCATION TYPE DESCRIPTION RESPONSIBLE

AGENCY DURATION OF TIME

IL 31 Sta. 409+00 to Sta 457+00 LT Aerial Line

Aerial line and power poles in conflict with improvement to be relocated

ComEd

TBD

IL 31 Sta 456+69 to Sta 480+50 RT Aerial Line

Aerial line and power poles in conflict with improvement to be relocated

ComEd

IL 31 Sta 457+70 Crossing Aerial Line

Aerial line and power poles in conflict with improvement to be relocated

ComEd

IL 31 Sta 464+30 Crossing Aerial Line

Aerial line and power poles in conflict with improvement to be relocated

ComEd

IL 31 Sta. 70+70 Crossing North Side

John Street Aerial Line

Aerial line and power poles in conflict with improvement to be relocated

ComEd

IL 120 Sta. 288+43 to Sta 299+70 LT Aerial Line

Aerial line and power poles in conflict with improvement to be relocated

ComEd

IL 31 Sta 401+00 to Sta 409+00 RT Gas

2” Gas Main in conflict with improvement to be relocated Nicor

130 Working Days

IL 31 Sta 409+00 to Sta 429+77 RT Gas

12” Gas Main in conflict with improvement to be relocated

Nicor

IL 31 Sta 429+77 to Sta 447+00 RT Gas

2’ Gas Main in conflict with improvement to be relocated Nicor

IL 31 Sta 453+488 to Sta 456+75 RT Gas

8” Gas Main in conflict with improvement to be relocated Nicor

IL 31 Sta. 459+85 to Sta 476+69 LT Gas

2” – 4” Gas Main in conflict with improvement to be relocated

Nicor

Front Street at Sta 481+20 RT Gas

2” Gas Main in conflict with improvement to be relocated Nicor

IL 120 Sta 297+00 to Sta. 308+30 RT Gas

2’ Gas Main in conflict with improvement to be relocated Nicor

SECTION FAP 336 23 RECON NORTH

IL 31 Sta. 408+95 to Sta. 412+10 LT

Underground cable in conduit

Underground is in conflict with the improvement and will be relocated

Comcast

TBD

IL 31 Sta. 412+00 to Sta 457+50 LT

Aerial Line Aerial line on pole is in conflict with the improvement and will be relocated

Comcast

IL 31 Station 415+85 LT Crossing

Underground cable in conduit

Underground is in conflict with the improvement and will be relocated

Comcast

IL 31 Station 421+85 to Sta. 425+25

Underground cable in conduit

Underground is in conflict with the improvement and will be relocated

Comcast

IL 31 Station 457+50 Crossing

Aerial Line Aerial line on Com Ed pole is in conflict with the improvement and will be relocated

Comcast

IL 31 Sta. 457+50 to Sta. 472+00 RT

Aerial Line Aerial line on pole is in conflict with the improvement and will be relocated

Comcast

IL 31 Sta 475+00 to Sta 481+00 RT

Aerial Line Aerial line on pole is in conflict with the improvement and will be relocated

Comcast

IL 120 Sta. 289+75 to Sta. 301+00 LT

Aerial Line Aerial line on pole is in conflict with the improvement and will be relocated

Comcast

IL 120 at Sta.

295+90 RT

Underground cable in conduit

Underground is in conflict with the improvement and will be relocated

Comcast

IL 31 Sta. 437+00 to 448+00 RT Aerial Line

Aerial line on pole in conflict with the improvement and will be relocated

AT&T

300 Working Days

IL 31 Sta 448+00 to Sta. 453+50 RT Buried Cable

Underground cable is in conflict with the improvement and will be relocated

AT&T

IL 43 Sta. 453+50 to Sta. 477+00 RT Aerial Line

Aerial line on pole in conflict with the improvement and will be relocated

AT&T

IL 120 Sta. 291+ to Sta. 300+ RT Buried Cable

Underground cable is in conflict with the improvement and will

AT&T

SECTION FAP 336 23 RECON NORTH

IL 31 at Kane Avenue

Fiber Optic Cable

Underground cable is in conflict with the improvement and will be relocated

I3 Broadband

90 Working Days

IL 31 at Lillian Avenue

Fiber Optic Cable

Underground cable is in conflict with the improvement and will be relocated

I3 Broadband

IL 31 at Main Street

Fiber Optic Cable

Underground cable is in conflict with the improvement and will be relocated

I3 Broadband

IL 120 at Millstream Dr/3rd Ave

Fiber Optic Cable

Underground cable is in conflict with the improvement and will

I3 Broadband

Pre-Stage: ________ Days Total Installation Stage 1: ________ Days Total Installation Stage 2: ________ Days Total Installation

The following contact information is what was used during the preparation of the plans as provided by the agency/company responsible for resolution of the conflict.

