This document is a comprehensive Invitation for Bids and Specifications issued by the City of Santa Cruz Public Works Department for the HSIP Cycle 11 & 12: Unsignalized Crossing Improvement Project. The project consists of installing concrete curbs, gutters, sidewalk, curb ramps, roadway signs, pedestrian-activated beacons, and striping and pavement markings at five locations: Laurel Street-Blackburn Street, Broadway-Pennsylvania Avenue, Seabright Avenue-Logan Street, High Street-Cardiff Place, and Soquel Avenue-Poplar Avenue. HSIP Cycle 11 includes 37 bid items ranging from mobilization and traffic control to various sign installations, pavement markings, and landscape work, while HSIP Cycle 12 includes 52 bid items with similar scopes. The project must be completed within 50 working days. Sealed bids are due November 5, 2026, at 2:00 PM Pacific Standard Time at the Public Works Department, 809 Center Street, Room 201, Santa Cruz, California 95060. Bidding documents are available for download at no charge from the City's website or for a $30 nonrefundable fee at the Public Works Department office. All bidders must hold a valid California Contractor's Class A License at the time of bid submittal, and all listed subcontractors must hold valid licenses suitable for their trade.
The City will award the contract to the lowest responsive and responsible bidder based on the total bid for both cycles combined. All bids must include a bid security of at least 10 percent of the proposal amount in the form of a certified check, cashier's check, or bidder's bond. Successful bidders must submit a signed agreement, executed Faithful Performance and Labor and Material bonds each equal to 100 percent of the contract price, insurance certificates, and other required documents within ten calendar days of receiving notice of award. Progress payments are subject to 5 percent retention withholding until 35 calendar days after recording the notice of completion. The project is subject to prevailing wage requirements as published by the California Department of Industrial Relations, and all contractors and subcontractors must register with the DIR prior to bid submittal and maintain active registration throughout contract performance. The project is funded through two separate funding sources and is subject to Buy America provisions and the federal nondiscrimination requirements of Title 49 CFR Part 26.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HSIP_11&12_Final_Plans_Rev.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
�CITY OF
IAN1A
CRIil
PUBLIC WORKS DEPARTMENT
INVITATION FORBIDS,
SPECIFICATIONS, AND CONTRACT DOCUMENTS
FOR
"HSIP CYCLE 11 & 12: UNSIGNALIZED CROSSING IMPROVEMENT PROJECT "
CITY PROJECT NO. C402517 AND C402610
STA TE PROJECT NO. HSIPL-5025(087) AND HSIPL-5025(090)
SANTA CRUZ CITY COUNCIL
Fred Keeley, Mayor
Shebreh Kalantari-Johnson, Vice Mayor Gabriela Trigueiro
Sonja Brunner Scott Newsome Susie O'Hara Renee Golder
Matt Huffaker, City Manager
Bonnie Bush, City Clerk Administrator
Catherine "Cassie" Bronson, City Attorney
Nathan Nguyen, Public Works Department Director
Kevin Crossley, City Engineer/Assistant Public Works Director
BIDS DUE NOVEMBER 5, 2026 @ 2:00 PM PACIFIC STANDARD TIME
Closing time to receive bids will be verified by the on-line clock maintained by the
US Naval Observatory, found at: https://time.gov/
HSIP l I & 12: UNSIGNALIZED CROSSING IMPROVEMENT PROJECT - Page i
HSIP 11 & 12: UNSIGNALIZED CROSSING IMPROVEMENT PROJECT – Page ii
TABLE OF CONTENTS
NOTICE INVITING SEALED PROPOSALS OR BIDS
SECTION 2 - PROPOSAL REQUIREMENTS AND CONDITIONS
2.01 GENERAL
2.02 OBTAINING PLANS AND SPECIFICATIONS
2.03 CONTENTS OF PROPOSAL FORMS
2.04 ESTIMATED QUANTITIES
2.05 EXAMINATION OF DRAWINGS, SPECIFICATIONS, AND SITE OF WORK
2.06 PROPOSAL FORM
2.07 QUERIES ON BIDDING
2.08 REJECTION OF PROPOSALS
2.09 PROPOSAL GUARANTEE
2.10 WITHDRAWAL OF PROPOSALS
2.11 PUBLIC OPENING OF PROPOSALS
2.12 JOINT PROPOSALS
2.13 DISQUALIFICATION OF BIDDERS
2.14 BID RIGGING
2.15 ADDENDUM
2.16 LIST OF SUBCONTRACTORS
2.17 COMPETENCY OF BIDDER
2.18 RELIEF OF BIDDERS
2.19 PUBLIC BID REQUIREMENTS
2.20 PROPOSAL FORM
2.21 BASIS OF BID
2.22 LIST OF SUBCONTRACTORS
2.23 CONTRACTOR REFERENCE INFORMATION
2.24 DIR COMPLIANCE AFFIDAVIT
2.25 NON-COLLUSION DECLARATION
2.26 BIDDER’S FINANCIAL QUALIFICATION
2.27 BIDDERS BOND
2.28 AGREEMENT
2.29 FAITHFUL PERFORMANCE BOND
2.30 LABOR AND MATERIAL BOND
2.31 WORKER’S COMPENSATION ACKNOWLEDGMENT CERTIFICATE
2.32 CERTIFICATE OF WORKERS’ COMPENSATION INSURANCE FOR THE CITY OF SANTA CRUZ
HSIP 11 & 12: UNSIGNALIZED CROSSING IMPROVEMENT PROJECT – Page iii
2.33 CERTIFICATE OF STATE CONTRACTOR’S LICENSE
2.34 CONTRACTOR LICENSE INFORMATION
SECTION 3 – AWARD AND EXECUTION OF CONTRACT
3.01 GENERAL
3.02 CONSIDERATION OF PROPOSALS
3.03 AWARD OF CONTRACT
3.04 RETURN OF PROPOSAL GUARANTEES
3.05 CONTRACT BONDS
3.06 EXECUTION OF CONTRACT
3.07 FAILURE TO EXECUTE CONTRACT
SECTION 4 – BEGINNING OF WORK, TIME OF COMPLETION AND LIQUIDATED DAMAGES
