DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
SHORE INFRASTRUCTURE LOGISTICS CENTER
SPECIFICATIONS FOR
REPAIR HVAC CONTROLS – MULTI-MISSION BUILDING
PSN 8436907
AT
USCG STATION JONES BEACH
1 WEST END BOAT BASIN
FREEPORT, (LONG ISLAND), NEW YORK
(NASSAU COUNTY)
David Dill - Design Project Mgr. Gerry Gosselin - Design Branch Chief
A. A. JACOBS, BY DIRECTION
COMMANDING OFFICER
UNITED STATES COAST GUARD
CIVIL ENGINEERING UNIT PROVIDENCE
475 KILVERT STREET SUITE 100
WARWICK, RHODE ISLAND 02886
USCG STATION JONES BEACH
Freeport, NY
DESIGN-BUILD SPECIFICATIONS Repair HVAC Controls MMB
USCG Station Jones Beach aerial view (2010), looking generally North. Photo pre-dates recent work to raise the roof on the Boat Maintenance Facility (aka “Boathouse, or ‘BMF’) at upper left, and waterfront improvements post Superstorm Sandy. T-Shaped Multi-Mission Building is in foreground. Gable end of UPH room wing faces water.
USCG STATION Jones Beach
SPECIFICATIONS Repair HVAC Controls MMB
TABLE OF CONTENTS
Page 1/1
PROJECT MANUAL
TABLE OF CONTENTS
COVER PAGE
AERIAL PHOTO
SPECIFICATIONS
DIVISION 01
01 11 00 Summary of Work 01 14 00 Work Restrictions 01 32 00 Construction Schedule and Schedule of Values 01 33 00 Submittal Procedures 01 35 26 Government Safety Requirements 01 50 00 Temporary Facilities and Controls 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data
DIVISION 26
26 00 00 Basic Electrical Materials and Methods
REFERENCE MATERIALS
The following information is provided electronically on a DVD.
1. Multi-Mission Station, Station Short Beach, USCG Facilities
Design & Construction Center Project No. 03-27-83, prepared by John J. Kassner & CO., Inc. Architects-Landscape Architects, Lake Success, NY 11042, Design Drawings dated 7-18-1986, with various record/as-built drawings dated variously undated through 9/19/1990; drawings M-2 through M-7.
2. HVAC System Renovations, USCG Civil Engineering Unit Providence, Project No. 01-P9454, design drawings dated 12/16/2003, annotated as Record/As Built Drawings by Verrazano Construction Co., drawings T-1 and M-1 through M-7. Record Drawings: PDF Files; Design Drawings: AutoCAD files.
3. HVAC System Repairs, USCG Civil Engineering Unit Providence, Project No. 627965, Specifications dated 30 APR 2008.
4. NFPA/NEC Code Repairs, Civil Engineering Unit Providence, Project No. 3809133, Drawing M-1, dated 12/6/2011.
5. Photographs.
GENERAL REQUIREMENTS
01 11 00 Page 1/13
DIVISION 01
SECTION 01 11 00
SUMMARY OF WORK
1 PART 1 GENERAL
1.1 Project Location
The Facility is located at
U.S. Coast Guard Station Jones Beach 1 West End Boat Basin Freeport, (Long Island, Nassau County), New York 11520
1.2 SITE POINT OF CONTACT
For the purposes of arranging a site visit, the Site Point of Contact is:
MKC Patrick Cohan Engineering Petty Officer U.S. Coast Guard Station Fire Island
(516) 785-2995
1.3 FACILITY DESCRIPTION
The Multi-Mission Building is a 9,648 Sq. ft. single story, slab on grade building constructed in 1988. Commercial construction building methods and materials used include masonry and Concrete Masonry Units for vertical support members, structural wood trusses for roof framing, and brick veneer at exterior walls.
The original primary HVAC systems for the building included through-wall Water Source Heat Pump PTAC units, supported by a cooling tower and boilers, along with AHUs for outside air for occupied areas and a makeup air handling unit for the Galley exhaust hood. PTACs were removed and replaced with a Variable Air Volume system supplemented by baseboard radiation by CEU Providence in 2003. The primary system components include 21 Variable Air Volume Air Terminal Units with onboard controllers (‘VAV boxes) and no reheat coils, 21 ton dual compressor Outside Air Cooled Condensing Unit, 7200 CFM York “Solution” Built-up, draw through Air handling unit equipped with a pre-heat coil and DX cooling coil, Outside and Return Air dampers, and a Variable Speed drive that adjusts Supply Air Fan speed based on input from 3 Duct Static Pressure sensors. The reverse return Heat Pump Water
Page 2/13 loop was re-purposed to serve baseboard radiation (~ 31 settings) in the areas where the original through-wall WSHPs were installed. Thermostats are connected to a controller on each VAV box, which are designed to sequence the VAV Damper and radiation control valve serving the control zone.