Agency/Company Responsible to

Resolve Conflict

Name of contact Phone E-mail address

ComEd Paul Casperson 630-234-4859 paul.casperon@comed.com ComEd Marcus Theodore 312-253-1800 mtheodore@hbkengineering.com Nicor Charles Parrot 630-388-2362 cparrott@southernco.com

MCI/Verizon Joe Chaney Jr 312-617-2131 Joe.Chaney@verizon.com MCI/Verizon Kendrick Lomax 312-612-5216 klomax@telecom-eng.com Everstream Gino Esposito 224-423-2909 gesposito@everstream.net

Comcast Louis Sarno 224-465-0012 Louis_sarno2@comcast.com AT&T Alexander Bryant 630-573-6456 ab8652@att.com

City of McHenry Greg Gruen 815-363-2185 ggruen@cityofmchenry.org

Utilities To Be Watched and Protected. The areas of concern noted below have been identified by following the suggested staging plan included for the contract. The information provided is not a comprehensive list of all remaining utilities, but those which during coordination were identified as ones which might require the Contractor to take into consideration when making the determination of the means and methods that would be required to construct the proposed improvement. In some instances, the Contractor will be responsible to notify the owner in advance of the work to take place so necessary staffing on the owner’s part can be secured.

Pre-Stage No facilities requiring extra consideration

Stage 1 No facilities requiring extra consideration

SECTION FAP 336 23 RECON NORTH

Stage 2 No facilities requiring extra consideration

The following contact information is what was used during the preparation of the plans as provided by the owner of the facility.

Agency/Company Responsible to

Resolve Conflict

Name of contact Phone E-mail address

N/A

The above represents the best information available to the Department and is included for the convenience of the bidder. The days required for conflict resolution should be considered in the bid as this information has also been factored into the timeline identified for the project when setting the completion date. The applicable portions of the Standard Specifications shall apply.

Estimated duration of time provided above for the first conflicts identified will begin on the date of the executed contract regardless of the status of the utility relocations. The responsible agencies will be working toward resolving subsequent conflicts in conjunction with the Contractor’s activities in the number of days noted.

The estimated relocation duration must be part of the progress schedule submitted by the contractor. A utility kickoff meeting will be scheduled between the Department, the Contractor. and the utility companies when necessary.

The Contractor is responsible for contacting JULIE (or DIGGER/CUAN within the City of Chicago) prior to any excavation work. Please note that IDOT electrical facilities are not part of the one-call locating services, such as JULIE or DIGGER.

If the contract requires the services of an electrical contractor, it is the Contractor’s responsibility, at their own expense, to locate existing IDOT electrical facilities before commencing work. For contracts that do not require an electrical contractor, the Contractor may request one free locate of IDOT electrical facilities by contacting the Department’s electrical maintenance contractor.

Additional locate requests will be at the contractor’s expense.

The Department’s electrical maintenance contractor must be notified at least 72 hours in advance of the work by calling 773-287-7600 or emailing dispatch@meade100.com to arrange for the locating of underground electrical facilities.

Please note, the marking of underground facilities does not absolve the Contractor of their responsibility to repair or replace any facilities damaged during construction at their expense.

SECTION FAP 336 23 RECON NORTH

EMBANKMENT I (D1)

Effective: March 1, 2011 Revised: November 1, 2013

Description. This work shall be according to Section 205 of the Standard Specifications except for the following.

Material. All material shall be approved by the District Geotechnical Engineer. The proposed material must meet the following requirements.

a) The laboratory standard dry density shall be a minimum of 90 lb/cu ft when determined according to AASHTO T 99 (Method C).

b) The organic content shall be less than ten percent determined according to AASHTO T 194 (Wet Combustion).

c) Soils which demonstrate the following properties shall be restricted to the interior of the embankment and shall be covered on both the sides and top of the embankment by a minimum of 3 ft of soil not considered detrimental in terms of erosion potential or excess volume change.