4.01 BEGINNING OF WORK, TIME OF COMPLETION AND LIQUIDATED DAMAGES
4.02 PRE-CONSTRUCTION CONFERENCE
4.03 ARCHAELOGICAL DISCOVERIES
SECTION 5 – GENERAL CONDITIONS
5.01 WORK TO BE DONE
5.02 MAINTENANCE AND CLEAN-UP
5.03 CHANGES
5.031 DIFFERING SITE CONDITIONS
5.04 PROTESTS
5.05 CONTRACTOR’S INSURANCE
5.051 CERTIFICATE REQUIREMENTS
5.052 MINIMUM SCOPE AND LIMITS OF INSURANCE
5.053 OTHER INSURANCE PROVISIONS
5.054 SUBCONTRACTORS
5.055 SPECIAL RISK/CIRCUMSTANCES
5.06 AUTHORITY OF ENGINEER
5.07 CONFORMITY WITH DRAWINGS AND ALLOWABLE DEVIATIONS
5.08 SUPERINTENDENCE
5.09 LAYOUT OF WORK AND SURVEYS
5.10 INSPECTION
5.11 TESTING BY CONTRACTOR
5.12 REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORKS
5.13 CONSTRUCTION EQUIPMENT AND PLANT
5.14 USE OF COMPLETED PORTIONS
5.15 LEGAL ADDRESS OF THE CONTRACTOR
5.16 FINAL INSPECTION
HSIP 11 & 12: UNSIGNALIZED CROSSING IMPROVEMENT PROJECT – Page iv
5.17 ACCEPTANCE OF CONTRACT
5.18 COORDINATION OF SPECIFICATIONS & DRAWINGS
5.19 INTERPRETATION OF SPECIFCATIONS & DRAWINGS
5.20 STATE SPECIFICATIONS
5.21 REASONABLENESS OF INTERPRETATIONS
5.22 LAWS TO BE OBSERVED
5.23 LABOR NONDISCRIMINATION
5.24 PREVAILING WAGES
5.25 HOURS OF LABOR
5.26 APPRENTICES
5.27 PERMITS AND LICENSES
5.28 PATENTS & COPYRIGHTS
5.29 SANITARY FACILITIES
5.30 PUBLIC SAFETY
5.31 ACCIDENT PREVENTION
5.32 EXPLOSIVES
5.33 FIRES
5.34 INTERFERENCE WITH FIRE HYDRANTS, HIGHWAYS, AND FENCES
5.35 PRESERVATION OF PROPERTY
5.36 PUBLIC CONVENIENCE
5.37 CONTRACTOR’S RESPONSIBILITY FOR WORK
5.38 RESPONSIBILITY FOR DAMAGES
5.39 PAYMENT OF TAXES
5.40 PROPERTY RIGHTS IN MATERIALS
5.41 RIGHTS IN LAND & IMPROVEMENTS
5.42 TITLE TO MATERIALS FOUND ON THE WORK
5.43 PERSONAL LIABILITY
5.44 TRESPASS
5.45 SUBCONTRACTING
5.46 PROMPT PROGRESS PAYMENT TO SUBCONTRACTORS
5.47 PROTECTION OF PUBLIC UTILITIES
5.48 PUBLICATIONS
5.49 LANDS & RIGHTS-OF-WAY
5.50 ASSIGNMENT
5.51 COMMENCEMENT OF WORK
5.52 WORK PROGRESS SCHEDULE
5.53 TEMPORARY SUSPENSION OF WORK
5.54 TEMPORARY SUSPENSION OF WORK FOR THE CONVENIENCE & BENEFIT OF THE CITY
HSIP 11 & 12: UNSIGNALIZED CROSSING IMPROVEMENT PROJECT – Page v
5.55 SUSPENSION OF WORK BECAUSE OF CONDITIONS BEYOND CONTROL OF CITY OR CONTRACTOR
5.56 TERMINATION OF UNSATISFACTORY SUBCONTRACTS
5.57 CHARACTER OF WORKERS
5.58 TERMINATION OF CONTRACT
5.59 RIGHT-OF-WAY DELAYS
5.60 CONTRACTOR’S COST DATA
5.61 COORDINATION WITH UTILITIES
5.62 RESPONSIBILITY FOR ACCURACY
5.63 TEMPORARY FACILITIES & SERVICES
5.64 UNFAVORABLE WEATHER & OTHER CONDITIONS
5.65 WEEKEND, HOLIDAY, AND NIGHT WORK
5.66 WORK TO BE DONE WITHOUT DIRECT PAYMENT
5.67 MEASUREMENT OF QUANTITIES
5.68 CHANGE ORDERS
5.69 FORCE ACCOUNT WORK
5.70 DEDUCTIONS FROM PAYMENTS
5.71 PARTIAL PAYMENT
5.72 FINAL PAYMENT
5.73 SCOPE OF PAYMENT
5.74 GUARANTEE
5.75 TEMPORARY CONSTRUCTION EASEMENT
5.76 BUY AMERICA REQUIREMENTS
SECTION 6 – BLANK
SECTION 7 – BLANK
SECTION 8 – CONTROL OF MATERIALS AND INSTALLED EQUIPMENT
8.01 QUALITY ASSURANCE PROGRAM (QAP)
8.02 FURNISHING AND QUALITY OF MATERIALS AND EQUIPMENT
8.03 SOURCE OF MATERIAL AND EQUIPMENT
8.04 STORAGE OF MATERIALS AND EQUIPMENT
8.05 DEFECTIVE MATERIALS
8.06 TRADE NAMES AND ALTERNATIVES
8.07 TESTING MATERIALS
8.071 FREQUENCY
8.072 CERTIFICATES OF COMPLIANCE
8.08 PLANT INSPECTION
SECTION 9 – DESCRIPTION OF WORK
9.01 WORK TO BE PERFORMED
HSIP 11 & 12: UNSIGNALIZED CROSSING IMPROVEMENT PROJECT – Page vi
SECTION 10 – TECHNICAL SPECIAL PROVISIONS
10.01 MOBILIZATION
10.02 TRAFFIC CONTROL AND CONSTRUCTION AREA SIGNS
10.03 CONTROL OF WORK
10.04 EXISTING HIGHWAY FACILITIES
10.05 WATER POLLUTION CONTROL
10.06 BEST MANAGEMENT PRACTICE
10.07 DUST CONTROL
10.08 CONSTRUCTION SURVEYING BY THE CONTRACTOR
10.09 CLEARING AND GRUBBING
10.10 EARTHWORK
10.11 AGGREGATE BASE
10.12 ASPHALT CONCRETE
10.13 MISCELLANEOUS CONCRETE
10.14 REINFORCEMENT
10.15 ROADWAY SIGNS AND POSTS
10.16 MARKINGS AND COATINGS
10.17 CAST-IN-PLACE/SURFACE APPLIED DETECTABLE WARNING SURFACE TILES
10.18 RECTANGULAR RAPID FLASHING BEACON SYSTEM
10.19 LANDSCAPE
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 1
NOTICE INVITING SEALED PROPOSALS OR BIDS
NOTICE IS HEREBY GIVEN that the City of Santa Cruz, California (the “City”), invites sealed Bids for the following “Project”:
"HSIP CYCLE 11 & 12: UNSIGNALIZED CROSSING IMPROVEMENT PROJECT "
CITY PROJECT NO. C402517 AND C402610
STATE PROJECT NO. HSIPL-5025(087) AND HSIPL-5025(090)
1. Date and Place of Opening Bids. Sealed bids for the construction of the Project will be received at the Public Works Department, 809 Center Street, Room 201, Santa Cruz, California 95060, until NOVEMBER 5, 2026 at 2:00 pm Pacific Standard Time in a sealed envelope plainly endorsed with the Project Name and Number, listed above. At that time, the Bids received will be publicly opened and read. Attendees will be required to wear face masks, social distance, and follow any other safety measures currently recommended by the County Public Health Officer. Bids received after the date and time stated above will be rejected as nonresponsive.
