P5149824Spc.pdf
PDF 948 KB Posted
- Solicitation number
- HSCGG1-14-B-PS6001
About this file
Specification PSN5149824
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| NY_STate_Consistency_Determination_(Moriches).pdf | ||
| Dept_of_Army_COE_Permit_Moriches.pdf | ||
| Amendment_0003_Permits.pdf | ||
| Amendment0002__04282014.pdf | ||
| Amendment_0001_040714.pdf | ||
| General_Decision_Number_NY14__Mod2_dtd_040414.doc | DOC document | |
| General_Decision_Number_NY14.doc | DOC document | |
| P5149824Dwgs.pdf | ||
| SF_1442.pdf | ||
| IFB.pdf | ||
| SF-24_Bid_Bond_form.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
SHORE INFRASTRUCTURE LOGISTICS CENTER
SPECIFICATIONS FOR
H. SANDY: REPAIR SHORELINE
PSN 5149824
AT
USCG SFO MORICHES
EAST MORICHES, NEW YORK
(SUFFOLK COUNTY)
DESIGN PROJECT MANAGER DESIGN TEAM SUPERVISOR
A. A. JACOBS, BY DIRECTION
COMMANDING OFFICER
UNITED STATES COAST GUARD
CIVIL ENGINEERING UNIT PROVIDENCE
475 KILVERT ST SUITE 100
WARWICK, RHODE ISLAND 02886
H. SANDY: REPAIR SHORELINE SFO MORICHES 5149824
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 32 00 CONSTRUCTION SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 77 00 CLOSEOUT SUBMITTALS
DIVISION 31 – EARTHWORK
31 23 00.00 20 EXCAVATION AND FILL
TABLE OF CONTENTS Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/10
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes constructing a vegetated berm by excavating fill from an on-site location, re-grading an area adjacent to the main access drive, creating a low area to improve drainage in the vicinity of the main gate, and incidental related work.
1.1.2 Location
The work is located at Coast Guard Moriches SFO, Moriches, NY, approximately as indicated.
1.2 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1. L3
OCATION OF UNDERGROUND FACILITIES
Obtain permission prior to start of excavation by contacting the Contracting Officer at least 15 calendar days in advance. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be installed. Verify elevations before excavating or grading.
1.3.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
SECTION 01 11 00 Page 1
SECTION 01 11 00 Page 2
1.4 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours.
1.5 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.
1.6 INSPECTION
The Contractor shall keep the Contracting Officer or duly appointed representative fully informed of contract operations and plans so that a representative may arrange to be present at various times that work is being performed.
1.6.1 Contractor’s Daily Log
The Contractor shall be complete the USCG Daily Log form at the end of each working day and deliver it to the Government Inspector. The Government Inspector will attest to its accuracy by initialing the form and forwarding that form to CEU Providence. The form will be provided to the Contractor by the Contracting Officer’s Representative.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
--End of Section--
SECTION 01 14 00
WORK RESTRICTIONS
02/10
1.1 RESTRICTIONS
A. Work shall not restrict any Coast Guard operation except by prior schedule and approval by the contracting officer.
B. Traffic through existing access drive shall be allowed at all times.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.2.2 Working Hours
Regular working hours shall consist of an 8 1/2 hour period established by the Contracting Officer Monday through Friday, excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.2.4 Occupied and Existing Building[s]
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
1.2.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
SECTION 01 14 00 Page 1
SECTION 01 14 00 Page 2
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to telephone service and electric service shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
1.3 SECURITY REQUIREMENTS
1.3.1 Areas Not Covered by Contract
The Contractor will not be permitted to enter buildings or areas not covered by the work included in this contract, except by prior approval of the Commanding Officer of the facility.
1.3.2 Parking
Prohibited on any piers and waterfront areas. Do not park on or block the marked fire lanes at any time. Vehicles may stop on the piers or waterfront areas for 15 minutes for loading and unloading.
SECTION 01 32 00
CONSTRUCTION SCHEDULE/SCHEDULE OF VALUES
1. S1
UBMITTALS
Submit the following in accordance with Section 01 33 00, "Submittal Procedures."
