Civil Engineering Unit Juneau, Alaska

Specifications for

REPAIR EXTERIOR AND DRAINAGE OF LAKE LOUISE

Kodiak, Alaska

Project # 3578866

4 March 2014

DIVISION 1 GENERAL CONDITIONS

01 00 00 SUMMARY OF WORK

01 01 00 STANDARD REQUIREMENTS

01 01 20 SPECIAL CONDITIONS AND SUBMITTALS

01 15 00 HEALTH AND SAFETY REQUIRMENTS

01 31 20 PROGRESS & PAYMENT SCHEDULES

01 40 10 CONTRACTOR’S QUALITY CONTROL

01 56 00 ENVIRONMENTAL CONTROLS

01 70 00 CONTRACT CLOSEOUT

01 78 10 OPERATION AND MAINTENANCE DATA

01 78 20 WARRANTY

DIVISION 2 SITE CONSTRUCTION

02 05 00 DEMOLITION AND REMOVAL

02 20 40 BASE COURSE

02 80 10 ASPHALT CONCRETE PAVEMENT

02 80 20 TACK COAT

02 80 60 REMOVE EXISTING ASPHALT SURFACING

DIVISION 3 CONCRETE

03 30 30 SIDEWALK, CURB AND GUTTER

DIVISION 6 WOOD AND PLASTICS

06 10 00 ROUGH CARPENTRY

DIVISION 7 THERMAL AND MOISTURE PROTECTION

07 25 00 WEATHER BARRIERS

07 30 01 ASPHALT SHINGLE REPLACEMENT

07 60 00 FLASHING AND SHEET METAL

DIVISION 15 MECHANICAL

15 19 30 FUEL TANK & PIPING SYSTEM

SECTION 01010 - SUMMARY OF WORK

SECTION 01 00 00

SUMMARY OF WORK

PART 1 – GENERAL

1.1 GENERAL

The WORK to be performed under this contract shall consist of furnishing all plant, tools, equipment, materials, supplies, manufactured articles, labor, transportation and services, including fuel, power, water, and essential communications, and performing all WORK, or other operations required for the fulfillment of the contract in strict accordance with the Contract Documents. The WORK shall be complete, and all work, materials, and services not expressly indicated or called for in the Contract Documents which may be necessary for the complete and proper construction of the WORK in good faith shall be provided by the CONTRACTOR as though originally so indicated.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

This project is the last phase of a multi-year effort to repair housing structures and sites in the Lake Louise Housing area. This project will consist of work related to Units 823 through 830, and site/drainage work for Units 808 to 812.

The project includes the below described work.

This is a performance based specification – refer to Section 010100 paragraph 1.0.3.1.

Standards of performance for work on the housing units themselves, is evidenced by the previously completed housing units.

The contract drawings show some, but not all, of the work required.

A. Heating fuel tanks: Remove and dispose of existing underground heating fuel storage tanks and install new above ground tanks. Includes construction of foundation pad, fenced enclosure, and plumbing to boilers. If present, tiger loops at boilers with supply and return fuel lines will maintained. If contaminated soil is encountered, this task shall include stockpiling, but no remediation. Soil shall be stockpiled on Coast Guard property at the site(s) indicated by the COR.

For purposes of bidding assume 30 CY total of contaminated soil will be removed during tank removals. Cost of stockpiling, testing, and hauling and other regulatory requirements are to be included in the Base Bid.

Note: Remediation is not included in the work. Soil shall be stockpiled on Coast Guard property (Pad 94 Nymans Peninsula or other location to be determined by the

COR).

REPAIR EXTERIOR AND DRAINAGE OF LAKE LOUISE SECTION 01 00 00

PROJECT 3578866 Page 1 of 5

B. Asphalt and Concrete: Repave Lake Louise Drive, construct new asphalt parking areas, remove and replace failed asphalt driveways including 18-inches of foundation/subbase materials, repair sidewalks as needed, replace curb and gutter in areas where repaving of road is performed. Pressure wash concrete slabs, patios, and retaining walls that are to remain. Repairing or sealing concrete is not required.

C. Earthwork, Drainage, and Grading: Regrade sites to facilitate surface water drainage away from structures and into existing water bodies. Install storm pipe and yard inlets as shown on the civil plans. Provide a minimum slope of 2% away from each building for a minimum of 6 feet to the greatest extent possible. Grading shown on the plans is for guidance and may need to be reworked as necessary to maintain the 2% minimum slopes based on field surveying during grading operations. Remove landscaping and trees to facilitate the work. Stumps shall be removed inside all proposed fenced yards, and within a 4 foot perimeter outside of the yard fences. Grade, topsoil and hydro seed all areas disturbed by construction activities. Disposal of stumps and trees shall be off Coast Guard property. Once yard areas are seeded, the first cutting (within 30 calendar days) is the contractor’s responsibility. Follow-on maintenance will be accomplished by the resident. The contractor will re-seed once (within 30 calendar days) after the initial seeding, regardless of the cause of lack of growth. Anticipate reseeding will be required on 100% of the areas. Schedule work such that all seeding will be complete prior to 15 August.