2. Location of Project. The Project is to be performed at the following locations:
a. HSIP Cycle 11
i. Laurel Street – Blackburn Street
ii. Broadway – Pennsylvania Avenue
iii. Seabright Avenue – Logan Street
b. HSIP Cycle 12
i. High Street – Cardiff Place
ii. Soquel Avenue – Poplar Avenue
3. Description of Work. The Project to be performed consists of furnishing all labor, materials, tools, equipment, and transportation required to complete the Project, with a scope of work to generally include, but is not limited to, the following: Installing concrete curbs, gutters, curb ramps, roadway signs, pedestrian activated beacons and striping and pavement markings. All other work not mentioned above that is required by the plans, City Standard Specifications, State Standard Specifications and the Special Provisions shall be performed, placed, constructed or installed. (the “Work”). For additional information, please contact the individual listed in Paragraph 16, below.
4. Time for Completion. The Project shall be completed in 50 working days. All time limits stated herein are of the essence
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 2
5. Bidding Documents. The “Bidding Documents” shall include this Notice Inviting Bids, the Bid Form including all attachments included herein, General Requirements, Technical Specifications (including all plans, drawings, and reports), Addenda, draft Agreement, the City’s Standard Specifications (dated 2002), as amended1, the State of California’s Department of Transportation Standard Specifications (dated 2025), as amended, and all other documents identified herein.
6. Obtaining the Bidding Documents. Bidding Documents may be downloaded, without charge, from: https://www.santacruzca.gov/Business-Development/Bidding-Information . Bidding Documents may be examined and copies secured from the office of the Public Works Department, 809 Center Street, Room 201, Santa Cruz, California 95060, for a nonrefundable fee of $30.00. Documents can also be obtained from ebidboard.com
Prospective bidders are urged to register with the designated website as a Bidding Documents holder, even if Bidding Documents are obtained from a source other than the designated website or City in either electronic or paper format. The designated website will be updated periodically with Addenda, reports, and other information relevant to submitting a bid for the Project. All official notifications, Addenda, and other Bidding Documents will be offered only through the designated website. Neither City nor any City official, employee, or agent will be responsible for Bidding Documents, including Addenda, if any, obtained from sources other than the designated website or the City.
7. Submitted Bid. Each sealed Bid shall comply with the Bidding Documents and be submitted on the Bid Form, including all attachments. Contractor must clearly and legibly set forth all information requested in the manner and form indicated.
By submitting a Bid, the Bidder represents that it has carefully examined and investigated the Project site and all Bidding Documents.
Each Bid shall include a bid security in the form of a certified check, cashier's check, or bidder's bond made payable to the order of the City of Santa Cruz, California, for an amount not less than (10) percent of the amount of the Proposal. The bid security shall be given as a guarantee that the successful bidder will enter into the contract, and will be declared forfeited if the successful bidder refuses or fails to enter into said contract.
All bidders shall submit with its Bid the included sworn statement of its financial responsibility, technical ability, and experience.
8. Addenda. All submitted Bids shall verify if the City has issued any addenda for this Project. It is the bidder’s sole responsibility to ensure that all addenda requirements are included in the submitted Bid. All addenda shall be posted on the City’s designated website
9. Withdrawing Submitted Bid. A bidder may withdraw a submitted Bid at any time prior to the time of bid opening only by written request to the City. Unless otherwise required by law, no bidder may withdraw its Bid for a period of sixty (60) days after the bid opening.
1 The City’s Standard Specifications (dated 2002) are located via the City Website at:
https://santacruzca.prelive.opencities.com/files/assets/city/v/1/pw/documents/pw-standards-standard-specs.pdf
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 3
10. Award of Contract. The City will award the Project to the lowest responsible and responsive bidder. The City reserves the right to reject any and all Bids, including but not limited to for any minor irregularities, or waive any informalities or minor defects in proposals received. The City may reject a Bid if it determines that any of the bid prices are materially unbalanced to the potential detriment of the City.
Within ten (10) calendar days after receiving written notice that the contract has been awarded, the successful bidder shall return to the City the signed agreement, together with the completed Labor and Material Bond and Faithful Performance Bond each in an amount equal to one hundred percent (100%) of the contract price (issued by a corporate surety company approved by the City Attorney), insurance certificates, and all other documents as required by the Bidding Documents.
11. Department of Industrial Relations Monitoring. This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations (DIR). Prevailing wages as published by the DIR are required for all workers, including those employed by subcontractors, for all non-federally funded projects.
