This is a work location and project scope document for the I-75 South Winter Litter and Mowing (WLS) project scheduled for January 2026, involving the Kentucky Transportation Cabinet and multiple counties across Districts 7, 8, and 11. The project encompasses litter removal and mowing operations along Interstate 75 and Kentucky Highway 92, spanning approximately 114.27 miles across Fayette, Madison, Rockcastle, Laurel, and Whitley counties, plus a 10.38-mile segment on KY 92 in Whitley County. The work includes mowing of approximately 1,120.6 acres with three mowing cycles per year and litter removal with five cycles per year on all routes. The contractor must complete each cycle within a maximum of 15 working days. The project is divided into multiple sections with specific milepost markers defining project limits, and batwing mowers are permitted on Interstate 75 routes.
The document does not contain information regarding pricing terms, set-asides, incumbent contractors, funding sources, or contract award dates. The file serves primarily as a work location and scope reference sheet for bidders to understand the geographic areas, route segments, acreage, and operational requirements for the litter and mowing maintenance project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet 1 of 1 Litter
Project Type 3 Number Removal Number Route Project Length Mowing of Cntrln of
Number System County Number Begin End (Miles) Acres Cycles Miles Cycles
I-75* Interstate Fayette FE01 034 0075 Madison Co. Line KY 418 6.347 101 3 6.4 5
097-104 (MP 97.543) (MP 103.890)
I-75* Interstate Madison FE01 076 0075 Rockcastle Co. Line Fayette Co. Line 24.135 503 3 24.1 5
073-098 (MP 73.408) (MP 97.543)
Subtotal (District 7) 30.482 604 30.5
I-75* Interstate Rockcastle FE01 102 0075 Laurel Co. Line Madison Co. Line 22.641 98 3 22.6 5
050-074 (MP 50.767) (MP 73.408)
Subtotal (District 8) 22.641 98 22.6
I-75* Interstate Laurel FE01 063 0075 Whitley Co. Line Rockcastle Co. Line 22.824 158.6 3 22.8 5
027-051 (MP 27.943) (MP 50.767)
I-75* Interstate Whitley FE01 118 0075 Tennessee State Line Laurel Co. Line 27.943 221 3 28 5
000-028 (MP 0.000) (MP 27.943)
KY 92 MP Whitley FE01 118 0092 McCreary Co. Line Happy Hollow Road 10.380 39 3 10.4 5
000-011 (MP 0.000) (MP 10.380)
Subtotal (District 11) 61.147 418.6 61.2
Grand Total 114.270 1,120.6 114.3
Limits of Project
I-75 South Mowing Work Location Sheet
* A batwing mower will be allowed on this route(s).
Maximum time to complete a cycle: 15 working days.