SPECIFICATIONS INVITATION FOR BID (IFB) HSCGG1-16-B-PEC201 PAINTING OF INTERIOR AND EXTERIOR SURFACES USCG ACADEMY NEW LONDON CT (NEW LONDON COUNTY)
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Painting of Interior and Exterior Surfaces
U.S. COAST GUARD ACADEMY
NEW LONDON, CT
PROJECT NO:
R. M. Hunter, LCDR
Date: 10 December, 2015
TABLE OF CONTENTS
DIVISION 1 GENERAL REQUIREMENTS
01010 SUMARY OF WORK……………………………………………………….1
01020 SPECIAL CONSIDERATIONS (OSHA AND ENVIRONMENTAL
PROTECTION ………………………………………………………………………3
01040 PROJECT COORDINATION……………………………………………… 6
01300 SUBMITALS………………………………………………………………..10
DIVISION 2 SITE WORK
02080 REMOVAL & DISPOSAL OF LEAD-CONTAINING PAINT………
02090 LEAD BASED PAINT STABILIZATION……………………….....……..23
DIVISION 9 FINSHES
099113 EXTERIOR PAINTING..………………………………..………………..26
099123 INTERIOR PAINTING………..……………………………..…………...36
099300 STAINING AND TRANSPARENT FINISHING………………..………44
SECTION 01010 – SUMMARY OF WORK
PART 1 – GENERAL
1.1 RELATED DOCUMENTS
A. Drawings, terms and conditions of this contract, including the general requirements and other division specifications, apply to this section.
1.2 PROJECT DESCRIPTION
A. This project consists of a Indefinite Delivery, Indefinite Quantity (IDIQ) contract for the painting of interior and exterior surfaces at the United States Coast Guard Academy, New London, Connecticut. This includes the temporary relocation of furniture, fixtures and equipment in those areas to be painted and potentially lead paint removal or encapsulation as detailed in SECTIONS 02080 and 02090.
B. All contractors are advised to visit the site prior to submitting bids to familiarize themselves with site conditions.
1.3 CONTRACTOR PERSONNEL EXPERIENCE REQUIREMENTS
A. Contractor personnel shall demonstrate a minimum of three (3) years of recent and relevant experience in the painting of Federal, educational, or military installations/facilities including evidence of satisfactory completion of three (3) projects similar in magnitude and nature to the awarded project. For experience to be considered recent, it must be within the last five (5) years. For project completion to be considered satisfactory, it must be of an acceptable quality and have been completed on time and within budget. Valid points of contact, phone numbers, and email addresses for each of the projects referenced is required for validation of performance. Proposed personnel must meet these minimum requirements in order to be eligible to perform work on task orders issued against IDIQ contracts awarded as a result of this solicitation."
1.4 WORK SEQUENCE
A. Work shall be conducted by the contractor to provide the least possible interference to the activities of the government’s personnel.
1.5 CONTRACTOR USE OF PREMISES
A. General: During the performance of work, the contractor shall have use of the premises and work site as specified by the Contracting Officer’s Representative (COR). Material storage, preparation areas, and work areas shall be as designated by the COR.
B. Parking: The contractor shall keep the roadways serving the premises clear and available to the government and government’s employees at all times. Do not use roadways for parking or storage of materials. The COR shall advise the contractor of available parking. Overnight parking of contractor’s vehicles is not authorized.
C. Use of Existing Buildings: The contractor’s use of the building is limited to the immediate project site and adjacent areas as required for the work being performed.
The contractor shall take all precautions necessary to protect the building during the performance of work. Bathroom facilities for contractor’s use shall be designated by the COR. Paint brushes and other equipment shall not be cleaned within these designated bathroom facilities.
D. Work Schedule: All work shall be done between 7:30 a.m. to 4:00 p.m., Monday through Friday, excluding Federal Holidays. The contractor will be required to have prior approval from the COR for any deviation from the above work schedule.
1.6 SAFETY PRECAUTIONS
A. These documents and the work hereby contemplated shall be governed at all times by applicable provisions of Federal Regulations, including, but not limited to, the current edition, with the latest amendment(s) of the following:
1. William-Steiger Occupational Safety and Health Act of 1970, Public Law 91-
596; Part 1926 – Occupational Safety and Health Standards, Chapter XVII of Title 29, Code of Federal Regulations (29 CFR Part 1926).
B. The contractor shall notify the Coast Guard Academy Fire Marshall via the COR prior to the start of any work which may affect or impair any fire protection system or which may present a fire hazard (i.e., sanding, welding, grinding, burning or utilizing of any flame producing device).
1.7 GOVERNMENT OCCUPANCY
A. The government shall occupy the work site and existing building during the performance of work. The contractor shall schedule and perform the work so as not to interfere with the government’s operations and shall cooperate with government to minimize conflicts and facilitate government usage.
1.8 COORDINATION WITH COR
A. Prior to commencing work on a newly issued Task Order, the contractor shall meet with the COR to discuss and develop mutual understandings concerning the scheduling, administering work, security and safety requirements The contractor shall contact the COR at least 3 working days in advance prior to commencing work on any newly issued Task Order.
1.9 SITE MAINTENANCE
A. The contractor shall perform daily cleanup of the work site, dumpster and storage areas. All dumpsters shall have watertight covers.