1) A grain size distribution with less than 35% passing the number 75 um (#200) sieve.

2) A plasticity index (Pl) of less than 12.

3) A liquid limit (LL) in excess of 50.

d) Reclaimed asphalt shall not be used within the ground water table or as a fill if ground water is present.

e) The RAP used shall be according to the current Bureau of Materials and Physical Research Policy Memorandum, “Reclaimed Asphalt Pavement (RAP) for Aggregate Applications”. Gradation deleterious count shall not exceed 10% of total RAP and 5% of other by total weight.

CONSTRUCTION REQUIREMENTS

Samples. Embankment material shall be sampled, tested, and approved before use. The contractor shall identify embankment sources, and provide equipment as the Engineer requires, for the collection of samples from those sources. Samples will be furnished to the Geotechnical Engineer a minimum of three weeks prior to use in order that laboratory tests for approval and compaction can be performed. Embankment material placement cannot begin until tests are completed and approval given.

Placing Material. In addition to Article 202.03, broken concrete, reclaimed asphalt with no expansive aggregate, or uncontaminated dirt and sand generated from construction or demolition activities shall be placed in 6 inches lifts and disked with the underlying lift until a uniform homogenous material is formed. This process also applies to the overlaying lifts. The disk must have a minimum blade diameter of 24 inches.

SECTION FAP 336 23 RECON NORTH

When embankments are to be constructed on hillsides or existing slopes that are steeper than 3H:1V, steps shall be keyed into the existing slope by stepping and benching as shown in the plans or as directed by the engineer.

Compaction. Soils classification for moisture content control will be determined by the soils inspector using visual field examination techniques and the IDH Textural Classification Chart.

When tested for density in place each lift shall have a maximum moisture content as follows.

a) A maximum of 110% of the optimum moisture for all forms of clay soils.

b) A maximum of 105% of the optimum moisture for all forms of clay loam soils.

Stability. The requirement for embankment stability in Article 205.04 will be measured with a dynamic cone penetrometer (DCP) according to the test method in the IDOT Geotechnical Manual. The penetration rate must be equal or less than 1.5 inches per blow.

Basis of Payment. This work will not be paid for separately but will be considered as included in the various items of excavation.

BIOSWALE

Description: This work includes furnishing all labor and materials necessary to construct bioswales as shown on the plans. Bioswales consist of topsoil, seeding, class 4 (MOD), heavy duty erosion control blanket, and native sodding, special in combinations as shown on the plans.

Method of Measurement: Topsoil will be measured for payment in accordance with Article 211.07.

Seeding, class 4 (MOD) will be measured for payment in accordance with the Seeding, Class 4 (MOD) special provision.

Heavy duty erosion control blanket will be measured for payment in accordance with Article 251.06.

Native sodding, special will be measured for payment in accordance with the special provision for Native Sodding, Special.

Basis of Payment: Topsoil will be paid for in accordance with Article 211.08.

Seeding, class 4 (MOD) will be paid for in accordance with the special provision for Seeding, Class 4 (MOD).

Heavy duty erosion control blanket will be paid for in accordance with Article 251.07.

Native sodding, special will be paid for in accordance with the special provision for Native Sodding, Special.

SECTION FAP 336 23 RECON NORTH

FAILURE TO COMPLETE PLANT CARE AND ESTABLISHMENT WORK ON TIME

Should the Contractor fail to complete the plant care and/or supplemental watering work within the scheduled time frame as specified in the Planting Woody Plants and Supplemental Watering special provisions, or within 24 hours notification from the Engineer, or within such extended times as may have been allowed by the Department, the Contractor shall be liable to the Department in the amount of:

• $50.00 per tree/per day

• $40.00 per large shrub/per day

• $35.00 per small shrub/per day

• $20.00 per vine/per day

• $20.00 per perennial/per day

• $20.00 per sq yd sod/per day not as penalty but as liquidated damages, for each calendar day or a portion thereof of overrun in the contract time or such extended time as may have been allowed.