In the summer of 2008, another project was completed to correct HVAC Equipment (including a replacement heating coil and control valve), balancing, and control issues.
In 2011, wiring at the VAV boxes (including lack of covers on junction boxes) was corrected. During field work for this project, excessive Supply Air duct leakage in the attic areas was observed.
1.4 CURRENT CONDITIONS – MMB HVAC SYSTEMS
1.4.1 AHU-1. Outside Air damper is rusted and difficult to move.
CG Health, Safety and Work-Life (HSWL) has noted poor indoor air quality since, at one point, the unit was not admitting outside air into the building, resulting in excessive CO2 levels. Outside and return air dampers are manually set in position. Combined with a control system that is no longer fully functioning as designed/programmed, this results in low supply air temperatures. Radiation in spaces served by VAV boxes (that are not equipped with reheat coils) cannot keep up with heating requirements imposed by the low SA temperatures (and faulty control valves) result in the use of electric space heaters for occupant comfort.
A relief air vent through the roof is in place above the ductwork for the AHU-1 return air system, but is not connected to the same.
1.4.2 HV-3. Heating & Ventilating Unit HV-3 provides make-up air to replace air removed from the galley Hood exhaust fan.
The unit supplies a trunk duct that is designed to deliver 800 CFM directly to the hood, with 650 CFM heated by a duct coil that serves the general galley and mess deck areas.
The outside air damper for this unit is rusted with an ineffective damper operator. Faulty operation of the Make-up air system (and possibly poor design) has resulted in frozen piping in the area on at least 2 occasions in the past several years, and caused uncomfortable cooking condition in the galley (Food Service staff wearing coats.)
1.4.3 Automatic Temperature Control (ATC) System. The ATC system is used to monitor and/or control alL of the equipment installed in the 2003 HVAC project, including VAV boxes, boilers, and AHU-1. The Operator Work Station (OWS)
Page 3/13 consists of a PC tower located in the mechanical room with a flat screen monitor. Operation and reliability of the Automatic Temperature Control (ATC) system is erratic, and can only be effectively serviced by York/JCI technicians (Johnson Controls/York, 6A Aerial Way, Syosset, NY 11791, Ms. Amanda Sargent, (516) 937-2340, Amanda.Sargent@jci.com). Its effective use is further compromised by broken or damaged terminal control devices.
The system in its present state includes a Graphical User Interface with screens for the heating plant and AHU-1 with real time values indicated for set points and current state. However, a “Hard Drive failure imminent” message was reported by the Station personnel as an error message.
VAV Boxes are not equipped with reheat coils, and are Envirotec SDR series, equipped with York CX-VAV controllers (ISNConneXsys family). Several representative VAV box photos are included in the Reference Materials, and document CX-VAV part no. 371-04474-001.
1.5 SUMMARY OF WORK
The USCG is planning to execute a project to replace the entire HVAC plant in the next 18 months, however, until this project is complete, the CG desires to correct conditions that affect occupant comfort in areas most commonly used by the crew for eating, sleeping and office/USCG operations purposes.
The following establishes the minimum Scope of Work:
1.5.1 AHU-1.
1. Replace Outside and Return dampers and damper operators with low leakage, quick response (less than 60 second stroke period) dampers and damper operators.
1.5.2 HV-3
1. Replace Outside Air damper and damper operator with low leakage, quick response (less than 60 second stroke period) damper and 2 position damper operator. Damper shall fail closed.
2. Replace control valve for duct mounted heating coil with modulating type, temperature sensor to control same, and Freezestat, all as required to achieve control sequence below. Control valve shall fail with flow through coil.
3. If not corrected by the above actions, identify the cause of frozen piping and recommend one or more methods to prevent future occurrences.
Page 4/13
4. Verify that HV-3, EF-16, and Duct Coil HC-1 (downstream of HV-3) operate in accordance with the following control sequence:
EF-16 and HV-3 shall be interlocked for simultaneous operation. When outside air temperature is less then 60ºF (adjustable), the two way control valve shall modulate to maintain 75ºF (adj.) downstream of HC-1.
Freezestat with serpentine sensor strung on the discharge face of HC-1 and set at 37ºF shall prevent HV-3 from operating, set Normally Open coil valve open and fully close the Normally Closed Outside Air damper.
1.5.3 Troubleshoot and Repair ATC Operator Work Station.
1. Update Operating System of existing York ISN ATC System.
Verify programming is correct; make necessary adjustments. Noting that the Station Jones Beach Engineering Officer reports that “:Hard Drive Failure Imminent” was displayed as an error message, work includes replacement of existing Hard drive in OWS computer, and any data/programming migration required to restore system operation.