No contractor or subcontractor may be listed on a Bid or awarded the contract for the Project unless registered with the DIR pursuant to Labor Code section 1725.5 and 1771.1. Refer to the DIR website, http://www.dir.ca.gov, to register and to find the correct wage rates and answers to questions related to prevailing wage requirements.
12. Buy America. This project is subject to the "Buy America" provisions of the Surface Transportation Assistance Act of 1982 as amended by the Intermodal Surface Transportation Efficiency Act of 1991 and as further amended by the Moving Ahead for Progress in the 21st Century Act (MAP-21) of 2012.
13. Licenses. Bidders and their proposed subcontractors shall hold such licenses as may be required by the laws of the State of California for the performance of the Work. The Contractor is required to ensure that all subcontractors listed in the Bid Form and working on this Project hold valid licenses and certifications suitable for their trade. Bidder is required to provide with its Bid satisfactory proof of licensure to the City.
Bidders bidding as the Prime Contractor shall possess a valid California Contractor’s Class “A” License at the time of bid submittal, and all listed subcontractors shall hold valid licenses suitable for their trade at the time of bid submittal. Failure to possess required licenses at the time of bid submittal may render the bid non-responsive and shall act as a bar to award of the contract to the bidder and shall result in a forfeiture of the bid security.
Bidder and all subcontractors shall maintain the required licenses throughout the entire Project until the City issues a Notice of Completion.
14. Retention. Progress payments are subject to 5% retention withholding until thirty-five (35) calendar days after recording the notice of completion. Pursuant to California Public Contract Code Section 22300, for monies earned by the General Contractor and withheld by the City to ensure the performance of the Contract. The General Contractor, may, at its option, choose to substitute securities meeting the requirements of California Public Contract Code Section
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 5
SECTION 1 - DEFINITIONS AND TERMS
Whenever in these specifications and other contract documents, the following abbreviations and terms or pronouns in place of them are used the intent and meaning shall be interpreted as follows:
ABBREVIATIONS
AASHTO American Association of State Highway and Transportation Officials AAN American Association of Nurserymen ACI American Concrete Institute AGMA American Gear Manufacturers Association AIEE American Institute of Electrical Engineers AISI American Iron and Steel Institute AISC American Institute of Steel Construction ANSI American National Standards Institute AREA American Railway Engineering Association ASA American Standards Association (United States of America Standards
Instruction) ASCE American Society of Civil Engineers ASHRAE American Society of Heating, Refrigerating and Air Conditions
Engineers ASME American Society of Mechanical Engineers ASTM American Society of Testing Materials AWS American Welding Society AWPA American Wood-Preservers’ Association AWWA American Water Works Association FS Federal Specification IEEE Institute of Electrical and Electronic Engineers NBFU National Board of Fire Underwriters NEMA National Electrical Manufacturers Association SAE Society of Automotive Engineers SSPWC Standard Specifications for Public Works Construction UL Underwriters Laboratories
All references to the specifications, standards, or other publications of any of the above are understood to refer to the current issue as revised or amended at the date of receipt of bids.
Acceptance - The formal written acceptance by the City Council of the Contract which has been completed in all respects in accordance with the Drawings and Specifications and any modifications thereof previously approved.
Addendum - A change in the Specifications or Drawings issued prior to the opening of Proposals.
Approved, Directed, Ordered, or Required - Whenever these words or their derivatives are used, it is the intent, unless otherwise clearly stated, that approval or direction by the Engineer is indicated.
Bidder - Any individual, firm, partnership, corporation, or combination thereof, submitting a proposal for the work contemplated, acting directly or through a duly authorized representative.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 6
City Standard Details - Wherever in these Specifications reference is made to the “City Standard Details”, reference shall be found on the City of Santa Cruz website, https://www.santacruzca.gov/files/assets/city/v/1/pw/documents/engineering/2025-standard-details-signed-6.30.25.pdf
Contract - The written agreement covering the performance of the work and the furnishing of labor, materials, tools, and equipment in the construction of the work. The Contract shall include the Notice of Contractors, Proposal, Drawings, Specification, Addenda, and Contract Bonds; also, any and all written supplemental agreements amending or extending the work in a substantial and acceptable manner. Supplemental agreements are written agreements covering alterations, amendments, or extensions to the Contract and include Contract change orders.
Contractor - The person or persons, firm, partnership, corporation, or combination thereof, private or municipal, who have entered into a contract with the City.
Days - Working days, unless otherwise designated.
City - the City of Santa Cruz.
Director - The Director of Public Works of the City of Santa Cruz.
Drawings - The official drawings, working drawings, detail drawings, and supplemental drawings, or reproductions thereof, which show the location, character, dimensions, and details of the work to be done, and which are to be considered as part of the Contract.
Engineer - The City Engineer acting either directly or through properly authorized agents, such agents acting within the scope of the particular duties delegated to them.
Liquidated Damages - The amount prescribed in the Specifications, pursuant to the authority of government code Section 14376, to be paid to the City or to be deducted from any payments due or to become due the Contractor for each day’s delay in completing the whole or any specified portions of the work beyond the time allowed in the Specifications.
Plans, Construction Plans - The drawings which are part of the Contract.
Proposal - The offer of the Bidder for the work when made out and submitted on the prescribed Proposal Form, properly signed and guaranteed.
Subcontractor - The person or persons, firm, partnership, corporation, or combination thereof, private or municipal who will perform work for the Contractor.
Work - All the work specified, indicated, shown, or contemplated in the Contract to construct the improvements, including all alterations, amendments, or extensions thereto made by supplemental agreements or written orders of the Director.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 7
State Standard Specifications - Wherever in these Specifications reference is made to the “State Standard Specifications”, reference shall be to specifications entitled “State of California, Department of Transportation, Standard Specifications,” 2025 edition, and which are incorporated herein and made a part hereof by reference. Where the terms “State” or the “Engineer” are used in the State Standard Specifications, they shall be considered as meaning the “City” or “Director” as defined hereinabove.
Technical Specifications - The technical specifications are specific clauses setting forth conditions or requirements peculiar to the work and supplementary to the Standard Specifications.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 8
SECTION 2 - PROPOSAL REQUIREMENTS AND CONDITIONS
2.01 GENERAL
The bidder's attention is directed to the provisions in Section 2, “Bidding,” of the State Standard Specifications and these Special Provisions for the requirements and conditions which the bidder must observe in the preparation of the proposal form and the submission of the bid.
