IAQ Testing Requirement/Procedures

View the file

Other files for this federal contract opportunity

Other files attached to Temporary housing units, specifically travel trailer models, newest first.
File Type Posted
AWARD NOTIFICATION.doc DOC document
HSFEHQ-09-R-0019 solication Final Version 01.02.2009.doc DOC document
IAQ Testing Procedures 12.19.2008.pdf PDF
TT Specification 12.15.2008.pdf PDF
HSFEHQ-09-R-0019 solication Final Version 12.19.2008.doc DOC document
TT Specification 12.15.2008.pdf PDF
SOW TT Specs.doc DOC document
HSFEHQ-09-R-0019 solication 12.11.08 DRAFT 1.doc DOC document
NEWUNIT IAQ110608.pdf PDF
Pre solicitation questions 11.25.2008.doc DOC document
TT Q A's .doc DOC document
TT Specs tt110608 —
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FEMA 2008

IAQ Testing Procedures

IAQ SCREENING TESTING PROCEDURES

FOR FEMA TEMPORARY HOUSING

A. Pre-Test Procedure (Test 1)

• As soon as unit is constructed (pre delivery or government acceptance), each temporary housing unit shall be stored for a mandatory twenty-four (24) hours waiting period with all windows, doors, vents, and other openings to the outside closed with the exception of the designed HVAC system and the HVAC system turned off (and if applicable, shut the outside air intake dampener). Interior doors in each unit, not opening to the outside of the unit, shall be open (bathroom/ bedroom doors...).

• If the manufacturer/contractor is to provide furnishings, decorative items (e.g. curtains, wallpaper, etc.), etc., those must be installed or in unit prior to the IAQ testing. All protective wrapping shall be removed and all materials exposed. This includes any materials or products in boxes. Shall remain as stated till delivery.

• The IH shall determine the predisposition of each unit (e.g. built a week ago and sitting in parking lot waiting for delivery and completely “sealed up”) prior to testing from observations and/or interviews with on-site production crew or supervisors. The IH shall document this information for each unit.

• If any of the above steps are not followed or it is found any step was not adhered to, the twenty-four (24) hour pre-test for the unit shall be recommenced within one day. This is to ensure consistency.

B. Pre-Test Procedure (Test 1)

• Once Section A has been complied with, within 24 hours it is mandatory the unit have all windows, doors, vents and other openings remain closed, interior doors remained opened and the HVAC system be turned on, set to 72 degrees Fahrenheit and remain on until testing for five (5) continuous days starting the day after the unit fails the first test. The units shall be stored in a controlled, secured location.

• Once each morning, at the beginning of the work day, walk into each unit to set the HVAC to heat or cool (72 degrees Fahrenheit) than close door. This will be dependant on the predicted high temperature for the location of the testing. Once each evening, at the close of business, walk into each unit to set the HVAC to heat or cool (72 degrees Fahrenheit) than close door. This will be dependant on the predicted high/low temperature for the location of the units. This is to be done as necessary. If high and low is predicated to be below 72 degrees Fahrenheit, leave on heat or vice versa for that day. At the time of each morning/evening HVAC setting check, take a visual reading of thermostat and verify temperature is +-5 degrees Fahrenheit of 72 degrees Fahrenheit to ensure

HVAC is running properly.

• If the manufacturer/contractor is to provide furnishings, decorative items (e.g. curtains, wallpaper, etc.), etc., those must be installed or in unit prior to the IAQ testing. All protective wrapping shall be removed and all materials exposed. This includes any materials or products in boxes. Shall remain as stated till delivery.

• The IH shall determine the predisposition of each unit (e.g. built a week ago and sitting in parking lot waiting for delivery and completely “sealed up”) prior to testing from observations and/or interviews with on-site production crew or supervisors. The IH shall document this information for each unit.

• If any of the above steps are not followed or it is found any step was not adhered to, the unit is required to begin the process starting with Section A within twenty-hours (24). This is to ensure

C. Testing Procedure (2nd test)

• After the five (5) day ventilation period, the indoor air for each unit shall be tested to document that the IAQ is below the required threshold limits. All testing should occur only between the hours of

7:00 a.m. – 6:00 p.m. This represents the typical peak in the temperature under normal weather patterns and will demonstrate an effort was made to conduct testing during the warm/humid part of the day. This likely will generate the highest possible readings. Unit shall remain sealed during testing, interior doors shall be open if they do not lead to the outside.

• The IAQ testing shall be conducted by qualified third party industrial hygienists (IH) trained and experienced in conducting industrial hygiene and/or IAQ air sampling.

• The HVAC system for each unit must be off prior to testing of each unit within twenty-four (24) hours of testing and remain off.

• The IH shall document the conditions in which testing is performed by field notes and photographs.

• The IAQ testing shall be performed for the following contaminants and recommended maximum allowable concentrations:

o Formaldehyde – Direct-reading instrumentation or Lab sampling, approved via NIOSH

2016.