In fixing the damages as set out herein, the desire is to establish a mode of calculation for the work since the Department’s actual loss, in the event of delay, cannot be predetermined, would be difficult of ascertainment, and a matter of argument and unprofitable litigation. This said mode is an equitable rule for measurement of the Department’s actual loss and fairly takes into account the loss of the tree(s) if the watering or plant care is delayed. The Department shall not be required to provide any actual loss in order to recover these liquidated damages provided herein, as said damages are very difficult to ascertain. Furthermore, no provision of this clause shall be construed as a penalty, as such is not the intention of the parties.

A calendar day is every day shown on the calendar and starts at 12:00 midnight and ends at the following 12:00 midnight, 24 hours later.

GENERAL REQUIREMENTS FOR WEED CONTROL SPRAYING

Experience. The Contractor shall have previous experience with the use of weed control chemicals. The Contractor shall have had at least three seasons of experience in ecological restoration and the ability to identify and differentiate between targeted weeds and vegetation to remain. The Contractor shall observe and comply with all sections of the Illinois Custom Spray Law, including licensing. Contractor personnel applying herbicides shall have a valid pesticide applicator license issued by the Illinois Department of Agriculture.

The licensed pesticide applicator shall attend the preconstruction meeting and submit their current license to the Engineer. The licensed pesticide applicator shall be qualified at a minimum in Right-of-Way and Aquatics. The licensed applicator shall work on-site.

Equipment. The equipment used shall consist of a vehicle-mounted tank, pump, spray bar, and handgun, plus any other accessories needed to complete the specified work. Spraying shall be done through multiple low-pressure flooding or broad jet nozzles mounted on spray bars operated not more than 36” above the ground. If different sizes or types of nozzles are used to make up

SECTION FAP 336 23 RECON NORTH

the spray pattern, the pressure, sizes, and capacities shall be adjusted to provide a uniform rate of application for each segment of the spray pattern. Hand spray guns may be used for spraying areas around traffic control devices, lighting standard and similar inaccessible areas. Maximum speed of the spray vehicle during application of chemical shall be10 miles per hour.

Pumps used shall have a volume and pressure capacity range sufficient to deliver the mixture at a pressure to provide the required coverage and to keep the spray pattern full and steady without pulsation or excessive pressure as to cause fogging. Maximum pressure for application shall be 15 PSI. Quick acting shut-off valves and spring-loaded ball check valves shall be provided to stop the spray pattern with a minimum of nozzle drip. In areas where the spray vehicle must traverse the right-of-way, a four-wheel drive vehicle with flotation tires will be required to minimize damage to the ground surface.

Additional equipment used shall consist of swiping gloves, wicks, wands, hand spray guns, and/or backpack sprayers, plus any other accessories needed to complete the specified work as directed by the Engineer. Wick applicators, swiping gloves, or other such devices may be required to ensure herbicides are applied only to target species. If hand spray guns used are attached to spray vehicle, maximum speed of the spray vehicle during application of chemical shall be 5 miles per hour. In areas where a vehicle is needed to traverse the right-of-way, a four-wheel drive vehicle with flotation tires will be required to minimize damage to the ground surface.

Prior to beginning work, the Contractor shall obtain approval from the Engineer of the spraying equipment proposed for completing this work. The proposed equipment shall be in an operational condition and available for inspection by the Engineer at least two weeks prior to the proposed starting time. If requested by the Engineer, the Contractor shall demonstrate the calibration of the equipment.

The equipment must provide consistently uniform coverage and keep the spray mixture sufficiently agitated or the work will be suspended until the equipment is repaired or replaced.

Spraying Areas. This work includes roadsides and other types of rights-of-way of various widths and gradients. Spray areas often extend more than 30 feet from the edge of the roadway, requiring both spray bar and handgun applications.

When the description of work requires weed control of a stated species, such as teasel, the chemical shall be applied only to locations where the stated species is present. When the description of work requires general weed control within a bed or area, such as broadleaf weed control in turf, then the chemical shall be applied to the entire bed or area.

Exclusion of Spraying Areas. Areas where weed control spraying is inappropriate or detrimental to the environment, desirable plantings, or private property shall be excluded from the spray area.

Spraying will not be permitted over any drainage swales or waterways, or other areas where the chemical label prohibits application. Spraying will not be permitted within 150 feet of a natural area or site where endangered or threatened species occur.