D. Fences: construct to enclose back yards, including atop retaining walls, and around above-ground fuel tank pads. Fences shall be 4 feet high, green PVC coated chain link with 4-foot-wide gates for yards and 6-feet high for above ground storage tanks. The fence posts and gates shall be set to minimize clearance openings under the fencing in areas of steeper slopes and/or drainage ditches.

E. Exterior of housing units: Roof replacement is limited to Buildings Numbers 827-830. Other repairs apply to ALL units.

1) Remove existing roofing materials such as asphalt shingle roofing, felt underlayment, metal fasteners, old caulking, foam fillers, rubber boots, debris etc.

2) Install new asphalt shingle roofing, 100% ice & water shield or underlayment, step flashing, rubber boots, metal fasteners, caulking, single membrane patching etc. in accordance with these plans and specifications, and manufacturers written instructions.

3) Remove/roof over existing skylights over porches and paint underside to match existing with two coats of exterior latex paint.

4) Pressure wash: the exterior of housing units, including all trim, gutters, and downspouts.

PROJECT 3578866 Page 2 of 5

5) Replace siding and trim on exterior of chimneys. Replace with manmade (Azek and cement board siding) materials, and metal flashings to provide a low maintenance surface.

6) Remove quarter round molding under gutters, repair/replace damaged fascia and gable end fascia boards, and cover gable end fascia boards and eave boards with metal flashing. Wrap eave fascia board with flashing, slide between gutter and fascia board, until it stops at gutter nails. Fur out gable ends prior to wrapping with metal.

7) Prep and paint all wood surfaces not covered by metal flashing. Prep work includes removal of any nails or devices used to hang holiday lights, or other items.

8) Provide vented vinyl soffits for entire structure, including porch roofs/overhangs.

9) Clean and paint exposed wood surfaces.

10) Repair or replace gutters, including sealing joints as necessary to facilitate drainage without leakage. Repair gutter downspouts and provide heavy duty, black rubber splash blocks.

11) Dryer Vent Cleaning: Clean and vacuum the dryer exhaust ducts. Replace outlet covers where damaged. Where exhaust duct exits wall, ensure airtight seal between duct and outlet cover.

12) Paint exterior doors where needed to make them either gray, white or natural wood color per COR guidance.

13) Remove every other birdblock, and associated cardboard vent tray. Install polystyrene vent tray from the exterior in this rafter space, or ensure soffit vents unobstructed to the attic space from inside the attic (see interior work below).

F. Decks (Buildings 824-830), stoops, porches, steps, and landscaping:

1) Construct or replace gravel drip perimeters; includes treated timber edging, weed control fabric, and washed gravel as well as removal of any existing landscaping in the work area. Objective is a fresh and maintainable appearance of the perimeter of the houses.

2) Remove & dispose existing wood stoops and replace stoops to patio doors w/ new stoops made of manufactured deck materials as specified in the Kodiak Standard Specs.

3) Remove & dispose existing wood self-help decks.

4) Install new decks where shown.

PROJECT 3578866 Page 3 of 5

5) Replace handrail, and balusters with manufactured materials.

6) Replace all structural joists and decking on the existing decks with new structural joists at 16” O.C., and manufactured deck material. Replace stair treads and any additional damaged structural members with pressure treated timber. The new structural members shall match the size and dimensions as shown on the existing deck as-built plans.

7) Replace lattice with fiberglass or vinyl screens.

8) Paint remaining wood members.

9) Seed and mulch any areas disturbed from construction activities.

G. Interior Work: The objective of the work is to tighten the air boundary between the attic and the occupied spaces, while improving the air flow though the attic.

1) Temporarily remove attic insulation to expose work areas.

2) Foam seal all ceiling penetrations.

3) Replace bathroom vent duct with new high quality flexible metal duct.

Where duct exits the building, ensure airtight seal between duct and roof cap.

4) Ensure unobstructed air flow /ventilation from soffit vent to attic.

5) For any work performed inside an occupied unit: the contractor shall provide a “housing monitor”. The housing monitor shall work directly for the contractor’s Project Manager and be on site at all times when work is being performed inside an occupied housing unit. The role of the monitor is to: coordinate with the housing occupant, provide advance notices of proposed work, and ensure safety and security of the occupants and their belongings, and, ensure cleanliness of the work activities inside the unit.

1.3 SITE OF THE WORK

A. The site is located at the U.S. Coast Guard Base Kodiak, Alaska.

1.4 DEFINITIONS APPLICABLE TO TECHNICAL SPECIFICATIONS.

The following words have the meaning defined in the Technical Portions of the

WORK:

Furnish - means to supply and deliver to the site, to unload and unpack ready for assembly, installation, testing, and start-up.

PROJECT 3578866 Page 4 of 5

PROJECT 3578866 Page 5 of 5

Indicated - is a word used to direct the CONTRACTOR to information contained on the drawings or in the Specifications. Terms such as "shown," "noted," "scheduled," and "specified" also may be used to assist in locating information but no limitation of location is implied or intended.

Install - defines operations at the site including assembly, erection, placing, anchoring, applying, shaping to dimension, finishing, curing, protecting, and cleaning, ready for use.

Installer - a person or firm engaged by the CONTRACTOR or its subcontract or any subcontractor for the performance of installation, erection, or application work at the site.

Installers must be expert in the operations they are engaged to perform.

Provide - is defined as furnish and install, ready for the intended use.

