HTC711-13-R-R017_Questions Answers_3rd_Round.pdf
PDF 411 KB Posted
- Attached to
- AFRICOM Dedicated Rotary Wing Services
- Solicitation number
- htc711-13-r-r017
About this file
Rotary Wing Question Answers Round 1 (1-35) Round 2 (36-72) Round 3 (73-121)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_5_HTC711-13-R-R017_SOL.pdf | ||
| Attachment_1_-_Rotary_Wing_PWS_v12.pdf | ||
| Attachment_3_-_Payment_Information.docx | DOCX document | |
| Amendment_4_HTC711-13-R-R017_SOL.doc | DOC document | |
| Attachment_1_-_Rotary_Wing_PWS_v11.pdf | ||
| Amendment_3_HTC711-13-R-R017_SOL.pdf | ||
| Attachment_7_DD254_HTC711-13-R-R017_1Rotary_Wing_Signed.pdf | ||
| HTC711-13-R-R017_Questions Answers_1st_Round.xlsx | XLSX spreadsheet | |
| Attachment_1_-_Rotary_Wing_PWS_v10.doc | DOC document | |
| Attachment_2a_HOGE.docx | DOCX document | |
| Amendment_2_HTC711-13-R-R017_SOL.doc | DOC document | |
| Attachment_4_-_Security_Controls_and_Template.docx | DOCX document | |
| Attachment_5_-_Past_Performance_Questionnaire.docx | DOCX document | |
| Attachment_6_WAWF_.doc | DOC document | |
| Attachment_1_-_Rotary_Wing_PWS_v9.doc | DOC document | |
| Attachment_3_-_Payment_Information.docx | DOCX document | |
| Attachment_2_Type_Aircraft_.doc | DOC document | |
| Amendment_1_HTC711-13-R-R017_SOL.doc | DOC document | |
| HTC711-13-R-R017_Final_ROTARY_WING_SOL.doc | DOC document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date
Received RFP Page # RFP Para # Question Comment Category US Government Response Status
1 12-Sep-13 N/A N/A
Is there a breakdown available of where current contractor personnel are located in support of the RW contract throughout the AOR? Personnel Contractor personnel are located in Obo, CAR. Closed
2 12-Sep-13 N/A N/A Is there any baggage scanning equipment available in Obo? Equipment No. Closed
3 12-Sep-13 N/A N/A Is there a list of any equipment that will be left in place from the previous contract holder? Equipment No. Closed
4 12-Sep-13 When is the contract award date scheduled? Contract Award Date
22 November 2013. This date was added to Addendums 52.212-1 & 52.212-2 (1st paragraph) via Amendment 0002. Closed
5 12-Sep-13 N/A N/A
Will there be a site survey of the facilities and outstations in the AOR prior to or after the award date? Site Survey
The acquisition office does not have the authority to grant/facilite offeror site visits, however, does not object to arrangement made directly by bidders. Closed
6 12-Sep-13 N/A N/A
Is there a training requirement from the Govt. to be maintained by the Contractor for key
Contractor personnel? (Pilots, Medical, etc.) If so, when will those requirements be made available? Training
In addition to the training requirements as required by Federal Aviation Regulation 133 and 135 and 32 CFR 861 or applicable CAA equivalent, please refer to the AFRICOM website (http://www.africom.mil/staff-resources/travel-to-africa) for information on training contractor personnel deploying to Africa. Closed
7 12-Sep-13 N/A N/A
Is there an APO available for mail? If not, what is the plan for sending and receiving mail for contractors? Assets Yes. Mail is sent and received through the Embassy in Kampala, Uganda. Closed
8 12-Sep-13 N/A N/A Is there a list of OFF LIMITS AREAS in Obo? Security There are no off limit areas in Obo, CAR as defined by the ACCE. Closed
9 12-Sep-13 Is there a requirement for the contractor to live on the compound or out in Obo? Personnel
There is not a requirement defining where to live. For operational considerations, the
Government recommends the Contractor lives on the compound next to US forces. IAW
PWS paragraph 1.4.7, the Contractor will provide for accommodations. Closed
10 12-Sep-13 N/A N/A
If the contractor is required to live on the compound in Obo, exactly how many living quarters
(if any) are currently available? Personnel
There are no living quarters designated for contractors on the compound however quarters may be subcontracted. IAW PWS paragraph 1.4.7, the Contractor will provide for accommodations. Closed
11 12-Sep-13 N/A N/A Is there a DFAC (dining facility) available for contractors to use on Obo? Assets
No. Contractor is responsible for their own supplies IAW PWS paragraph 1.4.7.
Contractor may use a subcontractor to provide food to personnel if so desired. Closed
12 12-Sep-13 Attch 1 - PWS pg 2 1.1
Is there a past performance history available of the types of flights conducted and their frequency? (Day, Night, NVG, Airborne Ops, Waterborne Ops, Sling loads, etc) Past Performance
This information is not releasable, however IAW PWS para 1.2.6.1 & 1.4.3, the contractor will be required to perform operations under various conditions as listed in the PWS. Closed
13 12-Sep-13 N/A N/A Is there a list available of assets and or services available in Obo? Assets Please clarify and provide examples of "assets" and "services". Closed
14 12-Sep-13 N/A N/A Are contractors allowed to be armed on this contract? Personnel No. Closed
15 12-Sep-13 N/A N/A Are contractors allowed to sub-contract force protection services for this contract? Security
The contractor is not required to provide any security. The Government provides security at each outstation. United States Special Operations Forces (USSOF) provides security at each outstation. (The Contractor might want to provide security at their domicile, wherever they choose to live. It is not required, but it is recommended.
