PROJECT LABOR HOURS

HSFE06-11-R-1975

HAUL & INSTALL MISSION

June 6, 2011

Hauling Crew (Mobile Home) 720.03 HRS

Set up/Blocking Crew 463.22 HRS

Skirting Crew 294.70 HRS

Carpentry Crew 518.42 HRS

Pipe Installation Crew (above ground) 240.15 HRS

Electrical Crew 398.51 HRS

HVAC Crew 450.00 HRS

General Labor 839.87 HRS

These are the estimated hours to install 25 units