SD-01 Preconstruction Submittals
Construction Schedule
Schedule of Values
1.2 CONSTRUCTION SCHEDULE
At the Pre-Construction Conference, submit a Construction Schedule and Schedule of Values in accordance with FAR Clause 52.236.15. The Schedule of Values shall be based on the actual breakdown of the bid price. The cost of insurance shall not be listed as a separate item but included as part of each item of work. The actual cost of bonds may be paid as the first progress payment when a receipt from the bonding company is presented to the Contracting Officer. For contracts under $25,000, a Schedule of Values is not required. In addition, keep the Government Inspector informed daily of the expected delivery dates for major pieces of equipment and materials.
The Construction Schedule shall clearly indicate the start and completion dates of major work components. The Schedule of Values shall clearly indicate unit value of all major work components.
The Construction Schedule shall incorporate at a minimum the following activities:
a. Mobilization
b. Demobilization
c. Pre-Construction Submittals
d. Work Activities
e. In-Progress Submittals
f. Final Government Inspection
g. Close-Out Submittals; i.e. Testing Balancing Reports, Warranties, Operation and Maintenance Manuals, Posted Instructions
h. As-Built Drawings
i. Factors which Constitute Potential Interruptions to Station Operations
Section 01 32 00 Page 1
Section 01 32 00 Page 2
Pre-Construction Submittals are those activities which encompass the obtaining, submission, review and approval of submittals necessary prior to the start of the related site work. Contractor shall annotate all such activities into the progress schedule with their forecasted time periods.
These activity periods shall not be exclusive of the contract performance period. No site work shall commence until the respective submittals have been approved.
The value of all major work components within the project shall be identified on the Schedule of Values on a unit quantity and unit cost basis, e.g. number of squares and cost per square of roofing, number of lineal feet and cost per lineal foot of conduit, number of panels and cost per panel etc. Lump sum items shall only be paid for when 100% complete.
Do not include mobilization and demobilization line items on the Schedule of Values.
The Construction Schedule and Schedule of Values as approved by the Government is not a substitute for quantities conveyed by the specification and drawings and those required for a complete job.
Omissions and errors on the Construction Schedule and Schedule of Values are the responsibility of the Contractor.
Payments will not be made until the schedule of prices has been submitted to and approved by the Contracting Officer.
1.3 UPDATED SCHEDULES
Update the construction schedule and equipment delivery schedule at monthly intervals or when schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.
3.1 PROGRESS UPDATES
3.1.1 General
A revised Construction Schedule/Schedule of Values shall be issued by the Contractor on a monthly basis. In addition, any revisions to the Construction Schedule/Schedule of Values such as modifications or delays shall be reflected by Contractor submission of an updated Construction Schedule/Schedule of Values.
3.1.2 Modifications
When a modification is issued by the Government, record the modification as the last activity of the Construction Schedule and Schedule of Values and include the value of the modification. Adjust the Schedule of Values to reflect the inclusion of the modification. Revise the Construction Schedule portion of the form to annotate the progress change. Enter all odifications in this manner in sequential order. m
SECTION 01 33 00
SUBMITTAL PROCEDURES
1.1 DEFINITIONS
1.1.1 Submittal
Shop drawings, product data, samples, and administrative submittals presented for review and approval. Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."
1.1.2 Types of Submittals
All submittals are classified as indicated in paragraph "Submittal Descriptions (SD)". Submittals also are grouped as follows:
a. Shop drawings: As used in this section, drawings, schedules, diagrams, and other data prepared specifically for this contract, by contractor or through contractor by way of subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate portion of work.
b. Product data: Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data, and other data to illustrate portion of work, but not prepared exclusively for this contract.
c. Samples: Physical examples of products, materials, equipment, assemblies, or workmanship that are physically identical to portion of work, illustrating portion of work or establishing standards for evaluating appearance of finished work or both.
d. Administrative submittals: Data presented for reviews and approval to ensure that administrative requirements of project are adequately met but not to ensure directly that work is in accordance with design concept and in compliance with contract documents.
1.1.3 Submittal Descriptions (SD)
Construction Progress Schedule Submittal register Schedule of values Health and safety plan Work plan Quality control plan Environmental protection plan
SECTION 01 33 00 Page 1
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the contractor for integrating the product or system into the project.