2. Verify proper Operation of AHU-1 Heating Coil Control valve.
3. Restore Sequences of Operation for AHU-1, associated ACCU-1, VFD, and VAV boxes to approximate the specified Sequences of Operation, per Record Drawing M-7 of PSN 01- P9454. Demonstrate operation of 100% outside air delivery to Supply air system with all VAV boxes open 100%, and record Supply Air, Return Air, and VAV box CFM to each zone served.
4. Assume the replacement of (3) Duct Static pressure sensors in ductwork accessible in the attic areas of the
MMB.
5. Relocate the existing Operator Work Station (OWS) from the MMB boiler room into nearby Training Space (Rm 115).
Provide cabling, conduit, and penetrations through wall and ceiling assemblies as required. Seal all penetrations as required for 2 hour fire rated assemblies, using intumescent fire sealant.
6. Provide brief summary of actual repairs and programming completed, including Graphical User Interface printscreens of major systems (e.g., Heating Plant, Cooling plant) as closeout materials.
7. OWS Troubleshooting and programming shall be accomplished by a Johnson Controls/York HVAC controls technician.
1.5.4 Testing, Adjusting & Balancing (TAB)
Page 5/13
1. Adjust supply and return CFM volumes of AHU-1 and VAV system, including VAV boxes, and supply and return diffusers.
2. Galley Make-Up and Exhaust Air. Adjust supply volumes to areas served by HV-3, including galley exhaust hood, and supply air diffusers; balance heating hot water flow through heating coil supplied by HV-3 to originally specified flow rate; adjust exhaust air volume of Galley Exhaust Fan EF-16. Nominal Supply and exhaust volumes are 2,000 CFM. Balance HV-3 and EF-16 to result in a slight negative pressure in the galley/mess deck area relative to adjacent spaces. (Refer to sheet M-7 sheet 41 of 55 of original construction for originally specified equipment performance and flow rates.)
3. Provide a TAB report based on field work and report preparation by NEBB or AABC-certified TAB professional.
TAB efforts conducted and Report submitted shall be prepared in a report format, and with information consistent with and/required by the certifying organization.
1.5.5 Radiation Control Valves. Refer to reference drawings for
2003 HVAC Renovation Project (PSN 01-P9454) at Drawing M-3 Sheet 4 of 8. Replace inoperative or failing low voltage control valves (~31 locations – see risers on M-3 and field verify exact quantity and locations) for all terminal heating equipment (primarily radiation control valves) with Normally Open similar type, which shall communicate with and respond to a call for heat from the existing associated thermostat or VAV box zone controller. Verify proper operation in accordance with Control Sequence of Operation as described on reference drawings for PSN 01-P9454, on Drawing M-7 Sheet 8 of 8.all required domestic hot water heating, water filtration, water pressure booster equipment, piping, controls, cables and accessories required for a complete and operable domestic hot water heating system for the MMB. This includes replacement of existing electric water heating plant with LP Gas fired type equipment, and storage tanks as required to serve domestic hot water heating requirements.
1.5.6 Refer to RFP and other Specification Sections for
additional information and Requirements.
1.6 SUBMITTALS
Government approval is required for submittals. The following shall be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Page 6/13
None
SD-03 Product Data
Sequences of Operation for
(1) HV-3/EF-16/HC-1 System
(2) VAV System, addressing and including all components and set points.
Schedule of Pipe and fittings, proposed for use including (as applicable)
Steel Pipe Copper Pipe
Control Valves and Valve Operators
Dampers and Damper Operators
Any Control devices proposed or required for installation.
Labels, signs and labeling.
Manufacturer's installation instructions and procedures on all parts and equipment.
SD-06 Test Reports
Testing, Adjusting & Balance Report, including drawings to correlate flow readings associated with each heating coil, VAV box, register, and diffuser.
Brief summary of actual repairs and programming completed on Automatic Temperature Controls System, including Graphical User Interface printscreens of major systems (e.g., Heating Plant, Cooling plant) as closeout materials.
SD-10 Operation and Maintenance Data
Operation and Maintenance Manuals.
Three complete copies of operation manuals in letter-size 3 ring binders, along with approved submittals and approval forms for all components provided.
The manuals shall include the manufacturer's name, model number, service manual, a brief description of each
Page 7/13 piece of equipment, and the basic operating features of each piece of equipment.
The manuals shall include piping, equipment layouts, and simplified wiring and control diagrams of the system as installed.
1.7 CONTINUITY OF SERVICE
The Multi-Mission Building will be occupied during construction. Conduct the work accordingly, including specific requirements regarding advance notification of interruption of building utilities.