USSOF at the outstations are also the security forces. But again, the Government doesn't perform 24/7 security patrols with armed guards.) Closed
16 12-Sep-13 N/A N/A Does the airfield at Obo have runway lighting? Airfield
Yes, however they are not permanent. They are portable lights that need to be set up manually with several hours notice. Closed
17 12-Sep-13 Attch 1 - PWS pg 9 4.1.1 Is there a time requirement for the PM to visit/live in Obo since he will be based in Entebbe? Personnel
There is no time requirement. The PM may visit Obo as required. That is encouraged.
IAW PWS paragraph 1.1.3.7, the PM has to receive CONOPS and mission scheduling in
Entebbe. This person will be the focal point for coordination with the ACCE regarding
RW operations occurring throughout the mission areas. Closed
18 12-Sep-13 N/A N/A Is there a medical facility in Obo or would the contractor have to provide one? Assets
There is not a medical facility at Obo. The nearest set up is manned by USSOF at Nzara, RoSS. IAW PWS paragraph 1.4.7, The contractor is responsible for providing all medical supplies and support for their personnel. The government is not responsible for supplying medical support although USSOF medics may volunteer to help with casualties.
The government has a contract in place for Personnel Recovery/Casualty Evacuation for the OOC location that may be used by the contractor to MEDEVAC contract personnel when required, any expenses occured will be paid by the contractor. Closed
19 12-Sep-13 N/A N/A Would the contractor be required to attend a CRC prior to deployment? If so, which one? Training
CONUS Replacement Center (CRC) Training is not required prior to deployment to Africa.
Please refer to the AFRICOM website (http://www.africom.mil/staff-resources/travel-to-africa) for information on training contractor employees prior to deploying to Africa and other additional information on travel to Africa. Closed
20 12-Sep-13 Attch 1 - PWS pg 7 1.5.2 Will the contractor be required to provide MEDEVAC services on call? Aircraft Services
No. However, IAW PWS paragraph 1.5.2, the contractor may be required to transport, "U.S. Armed Forces personnel suffering from medical emergencies in which life, limb, or eyesight may be lost". Closed
21 12-Sep-13 N/A N/A Is there any imagery available of the compound in Obo? Airfield Imagery is not releasable. Closed
22 12-Sep-13 Attch 1 - PWS pg 5 1.3.1
Is there a Clearance requirement for Fuelers, Aviation Mechanics or Flight Operations
Personnel? Personnel
No. IAW PWS Para 1.3.1 "All aircrew and site managers performing under this contract are required to possess a Secret security clearance in order to receive threat briefings." Closed
23 12-Sep-13 N/A N/A
Is the contractor expected to staff and run a Tactical Operations Center (TOC) or to supply personnel to work in one ran by the military? Assets
The ACCE has a TOC at Entebbe, Uganda; Dungu, DRC; Obo, CAR; and Nzara, RoSS. The
Contractor is not expected to staff and run a Tactical Operations Center (TOC) or required to supply personnel to work in one ran by the military. Closed
24 13-Sep-13 N/A Amendment 0001
The subject solicitation was issued on fedbizops on 11 September. When we downloaded that document, it was identified as a “draft” document dated 9 September with a proposal due date of 9 October. Yesterday all of the documents were taken off of fedbiz ops. This morning, all of the documents have been reloaded, but the solicitation is no longer marked as a draft.
However, the issuance date still shows 9 September and a proposal due date of 9 October. Do you anticipate that the issuance date and the proposal due date will be corrected to push the dates farther to the right?
Solicitation & Proposal
Due Date
See Amendment 0001 posted on 11 Sept 13, which changed the Solicitation issue date from 9 Sep 13 to 11 Sep 13 and the proposal due date and time from 9 Oct 13 at 2:00PM
CST to 11 Oct 13 at 4:00PM CST. Closed
25 16-Sep-13 Attch 1 - PWS pg 4 1.2
In light of the distances being contemplated for this operation, will the government consider adding to the lift requirement a requirement for a minimum leg length and/or flight duration in order that the end user gets an aircraft that can accomplish their mission? Aircraft Requirements Yes, See Amendment 0002, paragraph 1.2.9.2. for lift requirements. Closed
26 16-Sep-13
Attch 1 - PWS pg 4
-5 1.2.5
Considering aircraft lift capability is greatly reduced when ambient temperature is high, and considering central Africa has very high ambient temperatures, will the government add an ambient temperature parameter to the lift performance requirement in order to ensure the aircraft contracted is capable of lifting the specified load under the typical hot weather conditions anticipated for this operation? Aircraft Requirements Yes, See Amendment 0002, paragraph 1.2.9.2. for lift requirements. Closed
27 16-Sep-13 Attch 1 - PWS pg 5 1.2.6.1
Will the government grant an additional period of time to allow contractor to commence NVG operations? 60 days after operational date is preferable. Aircraft Requirements The Government's requirement remains unchanged. Closed
28 16-Sep-13 Attch 1 - PWS pg 5 1.3.1
Will the government delete the requirement for aircrew to possess security clearances, and if need be, require only that a loadmaster/passenger expediter possess a security clearance? Clearance
No. There is too much valuable information that enhances situational awareness and mission execution to delete this requirement. The Government's requirement remains unchanged. Closed
29 16-Sep-13
Attch 1 - PWS pg
10 4.2.5
In lieu of obtaining its own FCL, would it be acceptable for the contractor to outsource the respective functions/cleared personnel from a third-party company with a FCL? Clearance
No. The prime contractor must have a valid FCL at the SECRET level IAW Attch 1 - PWS para 4.2.5. Closed
30 19-Sep-13 N/A N/A What are the current facilities at Obo? Facilities
There are no designated contractor housing in Obo, CAR. Contractor may utilize a subcontractor to provide housing, etc for contractor personnel Closed
31 19-Sep-13 N/A N/A Does the government provide subsistence and if so, how much? Services
No. IAW PWS paragraph 1.4.7, "The Contractor shall procure all items necessary to support Contractor personnel at Obo, CAR. These items may include, but are not limited to accommodations, medical support, food, office supplies, training aids, computers, printers, beds, lockers, lamps, generators, bottled water, and anything else the
Contractor deems necessary to accomplish the contractual requirements outlined in this
PWS, such as equipment, logistical support, equipment training tasks, etc." Contractor may use a subcontractor to provide food to personnel if so desired. Closed
32 19-Sep-13 N/A N/A Is there any Government Furnished Equipment associated with this operation? Services No. Closed
33 19-Sep-13 Attch 1 - PWS pg 2 1.1 What is the definition of limited security? What is the current security status at Obo? Security
The intent of limited security in PWS para 1.1 is for the contractor to maintain vigilance, secure aircraft, restrict access as required, and secure equipment, mission materials, etc.