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)

END OF SECTION

SECTION 01 01 00 STANDARD REQUIREMENTS

SECTION 01 01 00

STANDARD REQUIREMENTS

1.0 SCOPE OF WORK

1.0.1 The work consists of construction activities on USCG facilities, as described in the drawings and specifications.

Work shall be executed in strict accordance with the best practice of the trades in a thorough, substantial, workman like manner by competent workmen.

The Contractor shall provide a competent, experienced, full time Superintendent who is acceptable to the Government, and who is authorized to make decisions on behalf of the Contractor, and who shall be constantly in charge of the work.

Work includes safety and environmental protection provisions as described.

Work includes all documentation, as-builts (including record surveys as may be required by Alaska licensed professional surveyor), final inspection, training and warranty, as specified.

The final completion and acceptance of all work, will be established by a written notice of acceptance issued by the Contracting Officer. No changes, deviations, or waivers shall be effective without a modification of the contract executed by the Contracting Officer (KO) authorizing such changes, deviations, or waivers.

1.0.2 Correspondence Identification: All correspondence and data submitted by the Contractor under this contract shall reference the Contract Number and Project Name.

REPAIR EXTERIOR AND DRAINAGE OF LAKE LOUISE SECTION 01 01 00

PROJECT 3578866 Page 1 of 20

1.0.3 Scope of Work: The contractor will provide for all labor, material, supplies, transportation, supervision and all other necessary items for a complete and usable project, performing all work in a workman like manner in complete compliance with the contract. Common trades which may be needed include: all construction trades and technical support personnel, including testing, surveying, and abatement, and any other trades common to the construction industry to include government work. The Contractor will be required to perform multi-discipline construction, repair and remodeling work using these trade workers.

1.0.3.1 Performance Based Statement of Work:

1.0.3.2 The Contractor will be required to typically perform construction from a the performance-based Statement of Work. The contractor is responsible for interpreting the performance based requirements from the specifications, plans and reference documents, including the “Kodiak Standard Specifications” to provide a complete and useable end product. The Statement of Work and reference documents, including the “Kodiak Standard Specifications” may not provide complete instructions on how to perform the work, or detail/integrate all associated components of the work. The contractor shall apply their experience and judgment in performing typical commercial construction practices to complete the work with limited additional Government guidance.

1.0.4 Where exact locations are not given for the positioning of equipment, devices, and work; they shall be positioned to permit easy access for maintenance and for removal and replacement of component parts. The Contractor is responsible for the coordination and proper relation of the work with the existing surroundings.

1.0.5 Schedule work to minimize interference with the facilities’ normal operations.

Before any of the work is initiated, the Contractor shall confer with the Contracting Officer (KO), or their authorized representative(s), typically at the Preconstruction Conference; and agree on: a sequence of work; means of access to premises and building; space for storage of materials and equipment; delivery of materials and use of approaches; use of corridors, stairways, and means of communications; and the extent of protective measures required for existing adjacent occupied areas.

1.0.6 The Contractor may be required to provide shop drawings, procedures, or plans certified by an appropriately registered State of Alaska Professional Engineer, or other Certificated Professionals employed or retained by the contractor. The requirement for

PROJECT 3578866 Page 2 of 20 a professional shall not be construed to imply that normal work requires professional engineering certification. However, the possibility exists that technical specialties, unforeseen events or unexpected site conditions will require submittals or modifications to the completed designs that will require proof of licensing (i.e., an Engineer’s stamp).

The Government anticipates less than five percent of the Contract work will require this type of certification. When such conditions do occur, the contractor shall provide proof for the discipline appropriate. Unless specified otherwise, certifications shall be Alaskan.

1.0.7 PARTNERING: The Government intends to encourage the formation of a cohesive partnership with the Contractor. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objective is effective contract performance in achieving completion within budget, on schedule and in accordance with plans and specifications.

1.1 DEFINITIONS APPLICABLE TO TECHNICAL SPECIFICATIONS

The following words and abbreviations have the meaning defined in the Technical Portions of the WORK.

Furnish means to supply and deliver to the site, to unload and unpack ready for assembly, installation, testing, and start-up.

Indicated is a word used to direct the CONTRACTOR to information contained on the drawings or in the Specifications. Terms such as "shown," "noted," "scheduled," and "specified" also may be used to assist in locating information but no limitation of location is implied or intended.

Install defines operations at the site including assembly, erection, placing, anchoring, applying, shaping to dimension, finishing, curing, protecting, and cleaning, ready for the USCG use.

Installer: a person or firm engaged by the CONTRACTOR or any subcontractor

Provide is defined as furnish and install, ready for the intended use.

KO – Contracting officer

COR – Contracting Officer’s Representative

CI – Government Construction Inspector

PROJECT 3578866 Page 3 of 20

1.2 CONSTRUCTION PHASING & CONSTRAINTS

Standard constraints and phasing requirements to incorporate into the schedule and work activities are described below. Additional provisions may be specified in other sections of the contract.

1) Work Hours:

Housing/Barracks Areas:

Weekdays: Start no earlier than 0800. Complete no later than 1900.

Saturdays and Holidays: Start no earlier than 0900. Complete no later than 1800.

Non- Housing Areas: Start no earlier than 0700. Complete no later than 1900.

