ATTACHMENT 2 – SCHEDULE OF SUPPLIES/SERVICES
CONTRACT NO. HSCG85-17-R-P45K73
USCGC MUNRO (WMSL 755) DS PSA2 FY18 FQ2
B.1 CLIN 0001 - DEFINITE ITEMS
These are the items that, if there is an award at all, will be awarded. The proposal shall be evaluated to include the proposed price for each definite item.
ITEM
NO.
DESCRIPTION QTY UNIT UNIT
PRICE
AMOUNT
D-01 Galley Grease Fire Extinguishing System, Inspect and Test 1 JB $ $
D-02 Gas Turbine Module Fixed CO2 Fire Extinguishing System, Inspect and Test.
1 JB $ $
D-03 Heptafluoropropane (Hfp) Fire Extinguishing System, Inspect And Test
1 JB $ $
D-04 Water Mist Fire Extinguishing System, Inspect and Test 1 JB $ $ D-05 Portable Brow Storage, Relocate 1 JB $ $ D-07 Deck Covering (Slip-Resistant), Renew 1 JB $ $ D-08 Overhead Light Fixture, Modify 1 JB $ $ D-09 Auxiliary Seawater Piping, Modify 1 JB $ $ D-10 Handrail and Grabrail, Install 1 JB $ $ D-11 QAATDR/QAWTDR/BDR, Modify/Repalce (NSC3&F) 1 JB $ $ D-12 Sea Painter Boom, Replace 1 JB $ $ D-13 Cofferdam, Install 1 JB $ $
TOTAL AMOUNT OF ALL DEFINITE ITEMS $
B.2 CLIN 0002 - OPTIONAL ITEMS
Optional Items O-06 will be awarded if inspection reports reveal the necessity for activation, but before 05 September 2017, to maintain performance schedule, see clause entitled “Optional Items” and FAR 52.217-5, Evaluation of Offers of the basic contract.
ITEM
NO.
DESCRIPTION QTY UNIT UNIT
PRICE
AMOUNT
O-06 Tanks (Water Mist), Preserve “Partial” 1 JB $ $
TOTAL AMOUNT OF ALL OPTIONAL ITEMS $
TOTAL AMOUNT OF DEFINITE & OPTIONAL ITEMS $
B.3 COMPOSITE LABOR HOUR RATE APPLICABLE TO CONTRACT CHANGES
The following labor hour rate shall be used in pricing all contract changes in accordance with ATTACHMENT 3, Section 13, Page 8, entitled "COMPOSITE LABOR RATE.”
LABOR HOUR RATE
ESTIMATED QUANTITY
1082 hours
EXTENDED AMOUNT
**NOTE: The estimated quantity and extended amount indicated above are for evaluation of proposals only.
The proposed rate will apply to all changes involving additional work under this contract regardless of the actual total hours required.