PART 2 – PRODUCTS (Not applicable)
PART 3 – EXECUTION (Not applicable)
END OF SECTION
SECTION 01020 – SPECIAL CONDITIONS (OSHA & ENVIRONMENTAL PROTECTION
1.1 SUMMARY
A. The contractor is responsible for complying with all Federal, State and local environmental laws and requirements in the execution of this contract.
B. The contractor shall use the Contractor’s Waste Management Guide to assist in the management of all regulated waste (hazardous waste and Connecticut Regulated Waste) generated at the Academy. This guide shall be provided to the COR within 15 calendar days after contract award.
1.2 HAZARDOUS WASTE OPERATIONS
A. Contractors whose employees are exposed to hazardous waste, respond to emergencies involving hazardous materials, or participate in any cleanup or investigation of a government identified uncontrolled waste site, must follow all the requirements of 29 CFR 1910.120 which includes Site Safety and Health Plans, Emergency Contingency Plans and proper employee training. The contractor, if required by 29 CFR 1910.120, shall submit to the government within 15 calendar days after contract award, the Site Safety and Health Plans, Emergency Contingency Plans and proof of adequate worker training.
1.3 HAZARDOUS MATERIALS
A. The contractor shall submit to the COR a copy of the contractor’s OSHA-approved hazardous communication program as required by 29 CFR 1910.120. This copy of the contractor’s program shall be submitted within 15 calendar days after contract award.
B. The contractor shall submit to the COR a copy of the Safety Data Sheets (SDS) for each chemical or hazardous material to be used in the execution of this contract. The SDS shall be submitted within 7 calendar days prior to the product’s use. The government shall provide the contractor a copy of SDS for Academy hazardous materials that the contractor may be exposed to during the course of the project.
C. The government, upon review of the contractor’s SDS, has the right to deny the contractor the use of chemicals or products which, in the government’s judgment, pose an undue health risk, cause the generation or potential generation of hazardous waste, or result in the generation of other regulated wastes including wastewaters and air emissions.
D. The contractor shall have proper secondary containment for storage of all liquid hazardous materials at the work site. This secondary containment shall be capable of containing 10% of the volume of all container or 100% of the volume of the largest container whichever volume is the greater.
1.4 WASTE GENERATION
A. The contractor shall be responsible for the proper management and collection of all wastes generated. No wastes generated by the contractor shall be placed in any waste collection device located at the Academy.
B. The contractor shall provide waste collection containers for all wastes generated that include unregulated trash, Connecticut-Regulated Wastes (e.g. construction debris, unusable excavated materials, recyclable used oil), hazardous wastes, and wastewaters that cannot be discharged. The COR shall designate to the contractor the sites for waste storage.
C. All Connecticut-Regulated Waste generated by the contractor shall be managed in accordance with all Connecticut Department of Environmental Protection (CTDEP) requirements (RSCA Title 22A, Environmental Protection). The contractor is responsible for properly collecting, managing, and paying for the disposal of all Connecticut-Regulated Waste. All Connecticut-Regulated Waste shall be disposed of in permitted landfills, recycling, or treatment facilities. Procedures for the management of Connecticut-Regulated Waste will be reviewed at the preconstruction meeting.
D. All hazardous waste or potentially hazardous waste generated by the contractor shall be managed in accordance with all Resource Conservation and Recovery Act (RCRA 40 CFR 260-266, 268 and 270), and CTDEP requirements (RSCA 22a-449 (c)-100 through 110 and 22a-449(c)-11). The contractor shall be responsible for the proper collection and management of all hazardous waste. The contactor shall provide DOT approved shippable containers compatible for storing and for disposal of the collected contaminated material. The government will pay the cost of disposal of all hazardous waste. The contractor shall turn over custody of all hazardous waste to the government. The government reserves the option of either transferring hazardous waste to the Less Than 90 Day Accumulation Building at the Academy, or providing the services of a licensed hazardous waste transporter to pick-up the waste at the construction site for transport to a permitted Treatment, Storage and Disposal Facility (TSDF). All hazardous waste will be manifested using the Academy’s EPA hazardous waste generator identification number. Only the government shall sign all hazardous waste manifests and manifests for asbestos material. Procedures for the proper management of hazardous waste will be given to the contractor by the government at the preconstruction meeting.
E. The contractor shall not discharge wastewater to any sewer, sanitary or storm drain systems, without a permit or permission from the government. The contractor shall not discharge any wastewater to any building floor, grass area, sidewalk, or street without the permission of the government. Wastewater that is regulated (hazardous or Connecticut-Regulated Waste) and is collected shall be managed according to the requirements of this section.
1.5 SPILLS AND RELEASES
A. The contractor shall be responsible for, and shall pay all costs for the cleanup and the disposal of wastes from any spills or releases of any hazardous materials (including all wastes) to the environment. All non-incidental spills and releases shall be reported immediately to the Academy’s Fire and Emergency at 860-444-8555.
Refer to the Contractor’s Waste Management Guide for spill notification procedures.
B. If the contractor is performing a spill cleanup, the contractor shall perform the cleanup in a manner that complies with applicable Federal, State and local laws and requirements.
1.6 ABATEMENT OF AIR POLLUTION
A. The contractor shall comply with all Federal, State and local air pollution regulations, which include all CTDEP requirements of RSCA 22a-174.