Variations may be coordinated with/approved by the COR, including work to support outages.

2) Work which requires Government supervision or coordination shall not be performed on Federal Holidays or Sundays.

3) The on –site performance period includes; mobilization, to final clean up, punch list and demobilization.

4) All seeding activities shall be completed prior to 15 August. Reseed, fertilize, water, and protect disturbed areas as long as necessary to fully re-vegetate.

5) All asphalt paving shall be complete by 1 October.

6) Notifications; provide notifications as follows;

a. After hours work: 2 working days.

b. Mobilization/demobilization: 2 weeks.

1.3 TEMPORARY SERVICES

The contractor may obtain utility services from existing USCG services at no cost to the contractor. The contractor shall provide hookups and disconnects, and coordinate with on-site USCG personnel.

PROJECT 3578866 Page 4 of 20

Make all arrangements with the local utility providers and pay all fees, charges, and costs of any nature associated with establishing and installing temporary services which are not available via USCG systems.

Installation of temporary utility services shall at a minimum follow the local, state and federal codes governing the installation of the utility service being installed.

Water and sewer is available at the site. Connections to potable water shall have an isolation valve and reduced pressure principal backflow preventer. Fire hydrants shall not be used as a source without the permission of the COR.

Telephone Service: Telephone service is not owned by the USCG. Coordinate with the local telephone company for point of connection (POC) location for temporary telephone service, if required. Pay all installation fees and telephone usage charges directly to the telephone company to provide the service.

Electrical: Coordinate with the local Electrical company for point of connection (POC) location for temporary electrical service requirements beyond capabilities of existing USCG systems. Pay all installation fees and electrical usage charges directly to the electrical company to provide the service.

The Contractor shall provide all other temporary services, utilities, and equipment required, which are not provided by the Coast Guard. These include, but are not limited to: Clean up and disposal of trash and Portable or temporary toilet facilities: Maintain in a sanitary condition at all times. Establish the facilities in manner to minimize public viewing. COR/CI will approve location and installation.

1.4 OUTAGES AND PROTECTION

Before interrupting utility service, make a written request for the interruption to the COR at least 10 work days before the anticipated interruption. Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized. Permission and duration for outages will be granted by the COR based upon the need for the utility, and upon consideration of suitable bypasses, or alternate arrangements. Outages will be granted at the convenience of the Government.

Protection: The Contractor shall safeguard and protect from damage all utilities encountered or uncovered during digging, excavation, and backfilling.

Hand Digging: All excavations with the potential for damaging existing utilities using machine excavation shall be done by hand digging. Complete all excavations within 5

PROJECT 3578866 Page 5 of 20 feet of existing utilities by hand rather than machine methods, or expose piping or cables by hand digging prior to completing excavation by machine.

Contractor shall restore damaged piping, cable(s), and circuits to original condition and full operation if damage occurs through his failure to fully process the digging permit or comply with its instructions, or to obtain utility locations from private utilities. Notification of damage shall be made immediately to the affected utility, to the USCG representative as listed on the digging permit, and to the COR/CI; restoration efforts shall commence within 1 hour. Failure to commence restoration within the required time limit, or to make continuous progress toward restoration, or to complete acceptable restoration within a 4-hour time limit or an alternate time limit negotiated with and established by the COR/CI, shall result in suspension of all other contract work until acceptable restoration is completed and approved by the COR.

All work to repair damage to commercial utilities shall be coordinated through the utility.

In cases where a utility is damaged for reasons noted above, the Contractor shall, if lacking the qualified trades in his organization, employ as necessary such qualified trades or employ another Contractor having such trades to restore the utility to its original condition and full operation at no expense to the Government.

The Government reserves the right to protect damaged communications cables from further damage or deterioration and the right to restore priority circuits; these actions shall not relieve the Contractor of his full responsibility for restoration. Outages: Submit and coordinate outage requests for each outage.

1.4.1 Outages:

Steam outages will be allowed. It is the contractor’s responsibility to perform and schedule the work in a manner that limits the number of outages. Base operating personnel will turn off and reestablish the steam supply for each outage.

Temporary Steam Supply: The contractor shall maintain a temporary steam supply to the affected portions of the system, and buildings while performing the work.

Provide a temporary steam pipe supplying steam with a minimum diameter as approved by the COR.

PROJECT 3578866 Page 6 of 20

Temporary Condensate Return: Main Condensate shall not be wasted. Provide temporary condensate return, to ensure condensate returns to the central steam plant as coordinated with the COR.

Submit a steam outage plan that describes outage scheme, technical details of the outage such as installation of temporary lines and the location for condensate return/wasting.

Steam Supply to Two or More Buildings

Steam outages between 4 and 16 hours in duration will commence at 11:00 p.m.

and be completed by 3:00 p.m. the following day. The outages will be limited to one every two weeks throughout the performance of the work. The steam supply will be re-established by base operating personnel no later than 3:00 p.m. the following day and full steam pressure restored by 6:00 p.m.

Steam outages of less than 4 hours in duration will commence at 11:00 p.m. and be completed by 3:00 a.m. the following day. The outages shall be allowed once per week throughout the performance of the work.

