210811 RFP QA.pdf

PDF 500 KB Posted

Attached to
SDDC GATES Federal contract opportunity
Solicitation number
HTC711-21-R-D003
Issued by
Department of Defense United States Transportation Command

About this file

This document contains a question and answer file related to solicitation number HTC711-21-R-D003 for SDDC GATES contract management and training support services. The requirement includes designing, developing, implementing, and maintaining GATES training for an estimated 2,500 users worldwide. It also requires assisting with functional questions, testing, and customer issues related to GATES surface and water actions from any location. The contract period begins in September 2021, with deliverables for system levels C and D due no later than 30 and 60 days respectively from award. Pricing is undetermined and will depend on each vendor's technical approach. The required level of effort and number of FTEs are proprietary to each offeror. The Department of Defense United States Transportation Command is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to SDDC GATES, newest first.
File Type Posted
Atch 1a 210811 GATES PWS.pdf PDF
210811 RFP HTC711-21-R-D003 Amd 0001.pdf PDF
Atch 9 PPQ.pdf PDF
Atch 7 PP Log.pdf PDF
Atch 5 CLIN Structure.xlsx XLSX spreadsheet
Atch 1a GATES PWS.pdf PDF
Atch 8 PP Ref Sheet.pdf PDF
Atch 4 RFP Info Sheet.pdf PDF
Atch 3 DD254.pdf PDF
Atch 2 GATES QASP.pdf PDF
Atch 10 GFP.pdf PDF
Atch 6 Staffing Matrix.xlsx XLSX spreadsheet
Atch 1b Appendix 3 CWMT.pdf PDF
210719 RFP HTC711-21-R-D003.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HTC711-21-R-D003

SDDC GATES

# Question Answer Quick Reference

Item 1.3.3.3, Implementation and Maintenance states: "Final design should be ready no later than Aug for both levels." Would the Government please clarify as contract does not begin until September?

This was an oversight/typo and is not relevant to levels C and D.

Dates for C and D would be NLT than 30 days of contract award for level C and NLT 60 days from contract award for level D.

PWS 1.4.1 Deliverables, Table of Deliverables - Page 11

2 What will be the LOE for this opportunity? The LOE is determined by each vendor. RFP

3 How many FTEs are currently working on this opportunity?

The number of FTEs is predicated upon a vendors technological approach and is proprietary in nature. RFP

Date Answered: Posted 12 Aug 2021