The contractor is not required to provide secuirty as the United States Special
Operations Forces (USSOF) provides security. (The Contractor might want to provide security at their domicile, wherever they choose to live. It is not required, but it is recommended. USSOF at the outstations are also the security forces. But again, the
Government doesn't perform 24/7 security patrols with armed guards.) Closed
34 19-Sep-13 N/A N/A The contract specifies armed security, is this only to be provided by the contractor? Security
Please clarify where the contract specifies armed security. The Government provides security at each outstation. United States Special Operations Forces (USSOF) provides security at each outstation. (The Contractor might want to provide security at their domicile, wherever they choose to live. It is not required, but it is recommended.
USSOF at the outstations are also the security forces. But again, the Government doesn't perform 24/7 security patrols with armed guards.) Closed
35 20-Sep-13
Attch 1 - PWS pg
4, pg 9/10 1.2.4, 4.2.1, 4.2.5
Given the referenced PWS requirements, can a team (consisting of two companies) meet these requirements collectively by either having a Foreign approved DOD air carrier as the
Prime Contractor with a cleared Subcontractor (holds required FCL) providing the required cleared US personnel or can the cleared US company act as the Prime Contractor with a
Foreign approved DOD air carrier as the subcontractor.
DoD Approval and
Additional Standards;
General Security
Information; Facilities
Clearance Level (FCL)
No. The prime contractor must have a valid FCL at the SECRET level IAW Attch 1 - PWS para 4.2.5. Additionally, IAW 52.212-1(1), to be eligible to receive a contract award the offeror (prime contractor) must be an approved DOD air carrier as determined by HQ
AMC/A3B and the CARB. Closed
36 24-Sep-13 PWS pg 3 1.1.3
The contract lists the personnel authorized to utilize the aircraft. Will the contractor be approved to transport their own personnel for crew rotations, etc. on a space-available basis? Rotary Wing Service Yes, as long as the mission is not hampered. Closed
37 24-Sep-13 PWS pg 3 1.1.3.1
The PWS requires the contractor’s aircraft be equipped with SATCOM antennae connection to allow communication with U.S. Military ground units. Please provide the radio specs to ensure antennae compatibility with the Government’s required radios. Mission Planning
The SATCOM antennae shall be compatible with the following types of equipment:
Harris AN/PRC-150, AN/PRC-117G, Raytheon RT-167, AN/PRC-150, AN/PRC-152, THURAYA and Iridium phones. Closed
38 24-Sep-13 PWS pg 3 1.1.3.2
Does the government expect a contractor to provide crewing for the aircraft to maintain 24/7 availability? Or will missions be scheduled to allow for proper crew rest before the next tasking? Emergency Missions
The Government may task one plane for one or more tasks per day depending on mission requirements. IAW Attch 1 - PWS para 1.1.1 "missions will be scheduled at least seventy-two (72) hours in advance, unless otherwise agreed to by the contractor and
COR." Therefore, contractor will be able to schedule crews appropriately. Additionally, IAW PWS para 4.7.1 "Crew duty day requirements are governed by Federal Aviation
Regulation Part 133 or 135 or applicable CAA regulations." You won't need to maintain
24/7 availability at all times. Normally, missions will be scheduled the day prior so that crew and aircraft planning will allow for proper crew rest. This is a very dynamic mission, however. There may be times when 24/7 availability is necessary, but this will not be the standard. At all times, proper crew rest rules will be followed. So for planning purposes, crews may be on alternating shifts for certain mission requirements. Closed
39 24-Sep-13 PWS pg 3 1.1.3.4
With the intent of providing services within 1,000 meters of Kinetic activity, will the government require ballistic protection in the aircraft for the passenger and cockpit areas? Mission Requirements
The government does not require the ballistic protection in the aircraft for the passengers or cockpit area. Closed
40 24-Sep-13 PWS pg 4 1.2.5
Does a SOFA agreement currently exist in this region? Will the government provide a copy of any existing SOFA agreement for the contractors use in supporting this operation?
Rotary Wing
Requirements There is no SOFA agreement in the region. Closed
41 24-Sep-13 PWS pg 4 1.2.5
The PWS states, “each aircraft should have the capacity to transport 12 personnel weighing
250 pounds each to include their personnel protective gear to include their weapons with basic ammo load.” Will the government please confirm, these passengers may be accompanied by additional gear requiring the aircraft to not only be able to seat 12 passengers, but also properly stow their equipment?
Rotary Wing
Requirements
The aircraft needs to seat 12 passengers, the contractor is responsible for properly stowing and securing any additional cargo that is carried and is within the aircraft weight limit. The government will not demand the contractor to exceed the helicopter's capacity. However, if 12 pax are carried and there is no room for cargo, then any cargo not transported is expected to fly on another asset or another mission. See PWS paragrapgh 1.2.9.2 Closed
42 24-Sep-13 PWS pg 4 1.2.5
Will the government please confirm, the aircraft at a minimum shall be capable of transporting
12 passengers, their equipment, and provisioning for aircrews like camping equipment for emergency purposes or remain over nights (RONs) where there is no government provided services available?