Utility Outages: Outages on nights and weekends when facilities are not in use may be approved by the COR. Other outages shall not exceed the following in any 24-hour period:

Steam, Heat, Water, Electric, Storm Sewer, and Sanitary Sewer: Four hours is the maximum down time, without specific advance written permission.

1.5 UNDERGROUND UTILITIES

Submit digging requests per Base Kodiak procedures on the form provided, 10 working days in advance, and coordinate utility locates with other servicing utilities.

Mark the excavation route and intersecting utilities and parallel utilities within 10 feet of trench sides.

Where excavation will cross an existing utility line, use hand tools to excavate for a distance of 5-feet on each side of the intersections.

Once exposed, protect underground utilities from damage. Insure there is a dedicated spotter for each excavation during all excavation with power assisted excavating tools

PROJECT 3578866 Page 7 of 20 the spotter must be dedicated to watching the excavation and may not have any other supplemental duties during excavation activities. Ensure that new utility lines are complete, except for the connection, before interrupting existing

1.6 WEATHER

Delays caused by unusually severe weather (FAR Clause 52.249-10). Unusually severe weather will be considered unforeseeable and unusually severe if it is more severe than the statistical 3-year average for the appropriate weather parameters established by the National Weather Service.

Should warnings of severe weather be issued, the Contractor shall take every practical precaution to minimize danger to persons, the work, and to adjacent property.

Precautions shall include, but not limited to, closing all openings, removing all loose material, tools and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

If any part of this project is pursued during periods of cold or inclement weather, the Contractor shall take all appropriate precautions to protect facilities and work involved in the project scope from damage by cold/or inclement weather. The Contractor shall be responsible for snow removal around project site, parking areas, and thoroughfares.

Working conditions for this work are based on typical weather information in Kodiak (PROVIDED FOR INFORMATIONAL PURPOSES ONLY) as follows; the contractor shall verify actual conditions based on established databases (National Weather Service). These weather conditions are NOT used for design or materials/installation requirements; refer to technical specifications for design and materials/installation requirements.

Prevailing wind: northwest at 8 knots. Maximum wind: 101 knots.

Maximum temperature: 86 degrees F.

Minimum temperature: -12 degrees F.

January average mean temperature: 30.8 degrees F.

July average mean temperature: 54.2 degrees F.

Average annual precipitation: 54.42 inches.

Maximum annual precipitation: 91.1 inches.

60-minute duration rainfall rate: 0.7 inch/hr.

Design roof snow load: 40 psf.

PROJECT 3578866 Page 8 of 20

Freeze Data: Frost protection burial depth, 4 ft.

1.7 RECEIPT OF MATERIALS

Shipments of equipment, materials, and supplies shall be addressed to the contractor -not the Government. The contractor must be on hand to accept shipments; the Government will not accept shipments.

1.8 DELIVERY, STORAGE, AND HANDLING OF MATERIALS

No on-Base storage facilities are available to the contractor. Deliver, store, and handle products and materials within the contractor’s laydown area and according to the manufacturer's printed instructions and as follows:

Deliver products and materials in manufacturer's original unopened packages or containers bearing manufacturer's labels.

Store products subject to damage from the elements in weather tight enclosures;

maintain temperature and humidity within the ranges stated in the manufacturer's printed instructions.

Store fabricated products off the ground on platforms, blocking, or skids.

Cover or protect products that may discolor or deteriorate due to exposure to the elements. Provide ventilation to avoid condensation.

Store loose granulated material on solid surfaces such as paving, plywood, or sheet material to prevent mixing with foreign matter. Provide drainage to prevent sheet material from mixing with foreign matter. Provide drainage to prevent flow or ponding of rainwater. Prevent mixing of any stored materials.

1.9 PUBLIC CONVEYANCES

The CONTRACTOR shall make its own investigation of the condition of available public and private roads and of clearances, restrictions, bridge load limits, and other limitations affecting transportation and ingress and egress to the site of the WORK. It shall be the

PROJECT 3578866 Page 9 of 20

CONTRACTOR's responsibility to construct and maintain any haul roads required for its construction operations.

1.10 CLEANING

The CONTRACTOR shall provide complete cleaning services of completed work and work area, including re-grading any disturbed unpaved laydown areas.

The contractor shall provide cleaning services after final inspection, immediately prior to government acceptance.

1.11 INTERRUPTION OF TRAFFIC

If during the performance of work it becomes necessary to modify vehicular traffic patterns, notify the COR at least 10 days prior to the proposed interruption date, and submit a detailed Traffic and Fencing Plan as a preconstruction submittal.

1.11.1 Road Closures

Submit a detailed Traffic and Fencing Plan as a preconstruction submittal. The contractor’s plan shall show, but not limited to, traffic flow pattern, location of warning signs, flaggers, barricades, etc. This project will affect traffic in areas which are distant from the actual construction site. The contractor shall evaluate, as part of the road closure plan, area-wide traffic flow as it is affected by construction activities. Continuous pedestrian and vehicle access is required to all facilities, from at least one path of access. The Contractor needs to sequence their work to maintain access and continuity of operations.

a. Closure of more than one road at a time shall not be allowed.

b. No long term stockpiling of excavated material or debris shall be allowed in the work area.

c. For road closures, or traffic modifications; submit an “outage request” ten days in advance.

d. For any one-way temporary traffic, provide a flagger(s) from 0800 to 1630 Monday through Friday.