Interruption of utilities shall be minimized. Interruption of any utility for a period of more than 2 hours in a 24 hour period shall be approved in writing one week in advance by the COR. Interruption of utilities for more than 8 hours in any 24 hour period requires the provision of temporary utilities. This specifically applies to the interruption of domestic hot water.
1.8 PRE-PROPOSAL MEETING
The D-B Contractor shall participate in a conference call with the Contracting Officer and the CG Design Project Manager to review the requirements of this specification, and clarify and confirm the scope of work. The date and time shall be arranged, generally within two weeks of issuance of solicitation.
1.9 DEFINITIONS, ACRONYMN, AND ABBREVIATIONS
The following terms, when used in the Contract Documents, have the meaning described.
a. ACCU: Air Cooled Condensing Unit.
b. AHU: Air Handling Unit.
c. BMF: Boat Maintenance Facility, aka “Boathouse”.
d. Contracting Officer: The U.S. Coast Guard’s Contracting
Officer, or his/her designated representative.
e. Contracting Officer’s Representative (COR): The Coast
Guard’s assigned onsite technical representative.
f. Contractor: The word “Contractor” is also deemed to include the Design-Build Firm contracted with the U.S. Coast Guard for performance of work, including all engineering and construction services as well as the furnishing and installation of materials.
g. Contract Documents: This RFP and materials attached to, included by reference, and developed and approved by the government as part of the project.
Page 8/13
h. Construction Superintendent: Design-Build firm’s on site project supervisor responsible for overseeing all tradespersons and to assure that the construction is in compliance with the contract documents as well as assuring that all on-base regulations are followed. This person will also be the onsite point of contact for the Contracting Officer, and other Government personnel related to the project.
i. Design-Build (D-B): Design-Build means combining into a single contract the project’s design and construction phases, including construction engineering and inspection services.
j. Design-Build Firm (DBF): Design-Build Firm means any company, firm, partnership, corporation, association, joint venture, or other legal entity permitted by law to practice engineering and construction services in the State of New York.
k. Designer of Record (DOR)
The Professional Engineer or Architect registered in the State of New York that develops the concept and design for the project, performs the analysis and engineering calculations, and is responsible for the preparation of the following:
Answering all design and/or construction questions pertaining to the design;
Approval authority for technical submittals in conjunction with the Government’s Contracting Officer;
Final inspection and generation of “punch list” items that do not meet the design documents and/or approved submittals.
l. Furnish: Supply and deliver to installed location.
m. Furnished by others: Receive delivery at job-site or where called for and install.
n. H&V: Heating & Ventilating, as in “Heating & Ventilating
Unit” or HV-#.
o. Inspection: Visual observation by Contracting Officer or authorized representative.
p. Inspector: The US Coast Guard representative that is responsible for the oversight of construction activities to assure compliance of the project documents. The inspector may request that contractors provide manufacturer information of products being used during construction to assure that the construction documents are being complied with. The Coast Guard Construction Inspector may also inspect any materials that are on site as well as the installation to assure compliance with the construction and contract documents.
Page 9/13
q. Install: Mount and connect equipment and associated materials ready for use.
r. MMB: Multi-Mission Building
s. Occupied Areas: All areas, except the basement mechanical/electrical room, roof, enclosed voids below stairwells accessed through a door or panel, janitor’s closets.
t. Project Manager: The Contracting Officer for the U.S. Coast Guard that is responsible for the administration of the Design-Build Contract.
u. Project Sequence Number: A project-specific number assigned by the US Coast Guard to a particular scope of work, and commonly used to refer to a particular project.
v. Provide: Furnish, install and connect ready for use.
w. PSN: Project Serial Number.
x. Relocate: Disassemble, disconnect, and transport equipment to new locations, then clean, test and install ready for use.
y. Replace: Remove and provide new item.
z. VAV: Variable Air Volume.
aa. VFD: Variable Frequency Drive.
1.10 REFERENCE MATERIALS
The organization and execution of the Work shall be based on actual field verification of existing conditions. However, a significant amount of information is present on the materials listed below, provided electronically on a DVD.
1. Multi-Mission Station, Station Short Beach, USCG Facilities Design & Construction Center Project No. 03- 27-83, prepared by John J. Kassner & CO., Inc.
Architects-Landscape Architects, Lake Success, NY 11042, Design Drawings dated 7-18-1986, with various record/as-built drawings dated variously undated through 9/19/1990; drawings M-2 through M-7.
2. HVAC System Renovations, USCG Civil Engineering Unit Providence, Project No. 01-P9454, design drawings dated 12/16/2003, annotated as Record/As Built Drawings by Verrazano Construction Co., drawings T-1 and M-1 through M-7. Record Drawings: PDF Files; Design Drawings:
AutoCAD files.