Drawings prepared by or for the contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports
SECTION 01 33 00 Page 2
Daily checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data sheets concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative to confirm compliance with manufacturer's standards or instructions.
Factory test reports.
SD-10 Operation and Maintenance Data
Data intended to be incorporated in operations and maintenance manuals.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
As-built drawings
Special warranties
Posted operating instructions
Training plan
1.1.4 Approving Authority
Person authorized to approve submittal.
1.1.5 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce construction and materials, SECTION 01 33 00 Page 3 products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Submit the following in accordance with the requirements of this section.
Submittal register
1.3 USE OF SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data in columns (a), (b), (c), and (d) as delivered by government.
1.3.1 Submittal Register
Submit submittal register. Verify that all submittals required for project are listed and add missing submittals. Complete the following on the register:
Column (e) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
1.4 PROCEDURES FOR SUBMITTALS
1.4.1 Reviewing, Certifying, Approving Authority
Government organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals is the Project Manager unless otherwise specified for specific submittal.
1.4.2 Constraints
a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.
b. Submittals shall be complete for each definable feature of work;
components of definable feature interrelated as a system shall be submitted at same time.
c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.
d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.
1.4.3 Scheduling
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.
SECTION 01 33 00 Page 4
b. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 10 working days. Period of review for each resubmittal is the same as for initial submittal.
1.4.4 Variations
Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to government.
1.4.4.1 Proposing Variations
When proposing variation, deliver written request to the contracting officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to government. If lower cost is a benefit, also include an estimate of the cost saving. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
1.4.4.2 Warranting That Variation Are Compatible
When delivering a variation for approval, contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work, and deliver the same service life and performance.
1.4.4.3 Review Schedule Is Modified
In addition to normal submittal review period, a period of 5 working days will be allowed for consideration by the Government of submittals with variations.
1.4.5 Contractor's Responsibilities
a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.
b. Transmit submittals to Contracting Officer in accordance with schedule on approved Submittal Register, and to prevent delays in the work, delays to government, or delays to separate contractors.
c. Advise contracting officer of variation, as required by paragraph entitled "Variations."
d. Correct and resubmit submittal as directed by approving authority.
When resubmitting disapproved transmittals or transmittals noted for resubmittal, the contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.
e. Furnish additional copies of submittal when requested by contracting officer, to a limit of 4 copies per submittal.
SECTION 01 33 00 Page 5
f. Complete work which must be accomplished as basis of a submittal in time to allow submittal to occur as scheduled.
g. Ensure no work has begun until submittals for that work have been returned as "approved," except to the extent that a portion of work must be accomplished as basis of submittal.
1.4.6 Government Responsibilities
a. Note date on which submittal was received from contractor on each Contract Item Approval Request Form.
b. Review each submittal; and check and coordinate each submittal with requirements of work and contract documents.
c. Review submittals for conformance with project design concepts and compliance with contract documents.
d. Ensure that material is clearly legible.
e. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
f. Identify returned submittals with one of the actions defined in paragraph entitled "Actions Possible" and with markings appropriate for action indicated.
1.4.7 Actions Possible
Submittals will be returned with one of the following notations:
a. Submittals marked "approved" "approved as submitted" authorize contractor to proceed with work covered.
b. Submittals marked "approved" "see below" authorize contractor to proceed with work as noted provided contractor takes no exception to the notations.
c. Submittals marked "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with appropriate changes. No work shall proceed for this item until resubmittal is approved.
1.5 FORMAT OF SUBMITTALS
1.5.1 Transmittal Form
Transmit each submittal electronically, unless otherwise noted in the submittal register and/or where electronic submission is not feasible (i.e.
samples), to office of approving authority. The maximum file size that may be emailed is 10 MB; anything larger must be submitted hard copy or on a CD.
Transmit submittals with transmittal form prescribed by contracting officer and standard for project. The transmittal form shall identify contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled "Identifying
SECTION 01 33 00 Page 6
Submittals." Process transmittal forms to record actions regarding sample panels and sample installations. Note: Submittals requiring hard copy submission shall be provided with carbon copy transmittal form provided by the government.
