Amendment_0001.pdf
PDF 219 KB Posted
- Solicitation number
- HSCG88-17-R-PQQ091
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0003.pdf | ||
| Amendment_0002.pdf | ||
| RFP_HSCG88-17-R-PQQ091_4_May_2017.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 3
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0001 May 24, 2017 4985469
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE Contracting Officer USCG CEU Oakland 1301 Clay Street 7th Floor, Suite 700N Oakland, CA 94612-5203
Same as Block 6
8. NAME AND ADRESS OF CONTRACTOR (no., street, county, State and ZIP Code) √ 9.A AMENDMENT OF SOLICITATION NO.
ALL PROSPECTIVE BIDDERS
X HSCG88-17-R-PQQ091
9B. DATE (SEE ITEM 11)
May 4, 2017
10A. MODIFICATION OF CONTRACT/ORDER
NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the Offer submitted: or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/.ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority).
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to make the following changes:
(1) A second prebid site visit is scheduled for 30 May 2017 at 9:00 am Pacific Standard Time. All attendees are required to wear hard hats. Access to the site shall not be permitted without proper protective equipment.
(2) The NAICS code for this project is changed to 236220.
(3) Section H, Special Contract Requirements, paragraph entitled “CONTRACTOR EXPERIENCE IN HISTORIC LIGHTHOUSES OR TOWERS” is revised to read:
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
JASON DUGAN
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)PREVIOUS
EDITION UNUSABLE Prescribed by GSA, FAR (48 CFR) 53.243
Request for Proposal Number HSCG88-17-R-PQQ091 Amendment 0001 May 24, 2107
“The contractor or its proposed subcontractor or subcontractors must have completed at least two (2) projects involving the maintenance, repair or restoration of historic lighthouses or similar scopes of work involving structural repair of towers. To satisfy this experience requirement, the projects must have had a value of at least $200,000.”
(4) Section L, Instructions, Conditions and Notices to Offerors, L.7, paragraph “2. Part II – Technical Proposal” is revised to read:
“2. PART II – TECHNICAL PROPOSAL
Experience- Provide a list of at least two (2) and no more than four (4) contracts performed by the offeror or proposed subcontractors involving the maintenance, repair or restoration of historic lighthouses or similar scopes of work involving structural repair of towers. The projects must have had a value of at least $200,000.
The projects may have been performed for government agencies (city, state, local or federal), commercial, or nonprofit customers.
Complete Attachment 7, Experience Reference List for all submitted projects. Attach one additional sheet to clearly describe the project, the scope of work performed, and any additional information you desire to submit.
Each project is limited to one additional sheet. Pages may be printed or typewritten. Number all pages. Do not use font less than 12 point. Single space the text with margins of 1-inch (right, left, top and bottom). The offeror may use a different format in lieu of Attachment 7 and additional sheets as long as the same required information is included.
The completed Experience Reference List and additional sheets must be submitted with your offer and received by the RFP closing date and time.
The Contracting Officer has determined there is a high probability of adequate price competition in this acquisition.
Upon examination of the initial offers, the Contracting Officer will review this determination and if, in the contracting officer’s opinion, adequate price competition exists no additional cost information will be requested and certification under FAR 15.406-2 will not be required. However, if at any time during this competition the Contracting Officer determines that adequate price competition no longer exists offerors may be required to submit information to the extent necessary for the Contracting Officer to determine the reasonableness of the price.
Offerors should provide the submission of information to the Contracting Officer as prescribed in FAR 52.215-1(c)(1- 3). Send proposals to:
US Coast Guard Civil Engineering Unit Oakland ATTN: Jason Dugan 1301 Clay Street 7th Floor, Suite 700N Oakland CA 94612-5203”
Request for Proposal Number HSCG88-17-R-PQQ091 Amendment 0001 May 24, 2107
(5) Section M, Evaluation Factors for Award, M.2 Evaluation of Offers, paragraph 3 is revised to read:
“3. Technical Evaluation Factor: To be determined technically acceptable, the offeror or its proposed subcontractor or subcontractors must have completed at least two (2) projects involving the maintenance, repair or restoration of historic lighthouses or similar scopes of work involving structural repair of towers. To satisfy this experience requirement, the projects must have had a value of at least $200,000.”
(6) Attached is the attendance sheet for the prebid site visit conducted on May 19, 2017.