PROJECT 3578866 Page 10 of 20

e. Sign roads in the project area to indicate road closures and alternative routes.

Post signs to indicate pending road closures 3 days prior to the actual closure.

Install signs upstream of closure to warn traffic in advance of closed section.

Coordinate all signage requirements with the COR.

f. Temporary barriers shall be erected to delineate a corridor through which tenant vehicles and equipment can pass, and temporary fencing shall be installed to control normal pedestrian pathways.

g. The contractor shall erect a temporary barrier(s) to demark their work area(s).

Where necessary, the barriers should be supplemented with traffic control and informational signs.

h. Provide fence barriers to prevent unauthorized entry in excavation areas, where heavy equipment operates or is parked, demolition areas, and to protect existing facilities and adjacent properties from damage from construction operations.

Construct and maintain barricades as required by OSHA sufficient to prevent injury to persons and damage to property.

i. Provide barricades around trenches and holes to prevent access. Special precautions shall be taken to prevent accidental use of residential doorways abutting the work to safe guard residents and their pets.

j. Provide and maintain warning lights and signs as necessary to prevent damage or injury. Keep warning lights burning from dusk to dawn. Traffic Control devices shall be in constructed and installed in accordance with the Alaska Traffic Manual.

k. Install Asbestos Abatement barriers and signage for asbestos abatement work.

1.12 WARNING SIGNS

Provide warning signs at the limits of construction stating that access is restricted to authorized personnel and hard hats are required. Also provide warning signs to warn pedestrians and drivers to potentially dangerous areas.

1.13 BARRIERS AND TRENCH PLATES

PROJECT 3578866 Page 11 of 20

Provide temporary barriers with warning lights where construction work intersects existing roads, walkways, at open excavations, and where pedestrian and driver safety may be endangered in the area of work. Provide barriers and warning signs to re-route pedestrians and drivers around potentially dangerous areas. Barriers shall be manufacturer's standard A-frame, barrel, or Jersey style with flashing amber lights and reflective orange/white striping on both sides of the barrier. Minimum barrier height shall be 42". Monitor barricades for wind/weather conditions, and restore promptly.

Provide trench plates for excavations in roads left open overnight on Coast Guard property.

1.14 QUARTERS

No Government quarters are available for use under this contract.

1.15 SALVAGE

All existing materials which are to be removed, and are not indicated or specified for reuse in the new work, shall, unless otherwise specified, become the property of the contractor, be removed from government property at the Contractor’s expense, and be disposed of in accordance with Federal, State and local regulations. Remove all salvage from government property.

Excess clean soils excavated from the work site, and NOT reused in the construction may be disposed on USCG property. Coordinate requirements and location of disposal site with COR.

Excess clean concrete materials (with protruding rebar and other devices removed) may be disposed on USCG property, on Nymans Peninsula. Coordinate requirements and location of disposal site with COR.

1.16 EMERGENCY CONTACT

Maintain an after-working hours contact point, and provide the COR with a telephone number, so that the Government may contact the Contractor at any time in case of emergency.

Base Kodiak is a “911” response location. USCG typically provides first response under a mutual aide agreement, however, transportation and treatment are provided by community/commercial resources.

PROJECT 3578866 Page 12 of 20

1.17 IDENTIFICATION OF EMPLOYEES AND EQUIPMENT

Prior to the commencement of work, submit to the COR a complete list of all employees, representatives, and subcontractors, including name, age, and address.

Contact the COR regarding regulations concerning vehicle passes. Furnish a complete list of over-the-road vehicles and construction equipment to the COR. The list shall include the make, model, year built, and identifying marks.

Furnish similar lists to Base Military Police for obtaining contractor Base vehicle passes.

Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work.

All personnel shall carry proper identification (ID) when on site. Proper ID is defined as either the individual's driver's license, or state federal picture ID or Passport. The identification must be laminated, and show a facial picture of the individual.

1.18 FIRE PREVENTION AND PROTECTION

Perform all work in a fire-safe manner. Provide and maintain adequate fire fighting equipment during the entire construction period.

Comply with local fire protection regulations and, where the regulations do not apply, comply with the standards of the National Fire Protection Association.

Obtain hot work permits from the Base Fire Department. These permits are issued on a daily or weekly basis, depending on the work. Notify Fire Department 2 hours in advance.

For any hotwork performed within an existing or newly constructed structure, provide a dedicated independent fire watch, and maintain watch for 30 minutes after completion of hot work.

On site burning for disposal is not allowed.

Contractor Fire Prevention Responsibility

It is the inherent responsibility of the Contractor to practice good fire prevention measures while working on USCG property.

When work is accomplished in/on structures, contractor personnel will confine smoking to established/designated smoking area(s).

PROJECT 3578866 Page 13 of 20

Flammable paints, oil, varnishes, etc., stored inside structures must be in a metal storage cabinet. When stored outside, flammables must be in a controlled area.

Flammables being used outside of these areas are limited to a one day supply.

Temporary wiring must be in compliance with Article 305 of the National Electric Code.

1.19 LAYDOWN AREA AND ADJACENT WORK

1.19.1 A contractor’s laydown area will be provided in the general vicinity of the construction site. The contractor shall erect temporary barriers to demark their work/storage areas. There should be no expectation of security for the contractor’s materials.