3. HVAC System Repairs, USCG Civil Engineering Unit Providence, Project No. 627965, Specifications dated 30
APR 2008.
4. NFPA/NEC Code Repairs, Civil Engineering Unit Providence, Project No. 3809133, Drawing M-1, dated 12/6/2011.
Page 10/13
5. Photographs.
Page 11/13
2 PART 2 – PRODUCTS
2.1 CONTROLS
2.1.1 Restore Operation of existing Johnson Controls/York
electronic Controls system, to achieve the control sequences originally specified (refer to record drawings issued on design drawings dated 10/16/2013). Update the following existing algorithms as applicable: OA/RA proportioning to achieve minimum OA volume regardless of OA temperature; scheduling, energy management, and safety functions.
2.1.2 Provide wiring and conduit as required to connect devices furnished for installation as part of or adjunctive to the automatic controls system regardless of manufacturer or source of supply.
2.1.3 Provide power and control circuits, 120 volt maximum to electrical panels. Install wiring in accordance with requirements of the National Electric Code.
2.1.4 Provide wiring, conduit and devices required for proper system operation, including special electrical switches, transformers, disconnect switches, relays, circuit breaker protection and other devices as required.
2.1.5 Control valves shall be sized by the manufacturer, not more than 10 feet of pressure drop, equal percentage type, 316 stainless steel stem, replaceable composite disc, rubber diaphragms, screwed body for 2 inch and smaller, flanged body for 2-1/2 inch and larger, 125 psi, fail safe. Match existing type and sequence, unless otherwise approved by
COR.
2.1.6 Automatic dampers shall be low leakage type, less than ½% leakage at 1500 fpm and 4 inch static pressure; non-metallic material at sealing/mating surfaces of blades;
opposed blades for modulating function, parallel blades for two position function; blades not over 8 inches wide; edge and side seals; maximum pressure drop 0.1” at 1500 fpm;
proportioning piston type operator, oil filled if exposed to outside air or freezing conditions; square or keyed linkage connection at shafts, for size to match existing frame or duct openings. Unless otherwise called for, dampers shall fail safe for life safety, which shall take precedence over equipment protection. Confirm at time of submittal.
2.1.7 Motors for Motor Operated Dampers and Valves shall be
selected to be 100% open within 60 seconds of a signal to open. Note compliance with this requirement on shop drawings, including product data sheets and submittal for Sequences of Operation.
2.2 Piping and fittings: Match existing. Mechanical fittings
(similar to Pro-press type) also acceptable. Minimize hot work. The building is not sprinklered. Notify the Station
Page 12/13
Duty Officer/COMCEN in advance of any hotwork. Provide and post a fire watch during hot work operations.
3 PART 3 EXECUTION
3.1 TEST, ADJUSTMENT & BALANCING
3.1.1 Test, Adjustment and Balancing report shall be typed and three copies submitted for review, results shall be guaranteed. Contractor shall be subject to recall to site to verify the report information before acceptance of the report by the Owner’s Representative.
3.1.2 Contracting Officer’s Representative shall be advised two
(2) weeks in advance of date scheduled for Test, Adjustment and Balancing operations.
3.1.3 Balancing contractor shall be a member of the Associated Air Balance Council or the National Environmental Balancing Bureau.
3.1.4 Place systems in satisfactory operating condition.
Adjusting and balancing shall be accomplished as soon as the system/equipment repairs have been completed and before systems are turned over to owner for beneficial use and occupancy. Adjusting and balancing shall take place under appropriate outdoor temperature conditions. Change pulleys as required to meet system performance requirements.
Perform necessary mechanical adjustments in conjunction with balancing procedures. If found to be inoperative replace balancing cocks, flow balancers, and volume dampers as required to meet system performance requirements.
Replace dampers in systems that cannot be manipulated to satisfy balancing requirements. Prior to replacement, notify COR and respond as required to request for proposal to restore system operation.
3.1.5 Air systems: Test and adjust fan rpm to meet design
requirements. Test and record motor no load and full load amperes, and determine operating brake horsepower. Test and record system static pressures, suction and discharge.
Test and adjust zones for design supply, return and exhaust air cfm. Test and adjust system for design outside air CFM.
1. Test and record entering air and leaving air dry and wet bulb temperatures at coils.
2. Test and adjust zones to proper design supply, return, and exhaust cfm.
3. Adjust terminal units to design OA CFM.
4. Test and adjust each diffuser, grille and register to within 10% of design requirements.
3.1.6 Water systems: Set pumps to proper gallons per minute
delivery. Test and record suction and discharge pressures.
Test and record motor rated and full load amps. Check and set operating temperatures and adjust for design
Page 13/13 requirements. Check water temperatures and adjust flow for design requirements. Check water temperatures at outlet side of coils; note rise or drop of temperature from source.