Responsibility for Prevention of Damage to Private Property. The Contractor shall, at all times, exercise extreme caution to prevent damage to residential plantings, flower or vegetable gardens, vegetable crops, farm crops, orchard, or desirable plants adjacent to the roadside.

SECTION FAP 336 23 RECON NORTH

The Contractor or Department receives a complaint; the Contractor shall contact a complaint within ten days after receiving a claim for damages, either in person or by letter. The Contractor, or their authorized representative, shall make a personal contact with the complainant within 20 days. The Engineer shall also be notified by the Contractor of all claims for damage they received and shall keep the Engineer informed as to the progress in arriving at a settlement for such claims.

Communication with the Engineer. The Contractor is required to communicate with the Engineer to receive all required approvals in a timely way and to assure that the Engineer can accurately document the work performed.

All herbicide application shall be directly supervised by the Engineer for quality assurance and for payment purposes. If the Contractor performs work without the Engineer’s supervision, work will not be paid for.

It shall be the Contractor’s responsibility to assure that all chemical containers are opened and added to the spray mixture in the presence of the Engineer.

The Contractor shall obtain approval from the Engineer to proceed with spraying at each location 24 hours prior to the proposed spray operations.

The Contractor’s superintendent shall closely coordinate the work with the Engineer at all times in accordance with Article 105.06. The superintendent shall attend weekly progress meetings with the Engineer at the Engineer’s office or another mutually agreed upon location. The superintendent shall communicate with the Engineer in the field during weed control activities to facilitate accurate completion of work while it is occurring. At the request of the Engineer, the Contractor shall provide a cell phone number where the superintendent can be reached during working hours. The Contractor shall notify the Engineer at least 24 hours in advance of either discontinuing or resuming operations.

Notification of Pesticide Application, The Contractor will be required to properly provide notification of pesticide application as required by the IL SB3342 Pesticide Application on Rights-of Way Notification Act.

Two weeks prior to the application of pesticides, including but not limited to herbicides, insecticides, algaecides, and fungicides, the Contractor shall complete Operations form “OPER 758” which may be found at the following link: https://idot.illinois.gov/resources/forms.html

The Contractor shall return the completed form to the Engineer. The completed form will be uploaded on the IDOT website as required by the Department of Agriculture and SB3342 at:

https://idot.illinois.gov/transportation-system/environment/natural-resources/roadside-maintenance/pesticide-application.html

The Contractor shall confirm submission of the form has been uploaded before starting spraying operations. Submissions will be sorted by District 1 and McHenry. Allow at least a week for notifications to be uploaded.

Pesticide Application Daily Spray Record. The Contractor will be required to properly track pesticide applications as required by the ILG87 Permit. Reported data from this form will be collected and complied annually and reported to the IEPA as required.

SECTION FAP 336 23 RECON NORTH

Within 48 hours of the application of pesticides, including but not limited to herbicides, insecticides, algaecides, and fungicides, the Contractor shall complete and return to the Engineer, Operations form “OPER 2720”. OPER 2720 may be found at the following link:

https://idot.illinois.gov/resources/forms.html

PLANTING PERENNIAL PLANTS, ORNAMENTAL TYPE

Description: All work under this item shall be performed in accordance with Section 254 of the Standard Specifications except as modified herein. This work consists of planting ornamental type perennials in plant beds.

Delete Article 254.05 Layout of Planting and substitute the following:

When plants are specified to be planted in prepared soil planting beds, the planting bed shall be approved by the Engineer prior to planting. The Contractor shall be responsible for all plant layout. The layout must be performed by qualified personnel. The planting locations must be laid out as shown in the landscape plan. This will require the use of an engineer’s scale to determine some dimensions. Bed limits shall be painted or flagged. Individual plants layout shall be marked prior to installation. The Engineer will contact the Roadside Development Unit at (847) 705-4171 to approve the layout prior to installation. Allow a minimum of three days prior to installation for approval.

Add the following to Article 254.06 Planting Procedures:

When planting perennials in bed areas shown on the plans or as directed by the Engineer, the following work shall be performed prior to planting:

o Do not plant ornamental type perennials when soil is muddy.

o Trees and shrubs must be installed first to establish proper layout and to avoid damage to other plantings.

o Perennial plants shall be planted by a hand method approved by the Engineer. Open holes sized to accommodate roots, place plants so it is level with the surrounding soil and backfill with soil, working carefully to avoid damage to roots and to leave no voids.