1.5.2 Identifying Submittals
Identify submittals, except sample panel and sample installation, with the following information on each separate component of each submittal and transmittal form. The maximum file size for electronic submittals shall be no larger than 10 MB. Identify each copy of each submittal identically, with the following:
a. Project title and location.
b. Construction contract number.
c. Section number of the specification section by which submittal is required.
d. Submittal description (SD) number of each component of submittal.
e. When a resubmission, alphabetic suffix on submittal description, for example, SD-10A, to indicate resubmission.
f. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier contractor associated with submittal.
g. Product identification and location in project.
1.5.3 Format for Product Data
a. Present product data submittals for each section. Include table of contents, listing page and catalog item numbers for product data.
b. Indicate, by prominent notation, each product which is being submitted; indicate specification section number and paragraph number to which it pertains.
c. Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist. Identify this material as developed specifically for project.
1.5.4 Format for Shop Drawings
a. Shop drawings shall not be less than 8 1/2 by 11 inches nor more than 30 by 42 inches.
b. Present 8 1/2 by 11 inches sized shop drawings as part of the submittals required by section. Present larger drawings in sets.
c. Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled "Identifying Submittals."
SECTION 01 33 00 Page 7
d. Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Shop drawing dimensions shall be the same unit of measure as indicated on the contract drawings. Identify materials and products for work shown.
1.5.5 Format of Samples
a. Furnish samples in sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately same size as specified:
(1) Sample of Equipment or Device: Full size.
(2) Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by 11 inches.
(3) Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.
(4) Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.
(5) Sample of Non-Solid Materials: Pint. Examples of non-solid materials are sand and paint.
(6) Color Selection Samples: 2 by 4 inches.
(7) Sample Panel: 4 by 4 feet.
(8) Sample Installation: 100 square feet.
b. Samples Showing Range of Variation: Where variations are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range.
c. Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples shall be in undamaged condition at time of use.
d. Recording of Sample Installation: Note and preserve the notation of area constituting sample installation but remove notation at final clean up of project.
e. When color, texture or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
1.5.6 Format of Administrative Submittals
a. When submittal includes a document which is to be used in project or become part of project record, other than as a submittal, do not apply contractor's approval stamp to document, but to a separate sheet accompanying document.
SECTION 01 33 00 Page 8
SECTION 01 33 00 Page 9
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Copies of Product Data
a. When hard copy submission is required, submit four copies of submittals of product data.
1.6.2 Number of Copies of Shop Drawings
Submit shop drawings in compliance with quantity requirements specified for product data.
1.6.3 Number of Samples
a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to contractor.
b. Submit one sample panel. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of non-solid materials.
1.6.4 Number of Copies of Administrative Submittals
a. Unless otherwise specified, submit administrative submittals compliance with quantity requirements specified for product data.
SUBMITTAL REGISTER
Specification Section Number or Item Number
SD No., and Type of Submittal Material or Product
Specification Paragraph Number.
Requires Hard Copy Submission
Planned Submittal Date
Date Fwd to Appr Auth /Date Recd From Contr
Date Fwd to Other Reviewer
Date Recd From Other Reviewer
Action Code
Date of Action
Mailed to Contr / Recd From Appr Auth
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k)
Section
01 32 00
SD-01,
Preconstruction Submittals
1.1
1 Construction Schedule
1.1
2 Schedule of Values 1.1
Section
01 35 29
SD-07, Certificates 1.2
3 Accident Prevention Plan
1.2
4 Activity Hazard Analysis
1.2
Section
01 35 29
SD-11, Closeout Submittals
1.2
5 Reports 1.2
6 Certificate of Compliance
1.2
Section
01 50 00
SD-01
Preconstruction Submittals
1.2
7 Construction Site Plan
1.2
01 57 19
SD-01
Preconstruction Submittals
1.3
8 Environmental Protection Plan
1.3.
9 Storage Inventory Form
1.3
10 Dirt and Dust Control Plan
1.3
Section
01 57 19
SD-06, Test Reports 1.3
11 Laboratory analysis 1.3
Section
01 57 19
SD-11, Closeout Submittals
1.3
12 Preconstruction Survey
1.3
13 Solid Waste Disposal Permit
1.3.