B. The contractor shall not release any chlorofluorocarbons (CFCs) to the environment when executing this contract.
1.7 BACK FLOW PREVENTORS
A. The contractor shall install back flow preventers on any connection made to the public water utilities.
1.8 SARA TITLE III
A. The contractor shall report the usage of any SARA (Superfund Amendment
Reauthorization Act) Title III Extremely Hazardous Substances (EHSs) (list found in Appendix A of 40 CFR 355) to the COTR at or before the preconstruction meeting.
1.9 USE OF PRIMERS AND PAINTS
A. The contractor shall not use any primers or paint that contain lead, chromium, cadmium, and barium without the written consent of the Environmental Officer.
END OF SECTION 01020
SECTION 01040 – PROJECT COORDINATION
1.1 RELATED DOCUMENTS
A. Drawings, terms and conditions of this contract, including the general requirements and other division specification sections, apply to this section.
1.2 SUMMARY
A. This section specifies administrative and supervisory requirements necessary for the project coordination including but not necessarily limited to:
1. Issuance of Task Orders
2. Contractor’s Work Schedule
3. Coordination
4. Contractor’s Staff
1.3 ISSUANCE OF TASK ORDERS
A Under an IDIQ contract, the government will issue Task Orders that specify the actual amount of work to be performed and actual period of performance. The only work authorized under this contract is that which is performed upon receipt of such Task Order and after the Contracting Officer has issued a Notice to Proceed (NTP).
1.4 CONTRACTOR’S WORK SCHEDULE
A. Upon receipt of the Contracting Officer’s NTP, the contractor shall submit a work schedule to the COR within 7 calendar days.
1.5 COORDINATION
A. The contractor shall closely coordinate the scheduling of work with the COR. The
COR is required to provide adequate notification to building occupants of work to be performed and when it is to be performed.
B. Supervisory Personnel: The contractor shall provide a primary and alternate Project
Manager, phone numbers and email addresses.
C. Conservation: The contractor shall coordinate work activities to ensure that operations are carried out with consideration given to conservation of energy, water and materials.
1.6 CONTRACTOR’S STAFF
A. Within 7 calendar days of receipt of the NTP, the contractor shall submit a list of contractor and sub-contractor personnel to include full name and job title.
PART 2 – PRODUCTS (Not applicable)
PART 3 – EXECUTION
3.1 GENERAL
A. Manufacturer’s Instructions: The contractor shall comply with manufacturer’s instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in contract documents.
B. The contractor shall inspect materials and equipment immediately upon delivery and again prior to application. The contractor shall reject damaged and defective items.
3.2 CLEANING AND PROTECTION
A. During the handling and application, the contractor shall clean and protect work in progress and adjoining materials in place. The contractor shall apply protective covering where required to ensure protection from damage or deterioration at substantial completion.
B. The contractor shall clean and maintain completed work as necessary through the remainder of the work being performed.
C. Limiting Exposures: The contractor shall supervise work activities to ensure that no part of the completed or in progress work is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during work performance. Where applicable, such exposures include, but are not limited to, the following:
1. Excessively high or low temperatures
2. Excessively high or low humidity
3. Thermal shock
4. Air contamination or pollution
5. Water or ice
6. Heavy traffic
7. Soiling, staining and corrosion
8. Unusual wear or other misuse
9. Contact between incompatible materials
10. Excessive weathering
11. Unprotected storage
12. Improper shipping and handling
13. Theft and vandalism
3.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
A. The actual amount of work to be performed and the time of such performance will be determined by the Contracting Officer, who will issue a written Task Order to the contractor. The only work authorized under this contract is that which is performed upon receipt of such Task Order. The contractor shall commence work, prosecute the work diligently and shall complete entire work, ready for use and including cleanup, within the period of performance specified for that Task Order. Task Orders may be issued any time during the contract term and any Task Order in effect during this term shall be completed even if the term is exceeded.
3.4 DRAWINGS
A. Drawings Pertaining to Specifications: Any drawings or sketches accompanying
Task Orders shall be considered to be a part of the basic specification.
B. Drawing Verification and Control: Figures marked on drawings or sketches shall be followed in preference to scale measurements. The contractor shall compare all drawings or sketches and verify before laying out the work and shall be responsible for any errors that might have been avoided thereby.
3.5 SPECIFICATIONS AND PRINTS FURNISHED TO CONTRACTOR
A. If technical specifications and/or drawings accompany the Task Order, three copies of the technical specifications and three sets of the drawings will be furnished to the contractor without charge. Additional sets of the drawings and specifications can be obtained at no cost to the contractor by contacting the COR.
3.6 MATERIALS AND EQUIPMENT TO BE SALVAGED
A. All material and equipment that are removed or disconnected and are not indicated or specified for reuse by the government, shall become the property of the contractor and shall be removed from the site by the contractor at his/her expense daily.
3.7 GOVERNMENT FURNISHED FACILITIES, EQUIPMENT, MATERIALS AND
SERVICES
A. Government furnished facilities – None
B. Government furnished equipment – None
C. Government furnished materials – None
D. Government furnished services – None
E. Availability of Utilities: The government will furnish water and electrical power at existing outlets for work to be performed under the contract at no cost to the contractor. Information concerning the location of existing outlets may be obtained from the COR. The contractor shall provide and maintain, at his/her expense, the necessary service lines for existing government outlets to the site of work.
3.8 CONTRACTOR FURNISHED ITEMS
A. Except for items listed in paragraph 3.7 of this section, the contractor shall provide all equipment, materials and services to perform the requirements of this contract. If the quality of an item is not specified in this specification, it shall be of acceptable industrial grade and quality, equal to or better than the manufacturer’s original, and compatible with the existing system.