Maximum concentration – Less than 16 parts per billion (ppb) as directed by

FEMA

o Total Volatile Organic Compounds (tVOCs) – ppbRAE analyzer or similar direct-reading instrumentation

Maximum concentration – 500 micrograms per cubic meter (µg/M3) o Particulates (PM10) – Met One Discrete Particle Counter (DPC) or similar direct-reading instrumentation

Maximum concentration – 50 µg/M3 o 4-Phenylcyclohexene (4-PCH)* – Charcoal tube media and low-flow air sampling pump

Maximum concentration – 6.5 µg/M3

Still researching to determine if there is direct-reading technology to measure for this VOC similar to formaldehyde and tVOCs. This could possibly eliminate the need for laboratory analysis and longer (~1 hour) sampling times for 4-PCH.

* This test is only required if carpets and fabrics with styrene butadiene rubber (SBR) latex backing material are installed as part of the base building systems.

• With the exception of the 4-PCH and/or Formaldehyde, the IAQ testing shall be performed using direct-reading instrumentation or similar approved method which shall have a current factory calibration at time of testing and operated in accordance with the manufacturer’s specifications/recommendations. This must be an instrument which can test for all requested levels.

Must be able to test for levels of Formaldehyde at a minimum of 14 ppb. The instrument shall have an accuracy rate of at least ninety (90) percent.

• The tests shall be collected in the general breathing zone of approximately three to six feet from the floor and twelve inches from wall, away from any vent, for each housing unit. One test shall be taken in units with an open floor plan and sufficient air mixing; two tests shall be taken in units with two zones that may be isolated from each other.

• The IH shall conduct: an eight hour continuous sample of Formaldehyde will be collected in the center of the THU primary living room utilizing the National Institute Occupational Safety and

Health (NIOSH) Manual of Analytical Methods (NMAM) 2016. Each day of testing an outside sample shall be collected/recorded using the same method and times stated above.

• Samples will be collected utilizing standard industrial hygiene pumps or similar approved method, an accuracy rate of at least ninety (90) percent, samples must be drawn at a flow rate and collect an appropriate sample size required by the NMAM 2016, and be placed at a height comparable to a residents breathing zone, preferably between three (3) to six (6) feet in height. For every one hundred units tested, one unit shall be tested along with a DRAEGER testing device or similar to ensure accuracy.

• The IH shall document the weather conditions, elevation, temperature and relative humidity in the unit, outside of the unit and at the time of each test.

• At the end of each sampling day, the samples will be shipped to the designated analytical laboratory accredited by the AIHA Industrial Hygiene Accreditation.

• Sample and data collection shall be completed within three (3) to five (5) business days of work order issuance and will be submitted to the FEMA COTR at that time.

• If any of the above steps are not followed or it is found any step was not adhered to, the unit is required to begin the process starting with Section A within twenty-hours (24). This is to ensure consistency.

• While awaiting test results, unit shall be stored following the protocol stated in Section A.

• If test result is less then 16 ppb and meets VOC requirements, place a sticker in the unit with the

Test result, Date, Bar Code, Vin Number, Date of Test, Location of Test, name of Third Party conducting the testing and name of Manufacturer. Place sticker below kitchen sink or on a cabinet.

• If unit fails test, proceed with Section D. If unit passes, proceed with Section E.

• If any of the above steps are not followed or it is found any step was not adhered to, the unit is required to begin the process starting with Section A within one twenty-hours (24). This is to ensure

D. IAQ Re-Testing

• For any units having a failure, the IH shall determine the cause of the problem, report the problem to the COTR/PM and how the vendor and IH will bring the unit into compliance. Once the

COTR/PM approves the recommendation, the unit shall be retested implementing all previous procedures beginning with Section A.

• If unit fails the additional testing, it will not be accepted by the government.

E. Reporting

• The IH shall provide one report for each model/unit/type tested at the vendor’s facility. Each report will include a summary of the testing data, pertinent observations made by field staff, representative photograph of exterior and interior of each model/type/unit, evaluations and conclusions based upon the testing data, and recommendations. Also included will be copies of the field documentation for the testing of each model/unit/type of housing.

F. Limitations / Qualifications

• The data from the limited IAQ testing will be used as a screening assessment tool for each housing unit to determine concentrations of certain IAQ contaminants inside the units at the time the units are completed with construction and are ready for delivery to end-users. The data will only represent the airborne concentrations of the specified contaminants for the specific time and location of each sampling point. Airborne contaminant concentrations may increase or decrease after our limited screening IAQ testing within each housing unit depending upon multiple variables such as temperature, elevation, relative humidity, and outside air ventilation rates.

• To determine the actual affects of poor IAQ within an environment, the assessment and testing would ideally be conducted under actual/normal operating conditions in the geographic location the unit(s) are to be located. There are multiple factors/variables that can affect the IAQ within a unit over a period of minutes, hours, days, weeks, months, and years.