14 Waste determination documentation
1.3
15 Disposal documentation for hazardous and regulated waste
1.3
16 Solid waste disposal report
1.3
17 Contractor Hazardous Material Inventory Log
1.3.
01 77 00
SD-11, Closeout Submittals
1.1
18 As-Built Drawings 1.1
19 Record of Materials 1.1
Section
31 23 00.00
SD-01
Preconstruction Submittals
1.1
20 Excavation/ hauling/ grading/ placement Plan
1.1
21 Survey Plan:
Shoreline Area
1.1
22 Survey Plan:
Entrance Area
1.1
Section
21 23 00.00
SD-07, Certificates
1.1
23 Cape American Beachgrass
1.1
Section
21 23 00.00
SD-11, Closeout Submittals
1.1
24 Survey plan: As-built borrow area;
shoreline area;
entrance area
1.1
SECTION 01 35 29
SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
11/07
1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI A10.32 (2004) Personal Fall Protection - Safety
Requirements for Construction and Demolition Operations
ANSI A10.34 (2001; R 2005) Protection of the Public on or
Adjacent to Construction Sites
ANSI Z359.1 (1992; Errata 1994; R 1999) Safety
Requirements for Personal Fall Arrest Systems, Subsystems and Components
CODE OF FEDERAL REGULATIONS (CFR)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1919 Gear Certification
29 CFR 1926 Safety and Health Regulations for
Construction
29 CFR 1926.500 Fall Protection
CORPS OF ENGINEERS (COE)
EM 385-1-1 (2003) Safety -- Safety and Health
Requirements
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2006; Errata 2006) Standard for Portable
Fire Extinguishers
NFPA 241 (2004) Safeguarding Construction, Alteration, and Demolition Operations
NFPA 70 (2005; TIA 2005) National Electrical Code
NFPA 70E (2004; AMD 2004) Electrical Safety in the
Workplace
SECTION 01 35 29 Page 1
1.2 SUBMITTALS
Accident Prevention Plan (APP)
Activity Hazard Analysis (AHA)
Submit one copy of each permit attached to each Daily Production Report.
Reports
Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."
Certificate of Compliance
1.3 QUALITY ASSURANCE
1.3.1 Meetings
The Safety Officer shall attend the pre-construction conference.
1.3.1.1 Weekly Safety Meetings
Hold weekly at the project site. Attach minutes showing contract title, signatures of attendees and a list of topics discussed to the QC Contractor Quality Control daily report.
1.3.1.2 Work Phase Meetings
The appropriate AHA shall be reviewed and attendance documented by the Contractor at the preparatory, initial, and follow-up phases of quality control inspection.
1.3.1.3 New Employee Indoctrination
New employees will be informed of specific site hazards before they begin work. Documentation of this orientation shall be kept on file at the project site.
1.3.2 Certifications
1.3.2.1 Accident Prevention Plan (APP)
Submit the APP at least 15 calendar days prior to start of work at the job site, following Appendix A of EM-385-1-1. Make the APP site specific.
Submit the AHA for review at least 15 calendar days prior to the start of each phase. Format subsequent AHA as amendments to the APP. In accordance
SECTION 01 35 29 Page 2 with contract quality control requirements each AHA will be reviewed during an on-site preparatory inspection.
1.4 ACCIDENT PREVENTION PLAN (APP)
Prepare the APP in accordance with EM-385-1-1 Table 1-1. Include the associated AHA and other specific plans, programs and procedures detailed in Paragraphs 01.A.09 and 01.A.10 of EM-385-1-1, some of which are listed below.
1.4.1 Contents of the Accident Prevention Plan
a. Name and safety related qualifications of safety officer (including training and any certifications).
b. Qualifications of competent and of qualified persons.
c. Identity of the individual who will complete exposure data (hours worked); accident investigations, reports and logs; and immediate notification of accidents to include subcontractors.
d. Emergency response plan. Conform to EM-385-1-1, paragraph 01.E and include a map denoting the route to the nearest emergency care facility with emergency phone numbers. Contractor may be required to demonstrate emergency response.