The Bidder's Bond form mentioned in the last paragraph in Section 2-1.34, “Bidder’s Security,” of the State Standard Specifications will be found following the signature page of the Proposal.
In conformance with Public Contract Code Section 7106, a Noncollusion Affidavit is included in the Proposal. Signing the Proposal shall also constitute signature of the Noncollusion Affidavit.
The contractor, sub recipient, or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of Title 49 CFR (Code of Federal Regulations) part 26 in the award and administration of US DOT assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy, as the recipient deems appropriate. Each subcontract signed by the bidder must include this assurance.
Failure of the bidder to fulfill the requirements of the Special Provisions for submittals required to be furnished after bid opening, including but not limited to escrowed bid documents, where applicable, may subject the bidder to a determination of the bidder's responsibility in the event it is the apparent low bidder on a future public works contracts.
2.02 OBTAINING PLANS AND SPECIFICATIONS
City Standard Specifications and Plans may be obtained at the office of the City Engineer, City Hall Annex, 809 Center Street, Room 201, Santa Cruz, California 95060 for $30.00 non-refundable fee.
These documents may also be accessed and downloaded electronically for no-fee from the City of Santa Cruz website, https://www.santacruzca.gov/Business-Development/Bidding-Information.
2.03 CONTENTS OF PROPOSAL FORMS
Prospective bidders will be furnished proposal forms which describe the contemplated construction and, where appropriate, show the approximate estimate of the quantities of the various kinds of work to be performed or materials to be furnished, with a schedule of items for which bid prices are asked.
The unit prices or lump sum amounts bid shall include full compensation for furnishing all labor, materials, tools, and equipment and doing all work complete in place as shown on the Drawings or stipulated in the Specifications for that particular item of work.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 9
2.04 ESTIMATED QUANTITIES
The quantities given in the Proposal are approximate only, being given as a basis for the comparison of Proposals, and the City does not, expressly or by implication, agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work, or to omit portions of the work, as may be deemed necessary or advisable by the Director. No allowance will be made for anticipated profit on work that is deleted or decreased.
2.05 EXAMINATION OF DRAWINGS, SPECIFICATIONS, AND SITE OF WORK
The Bidder shall examine carefully the site of the work contemplated and the Proposal, Drawings, and Specifications therefor. The submission of a Proposal will be conclusive evidence that the bidder has investigated and is fully aware of the conditions and difficulties to be encountered, of the character, quality, and quantities or work to be performed and materials to be furnished, and of the requirements of the Proposal, Drawings, and Specifications; as to the nature and location of the work, the general and local conditions, particularly those bearing upon transportation, disposal, handling and storage of material, availability of labor, water, electric power, roads, and uncertainties of weather, or similar physical conditions at the site; and the conformation and condition of the ground, the character and quality and quantity of surface and subsurface materials, including groundwater, to be encountered; the character of equipment and facilities needed preliminary to and during the prosecution of the work; and all other matters which can in any way affect the work or the cost thereof under this Contract. Any failure by the Contractor to acquaint himself/herself with all the available information concerning these conditions will not relieve him/her from responsibility for estimating properly the difficulty or cost of successfully performing the work.
If there is any doubt as to the true meaning of any part of the Plans, Specifications, or the Contract documents, or if discrepancies in or omissions from the Drawings or Specifications are found, a request should be made to the Director for an interpretation or correction thereof, which will be given in the form of addenda to all bidders, if time permits. Otherwise, in figuring the work, bidders shall consider that any discrepancies or conflict between Drawings and Specifications shall be governed by Section 5.23 of these Specifications.
No payment shall subsequently be made to the Contractor because of error on his/her part or of negligence or failure to acquaint himself/herself with the existing conditions, limitations, or features of the site or requirements of the Contract documents; or by reason of any estimate, tests, or representations of any officer, employee, or agent of the City.
Where investigation of subsurface conditions has been made by the City in respect to foundation or other design, bidders may inspect the records of the City as to such investigation, including examination of samples and drill cores, if any. When logs of test boring showing a record of the data obtained by the City’s investigation of subsurface conditions are made available, said logs represent only the opinion of the City as to the character of materials encountered by it in its test borings and are made available only for the convenience of bidders.
Investigations of subsurface conditions are made for the purpose of design, and the City assumes no responsibility whatever in respect to the sufficiency of test borings or accuracy of the log of test borings, or other preliminary investigations, or of the interpretation thereof. There is no guarantee
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 10 expressed or implied that the conditions indicated are representative of those existing throughout the work, or any part of it, or that unforeseen developments may not occur.
Making such information available to bidders is not to be construed in any way as a waiver of the provisions of the first paragraph of this Section and bidders must satisfy themselves through their own investigations as to conditions to be encountered.
No information derived from such inspection of records of preliminary investigation made by the City, or from the Director, or from his/her assistants, or from the maps, Specifications, profiles, or Drawings will in any way relieve the Contractor from any risk or from properly fulfilling all the terms of the Contract. Records of such preliminary investigations as may have been made by the City may be inspected at the office of the Director, City Hall, Santa Cruz, California, 95060, or at such other locations as may be stated in the Notice to Contractors.
2.06 PROPOSAL FORM
The Proposal form furnished by the City, when filled out by the bidder and executed, shall be submitted as his/her Proposal. All Proposals should give the prices proposed, both in writing and in figures in the respective spaces provided, and shall be signed by the bidder, who should fill out all blanks in the Proposal form as therein required. In the event of a discrepancy between writing and figures, the writing shall prevail over the figures.
A copy of each addendum to the Specifications or Drawings shall be attached securely to the Specifications containing the Proposal (refer to Section 2.13).
2.07 QUERIES ON BIDDING
Questions regarding the Specifications, Drawings, or any other portion of the Contract or any addenda thereto shall be directed to the City Engineer, care of Dan Cabreros, Assistant Engineer, at City Hall, 809 Center Street, Room 201, Santa Cruz, California, 95060, in writing. An e-mail to dcabreros@santacruzca.gov is acceptable. All efforts will be made by the City to answer questions received, and all answers will be distributed to all bidders electronically. No interpretation of the meaning of the Specifications, Drawings, or other pre-bid documents will be made to any bidder orally. All questions shall be submitted no less than ten (5) business days prior to the bid opening date.
