PENDANT.SPEC_(WYTL_65B)_DD_FQ1_AJN_18R0.doc

DOC document 2 MB Posted

Attached to
CGC PENDANT DRYDOCK REPAIRS
Solicitation number
HSCG85-18-Q-P45L21
Issued by

About this file

SPECIFICATION FOR THE CGC PENDANT

View the file

Other files

File Type Posted
PENDANTCOMBINE_SYNOPSIS_SOLICITATION24AUG2017.docx DOCX document
PENDANT_Request_for_Clarification.docx DOCX document
PENDANT.Ombudsman_Notice.doc DOC document
PENDANT.SECTION_B_SERVICE_AND_SUPPLIES_(BLANK).xls XLS spreadsheet
PENDANT.Past_Performance_Questionnaire.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC PENDANT (WYTL 65608)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2018

Developed By: Alexander J Norton (Rev-0, 16 June 2017)

TABLE OF CONTENTS

iiiRevisions Record ivConsolidated List of References viiiConsolidated List of Government-furnished Property ixConsolidated List of Critical Inspection Items xPrincipal Characteristics - Tender

1General Requirements

11WORK ITEM 1: Hull Plating (U/W Body), Inspect

15WORK ITEM 2: Appendages (U/W) - Internal, Preserve

17WORK ITEM 3: Propulsion Shafting; Remove, Inspect, and Reinstall

22WORK ITEM 4: Propulsion Shafting, Straighten

24WORK ITEM 5: Stern Tube, Renew

28WORK ITEM 6: Propeller, Remove, Inspect, and Reinstall

31WORK ITEM 7: Keel Coolers, Clean, Inspect and Hydro

36WORK ITEM 8: Fathometer Transducer, Renew

40WORK ITEM 9: Sea Valves and Waster Pieces, Overhaul or Renew

45WORK ITEM 10: Sea Strainers (All Sizes), Renew

48WORK ITEM 11: Sea Strainers - Duplex (All Sizes), Overhaul

52WORK ITEM 12: Hot Water Accumulator Tanks, Clean and Inspect

55WORK ITEM 13: Rudder Assembly; Remove, Inspect And Reinstall

60WORK ITEM 14: Rudder Stock Bearings Clearances, Check

64WORK ITEM 15: U/W Body, Preserve (100%)

68WORK ITEM 16: U/W Body, Preserve (Partial - Condition A)

73WORK ITEM 17: U/W Body, Preserve (Partial - Condition B)

78WORK ITEM 18: U/W Body, Preserve (Partial - Condition C)

83WORK ITEM 19: Hull Plating Freeboard, Preserve “100%”

87WORK ITEM 20: Main Mast, Preserve, 100%

91WORK ITEM 21: Cathodic Protection / Zinc Anodes, Renew

94WORK ITEM 22: Drydock

98WORK ITEM 23: Sea Trial Performance, Support, Provide

102WORK ITEM 24: Sewage Pump (Forward), Upgrade

106WORK ITEM 25: Stack Handrail, Renew

108WORK ITEM 26: Decks - Exterior, Preserve 100%

111WORK ITEM 27: Hull Plating, Forward, Renew

114WORK ITEM 28: Sewage and Grey Water Tanks, Commercial Clean

117WORK ITEM 29: Bulwark Stiffeners Repair

121WORK ITEM 30: Hull and Structural Plating (General) -10.2-Pound Steel, Renew

123WORK ITEM 31: Hull and Structural Plating (General) - 12.75-Pound Steel Plate, Renew

125WORK ITEM 32: Hull And Structural Plating (General) - 20.4-Pound Steel Plate, Renew

127WORK ITEM 33: Hull and Structural Plating (General) - 7.65- Pound Steel Plate, Renew

129WORK ITEM 34: Temporary Services, Provide - Tender

132WORK ITEM 35: Sewage Piping, Clean And Flush

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE
REV#
WORK ITEM#
CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

Consolidated List of References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:

· MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

· Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

· Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws:: www.gpoaccess.gov The Government is aware of the following internet web links where contractors may procure commercial specifications:

· American Welding Society (AWS): http://www.awspubs.com/index.php

· ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/

· NFPA: http://www.nfpa.org

· SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

Coast Guard Drawing 65 WYT 0103-002, Rev B, Outboard, Inboard Profiles, and General Arrangements

Coast Guard Drawing 65 WYT 1112-001, Rev A, Strut, Skeg, Main Engine and Generator Foundation Details

Coast Guard Drawing 65 WYT 1112-8, Rev A, Sewage Retent Tnk & Pump Fdn A,B,C & D Classes

Coast Guard Drawing 65 WYT 1112-9, Rev B, Sewage Retent Tank & Pump Fdn; A,B,C & D Classes

Coast Guard Drawing 65 WYT 2901-005, Rev A, Curves of Form

Coast Guard Drawing 65 WYT 4804-001, Rev -, Fresh Water System

Coast Guard Drawing 65 WYT 4808-2, Rev -, Drain Collection Tank & Pumped Drains

Coast Guard Drawing 65 WYT 4808-5, Rev F, Arrgmt & Det's Sewage System Retention Tank & Piping

Coast Guard Drawing 65 WYT 4808-5, Rev G, Arrangement & Detail for Sewage Retention Tank and Piping System

Coast Guard Drawing 65B WYT 0103-3, Rev -, Booklets of General Plans (65607-65609)

Coast Guard Drawing 65B WYT 0500-002, Rev A, Lines and Offsets

Coast Guard Drawing 65B WYT 0700-004, Rev -, Docking Block Arrangement (‘B’ & ‘C’ Class)

Coast Guard Drawing 65B WYT 0700-004, Rev -, Docking Block Arrangement (“B &C” Class)

Coast Guard Drawing 65B WYT 1101-001, Rev E, Construction Plan, Shell Expansion and Sections

Coast Guard Drawing 65B WYT 1702-1, Rev B, Mast & Rigging (65607-12)

Coast Guard Drawing 65B WYT 1702-3, Mast Arrangement and Details

Coast Guard Drawing 65B WYT 1702-4, Mast Arrg & Dets

Coast Guard Drawing 65B WYT 2200-001, Rev B, Rudder and Steering Gear

Coast Guard Drawing 65B WYT 2200-001, Rev C, Rudder and Steering Gear (65607-65612)

Coast Guard Drawing 65B WYT 2200-001, Rev C, Rudder and Steering Gear (65607-65612)

Coast Guard Drawing 65B WYT 4000-001, Rev C, Machinery Arrangement (65607-12)

Coast Guard Drawing 65B WYT 4103-004, Rev C, Engine Starting F/O and Engine Cooling System Arrangement and Details (65607-15)

Coast Guard Drawing 65B WYT 4301-002, Rev C, Shafting & Bearings

Coast Guard Drawing 65B WYT 4400-003, Rev E, Propeller

Coast Guard Drawing 65B WYT 4800-2, Rev A, Firemain and Bilge System & Plumbing Drains

Coast Guard Drawing 65B WYT 4800-2, Rev A, Firemain and Bilge System & Plumbing Drains

Coast Guard Drawing 65B-WYT 4301-4, Rev A, Propulsion Shaft Single Sheet Detail

Coast Guard Drawing 65B-WYT 0103-3, Rev -, Booklets of General Plans (65607-65609)

Coast Guard Drawing 65B-WYT 103-003, Rev -, Booklet of Gen Plans (65607-09)

Coast Guard Drawing 65B-WYT 103-15, Rev -, Booklet of Gen Plans (65610-12)

Coast Guard Drawing 65B-WYT 103-4, Rev A, Booklet of General Plans

Coast Guard Drawing 65B-WYT 1101-001, Rev E, Const Plan Shell Expand Sects (65607-12)

Coast Guard Drawing 65B-WYT 1101-1, Rev -, Const Pln Shell Exp & Sects (65607-12)

Coast Guard Drawing 65B-WYT 1101-1, Rev E, Constr Plan Shell Exp and Sect

Coast Guard Drawing 65B-WYT-1202-1, Rev C, WYTL 65607 - 65612 Liferails and Grabrods