Rotary Wing
Requirements
Transport of 12 passenger is accurate for this requirement. Passengers will be dropped off at locations or HLZs where no services are available (i.e., literally in the middle of the jungle), however air assets will return to an outstation collocated with USSOF after dropping off pax/cargo. Some villages and cities have hotels. At other locations local partner nation forces agrees to provide lodging at their camp for mission personnel, including the Contractor crew. This may/may not include tents, small shacks, or a well-constructed building with water and electricity. Although very rare, if it is expected that an air asset has to RON on a remote site, you can bring your own equipment (MREs, water, equipment, etc.). In the event an air asset cannot return to an outstation, USSOF accompanying the aircraft will provide force protection.
Closed
43 24-Sep-13 PWS pg 5 1.3.1 Will the government accept interim SECRET level security clearances on this contract? Personnel
Yes, Interim personnel clearances are acceptable for accessing classified information.
However, the investigation must show "OPEN" at OPM before any interim will be accepted. This ensures that the name, fingerprint and criminal records searches have been completed.
Closed
44 24-Sep-13 PWS pg 5 1.3.6 Will the government reimburse for Defense Base Act insurance? Personnel DBA Insurance should be bid into the contractor's fixed operation costs. Closed
45 24-Sep-13 PWS pg 6 1.3.3
Will the government allow contractors to utilize the FW contract assets on a space-available basis to support crew rotations and resupply efforts in Obo, CAR? Personnel
The Government may task the fixed wing aircraft to bring support materials, etc out to
Obo, CAR, however, these missions are at the Government's discretion.
Closed
46 24-Sep-13 PWS pg 7 1.4.8
The PWS states, “Contractor is responsible to provide or purchase aviation fuel for helicopter operations at all locations to include Obo, Djema, Nzara, Dungu, and Entebbe.” Fuel is not simply available for purchase at these locations requiring contractors to truck fuel deep into the jungle. By road, Obo is approximately a 7 week one way trip. In order to ensure there is no interruption in service at these locations, will the government require all contractors to present their fuel logistics plan as part of their proposal? Fuel No Closed
47 24-Sep-13 PWS pg 9 4.1.1
The PWS states, “The contractor will provide a project manager (PM) and an alternate PM to be located in Entebbe, Uganda.” Is it the government’s intention to have the PM and alternate
PM on site at the same time, or is this referencing rotation? Points of Contact
The PM and alternate can rotate. The contractor will have someone available at all times to answer any questions or address any concerns the government may have pertain to the mission. Closed
48 24-Sep-13 PWS pg 12 4.6.1
Will the government provide access to secure communication equipment at the operations center to allow contractor to communicate with secure communication equipment installed in the aircraft? Communications
Yes. With your security clearance, you'll have access to the OPCENs and the classified phone systems and radios. Closed
49 24-Sep-13 PWS pg 12 4.6.1
The PWS states, “When operating missions, the contractor’s operations center will be required to maintain secure voice communications.” Does this mean in the aircraft to ground forces?
From the operations center in Entebbe to the aircraft? Will the government please further define this requirement. Communications
Ground forces and OPCENs need to be in contact with the aircraft. At times, due to range and line of sight limitations, the OPCENs may not be in direct contact with the aircraft. Other OPCENs or ground forces will still be in contact. Closed
50 24-Sep-13 PWS pg 8 3.4
In the event the contractor is required to remain overnight in a location where lodging is not available, are we expected to be equipped to care for up to 12 government passengers overnight?
Reimbursable Services and Costs No. The Government/host nation personnel will care for themselves. Closed
51 24-Sep-13 PWS pg 8 3.5
The government offers per diem and reimbursement for lodging should a contractor be required to RON en route. In this operating environment there, are no rentable accommodations. Will the government confirm the contractor is required to provision for en route RON’s where no food or lodging is available?
Reimbursable Services and Costs
Air assets will return to an outstation collocated with USSOF after dropping off pax/cargo. Although very rare, if it is expected that an air asset has to RON on a remote site, you can bring your own equipment (MREs, water, equipment, etc.). Some villages and cities have hotels. At other locations local partner nation forces agrees to provide lodging at their camp for mission personnel, including the Contractor crew. This may/may not include tents, small shacks, or a well-constructed building with water and electricity. closed
52 24-Sep-13 Solicitation CLINs
Will the government please verify the delivery schedule of the CLINs? There appear to be some gaps in the schedule. CLINs
CLINs are divided by task orders, each task order has a separate set of CLINs. Please clarify where gaps appear in the schedule. Closed
53 24-Sep-13 PWS pg 5 1.2.6
In order to provide the government with greater capability at landing zones where tall grass can be an inhibitor of extraction, will the government require a rescue hoist on each aircraft and Part 133 Hoist operator for hoist missions? Aircraft Equipment
No, Hoist capability is not required. The Government's requirement remains unchanged. Closed
54 24-Sep-13 PWS pg 2 1.1 What are the potential operating locations for the DRC, envisioned in this part of the PWS Scope of Contract
Dungu, DRC is the primary location considered for this country. Other potential locations are classified for mission purposes. Closed
55 24-Sep-13 PWS pg 3 1.1.3 Will partner nation forces always fly accompanied/escorted with a US force person abroad? Rotary Wing Service
USSOF will always fly with partner nation forces if they are armed, they may or may not be accompanied/escorted if not armed. Closed
56 24-Sep-13 PWS pg 3 1.1.3.4
Can the government provide us with a short-short list of weapons systems believed to be in the hands of rebels (or hostile) actors in CAR – so we can generate operational risk assessments related to this part of the PWS? Including actors of LRA, Seleka Rebels, Bozize loyalists, or other rebel groups within the operational area? Mission Requirements
This information is classified, however you may find some useful information through independent research. Closed
57 24-Sep-13 PWS pg 27
1.4.7 &
252.225.7040 ( c)
Does contract clause 252.225.7040 (c) apply to Obo, Nzara, other parts of South Sudan, and
DRC? “…Combatant Commander will develop a security plan for protection of Contractor personnel in locations where there is not sufficient or legitimate civil authority.” What are the limits of the Commander’s responsibility for physical security of contractor personnel in those field camp locations?