e. Fall Protection and Prevention (FP&P) Plan. The plan shall be site specific and address all fall hazards in the work place. It shall address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A qualified person shall prepare the plan. The plan shall include fall protection and prevention systems, equipment and methods employed, responsibilities, rescue and escape equipment and operations, training requirements, and monitoring methods. FP&P Plan shall be revised [once every six months] for lengthy projects, to reflect any new changes during the course of construction, due to changes of personnel, equipment, systems or work habits.
f. Silica Exposure Reduction. The plan shall include specific procedures to prevent employee silica inhalation exposures.
g. Excavation Plan. The safety and health aspects prepared in accordance with Section 31 23 00.00 20, Excavation and Fill.
h. Training Records and Requirements. List of mandatory training and certifications which are applicable to this project (e.g. explosive actuated tools, confined space entry, fall protection, crane operation, vehicle operator, forklift operators, personal protective equipment); list of requirements for periodic retraining/certification; outline requirements for supervisory and employee safety meetings.
i. Severe Weather Plan. Procedures of ceasing on-site operations during lightning or upon reaching maximum allowed wind velocities.
SECTION 01 35 29 Page 3
j. Emergency Lighting and Power Systems Plan (e.g. periodic testing of batteries for emergency lighting.)
1.5 ACTIVITY HAZARD ANALYSIS (AHA)
Prepare for each phase of the work. As a minimum, define activity being performed, sequence of work, specific hazards anticipated, control measures to eliminate or reduce each hazard to acceptable levels, training requirements for all involved, and the competent person in charge of that phase of work. For work with fall hazards, including fall hazards associated with scaffold erection and removal, identify the appropriate fall arrest systems. For work with materials handling equipment, address safeguarding measures related to materials handling equipment. For work requiring excavations, include excavation safeguarding requirements. The appropriate AHA shall be reviewed and attendance documented by the Contractor at the preparatory, initial, and follow-up phases of quality control inspection.
2 PRODUCTS
Not Used.
3 EXECUTION
3.1 CONSTRUCTION
Comply with EM-385-1-1, NFPA 241, the accident prevention plan, the activity hazard analysis and other related submittals and activity fire and safety regulations.
3.1.1 Hazardous Material Exclusions
Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited.
Exceptions to the use of any of the above excluded materials may be considered by Contracting Officer upon written request by Contractor.
3.1.2 Unforeseen Hazardous Material
The design should have identified materials such as PCB, lead paint, and friable and nonfriable asbestos. If [dditional material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."
SECTION 01 35 29 Page 4
3.2 PERSONNEL PROTECTION
3.2.1 Hazardous Noise
Provide hazardous noise signs, and hearing protection, wherever equipment and work procedures produce sound-pressure levels greater than 85 dBA steady state or 140 dBA impulse, regardless of the duration of the exposure.
3.2.2 Fall Protection
Enforce use of the fall protection device designated for each specific work activity in the FP&P plan and/or AHA all times when an employee is on a surface 6 feet or more above lower levels. Personal fall arrest systems are required when working from an articulating or extendible boom, scissor lifts, swing stages, or suspended platform. Fall protection must comply with ANSI A10.32.
3.3 EXCAVATIONS
The competent person for excavation performed as a result of contract work shall be on-site when work is being performed in excavation, and shall inspect excavations prior to entry by workers. The competent person must evaluate for all hazards, including atmospheric, that may be associated with the work, and shall have the resources necessary to correct hazards promptly. Prior to digging the appropriate digging permit must be obtained.
All underground utilities in the work area must be positively identified by a utility locating service and coordinated with Station Utility Departments.
The Contractor must physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. If construction is parallel to an existing utility the utility shall be exposed by hand digging every 100 feet if parallel within 5 feet of the excavation. Trench and shoring systems must be identified in the accepted safety plan and activity hazard analysis. Extreme care must be used when excavating near direct burial electric underground cables.
Trenching machines with digging chain drives shall be operated only when the spotters/laborers are in plain view of the operator. Operator and spotters/laborers shall be provided training on the hazards of the digging chain drives with emphasis on the distance that needs to be maintained when the digging chain is operating. Documentation of the training shall be kept on file in the project site office or trailer.