Coast Guard Drawing 65-WYT 4301-2, Rev J, 65601 Thru 65615 Shafting Plan

Coast Guard Drawing 65-WYT 4808-1, Rev -, Gravity Drains & Flushing Systems

Coast Guard Drawing 65-WYT 1201-2, Rev -, Towrail & Guardrails

Coast Guard Drawing 65-WYT 1202-1, Rev A, Liferails & Grab Rods

Coast Guard Drawing 65-WYT 4301-002, Rev H, 65601 Thru 65615 Shafting Plan

Coast Guard Drawing 65WYT-4808-005, Rev G, Arrgt & Det for Sewage Retention Tank Piping System

Coast Guard Drawing 65WYT-6201-001, Rev F, Electrical Systems Diagrammatic

Coast Guard Drawing 65WYT-6202-005, Rev B, Electrical Systems Diagrammatic

Coast Guard Drawing FL 6713-203, Rev B, CRP-V850 Transducer (B-14) Adapter Assembly

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Requirements for Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2012, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, And Installation

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary Services

OTHER REFERENCES

«OTHERREF»

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities

American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End

ASTM International (ASTM) D1330, 2010 Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D3359, 2009, Standard Test Methods for Measuring Adhesion by Tape Test

ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates

Commercial Item Description (CID) A-A-52624, Nov 2008, Antifreeze, Multi Engine Type, Ethylene Glycol (For Caterpillar equipment applications, use CAT Extended Life Pre-Mix coolant.)

Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust-Petrolatum

DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems

Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert

Fernstrum Gridcooler Installation and Maintenance Manual, 2013, Form 175

International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing Tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50 m, Inclusive

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves

MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)

MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application

MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application

MIL-PRF-24647, 2013, Paint System, Anticorrosive and Antifouling, Ship Hull

MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull

MIL-PRF-24647, Jun 2013, Paint System, Anticorrosive and Antifouling, Ship Hull

MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main Propulsion Shafting

Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-PRO-160, Jan 2011, Chapter 16, Cofferdams

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014, Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 7/NACE No.4, 2007, Brush-Off Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-4/NACE WJ-4, 2012, Waterjet Cleaning of Metals – Light Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007 Near-White Blast Cleaning

Consolidated List of Government-furnished Property

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK ITEM
MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/Unit)

3
Y
**Propeller shaft
NSN: 2010-01-534-9802
1 ea.
12,591
6
Y
Propeller
NSN: 2010-01-482-6135
1 ea.
6,561.81
7
N
MDE Keel Cooler Gasket Set
GD12-2C
1
88.75
7
N
SSDG Keel Cooler Gasket Set
GB12-1A
2
61.40
7
N
**MDE Keel Cooler (See Note 1)
4420-01-482-4075 (D16102)
1
6457.60
7
N
**SSDG Keel Cooler
4420-01-482-3385 (B1260B-S2)
2
2964.85
7
N
**50/50 Premix Coolant
N/A
110 gallons
200.00
8
N
***Fathometer Transducer, Shallow Water, 50-200 kHz (Airmar Technology SS505)
NSN: 5845-01-470-2500
1 ea.
343.63
11
Y
**2 1/2 inch Duplex Strainer
PN: GROCO VD-2500
2 ea.
1,338.90
11
Y
**4- inch Duplex Strainer
NSN: 4730-01-173-1413 PN: 72-48F
1 ea.
7454.94
22
Y
*Transducer Cover Plate
N/A
1 ea.
50.00
24
N
Pump, Centrifugal, Monel, Trim, 2-1/2" Fldg Suction, 2" Fldg Disch, 30 Gpm @ 45 Ft Tdh, Bronze
PN: 4000 Series Model DHKV (A60)
1 ea.
9,696.00
24
N
Valve, Ball, 2” Ips, Brz Body, Monel Trim, Silbraz Socket Ends, Teflon Seal 225 Wog
NSN:4820-01-539-3104 PN: PBM 2in SPB-H1S-B-L
3 ea.
1856.23