Support Operations and
Clause
USSOF will provide force protection for the Contractor crew and air asset. The limits will depend on force size, location, perceived/known threat location and capabilities, environmental concerns, etc. Closed
58 24-Sep-13 PWS pg 7 1.4.8
Will the government provide any security for fuel dumps at forward locations or will that responsibility fall on the contractor? Support Operations The Contractor is responsible for providing fuel and securing it at the forward locations. Closed
59 24-Sep-13 PWS pg 11 4.2.11
The PWS states, “Contractor personnel assigned elsewhere shall attend security training established by their respective Government security offices and/or installations.” What training will be required for personnel on this contract? What locations offer this training?
What is the lead time for personnel to process through these locations? Will the government reimburse travel expenses for personnel attending training under this requirement? Security Training
Please refer to the AFRICOM website (http://www.africom.mil/staff-resources/travel-to-africa) for further information on training contractor personnel deploying to Africa.
Additionally, the State Department website (http://www.state.gov/) is another source for information on travel to Africa. Only items identified in PWS Section 3 "Reimbursable
Services and Costs" are authorized for reimbursement under this contract. All other costs should be included in the contractor's fixed operation costs. Closed
60 24-Sep-13 Solicitation pg 33 252.225.7040 (m)
What are the trigger lines of risk-based scenarios, that drive the evacuation sequence and decision making for the Combatant Commander? This will aid in the proper development of emergency evacuations plans for this contract. Security
The triggers vary based on each dynamics/mission. Triggers and decision-making matrices are classified. Closed
61 24-Sep-13 PWS
Is this requirement to have crews available 24 hrs per day? For example 2 pilots during the day and 2 pilots during the night. Personnel
Contractors are not required to maintain 24/7 availability at all times. There may be times when 24/7 availability is necessary, but this will not be the standard. Normally, missions will be scheduled the day prior to allow aircraft planning and ensure proper crew rest rules will be followed at all times. So for planning purposes, crews may be on alternating shifts for certain mission requirements. Closed
62 24-Sep-13 PWS 4.2.2
In Para 4.2.2 it indicates that the contractor performing services under this contract and requiring classified access shall be citizens of the United States of America. Does this preclude us from using Canadian crews with Secret level Security clearances? Clearance
No, however, due to the dynamics of the missions, timely execution is imperatitive to the missions success, due to additional security requirements that have to be followed when briefing classified information to foreign nationals this could hinder or delay mission execution. Closed
63 24-Sep-13 PWS 1.3.1
Other than I.T. or ADP, which positions will need access to classified information? pilots, AME's, base management, senior management at HQ? Clearance
IAW PWS Para 1.3.1 "All aircrew and site managers performing under this contract are required to possess a Secret security clearance in order to receive threat briefings." Closed
64 24-Sep-13
Addendum 52.212-
Basis of Award (1)
Part-1 Technical
(v)
Given the tight timeline between award and stated operational readiness, is there any flexibility in the start dates to enable the operator to ready the aircraft. Operational date No, The contractor has to be operational ready to perform on 24 Dec 13. Closed
65 24-Sep-13
Non US Flag Carriers are still allowed to bid for the RW AFRICOM contract as long as they are listed as a SUB and not Prime and are CARB compliant. Correct? Proposal Submission
Any vendor can submit a bid for this solicitation, however, please refer to Addendums
52.212-1&2 for guidance on proposal submissions. Specifically, Addendum 52.212-1 (1) states "(1) Pursuant to DoDI 4500.53, to be eligible to receive a contract award, the offeror must be an approved Department of Defense (DOD) air carrier as determined by
HQ AMC/A3B and the Commercial Airlift Review Board (CARB) at time of proposal submission for the aircraft type proposed under this Solicitation. The offeror’s DOD approval must be for service equivalent to the service described in this solicitation. DOD approval must be received by the date of solicitation close and maintained throughout performance of this contract. The awardee for both IDIQ and subsequent task orders must be the entity that will operate the aircraft under this contract, unless subcontracting is required by international agreement. " Closed
66 25-Sep-13
Addendum 52.212-
1 (4) (vii) 39
This section specifies that we need to fill in blocks 6a, 6b, 6c, 8a, 8b and 8c of the DD254. Are we required to fill in blocks 8a, 8b and 8c or was this a typo? DD254
See Amendment 0003 which removes the requirement to fill in blocks 8a, 8b, and 8c of the DD254. Closed
67 26-Sep-13 PWS 1.1.2
“The base period will include 120 surge hours…” CLIN 0005 Base Period -- lists Max Quantity of 60
Surge Flight Hours. Can you please clarify which one will take precedence, or if we are only be required to price for 60 hours, but it could still be 120? Surge Hours See Amendment 0003 which changes the Surge Flight Hours from 60 to 120. Closed
68 26-Sep-13 N/A N/A Does the DD254 need to be submitted prior to proposal submission to obtain an interim FCL? DD254
IAW PWS para 4.2.5, "FCL procedures and security guidelines for adjudicative requirements are outlined in DOD 5220.22-M and DOD 5200.2-R. " Closed
69 26-Sep-13
PWS Section 1.3
pg. 5 1.3.2
What are the known certificates required to work in the AOR? Personal - Pilot mechanic certs? Visas for which of the countries? Personnel
There are no known certifications required to work in the AOR. All personnel should have visas from Uganda, DRC, and RoSS. At the minimum, all personnel need to arrive with Ugandan visas already approved. The ACCE can help get visas for DRC and RoSS after arrival if necessary.