Build up a small water basin of soil around each plant.

o Thoroughly water plant beds within 2 hours of installation. Do not wash soil onto crowns of plants.

Delete the first sentence of Article 254.08 Mulching and substitute the following:

A mulch sample shall be submitted to the Engineer for approval seven days prior to placing.

Within 24 hours, the entire ornamental type perennial plant bed shall be mulched with 2 inches of fine grade shredded hardwood bark mulch. Hardwood bark mulch shall be clean, finely shredded mixed-hardwood bark not to exceed 2 inches in its largest dimension, free of foreign matter, sticks, stones, and clods. All hardwood mulch shall be processed through a hammer mill. Hardwood bark not processed through a hammer mill shall not be accepted.

SECTION FAP 336 23 RECON NORTH

Care shall be taken to place the mulch to form a saucer around each perennial so as not to smother the plants or bury leaves, stems, or vines under mulch material.

Delete Article 254.08(b) Period of Establishment and substitute the following:

Perennial plants must undergo a 30-day period of establishment. Additional watering shall be performed not less than once a week for four weeks following installation. Any signs of stress exhibited by plant material must be given special consideration in determining water needs.

Water immediately if plants begin to wilt, or if top 1 inch to2 inches of soil is dry. Water shall be applied at the rate of a minimum of 2 gallons per square foot. Water to ensure that moisture penetrates throughout the root zone, including the surrounding soil, and only as frequently as necessary to maintain healthy growth. Do not over water.

Should excess moisture prevail, the Engineer may delete any or all the additional watering cycles. In severe weather, the Engineer may require additional watering.

Water must be applied in such a manner so as not to damage plant material. Water must trickle slowly into soil and completely soak the root zone. An open end hose is unacceptable.

Water early in the day and apply water as close to the soil as possible without washing out soil or mulch. Water at the base of the plant to keep as much water as possible off plant leaves in order to minimize fungus problems. Watering plants in beds shall be applied in such a manner that all plant holes are uniformly saturated without allowing water to flow beyond the periphery of the bed. Thoroughly saturate all areas of the perennial bed, not just individual plants. The plants to be watered and the method of application will be approved by the Engineer.

The Contractor will not be relieved in any way from the responsibility for unsatisfactory plants due to the amount of watering. Any loss of newly installed plant material determined by the Engineer to be due to lack of water, is the responsibility of the Contractor to replace at no additional cost. Any damage to plant material due to incorrect watering must be corrected or replaced at the Contractor’s expense, to the satisfaction of the Engineer.

Add the following Article 254.08 Period of Establishment:

During the period of establishment, weeds and grass growth shall be removed from within the mulched perennial beds. This weeding shall be performed a minimum of once per week or within 48 hours following notification by the Engineer during the 30-day period of establishment. The Contractor will not be relieved in any way from the responsibility for unsatisfactory plants due to the extent of weeding.

The weeding may be performed in any manner approved by the Engineer provided the weed and grass growth, including their roots and stems, are removed from the area specified. Mulch disturbed by the weeding operation shall be replaced to its original condition. All debris that results from this operation must be removed from the right-of-way and disposed of at the end of each day in accordance with Article 202.03.

Add the following to Article 254.09 Method of Measurement:

a) Disposal of weeds, sod, and debris (rock, stones, concrete, bottles, plastic bags, etc.)

removed from the perennial planting bed as specified in Article 202.03.

SECTION FAP 336 23 RECON NORTH

Add the following to Article 254.10 Basis of Payment:

a) Payment for shredded mulch shall be included in contract unit price of the perennial plant pay item.

b) The unit price shall include the cost of all materials, equipment, labor, plant care, removal, disposal, and incidentals required to complete the work as specified herein and to the satisfaction of the Engineer.

PLANTING PERENNIAL PLANTS, ORNAMENTAL TYPE

Description: All work under this item shall be performed in accordance with Section 254 of the Standard Specifications except as modified herein. This work consists of planting ornamental type perennials in plant beds.

When plants are specified to be planted in prepared soil planting beds, the planting bed shall be approved by the Engineer prior…