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item
Title
3
Propulsion Shafting; Remove, Inspect, and Reinstall
7
Keel Coolers, Clean, Inspect and Hydro
11
Sea Strainers - Duplex (All Sizes), Overhaul
13
Rudder Assembly; Remove, Inspect And Reinstall
15
U/W Body, Preserve (100%)

Principal Characteristics - Tender

65' WYTL (B-Class: 65607-65609)

Physical

Length overall
64' 10-1/2"
Depth
8' 11"
Maximum beam
19' 3/8"
Height of highest projection
N/A
Full load draft
6' 2"
Full load displacement
72 long tons
Shore tie voltage requirements
N/A
Frame spacing
1' 6"

Hull

Hull/ main weatherdeck material

Superstructure

Machinery

Number of propellers
1
Number of blades
4
Diameter of propeller
54"
Pitch
46"
RPM
400
Shaft diameter
N/A

00000_1216_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

Coast Guard Drawings

None

Coast Guard Publications

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Other References

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

· Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

· National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

· Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.1 SFLC Standard Specification 6310, Requirements for Preservation of Ship Structures.

3.7.1.1 SFLC Std Spec 6310, page C-2, Section C1.5.1. Change from "lead-containing paint as 0.06%" to "lead-containing paint as 0.009%".

3.7.1.2 SFLC Std Spec 6310, page 4, Section 2 References, Group- Other References. Add “The Society for Protective Coatings (SSPC) Paint Application Guide No. 11, 2008, Protecting Edges, Crevices, and Irregular Steel Surfaces by Stripe Coating”

3.7.1.3 SFLC Std Spec 6310, page Appendix C-6, add "Hempel Hempadur Multi-Strength GF 35870" with FED-STD-595 color "Black/Red" under ANTI-ABRASION COATING, ICE BREAKING CAPABLE VESSELS, <235’.

3.7.1.4 Standard Spec 6310, page Appendix A-7, Under "UNDERWATER (U/W) BODY/BOOT-TOP", Add line Column 1: Option for U/W Body and Boot-Top, Steel Hulls, <154', in Salt Water. Column 2: Blank. Column 3: SSPC-SP 10/NACE NO. 2 using grit conforming to MIL-A-22262 / (1.5-3.5) - or - SSPC-SP WJ-2(M)/NACE WJ-2(M). Columns 4 and 5: Same as "U/W Body and Boot-Top, Aluminum Hull, High Speed (>30 knots)".

3.7.2 SFLC Standard Specification 0000 General Requirements.

3.7.2.1 SFLC Std Spec 0000, paragraph 1.3 ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.2.2 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name
Hull #
Work Item #
Work Item Title

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE & TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION (Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL. HUMID-ITY
DEW PT.
SURFACE
AMBIENT
ΔT

| DP - Surface |

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings:

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading (mils)

Mean Reading (mils) IAW ASTM DD4417).

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.

Date
Test Locations
Conductivity (Microsiemens/CM)
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name
Hull #
Work Item #
Work Item Title
Coating Mfg
Product Name
Batch #
Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.

SPOT
1
2
3
4
5
AVERAGE VALUE

*BASE METAL READING (BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled)
Average DFT
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

11000_1016_FLT

REC_11000_UWHIB_FLT_65’ WYTL (‘B’ Class: Hulls 65607-65609) (1211) WORK ITEM 1: Hull Plating (U/W Body), Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 65B WYT 0700-004, Rev -, Docking Block Arrangement (“B &C” Class) Coast Guard Drawing 65B WYT 1101-001, Rev E, Construction Plan, Shell Expansion and Sections Coast Guard Drawing 65 WYT 1112-001, Rev A, Strut, Skeg, Main Engine and Generator Foundation Details Coast Guard Drawing 65B WYT 2200-001, Rev B, Rudder and Steering Gear

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Other References

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2 (References) as guidance. The Contractor shall provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:

· A hull repair supervisor and a marker.

· Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.

NOTES

1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.

3.2.1 Hull plating.

3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.

3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.

3.2.2 Sea chests and all other cooling system intake components. The Contractor shall inspect all sea chests, sea beam arrays, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.