The adjacent areas, are working areas. Equipment/people move past the work area.

Access to, and functions of the adjacent site shall remain operational during construction.

1.19.2 Material Stockpile and Laydown Area. The contractor’s laydown area shall be within the limits of construction. Additional laydown areas may be provided on Base.

Coordinate location with COR.

There shall be no long term stock piling of excavated soils in the work area(s). Excess excavated soil shall be transported and stockpiled within an approved laydown area, with proper erosion control methods. Restore stockpile area(s) upon completion of the work. Excess or unsuitable materials not incorporated into the work, may be accepted by the government, or shall be disposed of by the contractor off Base.

Demolished asphalt, concrete and other debris shall be removed daily from the work area. Demolished asphalt and concrete may be disposed on Base subject to government approval.

1.19.3 The contractor shall install security fencing around the work area(s) and laydown areas. Fencing shall be substantial, to prevent pedestrian and vehicle access, and to denote areas of construction. Temporary barriers shall be erected to delineate a corridor around the construction areas, for temporary pedestrian passage, and temporary fencing shall be installed to control/divert normal pedestrian pathways.

Where necessary, the barriers should be supplemented with traffic control and informational signs. Fencing placed in existing paved areas (which are not replaced with the work) shall be surface mounted.

PROJECT 3578866 Page 14 of 20

1.19.4 Contractor’s Parking Area: The Contractor shall limit parking to within the limits of fenced/barricaded construction work.

1.19.5 Maintain a tidy worksite. Proximity of the work to the Air Station and operating airfields makes this particularly important.

1.19.6 Disturbance to adjacent grass areas shall be restored, which may include cutting grass that has not been maintained due to contractor temporary work or other obstructions.

1.20 CONTRACT REQUIREMENTS

1.20.1 Reports a. Daily: The Contractor shall submit daily reports to the COR and CI on forms provided by the Government.

When: Daily reports shall be submitted to the Government OSR and COR by 9:00 am on the next work day. Any revisions requested by the Government shall be completed and resubmitted within 24 hours. If work is not completed on a regular work day due to weather or other constraints, submit a report indicating the reasons.

How: Submit daily reports electronically as pdf files. Reports should utilize a standard format/template throughout the project duration. The daily report files shall be named as follows: YYYYMMDD Project Daily Report, as described below. Whenever possible, the report and all attachments should be included in a single document.

YYYYMMDD – the date, e.g., 20130122 (for January 22, 2013)

Project – Abbreviated project name to help differentiate reports from different projects.

Daily Report – the words “Daily Report” Example: 20130122 Bldg 54 Abate Daily Report

PROJECT 3578866 Page 15 of 20

What: Use form CM-03. The COR may approve alternate forms provided that they include the necessary information in a consistent format. In general, daily reports should include the following information.

• Project title

• Contract number

• Weather, including inches of rainfall and maximum/minimum temperatures (should be more detailed for outdoor projects)

• List of prime contractor employees, their job category, and the number of hours worked on the project.

• List of heavy equipment, and the number of hours working.

• The detailed description of work performed (see below) should indicate what the equipment was used for.

• A detailed description of the work performed. Attach copies of plan sheets, details, or other drawings as necessary to clearly indicate the work performed by the Contractor and each subcontractor.

• List of materials delivered eir job category, and as m to ld e report by the Contractor’s Quality Control and thoroughly document the work.

This can include photographs.

d to the Contracting Officer.

1.20.2 Punch List

• List of official visitors

• For each subcontractor, list of employees, th the number of hours worked on the project.

• List of specific QC inspections and testing performed, including results and corrective actions. If inspection/test results are not yet available, describe what was done and submit results as soon they become available. The contractor shall use a syste assure that all such inspection reports are submitted.

• Resubmittals that provide such additional information shou consist of the entire Daily Report, not just the new sheets

• List of verbal instructions received from the Government.

• Certification of th

Representative.

• Other information to accurately

b. Weekly: Weekly payroll reports required by Labor Standards Provisions, shall be submitte

PROJECT 3578866 Page 16 of 20

Submit after pre-final inspection, and final inspection. The Discrepancies and Omissions list (punch list) is not an all-inclusive listing of discrepancies which exist between the contract specifications and the work as performed up to the date of the list. It is also not a waiver of any other Government Claim. The Government at all times reserves all of its rights and remedies under the Contract.

1.20.3 Notices to COR and CI

Unless otherwise provided for herein, advise the COR and CI a minimum of 72 hours in advance of the following planned actions:

Commencement or recommencement of work at the site.

Shutdowns.

Requests for inspection.

1.20.4 Cost Proposals for Modifications: Itemize every cost proposal submitted as outlined in this paragraph. Costs allocable to material, labor, equipment, subcontractors, overhead, bonding, insurance and profit must be separately itemized for each distinct category or item of work encompassed. Include documentation such as invoices, quotes, vendor estimates, or other supporting cost figures. Clearly state in the proposal if an extension in the performance period is required. For proposals involving time extensions, include rationale for the extension and a proposed adjusted progress schedule.

