Amendment 0004

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 3

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable) 0004 09 July 2016 2116856P45F66

6. ISSUED BY CODE HSCG85 7. ADMINISTERED BY (If other than Item 6) CODE

USCG COMMAND

Surface Forces Logistics Centers, C&PD2-LREPL 1301 Clay Street, Suite 800N, Oakland, CA 94612

SAME AS BLOCK #6

8. NAME AND ADRESS OF CONTRACTOR (no., street, county, State and ZIP Code) √ 9.A AMENDMENT OF SOLICITATION NO.

TO ALL PROSPECTIVE OFFERORS

HSCG85-16-R-P45F66

9B. DATE (SEE ITEM 11)

03 June 2016

10A. MODIFICATION OF CONTRACT/ORDER

NO. ?

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the Offer submitted: or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/.ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority).

E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SUBJECT: RFP No. HSCG85-16-R-P45F66 CGC STRATTON (WMSL 752), Dockside Repairs FQ4 FY16

SEE PAGE S 2 to 3 FOR DESCRIPTION

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Wilma L. Estrada, Contracting Officer 15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)PREVIOUS

EDITION UNUSABLE Prescribed by GSA, FAR (48 CFR) 53.243

CGC STRATTON (WMSL 752) Dockside Repairs FQ4 FY16 Amendment No. 0004

The purpose of this amendment is to:

1. Provide the three, attached missing drawings:

750-WMSL-101-021

750-WMSL-101-027

750-WMSL-501-004.

2. Reply to the following Requests for Clarification:

Question 1: This is in reference to Definite Item D-10, Surfaces, Preserve; Paragraphs 1.1 Table 1 and 3.4.1 – Water Jet Cleaning of Metals – Very Thorough Cleaning (SSPC-WJ-2/Nace WJ-2) or Power Tool Cleaning to Bare Metal (SSPC-SP11) only for Inaccessible areas.” Reference drawing indicates the area to be preserved is located center between JP-5 Pump room Port and FW Pump room Stbd, reference picture clearly shows space to be machinery space with electronic equipment and Insulation throughout.

Paint contractor recommends to preserve entire deck area Per Std Spec 6310, Appendix B Pg B5 Metal Decks – No application of Deck covering Steel: as SSPC-SP-11 (1.0) there by eliminating water spray, moisture damage, and electrical shorts to equipment, in spite of wrapping and Protection

Answer 1: Concur; preserve deck areas per STD Spec 6310, Appendix B pg B5 Metal Decks - No application of deck covering steel. SSPC-WJ2 may be used in lieu of abrasive to mitigate grit contamination in the turbine enclosure.

Question 2: This is in reference to Definite Item D-10, Gas Turbine air inlet Stbd 01-44-1& 2-0;

Paragraphs 1.1 Table 1 and 3.4.2 – “using the system specified in SFLC STD Spec 6310, Appendix B (Cutter and Boat Interior Painting Systems). Apply finish/top coat to match existing adjacent surfaces. Select option(s) as follows (Figure 2): Smoke Stack (Smoke Stack Casing, Steel Interior (containing insulated exhaust piping)

Statement conflicts references “Appendix B”, but uses terminology (BOLD TYPE) from Appendix A. Paint contractor recommends to preserve P/S Gas turbine inlets IAW SFLC STD Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems). Apply finish/top coat to match existing adjacent surfaces. Select option(s) as follows (Figure 2):

Smoke Stack (Smoke Stack Casing, Steel Interior (containing insulated exhaust piping). Paint contractor also recommends preparation by abrasive vacuum blast to SSPC SP-1O or Power Tool Cleaning to Bare Metal (SSPC-SP 11).

Answer 2: Preserve area IAW SFLC STD Spec 6310 Appendix *A* smoke stack (smoke stack Casing, steel interior (containing insulation exhaust piping)). This option requires SSPC-SP10 surface preparation standard; however, KTR may use SSPC/NACE-WJ2 to mitigate abrasive contamination of gas turbine intakes.

Question 3: This is in reference to Definite Item D-15, Deck Covering (Slip-Resistant), Renew;

Paragraphs 1.1 Table 1 and 3.1.5, Work Locations - MGT Inlet Compartments01 Level, Fr 44 to

52. Reference DWG Not In Para 2 References - MGT Inlet Compartments 01 Level, Fr 44 to

52. Listed on Table I 2nd Item down, Para 3.1.5 Work Location References silent drawing.

CGC STRATTON (WMSL 752) Dockside Repairs FQ4 FY16 Amendment No. 0004

Booklet Of Gen Plans O1 Deck unclear for access/ nomenclature. Please provide compartment numbers and reference drawing showing work location. All on Port side or one each side?

Answer 3: 1 each side (1 port, 1 starboard). Please reference 750-WMSL-259-009, Turbine, Combustion intake arrangement and supports, dets and L/M above 01 Level (ASC259007).