3.4 ELECTRICAL
3.4.1 Conduct of Electrical Work
Underground electrical spaces must be certified safe for entry before entering to conduct work. Cable intended to be cut must be positively identified and de-energized prior to performing each cut. Positive cable identification must be made prior to submitting any outage request for electrical systems. Arrangements are to be coordinated with the Contracting Officer and Station Utilities for identification. The Contracting Officer will not accept an outage request until the Contractor satisfactorily documents that the circuits have been clearly identified. Perform all high voltage cutting remotely. When racking in or live switching of circuit breakers, no additional person other than the switch operator will be allowed in the space during the actual operation. Plan so that work near
SECTION 01 35 29 Page 5
SECTION 01 35 29 Page 6 energized parts is minimized to the fullest extent possible. Use of electrical outages clear of any energized electrical sources is the preferred method. When working in energized substations, only qualified electrical workers shall be permitted to enter. When work requires Contractor to work near energized circuits as defined by the NFPA 70, high voltage personnel must use personal protective equipment that includes, as a minimum, electrical hard hat, safety shoes, insulating gloves with leather protective sleeves, fire retarding shirts, coveralls, face shields, and safety glasses. Insulating blankets, hearing protection, and switching suits may be required, depending on the specific job and as delineated in the Contractor AHA.
3.4.2 Portable Extension Cords
Portable extension cords shall be sized in accordance with manufacturer ratings for the tool to be powered.
3.5 CRYSTALLINE SILICA
Grinding, abrasive blasting, and foundry operations of construction materials containing crystalline silica, shall comply with OSHA regulations, such as 29 CFR 1910.94, and EM-385-1-1, (Appendix C). The Contractor shall develop and implement effective exposure control and elimination procedures to include dust control systems, engineering controls, and establishment of work area boundaries, as well as medical surveillance, training, air monitoring, and personal protective equipment.
3.6 HOUSEKEEPING
3.6.1 Clean-up
All debris in work areas shall be cleaned up daily or more frequently as necessary. Construction debris may be temporarily located in an approved location, however garbage accumulation must be removed each day.
3.6.2 Dust Control
In addition to the dust control measures required elsewhere in the contract documents dry cutting of brick or masonry shall be prohibited. Wet cutting must address control of water run off.
SECTION 01 50 00
TEMPORARY FACILITIES AND CONTROLS
5/10
1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (1999) National Electrical Code
NFPA 241 (1996) Safeguarding Construction, Alteration, and Demolition Operations
1. S2
Construction site plan
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit a site plan showing the locations of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes used for this contract. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1. T4
EMPORARY UTILITIES
1.4.1 Contractor Utilities
The Contractor shall provide his own utilities.
1.5 WEATHER PROTECTION
1.5.1 Site Storm Protection
When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions shall include, but are not limited to, removing loose materials, tools and equipment from exposed locations.
Section 01 50 00 Page 1
1.6 STATION OPERATION EFFECTS ON CONTRACTOR OPERATIONS
1.7 STORAGE AREAS
Contractor shall be responsible for security of his property. The Contract Clause entitled "FAR 52.236-10, Operations and Storage Areas" and the following apply:
1.7.1 Storage Size and Location
Store equipment within the limit of the work areas.
1. T8
EMPORARY SANITARY FACILITIES
Provide adequate sanitary conveniences of a type approved for the use of persons employed on the work, properly secluded from public observation, and maintained in such a manner as required and approved by the Contracting Officer. Maintain these conveniences at all times without nuisance. Upon completion of the work, remove the conveniences from the premises, leaving the premises clean and free from nuisance. Dispose of sewage through connection to a municipal, district, or station sanitary sewage system.
Where such systems are not available, use chemical toilets or comparably effective units, and periodically empty wastes into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility.
Include provisions for pest control and elimination of odors.
Not Used.
3.1 TEMPORARY PHYSICAL CONTROLS
3.1.1 Access Controls
3.1.1.1 Temporary Barricades
Contractor shall provide for barricading around all work areas to prevent public access.
3.1.1.2 Fencing
Prior to the start of work, segregate work areas with a temporary safety fence, including gates and warning signs, to protect the public from construction activities. The safety fence shall be bright orange. Safety fencing shall be a minimum of 42 inches high, supported and tightly secured to steel posts located on minimum 10 foot centers. Remove the fence from the work site upon completion of the contract.
