DNC Equipment Move-In.docx
DOCX document 12 KB Posted
- Solicitation number
- HSSS01-12-R-0075
About this file
DNC Estimated Move-In Dates
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Answers to Questions HSSS01-12-R-0075 - DNC.xlsx | XLSX spreadsheet | |
| DNC Final Equipment Total.xlsx | XLSX spreadsheet | |
| Wage Determination - DNC.txt | TXT text file | |
| DNC Equip Rental - Attachment 3.xlsx | XLSX spreadsheet | |
| DNC Perimeter Asset Solicitation SOW.docx | DOCX document | |
| Non-disclosure form - DNC.pdf | ||
| questions form.xlsx | XLSX spreadsheet | |
| RFP - HSSS01-12-R-0075.pdf | ||
| Clauses HSSS01-12-R-0075.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DNC – Equipment Move-In
Time Warner Cable Arena and Charlotte Convention Center:
1. There will be limited staging of equipment prior to Saturday September 1 unless we can find a location that the equipment can be stored in. Equipment placement will require agents or officers to secure until placement.
1. Saturday September 1 – Placement of equipment for TWCA and CCC pending availability of manpower to secure equipment
1. Sunday September 2 – Begin placement of fencing, barrier, equipment around TWCA and CCC
1. Monday September 3 – Continue placement of fencing, barrier and equipment; remainder of street closure will be effective Monday evening after event in Uptown Charlotte concludes.
1. All fencing, barriers, equipment in place by midnight Monday September 3 (Tuesday September 4 at 12:00 am)
Bank of America Stadium
1. There will be limited staging of equipment prior to Saturday September 1 unless we can find a location that the equipment can be stored in. Equipment placement will require agents or officers to secure until placement.
1. Sunday September 2 – Monday September 3 – Staging of fencing, barriers, and equipment for BoA; limited placement of fencing, barriers, and equipment.
1. Tuesday September 4 - Begin placement of fencing, barrier, equipment around BoA
1. Wednesday September 5 – Continue placement of fencing, barrier and equipment; remainder of street closure will be effective Wednesday evening.
1. All fencing, barriers, equipment in place by midnight Wednesday September 5 (Thursday September 6 at 12:00 am)