PROJECT LABOR HOURS
HSFE06-11-R-1975
HAUL & INSTALL MISSION
June 6, 2011
Hauling Crew (Mobile Home) 720.03 HRS
Set up/Blocking Crew 463.22 HRS
Skirting Crew 294.70 HRS
Carpentry Crew 518.42 HRS
Pipe Installation Crew (above ground) 240.15 HRS
Electrical Crew 398.51 HRS
HVAC Crew 450.00 HRS
General Labor 839.87 HRS
These are the estimated hours to install 25 units