3.1.7 Scope of Work includes Test, Adjustment and Balancing of the following systems and equipment:
1. AHU-1 and associated equipment noted above.
Demonstrate operation of 100% outside air delivery to Supply Air system with all VAV boxes open 100%, and record Supply Air, Return Air, and VAV box CFM to each zone served. Intent is to determine supply and return air system leakage, and building pressurization in this OA/Return Air damper. Consult with Design Project Manager to establish schedule for introduction of OA vs. outside air conditions.
Set VAV Zone CFM IAW design values on drawings for PSN 01-P9454 (see reference materials).
Adjust VFD for system to maintain 0.6” W.C. (adj.)
minimum at each duct static pressure sensor.
2. HV-3, EF-16, and associated Heating coil.
3. Heating Hot Water Pumps and terminal heating equipment, IAW flow rates in Specification for PSN 627965 on page 5 of 7(see reference materials).
4. Verify operation of Existing Differential Back Pressure Valve (refer to Sheet M6 of PSN 01-P9454).
3.2 TRAINING & FUNCTIONAL PERFORMANCE TESTING
Conduct training for Station Jones Beach Personnel incidental to or at the conclusion of the project. Notify COR in advance of installation of dampers and damper operators, valves and valve operators, and work on OWS.
At conclusion of project, and in the presence of the COR, demonstrate operation and use of OWS for troubleshooting HVAC system operation, including methods for adjustment of set points, and identification of possible causes for alarm conditions.
Conduct a Functional Performance Test of equipment provided, including demonstration of Sequence of Operations for all components and sub-systems of the AHU-1/ACCU-1 VAV System, HV-3/EF-16/HC-1.
-- End of Section --
WORK RESTRICTIONS
01 14 00 Page 1/3
SECTION 01 14 00
07/07
PART 1 GENERAL
1.1 SCHEDULE
The project is anticipated to require the contractor to schedule short duration (measures in periods less than 8 hours) includes interruptions in the availability of domestic cold and hot water services. These shall be scheduled in advance with the COR. Refer to other specification sections, including 01 11 00 GENERAL REQURIEMNTS at 1.6 CONTINUIITY OF SERVICE.
The Design-Build Firm shall prepare and present for review, at or in advance of the Project kick-off meeting, a Project Schedule. The Project Schedule shall include Design and Construction milestone dates. Refer to Section 01 32 00 CONSTRUCTION SCHEDULE AND SCHEDULE
OF VALUES.
1.2 SUBMITTALS
Government approval is required for submittals. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Plan for protection of Furniture, Equipment and Interior finishes;
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed for the project become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.3.2 Working Hours
Regular working hours shall consist of an 8 1/2 hour period established, with input from the contractor at the pre-construction conference, by the Contracting Officer Monday through Friday, excluding Government holidays.
Page 2/3
1.3.3 Work Outside Regular Hours
Work outside established work hours shall be approved 1 week in advance by the COR.
1.3.4 Occupied and Existing Buildings
The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the building during the construction period.
Areas where work is in progress shall be kept under slight negative pressure relative to adjacent areas to control the migration of construction-generated dust.
1.3.5 Protection of Furniture and Equipment (F&E)
Contractor is responsible for the protection of Furniture and any other Equipment (F&E) that remains in Work areas. The nature of the work is anticipated to include saw cutting or core drilling through masonry, demolition of fiberglass insulation, and other dust generating activities. Protection shall, at a minimum, include moving F&E away from the area of work, and covering with poly sheeting to prevent dust and debris from landing on the F&E, held in place with tape.
Prior to commencement of work, secure approval from Contracting Officer regarding proposed protection plan for F&E. Alternatively, relocate movable F&E away from the Contractor's working area as required to perform the work, protect the F&E, and replace the F&E in its original locations upon completion of the work.
The Government will remove and relocate certain other Government property, including television sets, clock/radios, and other electronic equipment in the areas of the building scheduled to receive work.
1.3.6 Protection of Finishes
Contractor is responsible for protection of interior floor and wall finishes. Protect any carpeted and other areas from damage.
Restore damaged flooring with materials and methods to match existing finishes.
1.3.7 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government
Page 3/3 holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, heating, and fire alarm, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
d. Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, and electrical services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.4 SECURITY REQUIREMENTS
1.4.1 Areas Not Covered by Contract
The Contractor will not be permitted to enter buildings or areas not covered by this contract, except on prior approval of the Contracting Officer.
1.4.2 Parking
Do not park on or block the fire lanes or roads that circle the building at any time.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
CONSTRUCTION SCHEDULE AND SCHEDULE OF VALUES
01 32 00
SECTION 01 32 00
PART 1 GENERAL
The Construction Schedule and the Schedule of Values shall be provided for approval as two separate documents.