3.9 ENVIRONMENTAL PROTECTION
A. The contractor shall comply with all federal, state and local environmental protection laws, regulations and standards. The contractor shall coordinate all environmental protection matters with the COR. The Activity Environmental Protection Coordinator or other authorized officials may inspect any of the facilities operated or maintained by the contractor at any time and without prior notice. If a regulatory agency assesses a monetary fine against the government for violations resulting from contractor actions, the contractor shall reimburse the government for the amount of the fine and related costs. The contractor shall clean up any oil or chemical spills resulting from his/her operations at his/her own expense. The contractor shall not create a nuisance or hazard to the health of military or civilian personnel.
3.10 DISPOSAL
A. Debris, rubbish, and non-usable materials resulting from the work under this contract shall be disposed of by the contractor at his/her expense off government property. The contractor shall manage disposal of hazardous waste in accordance with the Resource Conservation and Recovery Act and its associated state and local regulations and coordinate disposal with the COR (see Section 01020 for additional information).
END OF SECTION 01040
SECTION 01300- SUBMITTALS
1.1 DESCRIPTION
A. Wherever possible throughout the contract document the minimum acceptable quality of workmanship and materials has been defined either by manufacturer’s name and catalog number with the salient characteristics or by reference to recognized industry standards.
B. To ensure that the specified products are furnished and applied in accordance with the government’s intent, procedures have been established for advance submittal of product data and for its review and approval or rejection by the COR. Submittals shall be submitted using government furnished Coast Guard submittal forms.
1.2 PRODUCT HANDLING
A. Make all submittals for products, materials, request for substitutions and other items, in strict accordance with the provisions of this section of these specifications.
1.3 PRODUCT DATA
A. Manufacturer’s catalog sheets, brochures, diagrams, schedules, performance charts, illustrations and other standard descriptive data shall be clearly marked to identify pertinent materials and products.
1.4 SAMPLES
A. Samples shall be of sufficient size and quantity to illustrate the functional characteristics of the products or material, and a full range of color choices.
1.5 CERTIFICATE OF COMPLIANCE
A. Certificate of compliance for a material or product to be incorporated in the work shall originate from the manufacturer and shall include:
1. Reference to the Task Order for which the material or product is intended.
2. Reference to the specification paragraph with which the material or product complies.
1.6 COLORS
A. Unless the precise color is specifically described in the Task Order documents, wherever a choice of color is available in a specified product, submit accurate color charts to the COR for his review and selection.
1.7 CONTRACTOR’S RESPONSIBILITIES
A. Review product data and samples prior to submission.
B. Verify field measurements, catalog numbers and similar data.
C. Coordinate each submittal with requirements of work and/or contract/Task Order documents.
D. Contractor’s responsibility for errors and omissions in submittals is not relieved by the COR’s review of submittals.
E. Contractor’s responsibility for deviations in submittals form the requirements of the contract is not relieved by review of the submittals unless the COR gives written acceptance of the specific deviation.
F. The contractor shall not commence work that requires submittals until return of submittals with COR’s approval and initials or signature indicating review.
1.8 SUBMISSION REQUIREMENTS
A. Submit original and one copy of product data.
B. Submit number of samples listed in each of the specification sections, or as specified herein.
C. Accompany submittals with cover letter containing date, project title, project number and Task Order number (if applicable), contractor’s name and address, submittal number, and notification of deviations from contract documents, when applicable.
D. Submittals shall include data and revision dates, project title, project number, Task
Order number (if applicable), contractor’s name, product supplier and/or product manufacturer, specification section number, applicable standards, identification of deviations from contract documents,.
1.9 SUBMITTALS AND SUBMITTAL SCHEDULE
A. Submittals are required as follows: (Refer to the individual sections for specific submittal requirements)
SECTION Para SUBMITTAL DESCRIPTION DUE DATE 01020 1.1.B Contractor’s Waste Management
Guide 15 calendar days after contract award to the COR
01020 1.2.A Site Safety & Health Plans 15 calendar days after contract award to the COR
01020 1.2.A Emergency Contingency Plans 15 calendar days after contract award to the COR
01020 1.2.A Proof of Adequate Employee Training
15 calendar days after contract award to the COR
01020 1.3.A Contractor’s OSHA-Approved Hazardous Communication Program
15 calendar days after contract award to the COR
01020 1.3.B Safety Data Sheets (SDS) 7 calendar days before the product is used to the COR
01040 1.4.A Work Schedule for Individual Task Order
7 calendar days after receipt of the Notice to Proceed to the COR
01040 1.6.A List of Contractor’s & Sub- Contractor’s employees to include full name & title
7 calendar days after receipt of the Notice to Proceed to the COR
02080 1.6 Submittals as specified within the Section
When applicable and as specified within the Section
099113 1.3 Product Data 7 calendar days before the
099123 1.3 Product Data 7 calendar days before the
099300 1.3.A Product Data 7 calendar days before the
099300 1.3.B LEED Submittals 7 calendar days before the
END OF SECTION 01300
SECTION 02080 – REMOVAL & DISPOSAL OF LEAD-CONTAINING PAINT
1.1 SCOPE OF WORK
A. The contractor shall furnish all labor, material, equipment, transportation and supervision for the proper and safe removal, and handling of lead-containing paint materials as identified within the specific Task Order. Work shall be performed in accordance with applicable government regulations, as specified in this section and as indicated on accompanying drawings when applicable.