Closed
70 26-Sep-13
PWS Section 1.4 pg.7 1.4.8
Is the contractor responsible for supplying, storage, security and transporting fuel to all locations (Njema, Nzara, Dungu and Obo)? Will fuel be available for purchase at UN bases
(Dungu and Bunia)? If so, what is the method of payment? Fuel The Contractor is responsible for providing fuel and securing it at the forward locations. Closed
71 26-Sep-13
PWS Section 4.4 pg 12 4.6.1 Who is the JSC-A and what is the form of secure communications? Communications See Amendment 0003 removing this requirement. Closed
72 26-Sep-13
PWS Section 1 pg.
2 1.1 There are two runways in Obo. Will the contractor stage from the north or south runway? Airfield The contractor will be staged in the North. Closed
73 27-Sep-13
Amendment 2 pg
6 (e) N/A
Operational date of 24 DEC 2013. With the award date of 22 NOV, this leaves 31 days for preparation and mobilization. Does TRANSCOM foresee the Operational date moving to the right? Operational date
No, TRANSCOM does not foresee pushing these date to the right, we intend to award on
22 NOV 13 with performance start date of 24 DEC 2013. Closed
74 27-Sep-13 General N/A
Is this contract's intent to replace the current contractor or is it in addition to the current contractor? General This contract will replace the current contract. Closed
75 30-Sep-13 General N/A
Will the Government consider a small business set-aside preference to allow small businesses to be evaluated favorably in the award criteria? General
The Government determined a small business set-aside is not appropriate for this acquisition. Closed
76 30-Sep-13 PWS pg 5 1.3.1
RFP states that key personnel are required to have US Secret clearances. Is this limited to only the pilots and project managers? Clearances
IAW PWS Para 1.3.1 "All aircrew and site managers performing under this contract are required to possess a Secret security clearance in order to receive threat briefings." Closed
77 30-Sep-13 PWS pg 5 1.3.1
As the existing contract originally did not require US Secret clearance for contractor personnel, would the government consider allowing contractor pilots that are not US Citizens to support this contract in order to provide better availability of experienced NVG and PWS mission specific skills? The project manager and Obo based site manager or Lead Pilot could have a
SECRET clearance to receive mission information and brief pilots/crew only limited information to mantain control of SECRET information. Clearances
IAW PWS Para 1.3.1 "All aircrew and site managers performing under this contract are required to possess a Secret security clearance in order to receive threat briefings." Closed
78 30-Sep-13 PWS pg 5 1.3.1
Will the Government consider NATO or SECRET clearances from other major allied countries as acceptable? Clearances
There are other factors that need to be considered, therefore the Government cannot provide a definitive answer to this question. Closed
79 30-Sep-13 General N/A
Will the Government provide Space-Available for transportation of contractor personnel, equipment and/or cargo on Military Airlift to support the rotor wing program based in Obo? General
Space-A cannot be guaranteed, but there will probably be limited times when it can be used to support the RW program. However, it is the contractor's responsibility to provide support. Closed
80 30-Sep-13 General N/A
Will the Government allow the rotor wing provider to utilize available space on the contracted fixed wing aircraft that support the same mission and customer (Referring to the Sister
RFP/Contract, fixed wing air support, Central Africa Region, RFP#: HTC711-13-R-R016)? General
The Government may task the fixed wing aircraft to bring support materials, etc out to
Obo, CAR, however, these missions are at the Government's discretion. Closed
81 30-Sep-13 General N/A Is the rotor wing air carrier required to have Class D Ops Specs approval? Ops Specs
The contractor is required to have any Ops Spec approvals necessary to perform all the required outlined in the PWS. Closed
82 30-Sep-13 PWS pg 10 4.2.5
Must all or any (Companies or Individuals) have FCL SECRET clearances? Or Only Pilots and
Project managers required at this time? Clearances
IAW PWS paragraph 4.2.5 "The contractor must have a valid FCL at the SECRET level."
Additionally, IAW PWS paragraph 1.3.1. "All aircrew and site managers performing under this contract are required to possess a Secret security clearance in order to receive threat briefings." FCL clearance is for the company. Closed
83 30-Sep-13
Addendum 52.212-
1 Part III
If a subcontractor is a major key partner that will be supporting the contract, can that subcontractor’s past performance be used towards award evaluation as 1 of the 3 past performance questionnaires? PP Evaluations
IAW Addendum 52.212-1, 12, Part III - Past Performance Offerors shall ensure the past performance references for which the offeror has performed services, within 3 years of proposal submission, are as relevant as possible and similar in nature to the services described in this solicitation. This includes work for commercial customers, DoD and other Federal agencies, and subcontracts that are similar to the Government requirements. Closed
84 30-Sep-13
Addendum 52.212-
2 N/A
It is our understanding that our complete technical solution package will be considered and reviewed during the evaluation. Since our technical solution is made up of our combined team’s capabilities and past performance/experience can we assume that our subcontractor’s capabilities and experience should be able to contribute towards our award evaluation? Evaluation Criteria
The Government will evaluate proposals IAW Addendum 52.212-2, however, "The awardee for both IDIQ and subsequent task orders must be the entity that will operate the aircraft under this contract, unless subcontracting is required by international agreement." Closed
85 30-Sep-13 General N/A Is DBA insurance reimbursable? Insurance DBA Insurance should be bid into the contractor's fixed operation costs. Closed
86 30-Sep-13 General N/A Is there a preferred DBA Insurance Provider? Insurance The government has no preference. Closed
87 30-Sep-13 General N/A
Is there a SOFA agreement between the United States and each of these Central African countries we are operating in? If yes, could you please clarify that contractors for this mission are included under these terms and enjoy all the benefits? Clearance There is not a SOFA agreement. Closed
88 30-Sep-13 Solicitation N/A
Please explain why this contract has task orders versus option periods? Do these mean the same thing or what is the difference? Solicitation
The Government determined task orders to be appropriate for this acquisiton. Task
Orders under this contract will be awarded/funded based on the Government's need. Closed
89 30-Sep-13 PWS pg 2 1.1.1
“DoD will provide support when Roning”– Please confirm that the government will provide adequate housing and meals at each remote location if RON is required. Currently, the incumbent contractor provides their staff with tents, MRE/Meals, security, and adequate bed down equipment specific to the AOR threats whether natural or manmade. In order to ensure every bidder is working from the same assumptions and level playing field, should each bidder include this RON equipment in their pricing proposal for their personnel? Operations
Air assets will return to an outstation collocated with USSOF after dropping off pax/cargo. Although very rare, if it is expected that an air asset has to RON on a remote site, you can bring your own equipment (MREs, water, equipment, etc.). Some villages and cities have hotels. At other locations local partner nation forces agrees to provide lodging at their camp for mission personnel, including the Contractor crew. This may/may not include tents, small shacks, or a well-constructed building with water and electricity. Closed
90 30-Sep-13 PWS pg 2, 1.1.1
For RON situations, should the contractor plan to have tents, bedding, and meals aboard the aircraft for contractor personnel required to RON? Operations Yes, see answer to question 89 Closed
91 30-Sep-13 PWS pg 2, 1.1.1
Should all bidders assume any RON situations will be covered and taken care of by the
Government per PWS 1.1.1 wording indicating it will cover this requirement for contractor personnel? Operations No, see answer to question 89 Closed
92 30-Sep-13 General N/A
Will the government provide aircraft parking and security during the RON away from contractor base location? If no, will the GOV please provide the anticipated locations the operator will be or might be expected to RON at so that we can plan and set up adequate life support and aircraft security at these locations? Operations
Yes, parking is provided. Names and locations of other sites throughout the AOR cannot be released due to OPSEC. See answer to question 89 for additional information on
RONing. Closed
93 30-Sep-13 PWS pg 5 1.2.6.1
In order to receive contract award, must the winning contractor be NVG mission ready on day
31 after award? Equipment
Contractor needs to be operationally ready to perform IAW with requirements outlined in the PWS at contract start date, to include performing missions using NVG operations.
Additionally, IAW Addendum 52.212-2 (1) Part I - Technical (i) Technical Subfactor 1 -
"The proposed approach effectively demonstrates the offeror’s ability to comply with the PWS requirements, specifically requirements identified in Section 1 (1.1 - 1.1.2, 1.2.4,
1.2.5 – 1.2.6.1, 1.2.9.2 and 1.4.3) of the PWS." Closed
94 30-Sep-13 PWS pg 5 1.2.6.1
Will the bidding contractor be considered unacceptable if they cannot be NVG mission ready and PWS compliant on required operational mission start? (Day 31 after award). Requirements See answer to question 93. Closed
95 30-Sep-13 PWS pg 5 1.2.6.1
Please confirm the definition of NVG mission ready to include each helicopter must be NVG configured (FAA compliant and fully operational), each helicopter must have NVG goggles for each crew member plus 1 spare in each aircraft, and all crew or at a minimum 4 pilots NVG trained (ability to fly NVG with both helicopters at the same time) and FAA compliant to execute NVG operations on the 31st day after contract award? Requirements
PWS paragraph 1.2.6.1 outlines the requirement to have the capability to fly at night with the use of Night Vission Goggles (NVGs). Contractor needs to be operationally ready to perform IAW with requirements outlined in the PWS at contract start date, to include performing missions using NVG operations. Closed
96 30-Sep-13 General N/A Will the Government allow the contractor to be tax exempt in Uganda and all AOR countries? Taxes
The US Government does not have agreements with the Host Nation (HN), therefore, any VAT/local taxes will be paid by the contractor. Closed
97 30-Sep-13 General N/A
Should all contractors expect to price into their pricing proposal the 18% VAT on all fuel, life support, equipment and supplies? Taxes
The contractor should account of any costs which are not covered under PWS Section 3
"Reimbursable Services and Costs" in their pricing proposal. Closed
98 30-Sep-13 General N/A
Since the contractor is supporting the U.S. Government on this mission, could you please include a clause that makes the contract exempt from VAT and local business taxes? Taxes
The US Government does not have agreements with the Host Nation (HN), therefore, any VAT/local taxes will be paid by the contractor. Closed
99 30-Sep-13 General N/A Will the USG allow VAT to reimbursed under the cost reimbursable CLIN? Taxes
Only costs outlined in PWS Section 3 "Reimbursable Services and Costs" are authorized for reimbursement under this contract. Closed
100 30-Sep-13 General N/A
Due to AOR conditions, it is critical to have both perimeter security and a team of security guards to monitor the base camp and the fuel depots at each of the FOBs. Can the contractor expect the Government to provide the security support personnel/services for the home base location and the fuel depots at the FOBs? Or should the bidders expect to assume responsibility for this and include these costs in our pricing proposal? Security
The Government provides security at each outstation. United States Special Operations
Forces (USSOF) provides security at each outstation. (The Contractor might want to provide security at their domicile, wherever they choose to live. It is not required, but it is recommended. USSOF at the outstations are also the security forces. But again, the
Government doesn't perform 24/7 security patrols with armed guards.) The Contractor is required to secure their own fuel, this cost should be included in your pricing proposal. Closed
101 30-Sep-13 PWS 1.1 Is the housing and life support for the staff and support staff required to be OSHA complaint? Personnel
No, the OSH Act covers most private sector employers and their workers, in addition to some public sector employers and workers in the 50 states and certain territories and jurisdictions under federal authority. Those jurisdictions include the District of Columbia, Puerto Rico, the Virgin Islands, American Samoa, Guam, Northern Mariana Islands, Wake
Island, Johnston Island, and the Outer Continental Shelf Lands as defined in the Outer
Continental Shelf Lands Act. Closed
102 30-Sep-13 PWS 4.14.2
What are the minimum requirements for the Cyber Security piece that we should include with our proposal? What are the minimum contract requirements for Cyber Security for the program? 52.212-1
Addendum 52.212-1 (II) Part I - Technical (f) Information Assurance & Cyber Security outlines this requirement. Closed
103 30-Sep-13 General N/A
In our experience the FAA requires War Risk Insurance for flight operations in the Central
Africa Region. In order to ensure the playing field is level, will the government require the contractor to have War Risk Insurance for this contract? If yes, at what levels of coverage are required? Insurance
The contractor is required to have any insurance deemed necessary IAW FAA requirements to operate in the Central Africa Region under this contract. Closed
104 30-Sep-13 General N/A
What is the maximum distance (in miles) required to fly between the various departure sites and landing zones? Flight Miles See chart on Attachment 2a, distance from Obo to Entebbe 480nm Closed
105 30-Sep-13
Will the Government please clarify what standard of personnel training and/or pre-deployment actions are required? (CRC, DPC, Medical standards: to include various shots and immunizations; we ask the government consider time frames associated with these processes). Training
Please refer to the AFRICOM website (http://www.africom.mil/staff-resources/travel-to-africa) for information on training contractor personnel deploying to Africa. Additionally, the State Department website (http://www.state.gov/) is another source for information on travel to Africa. Closed
106 30-Sep-13
Will the Government provide CRC or DPC for contractor personnel deploying to theater?
Where will this be located and what is the process for enrollment? Training
Please refer to the AFRICOM website (http://www.africom.mil/staff-resources/travel-to-africa) for information on training contractor personnel deploying to Africa. Additionally, the State Department website (http://www.state.gov/) is another source for information on travel to Africa. Closed
107 30-Sep-13 General N/A Will the government provide aircraft parking space at the primary basing location? Operations
Parking space is available at FOS Obo for the RW assets as well as the other outstations.
There are RW pads at each location. If you arrive at Entebbe, you'll park alongside the government planes on TWY H. Closed
108 30-Sep-13 General N/A
As it states the Government will provide necessary over-flight clearances for the missions, will the Government assist in mission planning and getting approval for PPR requests for flight planning? Operations
No PPRs are required for Entebbe, Dungu, Nzara, or Obo. JSOAD-UG will assist with over-flight clearances. They submit monthly requests with all tail numbers involved in the mission, and those approvals are good for a month at a time. Closed
109 30-Sep-13 General N/A
What are the minimum requirements for the quality control plan that is to be submitted with the proposal? Proposal Requirements
The contractors Quality Control Plan is developed and implemented IAW FAR 133 and
135 and 32 CFR 861 or applicable CAA equivalent. See PWS paragraph 4.4.1. Closed
110 30-Sep-13 General N/A
Are contractors allowed to hire armed security at locations that may have increased security risks? Security
The contractor is not required to provide any security. The Government provides security at each outstation. United States Special Operations Forces (USSOF) provides security at each outstation. (The Contractor might want to provide security at their domicile, wherever they choose to live. It is not required, but it is recommended.
USSOF at the outstations are also the security forces. But again, the Government doesn't perform 24/7 security patrols with armed guards.) Closed
111 30-Sep-13 General N/A Will the Government allow contractor personnel to be armed while supporting this contract? Security
No, contractors are not allowed to be armed. The Government provides security at each outstation. United States Special Operations Forces (USSOF) provides security at each outstation. Closed
112 30-Sep-13 Solicitation N/A
For fuel reimbursements are contractors allowed to bill for total cost per gallon of fuel at remote locations? This could include transportation of fuel, storage of fuel, security of fuel, refueling costs, etc.…. Fuel
There is no a fuel reimbursement CLIN, but rather Fuel EPA Reimbursable CLINs (0006, etc). As stated in Attachment 3 - Payment Information and WAWF, fuel adjustments for these CLINs are IAW PWS paragraph 3.6 and TRANSFARs Clause 5552.216-9002.
TRANSFARs Clause 5552.216-9002 states "Allowable fuel adjustments will be made, upward or downward, only if the DESC price varies by more than 3 % per gallon from the base price established in the contract (hereafter referred to as the “pegged price”)". Any other costs associated with securing fuel, transporting fuel, etc should be bid into the contractor's pricing proposal. Closed
113 30-Sep-13 PWS 3.2
Is the contractor responsible for landing fees (and any other airport fees) associated with normal missions in support of this contract? Or is the Government responsible for landing fees?
Reimbursable Services and Costs
The contractor is responsible, however IAW PWS para 3.2, "The Government will reimburse the Contractor, at cost, for all airport fees assessed as a result of authorized performance under this contract." Closed
114 30-Sep-13 General N/A
Is the Government will be responsible for obtaining all over flight and landing clearances in performance of this requirement? Landing Clearances
The contractor is responsible for flight and landing clearance. There is a standing blanket clearance agreement within the four countries that states aircraft operating in support of Operation Observant Compass (OOC) are allowed into country. This agreement is worked with individual countries and includes aircraft information. Closed
115 30-Sep-13 General N/A
Should the contractor anticipate all the surge periods will be triggered during course of the contract? Mission Requirements Surge periods will be utilized based on the Government's need. Closed
116 30-Sep-13 PWS 1.1.2
How many surge periods are estimated for the base period of performance? Please provide this information for pricing and operational planning purposes. Mission Requirements The Government anticipates (2 surge periods) 120 hrs during the base period Closed
117 30-Sep-13 PWS 4.12
Will the government consider weekly reports instead of daily reports due to the fact that
Internet availability at the remote site Obo may have challenges in terms of Internet…