3.2.3 Rudders. The Contractor shall check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.

3.2.4 Propeller and shaft associated components. The Contractor shall inspect the condition of propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade; inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.

3.2.5 Transducers. The Contractor shall check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.

3.2.6 Zinc anodes.

3.2.6.1 The Contractor shall remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, sea beam array, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.

3.2.6.2 The Contractor shall visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.

3.2.7 Coating system inspections. The Contractor shall accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB). Document the condition found as “Partial - Condition A”, “Partial - Condition B”, “Partial Condition C”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.

NOTE

The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.

3.2.7.2 Dry film thickness (DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.

4. NOTES

4.1 Definitions.

4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.

4.1.2 "Partial - Condition B": The condition that exists where the anticorrosive (AC) undercoating system has incurred damage, but, the u/w body hull substrate is not exposed in any location.

4.1.3 "Partial - Condition C”: The condition that exists where damage is confined to the antifoulant (AF) topcoating; the epoxy undercoating system is not exposed in any location.

4.1.4 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.

4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

11402_UW_APPENDAGES_0712_FLT

REC_11400_UW_Appendages_FLT_65’ WYTL (‘B’ Class: Hulls 65607-65609) (1011) WORK ITEM 2: Appendages (U/W) - Internal, Preserve

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve internal surfaces of designated U/W appendage(s) (see Table 1).

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 65B WYT 0700-004, Rev -, Docking Block Arrangement (“B &C” Class) Coast Guard Drawing 65B WYT 1101-001, Rev E, Construction Plan, Shell Expansion and Sections Coast Guard Drawing 65 WYT 1112-001, Rev A, Strut, Skeg, Main Engine and Generator Foundation Details Coast Guard Drawing 65B WYT 2200-001, Rev B, Rudder and Steering Gear

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Other References

MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Preservation of void internal surfaces. The Contractor shall accomplish the following tasks for each appendage designated by the Coast Guard Inspector, using the Coast Guard Drawings listed in Section 2 (References) herein as guidance:

· Fill all appendage interior surfaces with a rust preventive compound conforming to MIL-PRF-16173, Class II, Grade 3, to coat all surfaces.

· Drain, collect, and dispose of remaining compound in accordance with all applicable Federal, state, and local regulations.

· Ensure that the coated surfaces are left exposed to the atmosphere for 24 hours to allow for adequate drying.

TABLE 1 - DRAIN PLUGS FOR U/W Appendages

APPENDAGE
FRAME
SIDE
Skeg
19 to 41
CL
Fwd Skeg
5 to 12
CL
Strut
40 to 41
CL
Rudder
Stern
CL

4. NOTES

This section is not applicable to this work item.

24310_0416_FLT

REC_24310_FLT_65’ WYTL (‘B’ Class: Hulls 65607-65609) (00313) WORK ITEM 3: Propulsion Shafting; Remove, Inspect, and Reinstall

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to remove, inspect, and reinstall the propeller shaft.

1.2 Government-furnished property.

MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/UNIT)

Y
**Propeller shaft
NSN: 2010-01-534-9802
1 ea.
12,591

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 65B-WYT 4301-4, Rev A, Propulsion Shaft Single Sheet Detail Coast Guard Drawing 65-WYT 4301-2, Rev J, 65601 Thru 65615 Shafting Plan Coast Guard Drawing 65B WYT 4301-002, Rev C, Shafting & Bearings

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Other References

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

· 3.2.1 Initial shaft coupling alignment check

· 3.2.3 Inspections

· 3.5 Government’s right for changing out shaft(s)

3.1.2 Tech Rep.

Not Applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

· Deck plates.

· Rope guard.

· Fairwater.

3.2 Work to be accomplished. Using Coast Guard Drawing 65 WYT 4301-2, 65B WYT 4301-2, 65B WYT 4301-4 as guidance, as applicable, the Contractor shall accomplish the following:

3.2.1 Initial shaft coupling alignment check. Prior to the vessel’s initial drydocking, perform the bore and face alignment between the reduction gear output flange and shaft coupling as follows and Submit A CIR:

· Angular (face-to-face) readings in 4 positions at 90° intervals;

· Parallel (coupling OD-to-coupling OD) readings in 12 positions at 30° intervals.