1.2 REFERENCES
A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
1. American National Standards Institute (ANSI)
ANSI X9.2 (1979; R 1991 Fundamentals Governing the Design &
Operation of Local Exhaust Systems
ANSI Z88.2 (1992) Respiratory Protection
2. Code of Federal Regulations (CFR)
29 CFR 1926.21 Safety Training and Education
29 CFR 1926.55 Gases, Vapors, Fumes, Dusts & Mists
29 CFR 1926.59 Hazard Communication
29 CFR 1926.62 Lead Exposure in Construction
29 CFR 1926.65 Hazardous Waste Operations & Emergency Response
29 CFR 1926.103 Respiratory Protection
40 CFR 260 Hazardous Waste Management Systems: General
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 262 Generators of Hazardous Waste
40 CFR 263 Transporters of Hazardous Waste
40 CFR 264 Owners & Operators of Hazardous Waste Treatment, Storage and Disposal Facilities
40 CFR 265 Interim Status Standard for Owners and Operators of
Hazardous Waste Treatment, Storage and Disposal facilities.
40 CFR 268 Land Disposal Restrictions
40 CFR 745 Lead Requirements for Lead-Based Paint Activities
49 CFR 172 Hazardous Materials, Tables, and Hazardous Materials
Communications Regulations
49 CFR 178 Shipping Container Specification
3. Underwriters Laboratories Inc (UL)
UL 586 (1990) High-Efficiency, Particulate, Air Filter Units
1.3 DEFINIITIONS
A. Action Level: Employee exposure, without regard to use of respirators, to an airborne concentration of lead of 30 micrograms per cubic meter of air , averaged over an 8-hour period in an occupational/industrial environment.
B. Area Sampling: Sampling of lead concentrations within the lead control area and inside the physical boundaries which is representative of the airborne lead concentrations, but is not collected in the breathing zone of personnel.
C. Competent Person (CP): As used in this section, refers to a person employed by the contractor who is trained in the recognition & control of lead hazards in accordance with current federal, state and local regulations. An industrial hygienist or safety professional certified for comprehensive practice by the American Board of Industrial Hygiene or by the Board of Certified Safety Professionals, is the best choice.
D. Contaminated Room: Room for removal of contaminated personal protective equipment (PPE).
E. Decontamination Shower Facility: That facility which encompasses a clean clothing storage room, and a contaminated clothing storage & disposal rooms, with a shower facility in between.
F. Eight-Hour Time-Weighted Average (TWA): Airborne concentration of lead to which an employee is exposed, averaged over an 8-hour workday as indicated in 29
CFR 1926.62.
G. High Efficiency Particulate Air (HEPA) Filter Equipment: HEPA filtered vacuuming equipment with a UL-586 filter system capable of collecting and retaining lead-contaminated paint dust. A high efficiency particulate filter means
99.97 percent efficient against 0.3 micron or larger size particles.
H. Lead: Metallic lead, inorganic lead compounds, and organic lead soaps.
I. Lead-Based Paint (LBP): Protective or decorative coating which contains lead.
J. Lead Control Area: An enclosed area or structure, constructed as a temporary containment equipped with HEPA filtered local exhaust, which prevents the spread of lead dust, paint chips or debris existing as a condition of lead-based paint removal operations. The lead control area is also isolated by physical boundaries to prevent unauthorized entry of personnel.
K. Lead Permissible Exposure Limit (PEL): Fifty micrograms per cubic meter of air as an 8-hour time-weighted average as determined by 29 CFR 1926.62. If an employee is exposed for more than eight hours in a work day, the PEL shall be determined by the following formula:
PEL (micrograms/cubic meter of air) = 400/No. hrs worked per day
L Personal Sampling: Sampling of airborne lead concentrations within the breathing zone of an employee to determine the 8-hour time-weighted average concentration in accordance with 29 CFR 1926.62. Samples shall be representative of the employee’s work tasks. Breathing zone shall be considered an area within a hemisphere, forward of the shoulders, with a radius of 6 to 9 inches and centered at the nose or mouth of an employee.
M. Physical Boundary: Area physically roped or partitioned off around an enclosed lead control area to limit unauthorized entry of personnel. As used in this section, “inside boundary” shall mean the same as “outside lead control area but inside boundary.”
N. Contracting Officer’s Representative (COR): The contracting officer’s agent who is authorized to exercise general contract administration and industrial hygiene inspection of the work under the direction of the contracting officer.
O. Contractor’s Monitor: Contractor’s agent who is authorized to perform industrial hygiene inspection of the work.
1.4 QUALITY ASSURANCE
A. Medical Examinations: Before exposure to lead-contaminated dust, provide workers with a comprehensive medical examination as required by 29 CFR 1926.62 and 29 CFR 1926.103. The examination will not be required if adequate records show that employees have been examined as required by 29 CFR 1926.62 within the last year.
1. Medical Records: Maintain complete and accurate records of employees for a period of at least 30 years or for the duration of employment or 30 years, whichever is longer.