Construction Schedule and Schedule of Values shall be maintained simultaneously. The Construction Schedule shall clearly indicate the start and completion dates; the Schedule of Values shall indicate the value of all major work components.
The Construction Schedule and Schedule of Values as approved by the Government is not a substitute for quantities covered by the specification and drawings and those required for a complete job.
Omissions and errors on the Construction Schedule and Schedule of Values are the responsibility of the Contractor.
Payments will not be made until the schedule of prices has been submitted to and approved by the Contracting Officer
1.1 SUBMITTALS
Submit the following in accordance with Section 01 33 00, "Submittal Procedures."
Construction Schedule Schedule of Values
1.2 CONSTRUCTION SCHEDULE
At the Pre-Construction Conference, submit a Construction Schedule and Schedule of Values in accordance with FAR Clause 52.236.15. The Schedule of Values shall be based on the actual breakdown of the bid price. The cost of insurance shall not be listed as a separate item but included as part of each item of work. The actual cost of bonds may be paid as the first progress payment when a receipt from the bonding company is presented to the Contracting Officer. In addition, keep the Government Inspector informed daily of the expected delivery dates for major pieces of equipment and materials.
Construction Schedule and Schedule of Values shall incorporate at a minimum the following activities:
a. Design Activities
Page 2/3
b. Mobilization
c. Demobilization
d. Pre-Construction Submittals
e. Work Activities
f. Product and In-Progress Submittals
g. Final Government Inspection
h. Close-Out Submittals; i.e. Testing Balancing Reports, Warranties, Operation and Maintenance Manuals, Posted Instructions
i. Record Drawings
j. Factors which Constitute Potential Interruptions to Station Operations
Pre-Construction Submittals are those activities which encompass the obtaining, submission, review and approval of submittals necessary prior to the start of the related site work. Contractor shall annotate all such activities into the progress schedule with their forecasted time periods. These activity periods shall not be exclusive of the contract performance period. No site work shall commence until the respective submittals have been approved.
1.3 SCHEDULE OF VALUES
The value of all major work components within the project shall be identified on the Schedule of Values, assigning value to principal portions of contract for construction. For projects where the work provided by a CSI Trade contractor is relatively small (e.g., less than 10 % of the contract value), this work may be represented by a single line on the Schedule of values. For larger CSI trades this work shall be broken down in labor, major materials and other similar lines to facilitate assessment of and payment for progress. Lump sum items shall only be paid for when 100% complete.
1.4 UPDATED SCHEDULES
Update the construction schedule and equipment delivery schedule at monthly intervals or when schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.
Page 3/3
3.1 PROGRESS UPDATES
3.1.1 General
A revised Construction Schedule and Schedule of Values shall be issued by the Contractor on a monthly basis. In addition, any revisions to the Construction Schedule and Schedule of Values such as modifications or delays shall be reflected by Contractor submission of an updated Construction Schedule and Schedule of Values.
3.1.2 Modifications
When a modification is issued by the Government, record the modification as the last activity of the Construction Schedule and Schedule of Values and include the value of the modification. Adjust the Schedule of Values to reflect the inclusion of the modification.
Revise the Construction Schedule to annotate the progress change.
Enter all modifications in this manner in sequential order.
--End of Section--
SPECIFICATIONS Replace Water Heating Plant- MMB
SUBMITTAL PROCEDURES
01 33 00 Page 1/12
SECTION 01 33 00
01/08
1.1 GENERAL
Submittals form a significant and important part of the Project Record and Close-out materials. Submittals shall identify completely, and in detail, the performance and features of all systems components and equipment provided as part of the project.
1.2 DEFINITIONS
1.2.1 Submittal
Shop drawings, product data, samples, and administrative submittals presented for review and approval. Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."
1.2.2 Types of Submittals
All submittals are classified as indicated in paragraph "Submittal Descriptions (SD)". Submittals also are grouped as follows:
a. Shop drawings: As used in this section, drawings, schedules, diagrams, and other data prepared specifically for this contract, by contractor or through contractor by way of subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate portion of work.
b. Product data: Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data and other data to illustrate a portion of work, but not prepared exclusively for this contract.
c. Samples: Physical examples of products, materials, equipment, assemblies, or workmanship that are physically identical to portion of work, illustrating portion of work or establishing standards for evaluating appearance of finished work or both.
d. Administrative submittals: Data presented for reviews and approval to ensure that administrative requirements of project are adequately met but not to ensure directly that
Page 2/12 work is in accordance with design concept and in compliance with contract documents.