2.08 REJECTION OF PROPOSALS
Proposals may be rejected if they show any alterations of form, additions not called for, conditional bids, incomplete bids, erasures, or irregularities of any kind. Proposals in which the prices, in the opinion of the City, are unbalanced, may be rejected.
When Proposals are signed by an agent, other than the officer or officers of a corporation authorized to sign contracts on its behalf, or a member of a partnership, a written authorization or Power of Attorney should be on file with the City prior to opening Proposals or submitted with the Proposal;
otherwise, the Proposal may be rejected as irregular and unauthorized.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 11
2.09 PROPOSAL GUARANTEE
All Proposals shall be presented under sealed cover and accompanied by one of the following forms of bidder’s security: cash, a cashier’s check, certified check, or a bidder’s bond executed by an admitted surety, made payable to the City of Santa Cruz. The security shall be in an amount equal to at least 10 percent of the total Contract price in the Proposal. A Proposal will not be considered unless one such form of bidder’s security is enclosed with it.
A bidder’s bond will not be accepted unless it substantially conforms to the bond form included with the Proposal form and is properly filled out and executed. If desired, the bond form included therein, properly filled out as directed, may be executed and used as the bidder’s bond. Blanks conforming to this form may be obtained by request from the City.
2.10 WITHDRAWAL OF PROPOSALS
Any Proposal may be withdrawn at any time prior to the time fixed in the Notice to Contractors for the opening of Proposals only by written request for the withdrawal of the Proposal filed with the City Clerk. The request shall be executed by the bidder or his/her duly authorized representative.
The withdrawal of a Proposal does not prejudice the right of the bidder to file a new Proposal. This Section does not authorize the withdrawal of any Proposal after the time fixed in the Notice to Contractors for the opening of Proposals.
2.11 PUBLIC OPENING OF PROPOSALS
Proposals will be opened and read publicly at the time and place indicated in the Notice to Contractors.
2.12 JOINT PROPOSALS
If two or more bidders desire to bid jointly on a single project or desire to combine their assets for so doing, they shall file an affidavit of joint venture with the City in the form approved by the City Attorney and such affidavit of joint venture will be valid only for the specified project for which it is filed. If such affidavit of joint venture is not filed as aforesaid and approved by the City prior to the time for opening Proposals on the specified project for which it is submitted, a joint proposal submitted by the same bidders may be disregarded.
2.13 DISQUALIFICATION OF BIDDERS
More than one Proposal form from an individual, firm, partnership, corporation, or a combination thereof under the same or different names will not be considered. If there is reason for believing that collusion exists among the bidders, none of the participants in such collusion will be considered for award of this Contract.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 12
2.14 BID RIGGING
The U.S. Department of Transportation (DOT) provides a toll-free hotline to report bid rigging activities. The hotline should be used to report bid rigging, bidder collusion, and other fraudulent activities. The hotline number is (800) 424-9071. The service is available 24 hours 7 days a week and is confidential and anonymous. The hotline is part of the DOT’s effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector General.
2.15 ADDENDUM
Addenda may be issued prior to opening of Proposals and shall become a part of the original Specifications and Drawings. The additions or changes contained in such addenda shall be considered by the Bidder in preparation of his/her Proposal. These addenda will be sent to each prospective bidder at the address indicated in his/her application for a Proposal form. A copy of each addendum so issued shall be attached to the Specifications containing the Proposal submitted by the bidder to the Public Works Department.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 13
2.16 LIST OF SUBCONTRACTORS
The Contractor shall perform with his/her own organization and with workers under his/her immediate supervision work of a value not less than fifty percent (50%) of the value of all work embraced in the Contract, except when certain items may be exempted by the Special Provisions from said fifty percent requirement.
In accordance with Chapter 2, Division 5, Title I of the Government Code of the State of California, Subletting and Subcontracting Fair Practices Act, each Proposal shall have listed on the form provided with the Proposal, (a) the name and the location of the place of business of each subcontractor who will perform work or labor or render service to the general contractor in or about the construction of the work or improvement in an amount in excess of one-half of one percent (0.5%) of the general contractor’s total bid or $10,000.00, whichever is greater, and, (b) the portion of the work which will be done by each such subcontractor.
All listed subcontractors must be registered with the state Department of Industrial Relations (DIR) and provide DIR registration number prior to proposal submittal
If a Contractor fails to specify a subcontractor for any portion of the work to be performed under this Contract is excess of one-half of one percent of the total bid, he/she agrees to perform that portion himself/herself.
2.17 COMPETENCY OF BIDDER
The bidder shall be licensed under the provisions of Chapter 9, Division 3, of the Business and Professions Code of the State of California to do the type of work contemplated in the project, and shall be skilled and regularly engaged in the general class or type of work called for under this Contract.
It is the intention to award a Contract only to a bidder who furnishes satisfactory evidence that he/she has the requisite experience and ability and that he/she has sufficient capital, facilities, and plant to enable him/her to prosecute the work successfully and promptly, and to complete it within the time stated in the Contract.
To determine the degree of responsibility to be credited to a bidder, any relevant evidence will be considered that the bidder, or personnel guaranteed to be employed in responsible charge of the work, has satisfactorily performed other contracts of like nature and magnitude or comparable difficulty at similar rates of progress.
2.18 RELIEF OF BIDDERS
Attention is directed to the provisions of Government Code Section 14350 to 14353, inclusive, (Subletting and Subcontracting Fair Practices Act), which sections are incorporated herein by this reference, concerning relief of bidders and in particular to the requirement therein that if the bidder claims a mistake was made in his/her bid, the bidder shall give the City written notice within five (5) days after the opening of the bids of the alleged mistake, specifying in the notice in detail how the mistake occurred.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 14
2.19 PUBLIC BID REQUIREMENTS
No contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
No contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or After April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 15
2.20 PROPOSAL FORM
Bidder’s Proposal for
TO: The Council of the City of Santa Cruz
PROPOSAL OF:
Business Address:
Business Telephone:
The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement, in the form specified in the Contract Documents, with the City of Santa Cruz (“City”) to perform all work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the Bidding Documents.