2. Medical Surveillance: Provide medical surveillance to all personnel exposed to lead as in 29 CFR 1926.62.
B. Competent Person (CP) Responsibilities:
1. Certify training as meeting all federal, state and local requirements.
2. Review and approve lead-based paint removal plan for conformance to the applicable referenced standards.
3. Continuously inspect lead-based paint removal work for conformance with the approved plan.
4. Perform air and wipe sampling.
5. Ensure work is performed in strict accordance with specifications at all times.
6. Control work to prevent hazardous exposure to human beings and to the environment at all times.
7. Certify the conditions of the work as called for elsewhere in this specification.
C. Training: Train each employee performing paint removal, disposal and air sampling operations prior to the time of initial job assignment and annually thereafter, in accordance with 29 CFR 1926.21, 29 CFR 1926.62, and state and local regulations.
1. Training Certification: Submit a certificate for each employee, signed and dated by the approved training source, stating that the employee has received the required lead training.
D. Respiratory Protection Program:
1. Furnish each employee required to wear a negative-pressure respirator or other appropriate type with a respirator fit test at the time of initial fitting and at least every 6-months thereafter as required by 29 CFR 1926.62.
2. Establish and implement a respiratory protection program as required by ANSI
Z88.2, 29 CFR 1926.103, 29 CFR 1926.62, and 29 CFR 1926.55.
E. Hazard Communication Program: Establish and implement a Hazard
Communication Program as required by 29 CFR 1926.59.
F. Hazardous Waste Management: The Hazardous Waste Management Plan shall comply with applicable requirements of federal, state, and local hazardous waste regulations and address the following:
1. Identification and classification of hazardous wastes associated with the work.
2. Estimated quantities of wastes to be generated and disposed of.
3. Names and qualifications (experience & training) of personnel who will be working on-site with hazardous wastes.
4. List of waste-handling equipment to be used in performing the work, to include cleaning, volume reduction and transport equipment.
5. Spill prevention, containment and clean-up contingency measures (including a health and safety plan) to be implemented in accordance with 29 CFR 1926.65.
6. Work plan & schedule for waste containment, removal and disposal. Wastes shall be cleaned up and containerized daily.
G. Safety and Health Compliance: In addition to the detailed requirements of this specification, comply with laws, ordinances, rules and regulations of federal, state and local authorities regarding removing, handling, and storing, of lead waste materials. Comply with the applicable requirements of the current issue of 29 CFR
1926.62. Submit matters regarding interpretation of standards to the Contracting Officer for resolution before starting work. Where specification requirements and the referenced documents vary, the most stringent requirement shall apply. All applicable federal, state and local laws, ordinances, criteria, rules and regulations regarding removing, handling and storing, of lead-contaminated materials apply.
H. Pre-Construction Conference: Along with the CP, meet with the Contracting
Officer and/or the COR to discuss in detail the hazardous waste management plan and the lead-based paint removal plan, including work procedures & precautions for the removal plan.
1.5 DESCRIPTION OF WORK
A. Removal of lead-contaminated paint materials from wood surfaces. The OSHA designated exposure assessment process will be used wherever initial paint removal work commences to determine if a hazardous airborne lead hazard exists. This process will determine whether there is a likelihood of exposure to airborne lead, regardless of the lead content. The exposure assessment is based on: the presence of lead in painted surfaces to be disturbed; the handling procedures to be employed (grinding, sanding, cutting, etc); and the experience and degree of training of the workers. The exposure assessment is designed to identify operations which exceed the OSHA designated action limit of 30 micrograms per cubic meter (ug/M). Any operation exceeding the action limit shall require personal air monitoring and respiratory protection.
1.6 SUBMITTALS
A. Submit the following in accordance with section 01300, “Submittals.”
1. SD-02 Manufacturer’s Catalog Data
a. Vacuum filters
b. Respirators
2. SD-06 Instructions
a. Chemicals and equipment
b. Materials
c. Material Safety Data Sheets (SDS) for all chemicals
3. SD-08 Statements
a. Qualifications of CP: Submit name, address and telephone number of the
CP selected to perform responsibilities specified in paragraph entitled “CP Responsibilities.” Provide previous experience of the CP. Submit proper documentation that the CP is trained and licensed in accordance with federal, state and local laws.
b. Testing laboratory and consultant qualifications: Submit the name, address and telephone number of the testing laboratory and consultant selected to perform the sampling, testing, and reporting of airborne concentrations of lead. Use a laboratory accredited under the EPA National Lead Laboratory Accreditation Program (NLLAP) by either the
American Association for Laboratory Accreditation (A2LA) or the American Industrial Hygiene Association (AIHA) and that is successfully participating in the Environmental Lead Proficiency Analytical Testing (ELPAT) program to perform sample analysis.
c. Lead-based paint removal plan, including CP approval (signature, date, and certification number): Submit a detailed job-specific plan of the work procedures to be used in the removal of LBP. The plan shall include a sketch showing the location, size, and details of lead control areas, location, and details of contamination facilities, viewing ports, and mechanical ventilation system. Include in the plan, eating, drinking, smoking & sanitary procedures, interface of trades, sequencing of lead-related work, collected waste water & paint debris disposal plan, air sampling plan, respirators, personal protective equipment, and a detailed description of the method of containment of the operation to ensure that airborne lead concentrations of 30 micrograms per cubic meter of air and baseline lead dust concentrations are not reached or exceeded outside of the lead control area. Include occupational and environmental sampling, training & strategy, sampling methodology, frequency, duration of sampling, and qualifications of sampling personnel in the air sampling portion of the plan.
d. Rental equipment notification
e. Respiratory protection program
f. Hazard communication program
g. Hazardous waste management plan
4. SD-12 Field Test Reports
a. Sampling results: Submit occupational and environmental sampling results to the COR within 3 working days of collection, signed by the testing laboratory employee performing the analysis, the employee that performed the sampling, and the CP.
5. SD-13 Certificates: Vacuum filters
6. SD-18 Records
a. Certification of medical examinations
b. Employee training certification
1.7 REMOVAL
A. Title to Materials: Materials resulting from demolition work, except as specified otherwise, shall become the property of the contractor and shall be disposed of as specified herein.
1.8 EQUIPMENT
A. Respirators: Furnish appropriate respirators approved by the Mine Safety and
Health Administration (MSHA) and the National Institute for Occupational Safety and Health (NIOSH), Department of Health and Human Services, for use in atmospheres containing lead dust. Respirators shall comply with the requirements of 29 CFR 1926.62.
B. Special Protective Clothing: Furnish personnel who will be exposed to lead-contaminated dust with proper disposable protective whole body clothing, head covering, gloves and foot coverings as required by CFR 1926.62. Furnish proper disposable plastic or rubber gloves to protect hands. Reduce the level of protection only after obtaining approval from the CP.
C. Rental Equipment Notification: If rental equipment is to be used during lead-based paint handling and disposal, notify the rental agency in writing concerning the intended use of the equipment. Furnish a copy of the written notification to the Contracting Officer.
D. Vacuum Filters: UL 586 labeled HEPA filters.
E. Equipment for Government Personnel: Furnish the COR with two complete sets of personal protective equipment (PPE) daily, as required herein, for entry into and inspection of the paint removal work within the lead controlled area. Personal protective equipment shall include disposable whole-body covering, including appropriate foot, head and hand protection. PPE shall remain the property of the contractor. Respiratory protection for the COR will be provided by the government.
PART 2 - PRODUCTS
2.1 CHEMICALS:
A. Submit applicable Material Safety Data Sheets (SDS) for all chemicals used in paint removal work. Use the least toxic product approved by the Contracting Officer.
2.2 MATERIALS:
A. The soluble metal content and the total metal content shall not exceed values which would cause a material to be classified as a hazardous waste.
PART 3 - EXECUTION
3.1 PERSONNEL PROTECTION AND DECONTAMINATION PROCEDURES
A. General: The contractor shall take all safety measures and precautions necessary to protect his employees and building occupants in accordance with OSHA Standard 29 CFR 1926, EPA standard 40 CFR, in the sections referenced in this specification and applicable state regulations. The contractor shall be solely responsible for enforcing personnel protection requirements.
B. Notification: Notify the COR 20 days prior to start of any paint removal work.
C. Protection of Existing Work to Remain: Perform paint removal work without damage or contamination of adjacent areas. Where existing work is damaged or contaminated, restore work to its original condition or better.
D. Boundary Requirements: Provide physical boundaries around the lead control area by roping off the area designated in the work plan.
E. Furnishings: The government will remove exposed equipment from the building before lead-based paint removal work begins.
F. Decontamination Shower Facility: Provide clean and contaminated change rooms and shower facilities in accordance with this specification and 29 CFR 1926.62.
G. Personnel Protection: Personnel shall wear and use protective clothing and equipment as specified herein. Eating, smoking, drinking or application of cosmetics is not permitted in the lead control area. No one will be permitted in the lead control area unless they have been appropriately trained and provided with protective equipment.
H. Warning Signs: Provide warning signs at approaches to lead control areas. Locate signs at such a distance that personnel may read the sign and take the necessary precautions before entering the area. Signs shall comply with the requirements of
29 CFR 1926.62.
3.2 WORK PROCEDURES
A. General: Perform removal of lead-based paint in accordance with approved lead-based paint removal plan. Use procedures and equipment required to limit occupational and environmental exposure to lead when lead-based paint is removed in accordance with 29 CFR 1926.62, except as specified herein. Lead-contaminated material(s), including paint chips and associated waste removed under this contract, shall be placed in approved containers as specified and delivered to the designated collection/storage area for disposal by the government.
B. Personnel Exiting Procedures: Whenever personnel exit the lead-controlled area, they shall perform the following procedures and shall not leave the work place wearing any clothing or equipment worn during the work day:
1. Vacuum themselves off.
2. Remove protective clothing in the contaminated change room, and place them in an approved impermeable disposal bag.
3. Change to clean clothes prior to leaving the physical boundary designated around the lead control area.
C. Air and Wipe Sampling: Air sample for lead in accordance with CFR 1926.62 and as specified herein. Air and wipe sampling shall be directed or performed by the
CP.
1. The CP shall be on the job site directing the air and wipe sampling and inspecting the lead-based paint removal work to ensure that the requirements of the contract have been satisfied during the entire lead-based paint removal operation.
2. Collect personal air samples on employees who are anticipated to have the greatest risk of exposure as determined by the CP. In addition, collect air samples on at least 25% of the work crew or a minimum of two employees, whichever is greater, during each work shift.
3. Submit results of air samples, signed by the CP, within 72 hours after the air samples are taken. Notify the Contracting Officer immediately of exposure to lead at or in excess of the action level of 30 micrograms per cubic meter of air outside of the lead control area.
4. Before any work begins, collect and analyze baseline wipe samples in accordance with methods defined in federal, state and local standards inside and outside of the physical boundary to assess the degree of dust contamination in the facility prior to lead-based paint removal.