1.2.3 Submittal Descriptions (SD)
Construction Progress Schedule Submittal register Schedule of values Work plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the contractor for integrating the product or system into the project.
Drawings prepared by or for the contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Calculations, mix designs, analyses or other data pertaining to a part of work.
Page 3/12
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports
Daily checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data sheets concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative to confirm compliance with manufacturer's standards or instructions.
Factory test reports.
Data intended to be incorporated in operations and maintenance manuals.
SD-11 Closeout Submittals
Page 4/12
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
As-built drawings
Special warranties
Posted operating instructions
Training plan
1.2.4 Approving Authority
Person authorized to approve submittal.
1.2.5 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Submit the following in accordance with this section.
Submittal register
1.4 USE OF SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses.
1.4.1 Submittal Register
Submit submittal register at 50% Design Submission. Verify that all submittals required for the project are listed. Include the following on the register:
Transmittal Number: Contractor assigned list of consecutive numbers.
Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Contractor Approval Date: Date Contractor needs approval of submittal.
Contractor Material: Date that Contractor needs material delivered to Contractor control.
Page 5/12
1.5 PROCEDURES FOR SUBMITTALS
1.5.1 Reviewing, Certifying, Approving Authority
Designer of Record and Contracting Officer shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals for the Government is the Contracting Officer unless otherwise specified for specific submittal.
1.5.2 Constraints
a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.
b. Submittals shall be complete for each definable feature of work; components of definable feature interrelated as a system shall be submitted at the same time.
c. When acceptability of a submittal is dependant on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.
d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.
1.5.3 Scheduling
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.
1.5.4 Variations
Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to Government.
1.5.4.1 Considering Variations
Discussion with Contracting Officer prior to submission, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Page 6/12
1.5.4.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
1.5.4.3 Warranting That Variation Are Compatible
When delivering a variation for approval, Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.5.4.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of 5 working days will be allowed for consideration by the Government of submittals with variations.
1.5.5 Contractor's Responsibilities
a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.
b. Transmit submittals to Contracting Officer in accordance with schedule on approved Submittal Register, and to prevent delays in the work, delays to the Government, or delays to separate Contractors.
c. Advise Contracting Officer of variation, as required by paragraph entitled "Variations."
d. Correct and resubmit submittal as directed by approving authority. When resubmitting disapproved transmittals or transmittals noted for resubmittal, the Contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.
e. Furnish additional copies of submittal when requested by the Contracting Officer, to a limit of 6 copies per
Page 7/12
f. Complete work which must be accomplished as basis of a submittal time to allow submittal to occur as scheduled.
g. Ensure no work has begun until submittals for that work have been returned as "approved," except to the extent that a portion of the work must be accomplished as basis of
1.5.6 Government Responsibilities, through the Contracting Officer
a. Note date on which submittal was received from Contractor on each Contract Item Approval Request Form.
b. Review each submittal; and check and coordinate each submittal with requirements of work and contract documents.
c. Review submittals for conformance with project design concepts and compliance with contract documents.
d. Ensure that material is clearly legible.
e. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents. Deliver review comments to contractor within 14 days of receipt of
f. Identify returned submittals with one of the actions defined in paragraph entitled "Actions Possible" and with markings appropriate for action indicated.
1.5.7 Actions Possible
Submittals will be returned with one of the following notations:
a. Submittals marked "approved" "approved as submitted" authorize Contractor to proceed with work covered.
b. Submittals marked "approved" "see below" authorize Contractor to proceed with work as noted provided Contractor takes no exception to the notations.
c. Submittals marked "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with approved changes. No work shall proceed for this item until resubmittal is approved.
1.6 FORMAT OF SUBMITTALS
Page 8/12
1.6.1 Transmittal Form
Transmit electronically each submittal, except sample installations and sample panels, to office of approving authority. Transmit submittals with transmittal form prescribed by Contracting Officer and standard for project. On the transmittal form identify Contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled "Identifying Submittals." Process transmittal forms to record actions regarding sample installations and panels.
1.6.2 Electronic Submittals and Other Materials
Submittals and other required materials shall be provided as noted below.
a. Submittals and other materials form an important part of the official project record, documentation of equipment and systems provided, and constitute a critical component of the maintenance manual for the life of the building or systems installed.
b. Electronic materials, if generated using scanning techniques, shall result in legible documents, prepared using original documents whenever possible.
c. Electronic submittals may be originated in any file format, but must be transmitted in a file format agreed upon by the Contracting Officer,(Adobe version 7.0 unless otherwise noted).
d. Maximum electronic file size shall be limited to 10MB.
e. All electronic submittals and other materials shall be identified as required in paragraph "identifying Submittals."
f. All Product Submittals shall be clearly annotated to indicate specific model of equipment…