1.20.5 Design Clarification Requests (DCR)

In the event that the contractor, subcontractor, or supplier, at any tier, determines that some portion of the Government supplied; drawings, specifications, or other contract documents require clarification or interpretation by the Government; the contractor shall submit a DCR on form CM-06 in writing to the COR, with a copy to the CI. DCRs may only be submitted by the prime contractor. In the DCR, the contractor shall set forth their interpretation or understanding of the requirement, along with reasons why such an understanding has been reached.

The Government will review all DCRs to determine whether they are DCRs within the meaning of this term. If the Government determines that the document is not a DCR, or missing required information from the contractor, it will be returned to the contractor without review as to content, for resubmittal in the proper manner (e.g., submittal, request for variation, etc.).

PROJECT 3578866 Page 17 of 20

Responses to DCRs will be issued within 14 work days of receipt of the request, unless the Government determines that a longer period of time is necessary to provide an adequate response. If a longer period of time is determined necessary by the Government, the Government will, within 14 days of receipt of the request, notify the contractor of the anticipated response time. The 14 days referred to herein will start on the date stamped received "in from the contractor" by the Government. If the contractor submits a DCR on an activity with 14 days or less of float on the current project schedule, the contractor shall not be entitled to any time extension due to the time it takes the Government to respond to the request, provided that the Government responds in the days set forth above.

Responses from the Government will not change any requirement of the contract documents unless so noted in the response to the DCR. If noted as a change, the Government will issue either a no-cost Field Adjustment or formal modification under the Changes clause. If the contractor believes that a response to a DCR will cause a change to the requirements of the contract documents, the contractor shall immediately give written notice to the Contracting Officer stating that the contractor considers the response to be a change. Failure to give such written notice immediately shall waive the contractor's right to seek additional time or cost under the Changes clause of the contract.

1.21 STANDARD SPECIFICATIONS AND CODES

In case of conflict between the referenced specifications or standards and this specification, this specification shall govern. When a number is suffixed to a referenced specification or standard, it denotes the effective amendment(s) or change to the document. Referenced specifications and standards are not available for distribution by the Coast Guard.

The work shall be performed in accordance with applicable provisions of the Law(s) and the latest publication and/or amendments of the following:

Williams-Steiger Occupational Safety and Health Act of 1970, Public Law 91-596, as amended in 1990.

By agreement between the US Department of Labor, Occupational Safety and Health Administration (OSHA) and State Department of Labor, Division of Occupational Safety and Health (DOSH), applicable OSHA regulations as amended by the State of Alaska are enforced for Contractors and Contractor personnel only by DOSH. At no time will the level of protection afforded the worker be less than the strictest of either the Federal or State regulations.

PROJECT 3578866 Page 18 of 20

Code of Federal Regulations, Title 29, Parts 1910 (Occupational Safety and Health Standards) and 1926 (Safety and Health Regulations for Construction).

Federal Standard 313B, as it pertains to the procurement, identification, marking and control of potentially toxic or hazardous materials, and to the reporting of information concerning these materials.

International Building and Mechanical Codes; Uniform Plumbing Codes

National Electric Code

NFPA 101, Life Safety Code

National Fire Protection Association Codes and Standards

Applicable portions of standards listed in the Specifications that are not in conflict with Contract Documents or with the Federal Acquisition Regulations (FAR).

Any and all USCG and local regulations as pertain to construction, safety, fire, health, and associated activities are hereby made part of this Specification.

Modifications or exceptions to standards shall be considered as amendments, and unmodified portions shall remain in full effect.

All site activities are to be conducted in accordance with applicable EPA and State regulations.

U.S. Army Corp of Engineer Safety and Health Requirements manual EM 385-1- 1 shall be strictly adhered to.

Applicable Standard Specifications: Referenced Technical Sections, including Asphalt Concrete Pavement to Standard Specifications shall mean the Alaska Department of Transportation and Public Facilities "Standard Specifications for Highway Construction - 2004" and any supplements or amendments thereto.

Relevant AKDOT or AASHTO standards may be substituted upon approval by

COR.

Notify the COR of any observed conflicts between the Contract Documents and governing code. COR will issue instructions as to procedures. If the Contractor performs any work knowing it to be contrary to governing code and without notice to the COR, they assume full responsibility.

1.22 CONSTRUCTION DOCUMENTS

The drawings and specifications will be supplied to the contractor in electronic format.

Publications incorporated into the technical provisions by reference will not be furnished.

PROJECT 3578866 Page 19 of 20

PROJECT 3578866 Page 20 of 20

The Contractor shall check all drawings and specifications furnished, immediately upon their receipt, and shall promptly notify the Contracting Officer of any discrepancies (this shall include all sheets and pages that are part of the set of contract documents). Large scale drawings shall take precedence over small scale drawings. The Contractor shall compare all contract drawings, and verify the dimensions and conditions at the site before laying out the work.

1.22.1 Order of Precedence

Where specifications or standards documents are referenced in these Contract documents, they apply as if they were incorporated into the contract, except if specifically noted otherwise. If there are differences between referenced documents and any contract documents the following precedence applies. Additionally, see FAR 52.236-21 and notify the Contracting Officer of any discrepancies.

Contract

Specifications

Drawings

Base Kodiak Standard Specifications. These specifications are the default requirements for items to be included in the work, but not specified in the contract specifications.

References

Applicable code or standard…