D. Air Sampling during Paint Removal Work: Conduct area air sampling daily, on each shift in which lead-based paint removal operations are performed, in areas immediately adjacent to the lead control area. Sufficient area monitoring shall be conducted to ensure unprotected personnel are not exposed at or above 30 micrograms per cubic meter of air. If 30 micrograms per cubic meter of air is reached or exceeded, stop work, correct the condition(s) causing the increased levels. Notify the Contracting Officer immediately. Determine if condition(s) require any further change in work methods. Removal work shall resume only after approval is given by the CP and the Contracting Officer. For outdoor operations, at least one sample on each shift shall be taken on the downwind side of the lead control area.
3.3 LEAD-BASED PAINT REMOVAL
A. General: Manual or power sanding of exterior surfaces is not permitted. Provide methodology for removing lead-based paint in the work plan. Remove paint within the areas designated on the drawings in order to completely expose the substrate.
Take whatever precautions necessary to minimize damage to the underlying substrate. Select paint removal processes to minimize contamination of work areas with lead-contaminated dust or other lead-contaminated debris/waste. Describe this paint removal process in the lead-based paint removal plan. Perform manual wet sanding and scraping to the maximum extent feasible.
B. Outdoor Lead Paint Removal: Provide containment system to collect paint chips from lead-based paint removal operations for various exterior building components indicated and to prevent air-borne contamination of surrounding buildings, plantings and personnel. Chemically remove lead-based paint from components before prepping materials for application of new paint finish is performed. Procedures for outdoor lead-paint removal and containment methods to be used shall be provided in the lead-paint removal plan.
C. Air and Wipe Sampling after Paint Removal: After the visual inspection, collect air samples inside and outside the lead control area to determine the airborne levels of lead inside and outside the work area. Collect wipe samples according to the HUD protocol to determine the lead content of settled dust and dirt in micrograms per square foot of surface area.
3.4 CLEAN-UP AND DISPOSAL
A. Clean-Up: Maintain surfaces of the lead control area free of accumulations of paint chips and dust. Restrict spread of dust and debris; keep waste from being distributed over the work area. Do not dry sweep or use compressed air to clean up the area. At the end of each shift and when the paint removal operation has been completed, clean the area of visible lead paint contamination by vacuuming with a HEPA filtered vacuum cleaner, wet-mopping the area and wet-wiping the area as indicated by the CP. Re-clean areas showing dust or residual paint chips or debris.
After visible dust, chips and debris is removed, wet-wipe and HEPA-vacuum all surfaces in the work area. If adjacent areas and/or property become contaminated at any time during the work, clean, visually inspect, and then wipe-sample all contaminated areas. The CP shall then certify in writing that the area has been cleaned of lead contamination before restarting work.
B. Certification: The CP shall certify in writing that the final air samples collected inside and outside the control area are less than 30 micrograms per cubic meter of air and that the surface wipe sample results collected inside and outside the work area are less than 100 micrograms per square foot on uncarpeted floors, less than 500 micrograms per square foot on interior window sills and less than 800 micrograms per square foot on window troughs; the respiratory protection used for the employees was adequate; the work procedures were performed in accordance with 29 CFR 1926.62 and 40 CFR 745; and that there were no visible accumulations of lead-based paint and dust left in the work site. Do not remove the lead control area or roped-off boundary and warning signs prior to the Contracting Officer’s acknowledgment of receipt of the CP certification.
C. Disposal: Collect lead-contaminated waste, scrap, debris, bags, containers, equipment, and lead-contaminated clothing which may produce airborne concentrations of lead particles. Label the containers in accordance with 29 CFR
1926.62 and 40 CFR 261. Contractor shall furnish all appropriate, approved containers for proper collection, transport and disposal of lead-contaminated waste materials. Deliver all lead-contaminated waste material to a designated collection/storage site at the Academy for disposal by the government.
1. Storage: Store waste materials in U.S. Department of Transportation (49 CFR
178) approved 55-gallon drums. Properly label each drum to identify the type of waste (49 CFR 172) and the date the drum was filled. The Contracting Officer or an authorized Government representative will assign an area for interim storage of waste-containing drums.
2. Handling, Storage, Transport & Disposal: Handle, store, and transport lead or lead-contaminated waste in accordance with 40 CFR 260, 40 CFR 261, 40 CFR 262, 40 CFR 263, 40 CFR 264, and 40 CFR 265.
END OF SECTION 02080
SECTION 02090 - LEAD BASED PAINT STABILIZATION
PART 1 - GENERAL
1.1 Stabilization of Lead Based Paint (LBP)
A. As specified in the individual Task Order, perform stabilization of Lead Based Paint in accordance with an approved lead-based paint removal plan. Removal plan must be approved by the USCG Academy Safety Occupational Health and Specialist (SOHS).
The plan must outline the procedures and equipment proposed to limit occupational and environmental exposure to lead when lead-based paint is removed in accordance with all work is in accordance with 29 CFR 1926.62 and 40 CFR 745 except as specified herein. Lead-contaminated material(s), including paint chips and associated waste removed under this contract, shall be placed in approved containers as specified and delivered to the designated collection/storage area for disposal by the government.
The plan must also provide the methodology for removing lead-based paint. Manual or power sanding of LBP is not permitted. Remove loose, peeling and otherwise unstable paint within the areas designated in order to completely expose the substrate.
Take whatever precautions necessary to minimize damage…