The undersigned Bidder understands that any or all quantities of work shown herein are approximate only and are subject to increase or decrease, and offers to do the work whether the quantities are increased or decreased at the unit prices as stated in the following tabulation. The undersigned Bidder agrees to take in full payment for the work, including all applicable state and local taxes, the amount shown on the bid sheet.
Please note closing time to receive bids will be verified according to local telephone company time.
IT IS UNDERSTOOD THAT THIS BID IS BASED UPON COMPLETION OF THE WORK
AS SPECIFIED IN THE SPECIAL PROVISIONS WITHIN 50 WORKING DAYS
WORKING DAYS, AND THE PRICES INCLUDE ALL STATE, FEDERAL, AND OTHER
TAXES APPLICABLE TO THE PROJECT.
The undersigned Bidder agrees to do any extra work, not covered by the above schedule of price, which may be ordered by the City, and to accept as full compensation therefore, such prices as may be agreed upon in writing by the City and the Contractor in accordance with the “Measurement and Payment” Section of the Standard Specifications.
If awarded the contract, the undersigned Bidder hereby agrees to submit the following documents to the City within ten (10) business days of the Notice of Award: a signed Agreement, executed bonds
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 16
(including Faithful Performance Bond and Payment Bond), proper evidence of insurance, and any other forms or documents identified in the Bidding Documents and Notice of Award. The undersigned Bidder further agrees to begin work within ten (10) days after receiving the Notice to Proceed.
The undersigned Bidder has carefully examined the form of the Agreement, the Standard Specifications, the Plans and Special Provisions for the project hereinbefore described and referred to in the “Invitation to Bidders” inviting proposals for "HSIP CYCLE 11 & 12:
UNSIGNALIZED CROSSING IMPROVEMENT PROJECT " CITY PROJECT NO.
C402517 AND C402610 STATE PROJECT NO. HSIPL-5025(087) AND HSIPL-5025(090)
and also the site of the work and will provide all necessary machinery, tools apparatus and other means of construction, and do all the work and furnish all materials required by said Specifications and Plans and Special Provisions in the manner described therein.
No bid will be considered for less than all items of this schedule and one contract will be awarded for the entire Project.
The undersigned has carefully checked the bid prices, and all computations involved in the preparation of this bid, and understands that the City of Santa Cruz will not be responsible for any errors or omissions on the part of the undersigned in making up this bid.
This Bid is made with a full knowledge of the kind, quantities, and quality of the work and of materials, equipment, and plans required. This proposal is also made after a complete, careful, and independent examination and investigation of the site of the work, local conditions affecting the same, and materials to be encountered.
The undersigned Bidder hereby acknowledges receipt of the following Addenda:
Addendum Number Addendum Date
The Bidder furthermore agrees that in case of its default in executing said Agreement with necessary bonds, the check or bond accompanying this Bid and money payable will become and remain the property of the City of Santa Cruz.
Enclosed is Bidder’s bond, certified check, or cashier’s check no. of the Bank for $ which is not less than 10 percent of the Bid submitted by the undersigned, payable to the City of Santa Cruz, California, and which is given as a guarantee that the undersigned will enter into the contract if awarded the work.
It is understood and agreed that the City may reject any or all proposals, or waive any informalities or minor defects in proposals received.
It is agreed that this bid may not be withdrawn over a period of sixty (60) days from the opening thereof.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 17
Bidder submits the following complete and executed documents herewith to form a complete Bid:
2.20 Proposal Form
2.21 Basis of Bid
2.22 List of Subcontractors
2.23 Contractor Reference Information
2.24 DIR Compliance Affidavit
2.25 Non-Collusion Declaration
2.26 Bidder’s Financial Qualification
2.27 Bidders Bond
Note: Bidders should not add any conditions or qualifying statement to this bid as otherwise the bid may be declared irregular as being not responsive to the Advertisement for Bids.
The undersigned declares under penalty of perjury that the information contained in this Bid and all accompanying documents are true and correct. A notary acknowledgment is required.
Dated: Firm Name:
Official Address: Phone:
Email Address:
By: Title:
State Contractor’s License No.:
DIR Registration No.:
Signature of Bidder:
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 18
2.21 BASIS OF BID
This project is funded through two separate funding sources. Accordingly, the Bid Schedule includes separate bid items associated with each funding source.
Bidders shall provide unit prices and extensions for all bid items. The Total Bid shall be the sum of all bid items from both funding sources. One contract will be awarded to the lowest responsive and responsible bidder based on the Total Bid for the entire project.