NOTE

The following methods for obtaining coupling/hub alignment measurements are acceptable:

1) Dial indicator to obtain total indicator run-out

2) Straight edge or feeler gage.

3.2.2 Removals.

Caution Be aware historically couplings have been difficult to remove, often requiring added heat to loosen.

Ensure shaft is protected and supported at all bearing journals (minimum), at all times, until reinstallation.

When transporting/moving/lifting, ensure the shaft is supported at all times at a minimum of three locations along the shaft.

Provide proper support to the reduction gear shaft flanges to prevent sagging.

· Mark existing shaft position, and match-mark shaft coupling bolts to their respective holes, to facilitate reinstallation procedures.

· Remove the shaft and attached components (as applicable) to a suitable repair facility.

3.2.3 Inspections. Clean the shaft free of all marine growth and surface contaminants, and accomplish the following inspections, as applicable (Submit A CIR):

3.2.3.1 Visual inspections. Visually inspect the following components, as applicable, for excessive wear and other mechanical defects such as nicks, cracks, and corrosion, etc. Determine the extent of repairs required for each stern tube assembly, if any.

· Shaft surfaces.

· Bearings, bearing carriers, epoxy-resin chocking and associated fasteners (as applicable).

· All shaft and propeller-associated fasteners.

· Stern tube surfaces (including seal flange as applicable).

· Couplings.

· Stern tube/shaft sealing systems.

3.2.3.2 Complete the following measurements:

NOTE(S)

Before taking shaft runout readings, slowly spin the shaft on a lathe for approximately two hours to eliminate any sagging that may have occurred during handling and storage.

· Measure keys and keyways.

· Measure all bearing sleeve or journal diameters.

· Measure runouts for shaft taper, shaft straightness, and coupling end diameters.

· With the key in-place, fit the shaft coupling to the shaft in shop and check the contact percentage by bluing. If the contact is less than 80%, the Contractor shall grind and hand stone the coupling hub to achieve a minimum of 80 percent contact, and verify by bluing again. Make a small inscription on the shaft to mark the coupling hub location and use it as a reference in final assembly. Measure and record the coupling face and bore runouts..

3.2.3.3 Perform NDE of all bearing sleeves, shaft tapers, coupling bolts, keyways, and weld repaired surfaces in accordance with SFLC Std Spec 0740, Appendix C..

3.2.3.4 After removal of the propeller shaft, the Contractor shall check and monitor the alignment of the stern tube, struts, and bearing housing bores relative to the shaft centerline including any offsets using an optical method (bore sighting) or taut wire method. This inspection shall be done within 72 hours after the shaft is removed so that any misalignment can be corrected in a timely fashion. Take all readings at night, preferably between midnight and dawn, to reduce the thermal distortion on the hull due to sunlight.

3.2.3.4.1 Take the initial reading and establish a baseline.

3.2.2.4.2 The shaft center reference line established by optical or piano wire method shall start from the center of reduction gear output shaft flange to a fixed point location where the propeller hub is centered.

3.2.2.4.3 Use as many reference points as possible to show if the bearing bores have been affected by the structural repair or hot work. Submit a report of how the shaft center reference line is established, locations of fix points, and any bearing offsets as noted.

3.2.2.4.4 Submit a CFR of findings, include any recommended repairs if the shaft alignment was affected by the structural repair or hot work.

3.2.2.5 Inspect the shaft fiberglass covering for porosity as follows:

3.2.2.5.1 Visually inspect the plastic covering for evidence of lack of adhesion, and other defects.

3.2.2.5.2 Conduct a high voltage spark test of the covering at 250 to 300 volts per mil of glass reinforcement (approximately 15,000 volts for a four-ply covering). Pay particular attention to the joining line between sleeves, couplings, and shafts.

3.2.3.3 Shaft tube air test. If a Change Request is authorized…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .