DNC Estimated Move-In Dates

View the file

Other files

File Type Posted
Answers to Questions HSSS01-12-R-0075 - DNC.xlsx XLSX spreadsheet
DNC Final Equipment Total.xlsx XLSX spreadsheet
Wage Determination - DNC.txt TXT text file
DNC Equip Rental - Attachment 3.xlsx XLSX spreadsheet
DNC Perimeter Asset Solicitation SOW.docx DOCX document
Non-disclosure form - DNC.pdf PDF
questions form.xlsx XLSX spreadsheet
RFP - HSSS01-12-R-0075.pdf PDF
Clauses HSSS01-12-R-0075.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DNC – Equipment Move-In

Time Warner Cable Arena and Charlotte Convention Center:

1. There will be limited staging of equipment prior to Saturday September 1 unless we can find a location that the equipment can be stored in. Equipment placement will require agents or officers to secure until placement.

1. Saturday September 1 – Placement of equipment for TWCA and CCC pending availability of manpower to secure equipment

1. Sunday September 2 – Begin placement of fencing, barrier, equipment around TWCA and CCC

1. Monday September 3 – Continue placement of fencing, barrier and equipment; remainder of street closure will be effective Monday evening after event in Uptown Charlotte concludes.

1. All fencing, barriers, equipment in place by midnight Monday September 3 (Tuesday September 4 at 12:00 am)

Bank of America Stadium

1. There will be limited staging of equipment prior to Saturday September 1 unless we can find a location that the equipment can be stored in. Equipment placement will require agents or officers to secure until placement.

1. Sunday September 2 – Monday September 3 – Staging of fencing, barriers, and equipment for BoA; limited placement of fencing, barriers, and equipment.

1. Tuesday September 4 - Begin placement of fencing, barrier, equipment around BoA

1. Wednesday September 5 – Continue placement of fencing, barrier and equipment; remainder of street closure will be effective Wednesday evening.

1. All fencing, barriers, equipment in place by midnight Wednesday September 5 (Thursday September 6 at 12:00 am)