Name of Bidder:
Project Name/Number:
HSIP CYCLE 11
Laurel Street – Blackburn Street
Broadway – Pennsylvania Avenue Seabright Avenue – Logan Street
Item No. Item Description Unit
Total Estimated Quantity
Unit Price ($) Item Total ($)
1 Mobilization LS 1
Traffic Control and Construction Area Signs LS 1
3 Demolition and Removal LS 1 4 Subgrade Preparation SY 241 5 PCC Curb Ramp SF 485 6 PCC Curb and Gutter LF 160 7 PCC Sidewalk SF 728
Detectable warning surface tile (Cast in Place) SF 105
9 Class 2 Aggregate Base TON 60 10 Asphalt Concrete (Type A) TON 27
4" to 6" River Rock Embedded into Wet Concrete SF 57
12 Adjust (E) Utility Box to Finished Grade EA 2
13 Relocate (E) Sign EA 21
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 19
14 Install (N) City Standard Post EA 4
15 Remove (E) City Standard Post EA 6
16 Install (N) RRFB Solar Assembly EA 7
17 Install (N) RRFB Light Bar EA 12
18 Install (N) Type 1B Post (4 In. NPS) EA 4
Install (N) Combined Push Button Post (2.5 In. NPS) EA 2
Install (N) Pedestrian Push Button Post (2.5 In. NPS) EA 3
21 Install Pull Box (Caltrans #3-1/2) EA 3
22 Install Conduit and Conductors LF 44
23 Install (N) Pedestrian Push Button EA 7
24 Install (N) R10-25 Sign (5" x 7") EA 7
Install (N) W11-2 Sign (Ped. Crossing) (30" x 30") EA 2
Install (N) W16-7P(R) Sign (Directional Arrow) (30" x 18") EA 2
Install (N) R1-5 Sign (Yield Here) (24" x
24") EA 4
28 Yield Line LF 53
Continental Xwalk - 24" White Thermoplastic Stripe, 24" Gap LF 260
30 Red Paint on Concrete Curb LF 70
31 Grind Thermoplastic Stripe LF 282
32 Grind Thermoplastic Stripe SF 22
33 4" White Thermoplastic Stripe LF 69
34 Thermoplastic Traffic Stripe - Detail 22 LF 55
35 D39Z Bicycle Conflict Zone Stripe LF 120
36 STOP Legend EA 1
37 ADA Frame and Grate EA 1
HSIP 11
SUBTOTAL
10%
CONTINGENCY
HSIP 11 TOTAL
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 20
HSIP CYCLE 12
High Street – Cardiff Place
Soquel Avenue – Poplar Avenue
Item No. Item Description Unit
Total Estimated Quantity Unit Price ($) Item Total ($)
1 Mobilization LS 1
Traffic Control and Construction Area Signs LS 1
3 Demolition and Removal LS 1 4 Subgrade Preparation SY 274 5 PCC Curb Ramp SF 418 6 PCC Curb and Gutter LF 34 7 PCC Sidewalk SF 551 8 PCC Caltrans Type B3 Curb LF 142
Detectable warning surface tile (Cast in Place) SF 162
10 Class 2 Aggregate Base TON 72 11 Asphalt Concrete (Type A) TON 44 12 Traffic Island SF 88
4" to 6" River Rock Embedded into Wet Concrete SF 88
14 Adjust (E) Utility Box to Finished Grade EA 1 15 Relocate (E) Sign EA 14 16 Remove (E) Sign EA 6 17 Install (N) City Standard Post EA 8 18 Remove (E) City Standard Post EA 11 19 Install (N) RRFB Solar Assembly EA 10 20 Install (N) RRFB Light Bar EA 9 21 Install (N) Type 1B Post (4 In. NPS) EA 1
Install (N) Combined Push Button Post (2.5 In. NPS) EA 8
Install (N) Pedestrian Push Button Post (2.5 In. NPS) EA 2
24 Install Pull Box (Caltrans #3-1/2) EA 2 25 Install Conduit and Conductors LF 30 26 Install (N) Pedestrian Push Button EA 10
Install (N) N-5 (CA) Object Marker Sign (24" x 24") EA 1
28 Install (N) R10-25 Sign (5" x 7") EA 10
Install (N) W11-15 Sign (Ped/Bike Crossing) (30" x 30") EA 6
Install (N) W16-7P(L&R) Sign (Directional Arrow) (30" X 18") EA 3
Install (N) W16-9P Sign (Ahead) (30" x
18") EA 2
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 21
Install (N) R1-5 Sign (Yield Here) (24" x
24") EA 3
33 Yield Line LF 94
Continental Xwalk - 24" White Thermoplastic Stripe, 24" Gap LF 170
Continental Xwalk - 24" Yellow Thermoplastic Stripe, 24" Gap LF 180
36 12" White Thermoplastic Stripe LF 16 37 12” Yellow Thermoplastic Stripe LF 20 38 Grind Thermoplastic Stripe LF 430 39 Grind Thermoplastic Marking SF 74 40 4" White Thermoplastic Stripe LF 57 41 8" White Thermoplastic Stripe LF 30 42 Thermoplastic Traffic Stripe – Detail 21 LF 15 43 Thermoplastic Traffic Stripe - Detail 22 LF 50 44 Thermoplastic Traffic Stripe - Detail 27B LF 238 45 Thermoplastic Traffic Stripe - Detail 29 LF 82 46 Thermoplastic Traffic Stripe - Detail 39 LF 220 47 Thermoplastic Traffic Stripe - Detail 39A LF 50 48 D39Z Bicycle Conflict Zone Stripe LF 72 49 A4 Caltrans Arrow Type 4 (Left & Right) EA 1
Bike and Through Arrow with Green vizigrip (BTAG) EA 2
Sharrow Marking with Green Vizigrip
(SHRG) EA 1
52 STOP Legend EA 1
SUBTOTAL
10% CONTINGENCY
HSIP 12 TOTAL
HSIP 11 + 12 TOTAL
HSIP 11 + 12 Total Basis of Bid Plus Contingency in Words:
The contingency is reserved for unforeseen project tasks. No payment will be made to the Contractor for any portion of the contingency unless a contract change order is approved by the City
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 22
Note: This page intentionally left blank.
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 23
2.22 LIST OF SUBCONTRACTORS
Project Name/Number: _____________________________
Bidder will use Subcontractors for the Work: □ YES □ NO
For each subcontractor to whom the Bidder proposes to subcontract portions of the work in an amount in excess of one-half of one percent, Bidder shall indicate on this form each proposed subcontractor’s legal/contracting entity name, business address and phone number, the Contractor’s State Licensing Board license number, the public works contractor registration number issued pursuant to California Labor Code Section 1725.5, the dollar amount and proportion (in percent) of the Work of each Subcontractor (of any tier) to whom a portion of the Work will be awarded via one or more subcontracts, and the work to be performed by the subcontractor.
(Attach additional sheets, if necessary)
Subcontractor’s Legal Name
Business Address and Phone Number
CSLB License Number
Public Works Contractor DIR
Number
Bid Items To Be Performed
Total Subcontract Amount and Percentage of
Total Bid Price
HSIP10 - ADVANCE DILEMMA ZONES AND RETROREFLECTIVE BORDERS – Page 24
2.23 CONTRACTOR REFERENCE INFORMATION
Failure to provide this information may constitute grounds for rejection of the bid.
The Bidder has been engaged in the contracting business under State License No.(s) for a period of years.
The following are five owners for whom the Bidder has constructed projects of similar scope to the Project. Such projects will have been completed within the past five years.
1. Name, Address, Phone No:
Project Description:
Date Completed:
2. Name, Address, Phone No:
3. Name, Address, Phone No:
4. Name, Address, Phone No:
5.