Section 01 50 00 Page 2
Section 01 50 00 Page 3
3.1.1.3 Signs
Place warning signs at the construction area perimeter designating the presence of construction hazards requiring unauthorized persons to keep out.
Signs must be placed on all sides of the project, with at least one sign every 300 feet. All points of entry shall have signs designating the construction site as a hard hat area.
3.2 TEMPORARY WIRING
Provide temporary wiring in accordance with NFPA 241 and NFPA 70, Article 305-6(b), Assured Equipment Grounding Conductor Program. Program shall include frequent inspection of all equipment and apparatus.
SECTION 01 57 19
TEMPORARY ENVIRONMENTAL CONTROLS
1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1910.1200 Hazard Communication
40 CFR 112 Oil Pollution Prevention
40 CFR 122.26 EPA National Pollutant Discharge Elimination
System Permit Regulations
40 CFR 241 Guidelines for Disposal of Solid Waste
40 CFR 243 Guidelines for the Storage and Collection of
Residential, Commercial, and Institutional Solid Waste
40 CFR 258 Subtitle D Landfill Requirements
40 CFR 260 Hazardous Waste Management Systems: General
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 262 Generators of Hazardous Waste
40 CFR 263 Transporters of Hazardous Waste
40 CFR 264 Owners and Operators of Hazardous Waste
Treatment, Storage, and Disposal Facilities
40 CFR 265 Interim Status Standard for Owners and
Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 266 Management of Specific Hazardous Wastes and
Specific Types of Hazardous Waste Management Facilities
40 CFR 268 Land Disposal Restrictions
40 CFR 270 EPA Administrated Permit Programs: The
Hazardous Waste Permit Program
Section 01 57 19 Page 1
40 CFR 271 Requirements for Authorization of State Hazardous Waste Programs
40 CFR 272 Approved State Hazardous Waste Management
Programs
40 CFR 273 Universal Waste Management
40 CFR 279 Used Oil Regulations
40 CFR 280 Owners and Operators of Underground Storage
Tanks
40 CFR 300 National Oil and Hazardous Substances
Pollution Contingency Plan
40 CFR 355 Emergency Planning and Notification
40 CFR 372-SUBPART D EPA Toxic Chemical Release Reporting
Regulations
40 CFR 716 Health and Safety Data Reporting
40 CFR 761 Polychlorinated Biphenyls (PCBs)
Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions
49 CFR 173 Shipments and Packagings
49 CFR 178 Packagings
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA SW-846 (1996) Evaluating Solid Waste
(Physical/Chemical Methods)
EPA 832-R-92-005 Storm Water Management for Construction
Activities
1.2 DEFINITIONS
1.2.1 Sediment
Soil and other debris that have eroded and have been transported by runoff water or wind.
1.2.2 Solid Waste
Garbage, refuse, debris, sludge, or other discharged material (except hazardous waste as defined in paragraph entitled "Hazardous Waste" or hazardous debris as defined in paragraph entitled "Hazardous Debris"), including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations.
Material not regulated as solid waste are: nuclear source or byproduct materials regulated under the Federal Atomic Energy Act of 1954 as amended;
suspended or dissolved materials in domestic sewage effluent or irrigation return flows, or other regulated point source discharges; regulated air
Section 01 57 19 Page 2 emissions; and fluids or wastes associated with natural gas or crude oil exploration or production.
a. Green waste: The vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots. Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.
b. Surplus soil: Existing soil that is in excess of what is required for this work, including aggregates intended, but not used, for on-site mixing of concrete, mortars and paving. Contaminated soil meeting the definition of hazardous material or hazardous waste is not included.
c. Inert construction and demolition debris: Broken or removed concrete, masonry, and rock asphalt paving; ceramics; roofing paper and shingles. Inert materials [may] [may not] be re-inforced with or contain ferrous wire, rods, accessories and weldments.
d. Wood: Dimension and non-dimension lumber, plywood, chipboard, hardboard. Treated and/or painted wood that meets the definition of lead contaminated or lead based contaminated paint is not included.
e. Scrap metal: Scrap and excess ferrous and non-ferrous metals such as re-inforcing steel, structural shapes, pipe and wire that are recovered or collected and disposed of as scrap.
This is the start of the file's text. The full file is on GovTribe.